6 – Sigma Training
Review
Outline
Topic 1 - Six Sigma Overview
Topic 2 – Team process and logistics
Topic 3 – Intro to Project Charter
Topic 4 – Project Charter Continued
Topic 5 – Think Measurement
Topic 6 – Pre-Project Planning - WBS
Topic 7 – Data Analysis
Topic 1 - Six Sigma Overview
What is Six Sigma?
• In statistics, sigma (s) refers to
“standard deviation” which is a
measure of variation.
• You will come to learn that
variation is the enemy of any
quality process.
• We need to understand, manage and
minimize process variation.
• Six Sigma is actually an aspiration
or goal of process performance.
• A Six Sigma process only yields 3.4
defects for every million
opportunities! In other words,
99.9997% of the products are
defect-free!
Six Sigma Levels
Six Sigma Levels
• Higher sigma level means lower defect rate. Let’s take a look at the defect rates of processes at different
sigma levels.
• A 3 Sigma processes has a defect rate of approximately 7%. What would happen if processes operate at
3 sigma?
• Virtually no modern computer would function*.
• 10,800,000 health care claims would be mishandled each year.
• 18,900 US Savings bonds would be lost every month.
• 54,000 checks would be lost each night by a single large bank.
• 4,050 invoices would be sent out incorrectly each month by a modest-sized telecommunications company.
• 540,000 erroneous call details would be recorded each day from a regional telecommunications company.
• 270,000,000 (270 million) erroneous credit card transactions would be recorded each year in the United States.
• Sigma level is the measure - Six is the goal!
Six Sigma - Fundamentally
Fundamentally….
Six Sigma is a set of techniques and tools for process improvement.
Six Sigma seeks to improve the quality of process outputs by
identifying and removing the causes of defects (errors)
Six Sigma tries to focus improvements from a customer’s need
perspective.
Customer is someone, group or process who receives an output.
Customers can be both internal and external.
Six Sigma incorporates measurements (statistics) as a way to both
identify areas to work on and results of improvement efforts.
Six Sigma Approach
Y=f(x) is the relational transfer function that is used by all Six
Sigma practitioners.
Y refers to the measure or output of a
process.
• The “Y” is the measure of process performance that
you're trying to improve.
f(x) means “function of x”.
• x’s are factors or inputs that affect the “Y”
In simple terms: “My process performance is
dependent on certain x’s”.
Y=f(x)Approach
Y=f(x)
X8
X6
X1
X5
X7
X3
X2
D-M-A-I-C
Define
•Define and quantify
the Problem &
Objective
Measure
•Baseline process, validate
measures & Identify all possible x’s
and dependent y’s
Analyze • Analyze & Validate Causes
identifying critical factors
Improve • Develop
Solutions
Control
• Implement &
sustain
solutions
Expectations from You
Develop Skills
• Gain insight into tools and techniques that can help you do your
jobs more effectively.
• Develop a “Problem-Solving” toolbox.
Develop Process and Customer-centric Approach to Problem-
Solving
• Understanding dependencies of tasks and processes
• Solving the Customer’s problem completely
• Use a consistent and disciplined approach on projects
Work more collaboratively
• Work with each other, both internal to TS and the rest of the
College, solving complex, cross-functional issues.
VOC – Review
• VOC stands for Voice of the Customer.
• The 4 primary forms are...
• VOC: Voice of the Customer
• VOB: Voice of the Business
• VOA: Voice of the Associate
• VOP: Voice of the Process
• VOC is gathered via
• Direct Methods
• Indirect Methods
• Discussion point
• How did you gather your Pain point?
D-M-A-I-C
Define
• Define and quantify
the Problem &
Objective
Measure
• Baseline process, validate
measures & Identify all possible
x’s and dependent y’s
Analyze • Analyze & Validate Causes
identifying critical factors
Improve • Develop
Solutions
Control
• Implement &
sustain
solutions
Lets spend the day here
- Define f(x)’s
- Affinity modeling
- Process mapping
• P4ME – Affinity Categories
• People: People who are involved in the process;
• Methods: How the process is completed (e.g.
procedures, policies, regulations, laws);
• Machines: Equipment or tools needed to perform
the process;
• Materials: Raw materials or information needed
to do the job;
• Measurements: Data collected from the process
for inspection or evaluation;
• Environment: Surroundings of the process (e.g.
location, time, culture)
P4MEAffinity Model
Y=f(x)
M
E
MM
P
M
Team Identification
• Self-awareness is key
• Understanding yourself helps you explain who you are and how you
work
• Key to comprehending team dynamics
• Understanding your team members helps you better interact with them
and understand their motivations, perspective, needs and wants
• Personality is only one basis of guiding interaction, not the only basis
• No one is black or white – everyone is nuanced
• Practical applications for forming teams
Project Charter
The purpose of the project charter is to get the project approved
Secure a Sponsor
High level timeline agreement
ROI agreement
High level deliverable agreement
Setting expectations
Lets Spend 20 Minutes putting a first draft of our charters
together
See template
Pareto Principle
• The Pareto Principle is commonly known as the “law of the vital few” or
“80:20 rule”.
• It means that the majority (approximately 80%) of effects come from a few
(approximately 20%) of the causes.
• Example of applying Pareto Principle:
• 80% of the defects of a process come from 20% of the causes.
• 80% of sales come from 20% of customers.
• Since this 80:20 rule was originally based upon the works of Wilfried Fritz
Pareto (aka. Vilfredo Pareto), the Pareto principle and references to it should
be capitalized because Pareto refers to a person (proper noun).
• Mr. Pareto is also credited for many works associated with the 80:20 some more loosely
than others:
• Pareto’s Law
• Pareto efficiency
• Pareto distribution etc.
What is FMEA?
• FMEA (Failure Modes & Effects Analysis) is an
analysis technique to identify, evaluate and prioritize a
potential deficiency in a process so that the project
team can design action plans to reduce the probability
of the failure/deficiency occurring.
• FMEA activity follows the process mapping and is
followed by a Pareto Analysis.
• FMEA is completed in cross-functional brainstorming
sessions in which attendees have a good understanding
of the entire process or a segment of it.
• There are seven (7) common forms of waste that are often
referred to as the Seven Deadly Muda.
• Technically there are more than seven forms of waste but if
you can remember these seven you'll capture 90+% of your
waste.
1. Defects
2. Over Production
3. Over Processing
4. Inventory
5. Motion
6. Transportation
7. Waiting
Cost of Poor Quality
Six Sigma Metrics
• There are many Six Sigma metrics and/or measures of
performance used by Six Sigma practitioners.
• In addition to the ones we’ll cover here, several others
(Sigma level, Cp, Cpk, Pp, Ppk, takt time, cycle time, utilization etc.)
will be covered in other modules throughout this
training.
• The Six Sigma metrics of interest here in the Define
Phase are:
• Defects per Unit (DPU)
• Defects per Million Opportunities (DPMO)
• Yield (Y)
• Rolled Throughput Yield (RTY)
What is SIPOC?
• SIPOC (Suppliers-Input-Process-Output-Customers) is a
high-level visualization tool to help identify and link
the different components in the process.
• It is usually applied in the Measure phase in order to
better understand the current state of the process and
define the scope of the project.
Activities
 Element of project work that requires an action to produce a deliverable.
 Have an expected duration.
 Consume budget and/or human resources.
 Are named in verb-noun format.
Example: Activities in a company project.
 Revise user manual.
 Make a sales presentation.
 Reserve conference room.
Verb (Action) Noun (Deliverable)
Revise user manual
Expected duration determined by (whatever)
Work Package
 Planned work or deliverables.
 Lowest-level component of the work breakdown structure.
 Cost and schedule can be easily estimated.
A work breakdown structure showing the work packages
The 8/80 Rule
 A general guideline regarding work packages: they require more
than 8, but fewer than 80, hours of effort to complete.
 Helps project managers create work package lists.
The Sequence Activities Process
 A planning process that involves identifying and documenting interactivity
dependencies among project activities for the purpose of creating the
project schedule.
Types of Activity Dependencies
Dependency Description
Mandatory Inherent to the work itself and are usually affected by physical constraints.
Discretionary Defined by the project and project management team at their discretion.
External Contingent on inputs from outside the project activities.
Precedence Relationship Types
Relationship Description
Finish-to-Start (FS) Activity A must finish before activity B can start.
Finish-to-Finish (FF) Activity A must finish before activity B can finish.
Start-to-Start (SS) Activity A must start before activity B can start.
Start-to-Finish (SF) Activity A must start before activity B can finish.
The Critical Path
 Path with the longest total duration.
 Has no scheduling flexibility.
1[6W] + 2[4W] + 4[3w] + 6[1W] = 14 Weeks
1[6W] + 3[5W] + 5[4w] + 6[1W] = 16 Weeks Critical Path
A network diagram showing the critical path of activities
Schedule Compression
• The shortening of the project schedule without affecting the
project scope.
• Two methods:
• Fast-tracking
• Crashing
Example: Schedule compression for building and installing
cabinets.
• Involves carpenter and sub-contractor.
• Sub-contractor installs cabinets while carpenter builds.
• Changes precedence.
How do you collect and analyze
data?
1. Implement the observational system you’ve planned.
2. Organize the data you’ve collected.
3. Conduct data graphing, visual inspection, statistical
analysis, or other operations on the data as appropriate.
4. Take note of any significant or interesting results.
5. Interpret the results.
What is Sampling
• Sampling is the process of selecting objects or
observations from a population of interest about
which we wish to make statistical inference.
• It is extensively used to collect information about a
population which can be physical or intangible objects.
SamplingPopulation Sample
Basic Sampling Steps
• Determine the population of interest
• Determine the sampling frame
• Determine the sampling strategy
• Calculate the sample size
• Conduct sampling
What is SPC
• Statistical process control (SPC) is a statistical method
to monitor the performance of a process using control
charts in order to keep the process in statistical
control.
• Statistical process control can be used to distinguish
between the special cause variation and the common
cause variation in the process.
• It presents the voice of the process.
What is MeasurementSystemAnalysis
• Measurement System Analysis (MSA) is a systematic
method to identify and analyze the variation
components in the measurement.
• It is a mandatory step in Six Sigma project to ensure
the data are reliable and trustworthy before making
any data-based decisions.
• It is the check point of data quality before we start any
further analysis and draw any conclusions from the
data.
Accuracy vs. Precision
• Accuracy
• The level of closeness between the average observed value and
the true value
• How well the observed value reflects the true value
• Precision
• The spread of measurement values
• How consistent the repeated measurements deliver the same
values under the same circumstances

Contenu connexe

Tendances

Six Sigma By :Rajeev
Six Sigma By :RajeevSix Sigma By :Rajeev
Six Sigma By :Rajeevrajeev
 
Six sigma an overview | Online Mini MBA (Free)
Six sigma  an overview | Online Mini MBA (Free)Six sigma  an overview | Online Mini MBA (Free)
Six sigma an overview | Online Mini MBA (Free)mybskool-online-courses
 
Lean Six Sigma Awareness Handouts
Lean Six Sigma Awareness HandoutsLean Six Sigma Awareness Handouts
Lean Six Sigma Awareness Handoutsguest0981f4
 
Lean Six Sigma Leadership 062507
Lean Six Sigma Leadership 062507Lean Six Sigma Leadership 062507
Lean Six Sigma Leadership 062507larrypenni
 
DMAIC-Six sigma process Improvement Approach
DMAIC-Six sigma process Improvement ApproachDMAIC-Six sigma process Improvement Approach
DMAIC-Six sigma process Improvement ApproachConfiz
 
Lean Six Sigma Yellow Belt Certification Brochure
Lean Six Sigma Yellow Belt Certification BrochureLean Six Sigma Yellow Belt Certification Brochure
Lean Six Sigma Yellow Belt Certification BrochurePartner
 
6 SIGMA AND KAIZEN
6 SIGMA AND KAIZEN6 SIGMA AND KAIZEN
6 SIGMA AND KAIZENRameshkori31
 
Lean Six Sigma 101
Lean Six Sigma 101Lean Six Sigma 101
Lean Six Sigma 101shailsood
 
Lean six sigma Yellow Belt Complete training
Lean six sigma Yellow Belt Complete trainingLean six sigma Yellow Belt Complete training
Lean six sigma Yellow Belt Complete trainingAnkit Sharma
 
Introduction to Six Sigma (Basic)
Introduction to Six Sigma (Basic)Introduction to Six Sigma (Basic)
Introduction to Six Sigma (Basic)Narendra Narendra
 
Measure phase lean six sigma tollgate template
Measure phase   lean six sigma tollgate templateMeasure phase   lean six sigma tollgate template
Measure phase lean six sigma tollgate templateSteven Bonacorsi
 
Six sigma - learn 6 sigma steps
Six sigma - learn 6 sigma stepsSix sigma - learn 6 sigma steps
Six sigma - learn 6 sigma stepsAleksey Savkin
 
Lean Six Sigma - Introduction
Lean Six Sigma - IntroductionLean Six Sigma - Introduction
Lean Six Sigma - Introductionvivek pandey
 
Lean six sigma (green belt)new
Lean six sigma (green belt)newLean six sigma (green belt)new
Lean six sigma (green belt)newHakeem-Ur- Rehman
 

Tendances (20)

Six Sigma By :Rajeev
Six Sigma By :RajeevSix Sigma By :Rajeev
Six Sigma By :Rajeev
 
Dmaic
DmaicDmaic
Dmaic
 
Six sigma an overview | Online Mini MBA (Free)
Six sigma  an overview | Online Mini MBA (Free)Six sigma  an overview | Online Mini MBA (Free)
Six sigma an overview | Online Mini MBA (Free)
 
Lean Six Sigma Awareness Handouts
Lean Six Sigma Awareness HandoutsLean Six Sigma Awareness Handouts
Lean Six Sigma Awareness Handouts
 
Lean Six Sigma Leadership 062507
Lean Six Sigma Leadership 062507Lean Six Sigma Leadership 062507
Lean Six Sigma Leadership 062507
 
yellow belt training
yellow belt trainingyellow belt training
yellow belt training
 
DMAIC-Six sigma process Improvement Approach
DMAIC-Six sigma process Improvement ApproachDMAIC-Six sigma process Improvement Approach
DMAIC-Six sigma process Improvement Approach
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Lean Six Sigma Yellow Belt Certification Brochure
Lean Six Sigma Yellow Belt Certification BrochureLean Six Sigma Yellow Belt Certification Brochure
Lean Six Sigma Yellow Belt Certification Brochure
 
6 SIGMA AND KAIZEN
6 SIGMA AND KAIZEN6 SIGMA AND KAIZEN
6 SIGMA AND KAIZEN
 
Lean Six Sigma 101
Lean Six Sigma 101Lean Six Sigma 101
Lean Six Sigma 101
 
Lean six sigma Yellow Belt Complete training
Lean six sigma Yellow Belt Complete trainingLean six sigma Yellow Belt Complete training
Lean six sigma Yellow Belt Complete training
 
Introduction to Six Sigma (Basic)
Introduction to Six Sigma (Basic)Introduction to Six Sigma (Basic)
Introduction to Six Sigma (Basic)
 
Measure phase lean six sigma tollgate template
Measure phase   lean six sigma tollgate templateMeasure phase   lean six sigma tollgate template
Measure phase lean six sigma tollgate template
 
Six sigma - learn 6 sigma steps
Six sigma - learn 6 sigma stepsSix sigma - learn 6 sigma steps
Six sigma - learn 6 sigma steps
 
Six Sigma Sample Project
Six Sigma Sample ProjectSix Sigma Sample Project
Six Sigma Sample Project
 
Lean Six Sigma - Introduction
Lean Six Sigma - IntroductionLean Six Sigma - Introduction
Lean Six Sigma - Introduction
 
Lean six sigma (green belt)new
Lean six sigma (green belt)newLean six sigma (green belt)new
Lean six sigma (green belt)new
 
Six Sigma Yellow Belt
Six Sigma Yellow BeltSix Sigma Yellow Belt
Six Sigma Yellow Belt
 
Green Belt Training
Green Belt TrainingGreen Belt Training
Green Belt Training
 

Similaire à Kabir Kassam: 6 – sigma training - Midterm Review

Introduction to Six Sigma.pptx
Introduction to Six Sigma.pptxIntroduction to Six Sigma.pptx
Introduction to Six Sigma.pptxAshweeniTiwari
 
Lean Six Sigma- Internal Training Slides-2.pptx
Lean Six Sigma- Internal Training Slides-2.pptxLean Six Sigma- Internal Training Slides-2.pptx
Lean Six Sigma- Internal Training Slides-2.pptxDebashishDolon
 
Lean Six Sigma - Concept & Application
Lean Six Sigma - Concept & ApplicationLean Six Sigma - Concept & Application
Lean Six Sigma - Concept & ApplicationHusnain Shahid
 
Lean Six Sigma Overview (presentation version)
Lean Six Sigma Overview (presentation version)Lean Six Sigma Overview (presentation version)
Lean Six Sigma Overview (presentation version)Corey Campbell
 
Transactional Blackbelts are different
Transactional Blackbelts are differentTransactional Blackbelts are different
Transactional Blackbelts are differentreachab7
 
Yellow belt training 68 s
Yellow belt training 68 sYellow belt training 68 s
Yellow belt training 68 sRachit Gaur
 
Ppt total quality management
Ppt total quality managementPpt total quality management
Ppt total quality managementAnitha Velusamy
 
Business process mapping
Business process mappingBusiness process mapping
Business process mappingDAVIS THOMAS
 
Basic overview six sigma
Basic overview six sigmaBasic overview six sigma
Basic overview six sigmaKhushmeetKhushi
 
six sigma - Himani Panwar
six sigma - Himani Panwarsix sigma - Himani Panwar
six sigma - Himani PanwarHimani Panwar
 
Lean Six Sigma Overview (print version)
Lean Six Sigma Overview (print version)Lean Six Sigma Overview (print version)
Lean Six Sigma Overview (print version)Corey Campbell
 
Basic Six Sigma Presentation
Basic Six Sigma PresentationBasic Six Sigma Presentation
Basic Six Sigma Presentationvivekissar
 
Operational Excellence – Getting Started
Operational Excellence – Getting StartedOperational Excellence – Getting Started
Operational Excellence – Getting StartedRonald Shewchuk
 

Similaire à Kabir Kassam: 6 – sigma training - Midterm Review (20)

Introduction to Six Sigma.pptx
Introduction to Six Sigma.pptxIntroduction to Six Sigma.pptx
Introduction to Six Sigma.pptx
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Lean Six Sigma- Internal Training Slides-2.pptx
Lean Six Sigma- Internal Training Slides-2.pptxLean Six Sigma- Internal Training Slides-2.pptx
Lean Six Sigma- Internal Training Slides-2.pptx
 
Lean Six Sigma - Concept & Application
Lean Six Sigma - Concept & ApplicationLean Six Sigma - Concept & Application
Lean Six Sigma - Concept & Application
 
Session 5
Session 5Session 5
Session 5
 
Six sigma
Six sigma Six sigma
Six sigma
 
CPI Training overview
CPI Training overviewCPI Training overview
CPI Training overview
 
Six sigma introduction
Six sigma introductionSix sigma introduction
Six sigma introduction
 
Lean Six Sigma Overview (presentation version)
Lean Six Sigma Overview (presentation version)Lean Six Sigma Overview (presentation version)
Lean Six Sigma Overview (presentation version)
 
Transactional Blackbelts are different
Transactional Blackbelts are differentTransactional Blackbelts are different
Transactional Blackbelts are different
 
Yellow belt training 68 s
Yellow belt training 68 sYellow belt training 68 s
Yellow belt training 68 s
 
Ppt total quality management
Ppt total quality managementPpt total quality management
Ppt total quality management
 
Business process mapping
Business process mappingBusiness process mapping
Business process mapping
 
Basic overview six sigma
Basic overview six sigmaBasic overview six sigma
Basic overview six sigma
 
six sigma - Himani Panwar
six sigma - Himani Panwarsix sigma - Himani Panwar
six sigma - Himani Panwar
 
Lean Six Sigma Overview (print version)
Lean Six Sigma Overview (print version)Lean Six Sigma Overview (print version)
Lean Six Sigma Overview (print version)
 
Basic Six Sigma Presentation
Basic Six Sigma PresentationBasic Six Sigma Presentation
Basic Six Sigma Presentation
 
6 sigma
6 sigma6 sigma
6 sigma
 
Operational Excellence – Getting Started
Operational Excellence – Getting StartedOperational Excellence – Getting Started
Operational Excellence – Getting Started
 
Six sigma
Six sigma Six sigma
Six sigma
 

Plus de Kabir Kassam

How to Boost Employee Morale
How to Boost Employee MoraleHow to Boost Employee Morale
How to Boost Employee MoraleKabir Kassam
 
5 Keys Tips For a Haalthy Work Enviorment - Kabir Kassam
5 Keys Tips For a Haalthy Work Enviorment - Kabir Kassam5 Keys Tips For a Haalthy Work Enviorment - Kabir Kassam
5 Keys Tips For a Haalthy Work Enviorment - Kabir KassamKabir Kassam
 
Ernie Banks: One of the Greats
Ernie Banks: One of the GreatsErnie Banks: One of the Greats
Ernie Banks: One of the GreatsKabir Kassam
 
Chicago Bulls Mid-Season Report
Chicago Bulls Mid-Season ReportChicago Bulls Mid-Season Report
Chicago Bulls Mid-Season ReportKabir Kassam
 
This Thanksgiving, Give Back!
This Thanksgiving, Give Back!This Thanksgiving, Give Back!
This Thanksgiving, Give Back!Kabir Kassam
 
Kabir Kassam Six Sigma Lesson 2
Kabir Kassam Six Sigma Lesson 2Kabir Kassam Six Sigma Lesson 2
Kabir Kassam Six Sigma Lesson 2Kabir Kassam
 
Kabir Kassam Six Sigma Lesson 1
Kabir Kassam Six Sigma Lesson 1Kabir Kassam Six Sigma Lesson 1
Kabir Kassam Six Sigma Lesson 1Kabir Kassam
 

Plus de Kabir Kassam (7)

How to Boost Employee Morale
How to Boost Employee MoraleHow to Boost Employee Morale
How to Boost Employee Morale
 
5 Keys Tips For a Haalthy Work Enviorment - Kabir Kassam
5 Keys Tips For a Haalthy Work Enviorment - Kabir Kassam5 Keys Tips For a Haalthy Work Enviorment - Kabir Kassam
5 Keys Tips For a Haalthy Work Enviorment - Kabir Kassam
 
Ernie Banks: One of the Greats
Ernie Banks: One of the GreatsErnie Banks: One of the Greats
Ernie Banks: One of the Greats
 
Chicago Bulls Mid-Season Report
Chicago Bulls Mid-Season ReportChicago Bulls Mid-Season Report
Chicago Bulls Mid-Season Report
 
This Thanksgiving, Give Back!
This Thanksgiving, Give Back!This Thanksgiving, Give Back!
This Thanksgiving, Give Back!
 
Kabir Kassam Six Sigma Lesson 2
Kabir Kassam Six Sigma Lesson 2Kabir Kassam Six Sigma Lesson 2
Kabir Kassam Six Sigma Lesson 2
 
Kabir Kassam Six Sigma Lesson 1
Kabir Kassam Six Sigma Lesson 1Kabir Kassam Six Sigma Lesson 1
Kabir Kassam Six Sigma Lesson 1
 

Dernier

ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
Food processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsFood processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsManeerUddin
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationRosabel UA
 

Dernier (20)

ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
Food processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsFood processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture hons
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translation
 

Kabir Kassam: 6 – sigma training - Midterm Review

  • 1. 6 – Sigma Training Review
  • 2. Outline Topic 1 - Six Sigma Overview Topic 2 – Team process and logistics Topic 3 – Intro to Project Charter Topic 4 – Project Charter Continued Topic 5 – Think Measurement Topic 6 – Pre-Project Planning - WBS Topic 7 – Data Analysis
  • 3. Topic 1 - Six Sigma Overview What is Six Sigma? • In statistics, sigma (s) refers to “standard deviation” which is a measure of variation. • You will come to learn that variation is the enemy of any quality process. • We need to understand, manage and minimize process variation. • Six Sigma is actually an aspiration or goal of process performance. • A Six Sigma process only yields 3.4 defects for every million opportunities! In other words, 99.9997% of the products are defect-free!
  • 4. Six Sigma Levels Six Sigma Levels • Higher sigma level means lower defect rate. Let’s take a look at the defect rates of processes at different sigma levels. • A 3 Sigma processes has a defect rate of approximately 7%. What would happen if processes operate at 3 sigma? • Virtually no modern computer would function*. • 10,800,000 health care claims would be mishandled each year. • 18,900 US Savings bonds would be lost every month. • 54,000 checks would be lost each night by a single large bank. • 4,050 invoices would be sent out incorrectly each month by a modest-sized telecommunications company. • 540,000 erroneous call details would be recorded each day from a regional telecommunications company. • 270,000,000 (270 million) erroneous credit card transactions would be recorded each year in the United States. • Sigma level is the measure - Six is the goal!
  • 5. Six Sigma - Fundamentally Fundamentally…. Six Sigma is a set of techniques and tools for process improvement. Six Sigma seeks to improve the quality of process outputs by identifying and removing the causes of defects (errors) Six Sigma tries to focus improvements from a customer’s need perspective. Customer is someone, group or process who receives an output. Customers can be both internal and external. Six Sigma incorporates measurements (statistics) as a way to both identify areas to work on and results of improvement efforts.
  • 6. Six Sigma Approach Y=f(x) is the relational transfer function that is used by all Six Sigma practitioners. Y refers to the measure or output of a process. • The “Y” is the measure of process performance that you're trying to improve. f(x) means “function of x”. • x’s are factors or inputs that affect the “Y” In simple terms: “My process performance is dependent on certain x’s”. Y=f(x)Approach Y=f(x) X8 X6 X1 X5 X7 X3 X2
  • 7. D-M-A-I-C Define •Define and quantify the Problem & Objective Measure •Baseline process, validate measures & Identify all possible x’s and dependent y’s Analyze • Analyze & Validate Causes identifying critical factors Improve • Develop Solutions Control • Implement & sustain solutions
  • 8. Expectations from You Develop Skills • Gain insight into tools and techniques that can help you do your jobs more effectively. • Develop a “Problem-Solving” toolbox. Develop Process and Customer-centric Approach to Problem- Solving • Understanding dependencies of tasks and processes • Solving the Customer’s problem completely • Use a consistent and disciplined approach on projects Work more collaboratively • Work with each other, both internal to TS and the rest of the College, solving complex, cross-functional issues.
  • 9. VOC – Review • VOC stands for Voice of the Customer. • The 4 primary forms are... • VOC: Voice of the Customer • VOB: Voice of the Business • VOA: Voice of the Associate • VOP: Voice of the Process • VOC is gathered via • Direct Methods • Indirect Methods • Discussion point • How did you gather your Pain point?
  • 10. D-M-A-I-C Define • Define and quantify the Problem & Objective Measure • Baseline process, validate measures & Identify all possible x’s and dependent y’s Analyze • Analyze & Validate Causes identifying critical factors Improve • Develop Solutions Control • Implement & sustain solutions Lets spend the day here - Define f(x)’s - Affinity modeling - Process mapping
  • 11. • P4ME – Affinity Categories • People: People who are involved in the process; • Methods: How the process is completed (e.g. procedures, policies, regulations, laws); • Machines: Equipment or tools needed to perform the process; • Materials: Raw materials or information needed to do the job; • Measurements: Data collected from the process for inspection or evaluation; • Environment: Surroundings of the process (e.g. location, time, culture) P4MEAffinity Model Y=f(x) M E MM P M
  • 12. Team Identification • Self-awareness is key • Understanding yourself helps you explain who you are and how you work • Key to comprehending team dynamics • Understanding your team members helps you better interact with them and understand their motivations, perspective, needs and wants • Personality is only one basis of guiding interaction, not the only basis • No one is black or white – everyone is nuanced • Practical applications for forming teams
  • 13. Project Charter The purpose of the project charter is to get the project approved Secure a Sponsor High level timeline agreement ROI agreement High level deliverable agreement Setting expectations Lets Spend 20 Minutes putting a first draft of our charters together See template
  • 14. Pareto Principle • The Pareto Principle is commonly known as the “law of the vital few” or “80:20 rule”. • It means that the majority (approximately 80%) of effects come from a few (approximately 20%) of the causes. • Example of applying Pareto Principle: • 80% of the defects of a process come from 20% of the causes. • 80% of sales come from 20% of customers. • Since this 80:20 rule was originally based upon the works of Wilfried Fritz Pareto (aka. Vilfredo Pareto), the Pareto principle and references to it should be capitalized because Pareto refers to a person (proper noun). • Mr. Pareto is also credited for many works associated with the 80:20 some more loosely than others: • Pareto’s Law • Pareto efficiency • Pareto distribution etc.
  • 15. What is FMEA? • FMEA (Failure Modes & Effects Analysis) is an analysis technique to identify, evaluate and prioritize a potential deficiency in a process so that the project team can design action plans to reduce the probability of the failure/deficiency occurring. • FMEA activity follows the process mapping and is followed by a Pareto Analysis. • FMEA is completed in cross-functional brainstorming sessions in which attendees have a good understanding of the entire process or a segment of it.
  • 16. • There are seven (7) common forms of waste that are often referred to as the Seven Deadly Muda. • Technically there are more than seven forms of waste but if you can remember these seven you'll capture 90+% of your waste. 1. Defects 2. Over Production 3. Over Processing 4. Inventory 5. Motion 6. Transportation 7. Waiting Cost of Poor Quality
  • 17. Six Sigma Metrics • There are many Six Sigma metrics and/or measures of performance used by Six Sigma practitioners. • In addition to the ones we’ll cover here, several others (Sigma level, Cp, Cpk, Pp, Ppk, takt time, cycle time, utilization etc.) will be covered in other modules throughout this training. • The Six Sigma metrics of interest here in the Define Phase are: • Defects per Unit (DPU) • Defects per Million Opportunities (DPMO) • Yield (Y) • Rolled Throughput Yield (RTY)
  • 18. What is SIPOC? • SIPOC (Suppliers-Input-Process-Output-Customers) is a high-level visualization tool to help identify and link the different components in the process. • It is usually applied in the Measure phase in order to better understand the current state of the process and define the scope of the project.
  • 19. Activities  Element of project work that requires an action to produce a deliverable.  Have an expected duration.  Consume budget and/or human resources.  Are named in verb-noun format. Example: Activities in a company project.  Revise user manual.  Make a sales presentation.  Reserve conference room. Verb (Action) Noun (Deliverable) Revise user manual Expected duration determined by (whatever)
  • 20. Work Package  Planned work or deliverables.  Lowest-level component of the work breakdown structure.  Cost and schedule can be easily estimated. A work breakdown structure showing the work packages
  • 21. The 8/80 Rule  A general guideline regarding work packages: they require more than 8, but fewer than 80, hours of effort to complete.  Helps project managers create work package lists.
  • 22. The Sequence Activities Process  A planning process that involves identifying and documenting interactivity dependencies among project activities for the purpose of creating the project schedule.
  • 23. Types of Activity Dependencies Dependency Description Mandatory Inherent to the work itself and are usually affected by physical constraints. Discretionary Defined by the project and project management team at their discretion. External Contingent on inputs from outside the project activities.
  • 24. Precedence Relationship Types Relationship Description Finish-to-Start (FS) Activity A must finish before activity B can start. Finish-to-Finish (FF) Activity A must finish before activity B can finish. Start-to-Start (SS) Activity A must start before activity B can start. Start-to-Finish (SF) Activity A must start before activity B can finish.
  • 25. The Critical Path  Path with the longest total duration.  Has no scheduling flexibility. 1[6W] + 2[4W] + 4[3w] + 6[1W] = 14 Weeks 1[6W] + 3[5W] + 5[4w] + 6[1W] = 16 Weeks Critical Path A network diagram showing the critical path of activities
  • 26. Schedule Compression • The shortening of the project schedule without affecting the project scope. • Two methods: • Fast-tracking • Crashing Example: Schedule compression for building and installing cabinets. • Involves carpenter and sub-contractor. • Sub-contractor installs cabinets while carpenter builds. • Changes precedence.
  • 27. How do you collect and analyze data? 1. Implement the observational system you’ve planned. 2. Organize the data you’ve collected. 3. Conduct data graphing, visual inspection, statistical analysis, or other operations on the data as appropriate. 4. Take note of any significant or interesting results. 5. Interpret the results.
  • 28. What is Sampling • Sampling is the process of selecting objects or observations from a population of interest about which we wish to make statistical inference. • It is extensively used to collect information about a population which can be physical or intangible objects. SamplingPopulation Sample
  • 29. Basic Sampling Steps • Determine the population of interest • Determine the sampling frame • Determine the sampling strategy • Calculate the sample size • Conduct sampling
  • 30. What is SPC • Statistical process control (SPC) is a statistical method to monitor the performance of a process using control charts in order to keep the process in statistical control. • Statistical process control can be used to distinguish between the special cause variation and the common cause variation in the process. • It presents the voice of the process.
  • 31. What is MeasurementSystemAnalysis • Measurement System Analysis (MSA) is a systematic method to identify and analyze the variation components in the measurement. • It is a mandatory step in Six Sigma project to ensure the data are reliable and trustworthy before making any data-based decisions. • It is the check point of data quality before we start any further analysis and draw any conclusions from the data.
  • 32. Accuracy vs. Precision • Accuracy • The level of closeness between the average observed value and the true value • How well the observed value reflects the true value • Precision • The spread of measurement values • How consistent the repeated measurements deliver the same values under the same circumstances