SlideShare une entreprise Scribd logo
1  sur  6
Télécharger pour lire hors ligne
MATERIALES MANO DE OBRA PRESTACIONES
excavacione de fundaciones m3 17.26 174.72B/. 25.50B/. 200.22B/. 0.27%
preparación de ref. fundación ml 359.60 318.00B/. 153.60B/. 79.50B/. 30.50B/. 581.60B/. 0.79%
exc. De tubería eléctrica m3 43.68B/. 12.75B/. 56.43B/. 0.08%
exc. De tubería sanitaria m3 43.68B/. 12.75B/. 56.43B/. 0.08%
colocación de refuerzo de
columnas y anclaje
ml 63.00 55.65B/. 153.60B/. 13.91B/. 30.50B/. 253.66B/. 0.34%
vaciado de concreto fund. m3 4.01 1,572.00B/. 131.04B/. 393.13B/. 33.00B/. 2,129.17B/. 2.89%
inst. de tuberías eléctricas ml 120.00B/. 200.00B/. 22.00B/. 342.00B/. 0.46%
inst. de tuberías aguas ml 85.00B/. 135.00B/. 15.00B/. 235.00B/. 0.32%
vaciado de concreto m3 8.45 1,656.78B/. 146.10B/. 414.20B/. 33.00B/. 2,250.08B/. 3.05%
col. De acero de columnas ml 530.00 75.99B/. 153.30B/. 18.99B/. 30.50B/. 278.78B/. 0.38%
col. De formaletas m2 41.30 138.00B/. 102.40B/. 34.50B/. 40.30B/. 315.20B/. 0.43%
vaciado de concreto para col. m3 3.07 601.33B/. 87.36B/. 150.33B/. 33.00B/. 872.02B/. 1.18%
desencofrado m2 41.30 43.68B/. 15.75B/. 59.43B/. 0.08%
preparación de ref. vigas ml 844.80 747.30B/. 204.80B/. 186.83B/. 30.50B/. 1,169.43B/. 1.59%
col. De formaletas m2 40.59 127.20B/. 204.80B/. 32.00B/. 40.30B/. 404.30B/. 0.55%
vaciado de concreto m3 2.93 574.28B/. 146.10B/. 143.57B/. 33.00B/. 896.95B/. 1.22%
desencofrado m2 40.59 43.68B/. 15.75B/. 59.43B/. 0.08%
col. De formaleta m2 112.64 356.50B/. 51.20B/. 89.13B/. 40.30B/. 537.13B/. 0.73%
CUADRO ANALITICO DE COSTOS
PRECIOS UNITARIOSPLANTABAJACOLUMNAS
VIGASPARA
LOSAS
SAPARAEL
NIVEL100 COSTO
% RELATIVO
DEL TOTAL
ACTIVIDAD UNIDAD CANTIDADITEM
EQUIPO Y
HERRAMIENTAS
PLANTA BAJA NIVEL 000
COLUMNAS PARA LOSA
VIGAS PARA LOSA DEL NIVEL 100
LOSA DE SEGUNDO NIVEL 100
FUNDACIONES
FUNDACIONES
inst. de tuberías eléctricas ml 210.00B/. 206.40B/. 22.00B/. 438.40B/. 0.59%
inst. de tuberías aguas ml 132.00B/. 146.88B/. 15.00B/. 293.88B/. 0.40%
col. de acero y refuerzos ml 182.85B/. 204.80B/. 45.72B/. 30.50B/. 463.87B/. 0.63%
vaciado de concreto m3 25.36 4,970.36B/. 146.10B/. 1,242.50B/. 33.00B/. 6,391.96B/. 8.66%
desencofrado ml 112.64 21.84B/. 15.75B/. 37.59B/. 0.05%
colocación de acero ml 364.00 181.00B/. 153.60B/. 45.20B/. 30.50B/. 410.30B/. 0.56%
colocación de formaleta m2 41.63 138.00B/. 102.40B/. 34.50B/. 40.30B/. 315.20B/. 0.43%
vaciado de concreto m3 3.07 601.33B/. 87.36B/. 150.33B/. 33.00B/. 872.02B/. 1.18%
desencofrado m2 41.63 43.68B/. 15.75B/. 59.43B/. 0.08%
colocación de bloques m2 392.16 3,581.05B/. 1,075.00B/. 895.26B/. 28.80B/. 5,580.11B/. 7.56%
col. Columna de amare ml 120.00 62.50B/. 153.60B/. 15.65B/. 30.50B/. 262.25B/. 0.36%
col. De formaleta m2 10.42 34.50B/. 102.40B/. 8.63B/. 40.30B/. 185.83B/. 0.25%
vaciado de concreto m3 0.80 156.80B/. 73.04B/. 39.20B/. 33.00B/. 302.04B/. 0.41%
desencofrado m2 10.42 21.84B/. 15.75B/. 37.59B/. 0.05%
colocación de viga de amare ml 253.48 129.63B/. 102.40B/. 32.41B/. 30.50B/. 294.94B/. 0.40%
col. De formaleta m2 45.12 149.50B/. 102.40B/. 37.38B/. 40.30B/. 329.58B/. 0.45%
vaciado de concreto m3 3.83 750.68B/. 204.80B/. 187.67B/. 33.00B/. 1,176.15B/. 1.59%
desencofrado ml 45.12 102.40B/. 15.75B/. 118.15B/. 0.16%
repello de paredes m2 784.00 11,760.00B/. 2,150.40B/. 512.00B/. 45.00B/. 14,467.40B/. 19.61%
estructura
ml 156.40 1,094.80B/. 782.00B/. 108.36B/. 140.00B/. 2,125.16B/. 2.88%
colocación de cubierta
m2 100.00 1,000.00B/. 700.00B/. 57.28B/. 120.00B/. 1,877.28B/. 2.54%
instalación de ventanas
4,000.00B/. 204.80B/. 1,000.00B/. 80.00B/. 5,284.80B/. 7.16%
instalación de puertas 3,000.00B/. 204.80B/. 750.00B/. 70.00B/. 4,024.80B/. 5.46%
LOSAPARAEL
NIVEL100
INSTALACION DE CIELO RASO
COLUMNAS
PARA
TECHO
BLOQUEODETODASLAS
PAREDES
INSTALACION
DETECHO
PUERTASY
VENTANAS
COLUMNAS PARA TECHO
BLOQUEOS DE TODAS LAS PAREDES
INSTALACION DE TECHO
INSTALACION DE PUERTAS Y VENTANAS
CIELO
RASO colocación de cielo
m2 124.40 1,990.40B/. 746.40B/. 70.40B/. 70.00B/. 2,877.20B/. 3.90%
inst. de piso de todas las áreas m2 135.11 2,026.65B/. 810.7B/. 203.00B/. 33.50B/. 3,073.81B/. 4.17%
inst. de paredes de baño y coci. m2 142.21 2,129.60B/. 568.8B/. 533.00B/. 33.50B/. 3,264.94B/. 4.43%
sistema eléctrico 1,880.00B/. 950.00B/. 76.50B/. 2,906.50B/. 3.94%
base + pintura final 1,800.00B/. 700.00B/. 109.50B/. 23.00B/. 2,632.50B/. 3.57%
artefacto sanitario 1,550.00B/. 350.00B/. 35.00B/. 1,935.00B/. 2.62%
transportar de caseta temporal 172.00B/. 75.00B/. 247.00B/. 0.33%
limpieza de terreno 225.00B/. 150.00B/. 375.00B/. 0.51%
inst. eléctrica definitiva 165.00B/. 200.00B/. 365.00B/. 0.49%
entrega de llave al dueño 50.00B/. 50.00B/. 0.07%
COSTO TOTAL DE LA OBRA 73,772.93B/. 100.00%
COSTO TOTAL DE LOS
MATERIALES
49,939.68B/. 67.69%
COSTO TOTAL DE LA MANO DE
OBRA
13,662.58B/. 18.52%
COSTO TOTAL DE LAS
PRESTACIONES
7,971.07B/. 10.80%
COSTO TOTAL DE LOS EQUIPO Y
HERRAMIENTAS
2,199.60B/. 2.98%
INSTALACION
ES
DEFINITIVAS
REVEST
IMIENT
OS
ACABADOSY
DETALLES
FINALES
COSTOSYPORCENTAJES
PORACTIVIDADES
REVESTIMIENTOS DE TODAS LAS AREAS
INSTALACIONES DEFINITIVAS
ACABADOS Y DETALLES FINALES
Cuadro analitico de costoso25
Cuadro analitico de costoso25
Cuadro analitico de costoso25

Contenu connexe

En vedette

Cuadro resumen analitico mapas conceptuales raquel (1)
Cuadro resumen analitico mapas conceptuales raquel (1)Cuadro resumen analitico mapas conceptuales raquel (1)
Cuadro resumen analitico mapas conceptuales raquel (1)Adeliith Romero Salas
 
Cuadro resumen analitico mapas conceptuales
Cuadro resumen analitico mapas conceptualesCuadro resumen analitico mapas conceptuales
Cuadro resumen analitico mapas conceptualeskmarengass
 
Cuadro Analítico de semejanzas y diferencias entre las Normas de Redacción AP...
Cuadro Analítico de semejanzas y diferencias entre las Normas de Redacción AP...Cuadro Analítico de semejanzas y diferencias entre las Normas de Redacción AP...
Cuadro Analítico de semejanzas y diferencias entre las Normas de Redacción AP...marialuz73
 
Cuadro comparativo
Cuadro comparativoCuadro comparativo
Cuadro comparativosaraifranco
 
Innovación,creatividad e invencion
Innovación,creatividad e invencionInnovación,creatividad e invencion
Innovación,creatividad e invencionYoana Gonzalez
 
Creatividad e Innovación
Creatividad e InnovaciónCreatividad e Innovación
Creatividad e Innovaciónconsultoriacimd
 
Libro Ejercicios Word
Libro Ejercicios WordLibro Ejercicios Word
Libro Ejercicios Wordmariacostas_
 

En vedette (9)

Cuadro resumen analitico mapas conceptuales raquel (1)
Cuadro resumen analitico mapas conceptuales raquel (1)Cuadro resumen analitico mapas conceptuales raquel (1)
Cuadro resumen analitico mapas conceptuales raquel (1)
 
Cuadro resumen analitico mapas conceptuales
Cuadro resumen analitico mapas conceptualesCuadro resumen analitico mapas conceptuales
Cuadro resumen analitico mapas conceptuales
 
Cuadro Analítico de semejanzas y diferencias entre las Normas de Redacción AP...
Cuadro Analítico de semejanzas y diferencias entre las Normas de Redacción AP...Cuadro Analítico de semejanzas y diferencias entre las Normas de Redacción AP...
Cuadro Analítico de semejanzas y diferencias entre las Normas de Redacción AP...
 
Cuadro comparativo
Cuadro comparativoCuadro comparativo
Cuadro comparativo
 
Word Avanzado
Word AvanzadoWord Avanzado
Word Avanzado
 
Aplicaciones de Word
Aplicaciones de WordAplicaciones de Word
Aplicaciones de Word
 
Innovación,creatividad e invencion
Innovación,creatividad e invencionInnovación,creatividad e invencion
Innovación,creatividad e invencion
 
Creatividad e Innovación
Creatividad e InnovaciónCreatividad e Innovación
Creatividad e Innovación
 
Libro Ejercicios Word
Libro Ejercicios WordLibro Ejercicios Word
Libro Ejercicios Word
 

Similaire à Cuadro analitico de costoso25

Ls bang gia ls ap dung 20 04-2019
Ls bang gia ls ap dung 20 04-2019Ls bang gia ls ap dung 20 04-2019
Ls bang gia ls ap dung 20 04-2019Dien Ha The
 
020 ejemplo de presupuesto (mano de obra, materiales y transporte)
020 ejemplo de presupuesto (mano de obra, materiales y transporte)020 ejemplo de presupuesto (mano de obra, materiales y transporte)
020 ejemplo de presupuesto (mano de obra, materiales y transporte)independiente
 
Om enterprises pricelist
Om enterprises pricelistOm enterprises pricelist
Om enterprises pricelistMaxpromotion
 
Bảng giá HPC - 05 Bảng giá Fuji ED&C - Fuji Electric
Bảng giá HPC - 05 Bảng giá Fuji ED&C - Fuji ElectricBảng giá HPC - 05 Bảng giá Fuji ED&C - Fuji Electric
Bảng giá HPC - 05 Bảng giá Fuji ED&C - Fuji ElectricCTY TNHH HẠO PHƯƠNG
 
Catalog MCCB ELCB Shillin Electric
Catalog MCCB ELCB Shillin Electric Catalog MCCB ELCB Shillin Electric
Catalog MCCB ELCB Shillin Electric Beeteco
 
Calendario valorizado sistema de recreacion amotape
Calendario valorizado  sistema de recreacion amotapeCalendario valorizado  sistema de recreacion amotape
Calendario valorizado sistema de recreacion amotapeEdikson Soto
 
Bang gia thiet_bi_dong_cat_ls
Bang gia thiet_bi_dong_cat_lsBang gia thiet_bi_dong_cat_ls
Bang gia thiet_bi_dong_cat_lstankhanh1989
 
Bang gia mcb_mccb_contactor_acb_hyundai_10-11-2012
Bang gia mcb_mccb_contactor_acb_hyundai_10-11-2012Bang gia mcb_mccb_contactor_acb_hyundai_10-11-2012
Bang gia mcb_mccb_contactor_acb_hyundai_10-11-2012Lãng Quên
 
Bang gia bien_tan_mitsubishi_2013
Bang gia bien_tan_mitsubishi_2013Bang gia bien_tan_mitsubishi_2013
Bang gia bien_tan_mitsubishi_2013Lãng Quên
 
Boiler ea case study 16 jan 2012 varanasi
Boiler ea case study  16 jan 2012 varanasiBoiler ea case study  16 jan 2012 varanasi
Boiler ea case study 16 jan 2012 varanasiD.Pawan Kumar
 
mega-himel-2019-latest
mega-himel-2019-latestmega-himel-2019-latest
mega-himel-2019-latestrobert Tiin
 

Similaire à Cuadro analitico de costoso25 (17)

Facade man hour
Facade man hourFacade man hour
Facade man hour
 
Ls bang gia ls ap dung 20 04-2019
Ls bang gia ls ap dung 20 04-2019Ls bang gia ls ap dung 20 04-2019
Ls bang gia ls ap dung 20 04-2019
 
020 ejemplo de presupuesto (mano de obra, materiales y transporte)
020 ejemplo de presupuesto (mano de obra, materiales y transporte)020 ejemplo de presupuesto (mano de obra, materiales y transporte)
020 ejemplo de presupuesto (mano de obra, materiales y transporte)
 
Modelo 1
Modelo 1Modelo 1
Modelo 1
 
009 planta de tratamiento de agua potable (ptap)
009 planta de tratamiento de agua potable (ptap)009 planta de tratamiento de agua potable (ptap)
009 planta de tratamiento de agua potable (ptap)
 
Om enterprises pricelist
Om enterprises pricelistOm enterprises pricelist
Om enterprises pricelist
 
Bảng giá HPC - 05 Bảng giá Fuji ED&C - Fuji Electric
Bảng giá HPC - 05 Bảng giá Fuji ED&C - Fuji ElectricBảng giá HPC - 05 Bảng giá Fuji ED&C - Fuji Electric
Bảng giá HPC - 05 Bảng giá Fuji ED&C - Fuji Electric
 
Catalog MCCB ELCB Shillin Electric
Catalog MCCB ELCB Shillin Electric Catalog MCCB ELCB Shillin Electric
Catalog MCCB ELCB Shillin Electric
 
01 requerimirnto
01 requerimirnto01 requerimirnto
01 requerimirnto
 
Calendario valorizado sistema de recreacion amotape
Calendario valorizado  sistema de recreacion amotapeCalendario valorizado  sistema de recreacion amotape
Calendario valorizado sistema de recreacion amotape
 
main_brochure
main_brochuremain_brochure
main_brochure
 
Avf250 v1.1.8en
Avf250 v1.1.8enAvf250 v1.1.8en
Avf250 v1.1.8en
 
Bang gia thiet_bi_dong_cat_ls
Bang gia thiet_bi_dong_cat_lsBang gia thiet_bi_dong_cat_ls
Bang gia thiet_bi_dong_cat_ls
 
Bang gia mcb_mccb_contactor_acb_hyundai_10-11-2012
Bang gia mcb_mccb_contactor_acb_hyundai_10-11-2012Bang gia mcb_mccb_contactor_acb_hyundai_10-11-2012
Bang gia mcb_mccb_contactor_acb_hyundai_10-11-2012
 
Bang gia bien_tan_mitsubishi_2013
Bang gia bien_tan_mitsubishi_2013Bang gia bien_tan_mitsubishi_2013
Bang gia bien_tan_mitsubishi_2013
 
Boiler ea case study 16 jan 2012 varanasi
Boiler ea case study  16 jan 2012 varanasiBoiler ea case study  16 jan 2012 varanasi
Boiler ea case study 16 jan 2012 varanasi
 
mega-himel-2019-latest
mega-himel-2019-latestmega-himel-2019-latest
mega-himel-2019-latest
 

Cuadro analitico de costoso25

  • 1. MATERIALES MANO DE OBRA PRESTACIONES excavacione de fundaciones m3 17.26 174.72B/. 25.50B/. 200.22B/. 0.27% preparación de ref. fundación ml 359.60 318.00B/. 153.60B/. 79.50B/. 30.50B/. 581.60B/. 0.79% exc. De tubería eléctrica m3 43.68B/. 12.75B/. 56.43B/. 0.08% exc. De tubería sanitaria m3 43.68B/. 12.75B/. 56.43B/. 0.08% colocación de refuerzo de columnas y anclaje ml 63.00 55.65B/. 153.60B/. 13.91B/. 30.50B/. 253.66B/. 0.34% vaciado de concreto fund. m3 4.01 1,572.00B/. 131.04B/. 393.13B/. 33.00B/. 2,129.17B/. 2.89% inst. de tuberías eléctricas ml 120.00B/. 200.00B/. 22.00B/. 342.00B/. 0.46% inst. de tuberías aguas ml 85.00B/. 135.00B/. 15.00B/. 235.00B/. 0.32% vaciado de concreto m3 8.45 1,656.78B/. 146.10B/. 414.20B/. 33.00B/. 2,250.08B/. 3.05% col. De acero de columnas ml 530.00 75.99B/. 153.30B/. 18.99B/. 30.50B/. 278.78B/. 0.38% col. De formaletas m2 41.30 138.00B/. 102.40B/. 34.50B/. 40.30B/. 315.20B/. 0.43% vaciado de concreto para col. m3 3.07 601.33B/. 87.36B/. 150.33B/. 33.00B/. 872.02B/. 1.18% desencofrado m2 41.30 43.68B/. 15.75B/. 59.43B/. 0.08% preparación de ref. vigas ml 844.80 747.30B/. 204.80B/. 186.83B/. 30.50B/. 1,169.43B/. 1.59% col. De formaletas m2 40.59 127.20B/. 204.80B/. 32.00B/. 40.30B/. 404.30B/. 0.55% vaciado de concreto m3 2.93 574.28B/. 146.10B/. 143.57B/. 33.00B/. 896.95B/. 1.22% desencofrado m2 40.59 43.68B/. 15.75B/. 59.43B/. 0.08% col. De formaleta m2 112.64 356.50B/. 51.20B/. 89.13B/. 40.30B/. 537.13B/. 0.73% CUADRO ANALITICO DE COSTOS PRECIOS UNITARIOSPLANTABAJACOLUMNAS VIGASPARA LOSAS SAPARAEL NIVEL100 COSTO % RELATIVO DEL TOTAL ACTIVIDAD UNIDAD CANTIDADITEM EQUIPO Y HERRAMIENTAS PLANTA BAJA NIVEL 000 COLUMNAS PARA LOSA VIGAS PARA LOSA DEL NIVEL 100 LOSA DE SEGUNDO NIVEL 100 FUNDACIONES FUNDACIONES
  • 2. inst. de tuberías eléctricas ml 210.00B/. 206.40B/. 22.00B/. 438.40B/. 0.59% inst. de tuberías aguas ml 132.00B/. 146.88B/. 15.00B/. 293.88B/. 0.40% col. de acero y refuerzos ml 182.85B/. 204.80B/. 45.72B/. 30.50B/. 463.87B/. 0.63% vaciado de concreto m3 25.36 4,970.36B/. 146.10B/. 1,242.50B/. 33.00B/. 6,391.96B/. 8.66% desencofrado ml 112.64 21.84B/. 15.75B/. 37.59B/. 0.05% colocación de acero ml 364.00 181.00B/. 153.60B/. 45.20B/. 30.50B/. 410.30B/. 0.56% colocación de formaleta m2 41.63 138.00B/. 102.40B/. 34.50B/. 40.30B/. 315.20B/. 0.43% vaciado de concreto m3 3.07 601.33B/. 87.36B/. 150.33B/. 33.00B/. 872.02B/. 1.18% desencofrado m2 41.63 43.68B/. 15.75B/. 59.43B/. 0.08% colocación de bloques m2 392.16 3,581.05B/. 1,075.00B/. 895.26B/. 28.80B/. 5,580.11B/. 7.56% col. Columna de amare ml 120.00 62.50B/. 153.60B/. 15.65B/. 30.50B/. 262.25B/. 0.36% col. De formaleta m2 10.42 34.50B/. 102.40B/. 8.63B/. 40.30B/. 185.83B/. 0.25% vaciado de concreto m3 0.80 156.80B/. 73.04B/. 39.20B/. 33.00B/. 302.04B/. 0.41% desencofrado m2 10.42 21.84B/. 15.75B/. 37.59B/. 0.05% colocación de viga de amare ml 253.48 129.63B/. 102.40B/. 32.41B/. 30.50B/. 294.94B/. 0.40% col. De formaleta m2 45.12 149.50B/. 102.40B/. 37.38B/. 40.30B/. 329.58B/. 0.45% vaciado de concreto m3 3.83 750.68B/. 204.80B/. 187.67B/. 33.00B/. 1,176.15B/. 1.59% desencofrado ml 45.12 102.40B/. 15.75B/. 118.15B/. 0.16% repello de paredes m2 784.00 11,760.00B/. 2,150.40B/. 512.00B/. 45.00B/. 14,467.40B/. 19.61% estructura ml 156.40 1,094.80B/. 782.00B/. 108.36B/. 140.00B/. 2,125.16B/. 2.88% colocación de cubierta m2 100.00 1,000.00B/. 700.00B/. 57.28B/. 120.00B/. 1,877.28B/. 2.54% instalación de ventanas 4,000.00B/. 204.80B/. 1,000.00B/. 80.00B/. 5,284.80B/. 7.16% instalación de puertas 3,000.00B/. 204.80B/. 750.00B/. 70.00B/. 4,024.80B/. 5.46% LOSAPARAEL NIVEL100 INSTALACION DE CIELO RASO COLUMNAS PARA TECHO BLOQUEODETODASLAS PAREDES INSTALACION DETECHO PUERTASY VENTANAS COLUMNAS PARA TECHO BLOQUEOS DE TODAS LAS PAREDES INSTALACION DE TECHO INSTALACION DE PUERTAS Y VENTANAS
  • 3. CIELO RASO colocación de cielo m2 124.40 1,990.40B/. 746.40B/. 70.40B/. 70.00B/. 2,877.20B/. 3.90% inst. de piso de todas las áreas m2 135.11 2,026.65B/. 810.7B/. 203.00B/. 33.50B/. 3,073.81B/. 4.17% inst. de paredes de baño y coci. m2 142.21 2,129.60B/. 568.8B/. 533.00B/. 33.50B/. 3,264.94B/. 4.43% sistema eléctrico 1,880.00B/. 950.00B/. 76.50B/. 2,906.50B/. 3.94% base + pintura final 1,800.00B/. 700.00B/. 109.50B/. 23.00B/. 2,632.50B/. 3.57% artefacto sanitario 1,550.00B/. 350.00B/. 35.00B/. 1,935.00B/. 2.62% transportar de caseta temporal 172.00B/. 75.00B/. 247.00B/. 0.33% limpieza de terreno 225.00B/. 150.00B/. 375.00B/. 0.51% inst. eléctrica definitiva 165.00B/. 200.00B/. 365.00B/. 0.49% entrega de llave al dueño 50.00B/. 50.00B/. 0.07% COSTO TOTAL DE LA OBRA 73,772.93B/. 100.00% COSTO TOTAL DE LOS MATERIALES 49,939.68B/. 67.69% COSTO TOTAL DE LA MANO DE OBRA 13,662.58B/. 18.52% COSTO TOTAL DE LAS PRESTACIONES 7,971.07B/. 10.80% COSTO TOTAL DE LOS EQUIPO Y HERRAMIENTAS 2,199.60B/. 2.98% INSTALACION ES DEFINITIVAS REVEST IMIENT OS ACABADOSY DETALLES FINALES COSTOSYPORCENTAJES PORACTIVIDADES REVESTIMIENTOS DE TODAS LAS AREAS INSTALACIONES DEFINITIVAS ACABADOS Y DETALLES FINALES