2. Ground Investigation for
Tunnelling Projects
Topics to be discussed
• Objective
• During Project Planning and
Feasibility Study Stages
• During Design Stage
• During Construction
• Strategy and Techniques of GI
3. Objectives of GI Planning
(a) Suitability To assess the general suitability of the site
(b) Design To enable an adequate and economic design.
(c) Construction
(i) To plan the best method of construction;
(ii) To foresee and provide against difficulties
and delays that may arise during
construction; and
(iii) To explore sources of indigenous
materials for use in construction.
(d) Effect of Change
To determine the changes that may arise in the
ground and environmental conditions.
12. GI Planning
Fookes’ (1997) study indicated:
• ~50% of the anticipated geological model
from desk study.
• ~65% of the geology should be know if a
walkover survey is added to the desk
study.
• 95% if comprehensive GI works to be
done.
14. US National Committee on Tunnelling
Technology (1984) suggested:
• 1.5 linear metre of borehole per route
metre tunnel alignment, and
• 3% of cost of tunnelling civil works for
ground investigation.
15. GI Planning During Project Planning and
Feasibility Study Stages
Key Issue
• to provide sufficient data for the evaluation
of alternative tunnel routes & portals &
shafts locations
• to assess the technical feasibility and
economic viability of the project
• initial cost and construction programme
estimates
16. GI Planning During Project Planning and
Feasibility Study Stages
Methodology:
• Carry out desk study (including site
reconnaissance by walkover surveys &
mapping, collecting background GI
information, and aerial photograph
interpretation).
• where practicable, very limited ground
investigation works should be carried out.
18. GI Planning During Detail Design Stage
Objective:
• Finalising the tunnel alignment;
• Establishing the potential tunnel influence zone
for identification of sensitive ground and facilities
• Improving the cost and construction programme
estimates
• Preparation of Geotechnical Baseline Report for
construction reference (to allow equitable risk
sharing for difficult and unexpected ground
conditions between the contractor and the
employer)
19. GI Planning During Construction Stage
Objective:
• Provide information to determine possible
variations and potential impacts on cost and
construction programme as early as possible.
• Provide data to assess the impacts caused by
the tunnelling, ground supports and risk
mitigation works designed and implemented by
the Contractor, and to review the long-term
performance of the tunnel.
20. GI Works in Construction Stage
Techniques:
• Conventional GI Practices
• Continuous probe drilling ahead
• Geophysical survey to tunnel face and
sidewall (e.g. Seismic Reflective Image)
26. Strategy and Techniques of GI for
Tunnel Projects
Tunnel Projects involved in:
• Soft Ground
• Hard Rock
• Karst Deposits
• Contaminated Land
Including Marine / River
Crossing Tunnels
45. GI Works in Karst Deposits
Deep Tunnel
DH
at least 1D
20m continuous fresh
rock recovered
DH
Drillhole spacing should
be 5m to 25m or closer
Cut & Cover Tunnel
Diaphragm wall
Founding level
problem
46. GI Guidelines in Karst Deposits
Typical Properties to be Determined
49. Appropriate GI Methods – Tunnelling in
Contaminated Land
Three matrices may need to be sampled:
• Soil
• Water
• Gas
50. Relevant Standards
• AS 4482.1–2005 : Guide to the investigation
and sampling of sites with potentially
contaminated soil, Part 1: Non-volatile and
semi-volatile compounds.
• AS 4482.2–1999 : Guide to the investigation
and sampling of sites with potentially
contaminated soil, Part 2: Volatile
substances.
• BS 10175: 2001 : Investigation of
Contaminated Sites – Code of Practice.
51. Type of Investigations
Indirect
• Geophysical
• Cone Penetration Test
• Gas Bar Probe Surveys
• Radioactive Surveys
Direct
• Drillholes and Trial Pits
• Samplings & Insitu Testing
• Monitoring Installations
52. Geophysical Surveys
(Contrasts of soil physio-chemical properties)
• Apparent Conductivity Anomalies -
differing soil types
• True Resistivity/Conductivity Surveys –
plumes
• Magnetic Field Intensity -
concentrations of heavy metals
53. Cone Penetration Test (1)
Laser Induced Flourescence
Cone (LIF)
• Standard CPT cone with a
laser light source to detect
the range of contaminants
• Laser energy [or Ultra-Violet
Optical Screening Tool
(UVOST)] results in the
compounds flourescing
which is then collected by a
fibre optic cable and
returned to a detector in the
CPT truck
54. Cone Penetration Test (2)
Membrane Interface Probe
(MIP)
• Heated membrane allows
organic hydrocarbons in the
gas phase to cross into a
sampling chamber where
they are driven by an inert
Netgeonge gas flow into a
detector
Detects:
BTEX/ PAH/ CH4/ PCB’s
55. Avoid Cross Contamination
• Plant/ equipments servicing before mobilising
to site
• Do not use GI drill rigs unless modified
– use of vegetable based greases and oils
• Steam Clean equipment and sterilise
– before investigation & between drillholes
– between sampling depths
– sampling and sub-sampling equipment
• Dry drilling as far as possible
57. Sampling
• Containers: jars, bags, glass bottles, gresham tubes
• Preservatives where necessary to fix degradable
compounds
• Cleanliness: avoid cross contamination by standardised
cleaning procedures
• Storage samples appropriately on site - in the dark at
4 °C
• Follow a strict “Chain-of-Custody” (i.e. a form contained
sample info) from site to the laboratory
60. Site Supervision
To obtain the greatest benefit from a
ground investigation, it is essential that
there is adequate direction and
supervision of the works by competent
personnel who have appropriate
knowledge and experience and the
authority to decide on variations to
the ground investigation when required.