overhead   23/11/04   2:28 PM   Page 1




                 AVOIDANCE OF
              ELECTRICAL HAZARDS
                WHEN WORKING
                NEAR OVERHEAD
                 ELECTRIC LINES




                                         ESB Code 9803203
overhead   23/11/04   2:28 PM   Page 2
overhead    23/11/04   2:28 PM   Page 3




                                                     Page 1 of 20




                          AVOIDANCE OF
                       ELECTRICAL HAZARDS
                         WHEN WORKING
                         NEAR OVERHEAD
                          ELECTRIC LINES

           Issued by:              ESB Networks
           Document Reference:     DTIS 191203-BOI
           Stores Code:            9803203
           Issue Date:             January 2004
           Review Cycle:           3
           Version:                Revision 2
overhead   23/11/04   2:28 PM   Page 4




                                                                            Page 2 of 20




             Additional copies available from your local ESB Networks Area office
overhead    23/11/04      2:28 PM   Page 5




                                                                              Page 3 of 20




           Contents

           Introduction                                                         5

           Statutory Regulations                                                5

           Consultation                                                         6

           Switchout of Overhead Lines                                          7

           Diversion of Overhead Lines                                          7

           Working in Proximity of Overhead Lines                               8

           Sites where there will be no work or passage of plant                8
           under a Live Overhead Line (all work outside the ‘at risk zone’)

           Sites where plant will pass under a live Overhead Line              10

           Sites where work will be done within the ‘at risk zone’
           of an Overhead Line                                                 11

           Maintenance of barriers and warning notices                         11

           Special Precautions                                                 11

           Communicating the Safety Message                                    13

           Emergency Contact Numbers                                           18

           Acknowledgement of receipt of booklet                               19
overhead   23/11/04   2:28 PM   Page 6




                                         Page 4 of 20
overhead    23/11/04    2:28 PM   Page 7




                                                                                  Page 5 of 20




           WORKING NEAR OVERHEAD LINES

           1.    Introduction

           People are killed and injured each year by accidental contact with overhead
           electrical lines. Most of these accidents occur when cranes, excavators, tipper
           trucks, crane mounted lorries, mobile extendable machinery, scaffolding,
           ladders, farm machinery, concrete delivery trucks etc. come close to or touch
           live overhead lines. Such accidents are caused by failure to take all practicable
           precautions to prevent accidental contact with these lines. Recommended
           methods and procedures are set out in this booklet which, if adopted, will
           provide a positive approach to the elimination of these tragedies.


           NOTE: GUARD AGAINST WORKING CLOSE TO LIVE OVERHEAD LINES.
           IF AT ALL POSSIBLE KEEP MACHINERY WELL AWAY (OUTSIDE THEIR
           REACH). PLAN THE WORK IN ADVANCE AND STAY SAFE.


           IT IS YOUR RESPONSIBILITY TO ENSURE THAT ANY MACHINERY OR
           EQUIPMENT (E.G. LADDERS, CRANES, SCAFFOLDING ETC.) SET UP
           OUTSIDE THE ‘AT RISK ZONE’ (SEE SECTION 7) IS STABLE AND THAT
           PRECAUTIONS ARE PUT IN PLACE TO PREVENT THEM FROM FALLING
           INTO THE ‘AT RISK ZONE’.


           2.    Statutory Regulations

           As with all work locations, there is an obligation under the Safety Health and
           Welfare at Work Act 1989 to provide a safe place of work for all employees. It
           is the duty of the employer when employees are working near overhead lines to
           ensure that they are aware of the hazard. The erection of barriers, bunting and
           goal posts as set out in chapters 6, 7, 8 and 9 of this booklet will alert
           employees and the general public to the hazard and act as a warning to keep
overhead    23/11/04    2:28 PM    Page 8




                                                                                   Page 6 of 20




           their distance.


           The General Application Regulations S.I. 44 of 1993 state in regulation 52 that
           overhead lines should be protected with suitable guards and barriers so as to
           prevent dangerous contact with a person, article, substance or any conducting
           material.


           The nine Principles of Prevention which are also contained in the 1993 General
           Application Regulations S.I.44, contain requirements on the avoidance,
           evaluation and elimination of risk and the adaptation of the workplace to reduce
           the risk. This imposes duties on the contractor to protect his/her employees
           from the dangers associated with working near overhead lines.


           Under the Construction Regulations S.I. No. 481 of 2001, the Project
           Supervisor (Construction Stage) must specify the control measures for dealing
           with the particular risks referred to in the preliminary safety and health plan,
           which may also include other significant risks associated with the project.
           Working near high voltage power lines is one of the listed hazards and must be
           risk assessed and the controls specified in the health and safety plan.


           3.     Consultation

           If danger exists in the work area due to overhead electrical lines running (a) over
           a site, (b) near the site boundaries or (c) over access roads to the site, it is
           essential that the Contractor or person undertaking the work should consult
           with ESB Networks. This consultation should take place at the planning stage
           so that the proposed work can be discussed in relation to any overhead
           electrical line that may exist on or near the proposed site. Such an approach will
           provide an adequate time span where the line can be switched out and earthed,
           but typically for only part of the day, or otherwise, i.e. that the line can be
           diverted or that other precautions, as described below, can be taken.
overhead    23/11/04     2:28 PM    Page 9




                                                                                     Page 7 of 20




           4.     Switchout of Overhead lines

           If supply conditions permit the switching out of an overhead electrical line it
           becomes a matter of arrangement between the Contractor and the local ESB
           Networks Office. Ample advance warning concerning any requirement of this
           nature is essential to allow time for changes to be made in existing feeding
           methods; for informing customers whose supply or quality of supply would be
           affected by the switch-out, etc.


           In many instances, such outages can be granted only for a short period, e.g. 2
           to 3 hours, due to loss of supply to customers over the switch-out periods and,
           unfortunately, at times this option, is not available at all because of the necessity
           to maintain an un-interrupted supply to particular types of customers. In general,
           switching out the line is not a practical solution in situations where work in
           proximity to overhead lines is on-going over a period of time.


           Where the switchout of an overhead line is granted, the contractor shall wait for
           confirmation by ESB Networks that the line is switched out and not assume that
           it is dead at a pre-arranged time. The contractor shall be contactable at all time
           during the switchout in case the ESB Networks need to switch the line back on.



           5.     Diversion of Overhead Lines

           Where diversion of the line is a practical option, contact with ESB Networks
           must be made as early as possible, e.g. at the planning stage as suggested
           above. Time spans for the diversion of LV/l0kV/20kV lines can ( be up to a few
           months due to wayleave serving, work load, etc., and that for higher voltages
           lines can be as much as one year due to planning permission submissions,
           wayleave serving, workload, etc. In certain circumstances it is impossible to
overhead    23/11/04    2:28 PM    Page 10




                                                                                  Page 8 of 20




           design a suitable line diversion due to the lack of an alternative route. In
           addition, if the work in proximity to a line is of a particular nature, e.g. not
           involving the erection of permanent structures over ground, a line diversion
           would not be an appropriate or justifiable means of dealing with the problem.
           Generally diversions of high voltage lines are not feasible.


           6.    Working in Proximity to Overhead lines

           Where switching out the line or diverting the line, as discussed under 4. and 5.
           above is not practicable, the precautions required to prevent accidents
           involving LIVE overhead lines depend on the nature of the work. There are three
           broad categories of work on site.


           (a)   Sites where there will be no work or passage of plant under a live line.
                 Here barriers are required to prevent close approach.


           (b)   Sites where plant will pass under a live line. Here, defined passageways
                 under the line must be made.


           (c)   Sites where work will be done beneath a live line. Here further
                 precautions must be taken in addition to the provision of barriers and
                 passageways.



           7.    Sites where there will be no work or passage of plant
                 under a Live Overhead Line (all work outside the ‘at
                 risk zone’)

           On sites where machinery or plant may accidentally come in contact with a live
           overhead line the Contractor should erect a barrier on the work side (limit of ‘at
overhead    23/11/04    2:28 PM   Page 11




                                                                                  Page 9 of 20




           risk zone’) at a minimum distance from the line. The barrier should run parallel
           to the overhead at a minimum distance of 6 metres from the nearest conductor
           of a low voltage, 10kV, 20kV and 38kV lines. This distance should be increased
           to a minimum of 10 metres for voltage of 110kV, 220kV and 400kV. The
           distance should be measured from the outer conductor to the barrier and not
           from the centre of the pole or mast. Consult ESB Networks to confirm the
           voltage of the line. These distances may be increased depending on the nature,
           frequency and duration of the work. The barrier should consist of fixed post
           fencing, steel drums painted red and white and filled with rubble, spaced 1.5
           metres apart or other means approved by a Health and Safety Authority
           Inspector. The barrier should be supplemented by notice boards indicating:
           "DANGER LIVE OVERHEAD LINES", which should be spaced at intervals of
           not more then 20 metres apart along the route. Where a crane, tipper truck or
           other high equipment is operating in the vicinity of a live line then the barrier
           should be further supplemented. This can be done with a line of bunting or
           other approved means of highlighting the hazard at a minimum height of 3
           metres immediately over the barrier, see Figure 1 and Figure 6.




                                              Figure 1
overhead    23/11/04    2:28 PM   Page 12




                                                                                Page 10 of 20




           8.    Sites where plant will pass under a live Overhead Line

           Where movement of plant is necessary under a live overhead line the
           Contractor should erect wooden or other non conducting material goal posts at
           the entrance to the passage on each side of the line. The goal posts should be
           in line with the protection barrier as detailed in 7 above, and the wooden cross-
           bar should be set at a height determined in consultation with ESB Networks.
           The passageway should be as narrow as possible and should not exceed 10
           metres in width and should be fenced or have steel drums on either side. Two
           large warning notice boards indicating "DANGER LIVE OVERHEAD LINES"
           should be placed near the goal posts at each entrance to the passage. The goal
           posts should be marked in red and white stripes, See Figure 2.




                                              Figure 2.
overhead       23/11/04   2:28 PM   Page 13




                                                                                  Page 11 of 20




           9.      Sites where work will be done within the ‘at risk zone’
                   of an Overhead Line

           In general when work has to be carried out close to (within the ‘at risk zone) of
           a live line, ESB Networks insists on the line being switched out for the duration
           of such work. In some situations, due to continuity of supply considerations, ESB
           Networks may be forced to permit work underneath a live line, but only after
           detailed consultation with them and with the understanding that strict safety
           precautions will be employed. In addition to the precautions outlined in 7 and 8,
           it will be necessary for the Contractor to erect a safety barrier underneath the
           line. This barrier may be made of timber or an earthed steel net and placed at a
           height determined by ESB Networks. It must be erected under the supervision
           of ESB Networks so as to avoid danger of contact with the overhead line.


           Generally, mobile and fixed cranes should be located in such a position that
           loads cannot be slewn over live lines. If there is a need to slew over power lines,
           always contact ESB Networks in advance to ensure that agreed precautions
           are put in place before the slewing operation.



           10. Maintenance of barriers and warning notices

           In all cases covered under 7 and 8 and 9 above, a care and maintenance
           system must be introduced by the Contractor in order to ensure that barriers
           and warning notices remain effective for the duration of the work.


           11.      Special Precautions

           •       Always remember that, in common with electrical utilities worldwide,
                   ESB Network's overhead electrical lines are bare conductors. In the rare
overhead       23/11/04   2:28 PM    Page 14




                                                                                   Page 12 of 20




                   situations where one finds covered conductors this covering is largely for
                   mechanical protection of the overhead line and is not a fully rated
                   insulation and must be treated with the same precautions as bare
                   conductor.


           •       ESB Networks must be contacted whenever it is proposed to work in the
                   vicinity of their overhead electrical lines.


           •       Contact with or coming close to overhead electrical lines can be lethal
                   whether they are carrying voltages as high as 400,000 volts or as low as
                   220 volts. High voltages in particular can arc across a distance in air, and
                   this makes it hazardous to come close to high voltage lines ranging from
                   10kV to 400kV.


           •       Clearance from overhead electrical lines should not be reduced by the
                   dumping or tipping of waste material, by landscaping operations or by
                   the creation of storage areas under these lines.


           •       Pre-planning of safe working procedures is essential.


           •       Liaison with ESB Networks should be continued until the construction
                   work has been completed.


           •       Access for plant and materials and the working of plant should be under
                   direct supervision of a responsible person appointed by the Contractor
                   to ensure that the safety precautions are observed.


           •       Self-adhesive danger stickers (obtainable free from ESB Networks) that
                   warn machinery operators of the hazards of working in close proximity to
                   overhead electrical lines should be placed on the cab window, doors or
overhead       23/11/04   2:28 PM    Page 15




                                                                                   Page 13 of 20




                   dash of machines and vehicles.


           •       Before starting work in the vicinity of overhead electrical lines, machinery
                   operators in particular, should be briefed by their responsible supervisors
                   on the dangers existing and the precautions to be observed.


           •       In the absence of specific information provided by ESB Networks, it
                   must be assumed at all times that an overhead electrical line is live.


           •       Should a vehicle accidentally come in contact with an overhead line, stay
                   in the cab if the vehicle is not on fire. If there is a danger of fire, you
                   should jump clear, stay clear and keep everyone else clear until ESB
                   Networks arrive. On no account should you return to the vehicle.


           •       It is your responsibility to enure that any machinery or equipment (eg.
                   ladders, cranes, scaffolding etc.) set up outside the ‘at risk zone’ (see
                   section 7) is stable and that precautions are put in place to prevent them
                   from falling into the ‘at risk zone’.


           12. Communicating the Safety Message

           •       ESB Networks advertise regularly on television and newspapers on the
                   dangers of working near overhead lines in an effort to ensure that
                   contractors and high machinery operators are fully aware of the hazards.


           •       In addition to this booklet, a safety poster giving brief details and
                   illustrations of the precautions required when working near overhead
                   lines is available from ESB Networks. The poster is entitled
                   “AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR
                   OVERHEAD ELECTRIC LINES”
overhead   23/11/04       2:28 PM        Page 16




                                                                                                                       Page 14 of 20




              AVOIDANCE OF ELECTRICAL
              HAZARDS WHEN WORKING
               NEAR OVERHEAD LINES
            At the planning stage and before starting
            work near an overhead line consult your
                         local ESB office.
                 THERE ARE TWO GENERAL CASES
               SITE WHERE THERE WILL BE NO WORK OR PASSAGE OF
                      PLANT UNDER A LIVE OVERHEAD LINE
                                                                                    • A barrier should run parallel to
                                                                                      the line. (See below for distance from line)
                                                                                    • This may be fixed post fencing
                                                                                      or steel drums filled with
                                                                                      rubble spaced 1.5 metres apart.
                                                                                    • If cranes are in use a line of
                                                                                      bunting at a height of 3
                                                                                      metres should supplement the
                                                                                      barriers. (See below for distance from line)
                                                                                    • Danger notice stating “Danger
                                                                                      Live Overhead Line” should be
                                                                                      spaced at intervals.



           SITE WHERE PLANT WILL PASS UNDER A LIVE OVERHEAD LINE
           • In addition to the above, Goal Posts
             should be erected as shown
           Dimensions as follows:
             Height of goalposts
               - As advised by ESB
            Width of Goalposts
             - Max. 10 metres.
            Height of bunting
             - 3 metres
            Distance between steel drums
             - 1.5 metres
            Distance between danger notices
                - 20 metres
            Horizontal distance of barrier to outside conductor on line
             - 6 metres minimum for LV, 10kV, 20kV, 38kV.
             - 10 metres minimum for 110kV, 220kV, 400kV.
                                   In general if work is to be undertaken directly under the line, ESB
                                  will insist that the line is switched off for the duration of the work.
                               ESB may permit working under a live line only if special agreed precautions are put in place.
                                         Booklet (ESB Code 9803203) also available which gives greater detail.



                                                  Figure 3.
overhead           23/11/04   2:28 PM   Page 17




                                                                                     Page 15 of 20




               •       Cab stickers, For Tipper Trucks, Cranes, Diggers and Tractors are also
                       available from ESB Networks. These should be stuck on a prominent
                       place on the vehicle and are a reminder to the Driver/Operator of the
                       hazards associated with the machine coming in contact with overhead
                       lines. All cab stickers contain the following safety message: “IF YOUR
                       MACHINE CONTACTS AN ESB Networks LINE, JUMP CLEAR AND
                       KEEP OTHERS CLEAR”

                                         ESB Code 9803052                       ESB Code 9803128




                                          9806636                     9806634
     9806635




     9806637                               9806632
                                                                      9806633




                                                     Figure 4.
overhead       23/11/04     2:28 PM     Page 18




                                                                               Page 16 of 20




           •       Two videos are also available which
                   cover the hazards associated with
                   electricity.     These       are   entitled     Lifelines
                                                                        Avoiding Accidents
                   “Lifelines” and “Power2Shock”. The
                   “Lifelines”      video    recreates      6              from Overhead
                   accidents caused by machinery                                   Lines &
                   coming in contact with overhead                            Underground
                   lines and underground cables. The                                Cables
                   6 accident scenarios depicted are
                   based on real situations where
                   people have lost their lives in the
                   past and involve the following:
                   Tipper      Truck,      Mobile      Crane,
                   Wheeled            Digger,         Painters
                                                                        ESB Code 9803503
                   Scaffolding, Cement Truck and
                   Tractor coming in contact with
                   overhead lines or underground
                   cables. The “Power2Shock“ video
                   cover the following 4 accident
                   scenarios: Mini Pillar Vandalism,
                   Tree Cutting, Elevated Platform and
                   Mini Digger


           All of the above are available from ESB
           Networks free of charge to interested
           parties.
           Bunting and danger signs can usually be
           sourced        locally   from    danger       sign
           manufacturers.                                                    ESB Code 9803509

                                                                 Figure 5.
overhead    23/11/04     2:28 PM    Page 19




                                                                         Page 19 of 20




           Example of Rigid Goalposts and Barriers



                          Goalposts
                   (rigid, not conductive)




                                                                    ‘At Risk Zone’




           Dimensions
           A - height to be specified by electricity supplier
           B - width to e determined by site conditions (max 10m)
           C - height 3-6m
           D - 6m (maximum)
           E - 6m (minimum)




                                              Figure 6.
overhead   23/11/04   2:28 PM   Page 20




                                                             Page 18 of 20




           ESB Networks EMERGENCY CONTACT NUMBER
                                   1850-372 999

           FOR TECHNICAL INFORMATION AND SUPPORT
           CONTACT ANY OF THE FOLLOWING NUMBERS
                      IN YOUR LOCATION




                                071-914 9349
                                                          046-9066770


                                                           Head Office
                                091-741923                 01-702 6119

                                                          Dublin Central
                                                         South and North
                                                           01-604 2807
                           061-430552        058-42449




                021-484 4313
overhead    23/11/04    2:28 PM      Page 21




                                                                              Page 19 of 20




                                  Acknowledgement of Receipt of
                                  Avoidance of Electrical Hazards
                          when Working Near Overhead Electric Lines


           I have received on the date under my signature ______ copies of the above
           booklet..


           Please detach this page and return to the ESB Networks member of staff who
           supplied the booklet(s)


           Only necessary to return one signed sheet, irrespective of the number of
           booklets received.


           You may wish to keep local records in a similar manner, for the booklets which
           you issue onwards to your staff or contractors



           Signed:          _______________________________________________


           Date:            _______________________________________________


           Company Name: _______________________________________________


           Address:         _______________________________________________


                            _______________________________________________


                            _______________________________________________
overhead   23/11/04    2:28 PM     Page 22




                                                                                    Page 20 of 20




                      Beware of buried cables
           • Check for the presence of underground cables when planning any dig or
             excavation. Contact ESB Networks at 1850 372 757 for details.
           • Make sure that your staff and sub-contractors are made aware of the presence of
             any cables and that they observe safe digging and excavating practices.
           • Remember, contact or even slight damage or movement can cause a cable to explode.


           Take particular care with:
           ✓ Excavators
           ✓ Mini-diggers
           ✓ Rock hammers
           ✓ Concrete saws
           ✓ Hand digging

           Supporting Safety in the Construction Industry.



       ELECTRICITY IS A GREAT FORCE OF NATURE. RESPECT ITS POWER.
overhead   23/11/04   2:28 PM   Page 23
overhead   23/11/04   2:28 PM   Page 24

Contenu connexe

Tendances

Lecture 8 -_electrical_hazard
Lecture 8 -_electrical_hazardLecture 8 -_electrical_hazard
Lecture 8 -_electrical_hazardShahbani Laa
 
Electrical overhead crane safety
Electrical overhead crane safetyElectrical overhead crane safety
Electrical overhead crane safetyaliashraf mohammady
 
Electrical safety ppt(1)
Electrical safety ppt(1)Electrical safety ppt(1)
Electrical safety ppt(1)Er Ramgarhia
 
Maintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of SubstationMaintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of SubstationSystem Protection
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stationsManohar Tatwawadi
 
Permit to work system
Permit to work systemPermit to work system
Permit to work systemAsif Khan
 
Working at heights training powerpoint
Working at heights training powerpointWorking at heights training powerpoint
Working at heights training powerpointJomish John
 
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdfssuser4bcf3b
 
30 workplace temporary electrical supply risk assessment templates
30 workplace temporary electrical supply risk assessment templates30 workplace temporary electrical supply risk assessment templates
30 workplace temporary electrical supply risk assessment templatesDwarika Bhushan Sharma
 
Vacuum Circuit Breaker (VCB) Working and Applications | Uses Of VCB
Vacuum Circuit Breaker (VCB) Working and Applications | Uses Of VCB Vacuum Circuit Breaker (VCB) Working and Applications | Uses Of VCB
Vacuum Circuit Breaker (VCB) Working and Applications | Uses Of VCB System Protection
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flashmichaeljmack
 
Electrical Safety Joliet Distribution Center
Electrical Safety Joliet Distribution CenterElectrical Safety Joliet Distribution Center
Electrical Safety Joliet Distribution Centertrevor_heller
 
Electrical hazards
Electrical hazardsElectrical hazards
Electrical hazardsKashif Riaz
 
ELECTRICAL SAFETY PRESENTATION.ppt
ELECTRICAL SAFETY PRESENTATION.pptELECTRICAL SAFETY PRESENTATION.ppt
ELECTRICAL SAFETY PRESENTATION.pptVIDHYUTtech
 
Protection of three phase synchronous generator
Protection of three phase synchronous generatorProtection of three phase synchronous generator
Protection of three phase synchronous generatorMohammad Abdullah
 

Tendances (20)

Lecture 8 -_electrical_hazard
Lecture 8 -_electrical_hazardLecture 8 -_electrical_hazard
Lecture 8 -_electrical_hazard
 
Electrical overhead crane safety
Electrical overhead crane safetyElectrical overhead crane safety
Electrical overhead crane safety
 
Electrical safety ppt(1)
Electrical safety ppt(1)Electrical safety ppt(1)
Electrical safety ppt(1)
 
Maintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of SubstationMaintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of Substation
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stations
 
Basic Electrical Safety by TEC
Basic Electrical Safety by TECBasic Electrical Safety by TEC
Basic Electrical Safety by TEC
 
Electrical Hazards by Cooper Bussmann
Electrical Hazards by Cooper BussmannElectrical Hazards by Cooper Bussmann
Electrical Hazards by Cooper Bussmann
 
Permit to work system
Permit to work systemPermit to work system
Permit to work system
 
Electrical safety
Electrical safetyElectrical safety
Electrical safety
 
Working at heights training powerpoint
Working at heights training powerpointWorking at heights training powerpoint
Working at heights training powerpoint
 
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
 
Electrical Hazards
Electrical Hazards Electrical Hazards
Electrical Hazards
 
30 workplace temporary electrical supply risk assessment templates
30 workplace temporary electrical supply risk assessment templates30 workplace temporary electrical supply risk assessment templates
30 workplace temporary electrical supply risk assessment templates
 
Vacuum Circuit Breaker (VCB) Working and Applications | Uses Of VCB
Vacuum Circuit Breaker (VCB) Working and Applications | Uses Of VCB Vacuum Circuit Breaker (VCB) Working and Applications | Uses Of VCB
Vacuum Circuit Breaker (VCB) Working and Applications | Uses Of VCB
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Electrical Safety Joliet Distribution Center
Electrical Safety Joliet Distribution CenterElectrical Safety Joliet Distribution Center
Electrical Safety Joliet Distribution Center
 
Electrical hazards
Electrical hazardsElectrical hazards
Electrical hazards
 
Electrical safety new
Electrical safety newElectrical safety new
Electrical safety new
 
ELECTRICAL SAFETY PRESENTATION.ppt
ELECTRICAL SAFETY PRESENTATION.pptELECTRICAL SAFETY PRESENTATION.ppt
ELECTRICAL SAFETY PRESENTATION.ppt
 
Protection of three phase synchronous generator
Protection of three phase synchronous generatorProtection of three phase synchronous generator
Protection of three phase synchronous generator
 

En vedette

Trapping and Crushing in MEWPS - Guidance from Strategic Forum Plant Safety ...
Trapping and Crushing in MEWPS -  Guidance from Strategic Forum Plant Safety ...Trapping and Crushing in MEWPS -  Guidance from Strategic Forum Plant Safety ...
Trapping and Crushing in MEWPS - Guidance from Strategic Forum Plant Safety ...Alan Bassett
 
The issues of electrical hazards at site and steps to prevent.
The issues of electrical hazards at site  and steps to prevent.The issues of electrical hazards at site  and steps to prevent.
The issues of electrical hazards at site and steps to prevent.tfkc1212
 
Practical Electrical Substation Safety for Engineers and Technicians
Practical Electrical Substation Safety for Engineers and TechniciansPractical Electrical Substation Safety for Engineers and Technicians
Practical Electrical Substation Safety for Engineers and TechniciansLiving Online
 
Electrical safety and Arc Flash Training
Electrical safety and Arc Flash TrainingElectrical safety and Arc Flash Training
Electrical safety and Arc Flash TrainingLarry Riley
 
Electrical hazardous
Electrical hazardousElectrical hazardous
Electrical hazardousDashne DM
 
Safety and order in electrical substations
Safety and order in electrical substationsSafety and order in electrical substations
Safety and order in electrical substationsYunz contracting
 
Electrical Hazards and their safety
Electrical Hazards and their safetyElectrical Hazards and their safety
Electrical Hazards and their safetyMoxit Khandhar
 
Top 10 rules for electric safety
Top 10 rules for electric safetyTop 10 rules for electric safety
Top 10 rules for electric safetyRock Wood
 

En vedette (13)

Trapping and Crushing in MEWPS - Guidance from Strategic Forum Plant Safety ...
Trapping and Crushing in MEWPS -  Guidance from Strategic Forum Plant Safety ...Trapping and Crushing in MEWPS -  Guidance from Strategic Forum Plant Safety ...
Trapping and Crushing in MEWPS - Guidance from Strategic Forum Plant Safety ...
 
The issues of electrical hazards at site and steps to prevent.
The issues of electrical hazards at site  and steps to prevent.The issues of electrical hazards at site  and steps to prevent.
The issues of electrical hazards at site and steps to prevent.
 
Appliance Test and Tag Part 1
Appliance Test and Tag Part 1Appliance Test and Tag Part 1
Appliance Test and Tag Part 1
 
Practical Electrical Substation Safety for Engineers and Technicians
Practical Electrical Substation Safety for Engineers and TechniciansPractical Electrical Substation Safety for Engineers and Technicians
Practical Electrical Substation Safety for Engineers and Technicians
 
Electrical safety and Arc Flash Training
Electrical safety and Arc Flash TrainingElectrical safety and Arc Flash Training
Electrical safety and Arc Flash Training
 
Electrical hazardous
Electrical hazardousElectrical hazardous
Electrical hazardous
 
Electrical Hazarad
Electrical HazaradElectrical Hazarad
Electrical Hazarad
 
Safety and order in electrical substations
Safety and order in electrical substationsSafety and order in electrical substations
Safety and order in electrical substations
 
253 642-1-pb
253 642-1-pb253 642-1-pb
253 642-1-pb
 
Session 2 General Safety Requirements
Session 2   General Safety RequirementsSession 2   General Safety Requirements
Session 2 General Safety Requirements
 
Electrical Hazards and their safety
Electrical Hazards and their safetyElectrical Hazards and their safety
Electrical Hazards and their safety
 
NFPA 70E Training By SASCO
NFPA 70E Training By SASCONFPA 70E Training By SASCO
NFPA 70E Training By SASCO
 
Top 10 rules for electric safety
Top 10 rules for electric safetyTop 10 rules for electric safety
Top 10 rules for electric safety
 

Similaire à Overhead lines electrical_hazards

Avoiding danger from underground services.
Avoiding danger from underground services.Avoiding danger from underground services.
Avoiding danger from underground services.amoramart
 
Operating Cranes and Plant near Overhead Electric Lines
Operating Cranes and Plant near Overhead Electric LinesOperating Cranes and Plant near Overhead Electric Lines
Operating Cranes and Plant near Overhead Electric Linespeterswork1
 
CN 203 - Lightning and Power Frequency Performance of MV Pole Mounted Transfo...
CN 203 - Lightning and Power Frequency Performance of MV Pole Mounted Transfo...CN 203 - Lightning and Power Frequency Performance of MV Pole Mounted Transfo...
CN 203 - Lightning and Power Frequency Performance of MV Pole Mounted Transfo...kevinrisi
 
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINECOMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINEIRJET Journal
 
Schneider electric : Neutral Earthing
Schneider electric : Neutral EarthingSchneider electric : Neutral Earthing
Schneider electric : Neutral EarthingEduardo Higino
 
Application data explusion links
Application data explusion linksApplication data explusion links
Application data explusion linksing_eliali4748
 
Surge Protection for Fieldbus Systems - ICA 2006
Surge Protection for Fieldbus Systems - ICA 2006Surge Protection for Fieldbus Systems - ICA 2006
Surge Protection for Fieldbus Systems - ICA 2006Alvin CJ Chin
 
Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)Ibrahim Ali
 
Detection of Underground Cable Fault using Arduino
Detection of Underground Cable Fault using ArduinoDetection of Underground Cable Fault using Arduino
Detection of Underground Cable Fault using ArduinoIRJET Journal
 
critical protection for medium voltage network.pdf
critical protection for medium voltage network.pdfcritical protection for medium voltage network.pdf
critical protection for medium voltage network.pdfLittleBro2
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...nak maneth
 
Electric protection
Electric protectionElectric protection
Electric protectionVinay Gupta
 
Water Treatment Plant Protection
Water Treatment Plant ProtectionWater Treatment Plant Protection
Water Treatment Plant ProtectionMike Nager
 
Substation Earthing Design
Substation Earthing DesignSubstation Earthing Design
Substation Earthing DesignIOSRJEEE
 
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...ILP Scotland CPD Webinar: What should Scotland consider when planning electri...
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...Institution of Lighting Professionals
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardIJAPEJOURNAL
 

Similaire à Overhead lines electrical_hazards (20)

Electricity on site
Electricity on siteElectricity on site
Electricity on site
 
Avoiding danger from underground services.
Avoiding danger from underground services.Avoiding danger from underground services.
Avoiding danger from underground services.
 
Operating Cranes and Plant near Overhead Electric Lines
Operating Cranes and Plant near Overhead Electric LinesOperating Cranes and Plant near Overhead Electric Lines
Operating Cranes and Plant near Overhead Electric Lines
 
CN 203 - Lightning and Power Frequency Performance of MV Pole Mounted Transfo...
CN 203 - Lightning and Power Frequency Performance of MV Pole Mounted Transfo...CN 203 - Lightning and Power Frequency Performance of MV Pole Mounted Transfo...
CN 203 - Lightning and Power Frequency Performance of MV Pole Mounted Transfo...
 
Electrical protection in mines John Ainsworth
Electrical protection in mines   John AinsworthElectrical protection in mines   John Ainsworth
Electrical protection in mines John Ainsworth
 
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINECOMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
 
Schneider electric : Neutral Earthing
Schneider electric : Neutral EarthingSchneider electric : Neutral Earthing
Schneider electric : Neutral Earthing
 
تأريض2
تأريض2تأريض2
تأريض2
 
Application data explusion links
Application data explusion linksApplication data explusion links
Application data explusion links
 
Surge Protection for Fieldbus Systems - ICA 2006
Surge Protection for Fieldbus Systems - ICA 2006Surge Protection for Fieldbus Systems - ICA 2006
Surge Protection for Fieldbus Systems - ICA 2006
 
Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)
 
Detection of Underground Cable Fault using Arduino
Detection of Underground Cable Fault using ArduinoDetection of Underground Cable Fault using Arduino
Detection of Underground Cable Fault using Arduino
 
critical protection for medium voltage network.pdf
critical protection for medium voltage network.pdfcritical protection for medium voltage network.pdf
critical protection for medium voltage network.pdf
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
 
Electric protection
Electric protectionElectric protection
Electric protection
 
Water Treatment Plant Protection
Water Treatment Plant ProtectionWater Treatment Plant Protection
Water Treatment Plant Protection
 
RAMS Tech Paper
RAMS Tech PaperRAMS Tech Paper
RAMS Tech Paper
 
Substation Earthing Design
Substation Earthing DesignSubstation Earthing Design
Substation Earthing Design
 
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...ILP Scotland CPD Webinar: What should Scotland consider when planning electri...
ILP Scotland CPD Webinar: What should Scotland consider when planning electri...
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazard
 

Plus de Lahmeyer International, UAE

Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01Lahmeyer International, UAE
 
Design of transmission lines in india a review of multiple swing angle
Design of transmission lines in india  a review of multiple swing angleDesign of transmission lines in india  a review of multiple swing angle
Design of transmission lines in india a review of multiple swing angleLahmeyer International, UAE
 
Counter mesaures aginst liquefaction induced settlemnt for ohl
Counter mesaures aginst liquefaction induced settlemnt for ohlCounter mesaures aginst liquefaction induced settlemnt for ohl
Counter mesaures aginst liquefaction induced settlemnt for ohlLahmeyer International, UAE
 

Plus de Lahmeyer International, UAE (20)

Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01
 
AP88 & AP91 shifting proposal
AP88 & AP91 shifting proposalAP88 & AP91 shifting proposal
AP88 & AP91 shifting proposal
 
Design of transmission lines in india a review of multiple swing angle
Design of transmission lines in india  a review of multiple swing angleDesign of transmission lines in india  a review of multiple swing angle
Design of transmission lines in india a review of multiple swing angle
 
Guide to sampling concrete
Guide to sampling concreteGuide to sampling concrete
Guide to sampling concrete
 
Guide to sampling concrete
Guide to sampling concreteGuide to sampling concrete
Guide to sampling concrete
 
Use of bentonite
Use of bentoniteUse of bentonite
Use of bentonite
 
Gb137
Gb137Gb137
Gb137
 
Ohl project risk register
Ohl project risk registerOhl project risk register
Ohl project risk register
 
Ohl project risk register
Ohl project risk registerOhl project risk register
Ohl project risk register
 
Counter mesaures aginst liquefaction induced settlemnt for ohl
Counter mesaures aginst liquefaction induced settlemnt for ohlCounter mesaures aginst liquefaction induced settlemnt for ohl
Counter mesaures aginst liquefaction induced settlemnt for ohl
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Copy of stub setting 2
Copy of stub setting 2Copy of stub setting 2
Copy of stub setting 2
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Copy of stub setting 3
Copy of stub setting 3Copy of stub setting 3
Copy of stub setting 3
 
Copy of stub setting 1
Copy of stub setting 1Copy of stub setting 1
Copy of stub setting 1
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Copy of stub setting 1
Copy of stub setting 1Copy of stub setting 1
Copy of stub setting 1
 

Dernier

Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsRoshan Dwivedi
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 

Dernier (20)

Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 

Overhead lines electrical_hazards

  • 1. overhead 23/11/04 2:28 PM Page 1 AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES ESB Code 9803203
  • 2. overhead 23/11/04 2:28 PM Page 2
  • 3. overhead 23/11/04 2:28 PM Page 3 Page 1 of 20 AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES Issued by: ESB Networks Document Reference: DTIS 191203-BOI Stores Code: 9803203 Issue Date: January 2004 Review Cycle: 3 Version: Revision 2
  • 4. overhead 23/11/04 2:28 PM Page 4 Page 2 of 20 Additional copies available from your local ESB Networks Area office
  • 5. overhead 23/11/04 2:28 PM Page 5 Page 3 of 20 Contents Introduction 5 Statutory Regulations 5 Consultation 6 Switchout of Overhead Lines 7 Diversion of Overhead Lines 7 Working in Proximity of Overhead Lines 8 Sites where there will be no work or passage of plant 8 under a Live Overhead Line (all work outside the ‘at risk zone’) Sites where plant will pass under a live Overhead Line 10 Sites where work will be done within the ‘at risk zone’ of an Overhead Line 11 Maintenance of barriers and warning notices 11 Special Precautions 11 Communicating the Safety Message 13 Emergency Contact Numbers 18 Acknowledgement of receipt of booklet 19
  • 6. overhead 23/11/04 2:28 PM Page 6 Page 4 of 20
  • 7. overhead 23/11/04 2:28 PM Page 7 Page 5 of 20 WORKING NEAR OVERHEAD LINES 1. Introduction People are killed and injured each year by accidental contact with overhead electrical lines. Most of these accidents occur when cranes, excavators, tipper trucks, crane mounted lorries, mobile extendable machinery, scaffolding, ladders, farm machinery, concrete delivery trucks etc. come close to or touch live overhead lines. Such accidents are caused by failure to take all practicable precautions to prevent accidental contact with these lines. Recommended methods and procedures are set out in this booklet which, if adopted, will provide a positive approach to the elimination of these tragedies. NOTE: GUARD AGAINST WORKING CLOSE TO LIVE OVERHEAD LINES. IF AT ALL POSSIBLE KEEP MACHINERY WELL AWAY (OUTSIDE THEIR REACH). PLAN THE WORK IN ADVANCE AND STAY SAFE. IT IS YOUR RESPONSIBILITY TO ENSURE THAT ANY MACHINERY OR EQUIPMENT (E.G. LADDERS, CRANES, SCAFFOLDING ETC.) SET UP OUTSIDE THE ‘AT RISK ZONE’ (SEE SECTION 7) IS STABLE AND THAT PRECAUTIONS ARE PUT IN PLACE TO PREVENT THEM FROM FALLING INTO THE ‘AT RISK ZONE’. 2. Statutory Regulations As with all work locations, there is an obligation under the Safety Health and Welfare at Work Act 1989 to provide a safe place of work for all employees. It is the duty of the employer when employees are working near overhead lines to ensure that they are aware of the hazard. The erection of barriers, bunting and goal posts as set out in chapters 6, 7, 8 and 9 of this booklet will alert employees and the general public to the hazard and act as a warning to keep
  • 8. overhead 23/11/04 2:28 PM Page 8 Page 6 of 20 their distance. The General Application Regulations S.I. 44 of 1993 state in regulation 52 that overhead lines should be protected with suitable guards and barriers so as to prevent dangerous contact with a person, article, substance or any conducting material. The nine Principles of Prevention which are also contained in the 1993 General Application Regulations S.I.44, contain requirements on the avoidance, evaluation and elimination of risk and the adaptation of the workplace to reduce the risk. This imposes duties on the contractor to protect his/her employees from the dangers associated with working near overhead lines. Under the Construction Regulations S.I. No. 481 of 2001, the Project Supervisor (Construction Stage) must specify the control measures for dealing with the particular risks referred to in the preliminary safety and health plan, which may also include other significant risks associated with the project. Working near high voltage power lines is one of the listed hazards and must be risk assessed and the controls specified in the health and safety plan. 3. Consultation If danger exists in the work area due to overhead electrical lines running (a) over a site, (b) near the site boundaries or (c) over access roads to the site, it is essential that the Contractor or person undertaking the work should consult with ESB Networks. This consultation should take place at the planning stage so that the proposed work can be discussed in relation to any overhead electrical line that may exist on or near the proposed site. Such an approach will provide an adequate time span where the line can be switched out and earthed, but typically for only part of the day, or otherwise, i.e. that the line can be diverted or that other precautions, as described below, can be taken.
  • 9. overhead 23/11/04 2:28 PM Page 9 Page 7 of 20 4. Switchout of Overhead lines If supply conditions permit the switching out of an overhead electrical line it becomes a matter of arrangement between the Contractor and the local ESB Networks Office. Ample advance warning concerning any requirement of this nature is essential to allow time for changes to be made in existing feeding methods; for informing customers whose supply or quality of supply would be affected by the switch-out, etc. In many instances, such outages can be granted only for a short period, e.g. 2 to 3 hours, due to loss of supply to customers over the switch-out periods and, unfortunately, at times this option, is not available at all because of the necessity to maintain an un-interrupted supply to particular types of customers. In general, switching out the line is not a practical solution in situations where work in proximity to overhead lines is on-going over a period of time. Where the switchout of an overhead line is granted, the contractor shall wait for confirmation by ESB Networks that the line is switched out and not assume that it is dead at a pre-arranged time. The contractor shall be contactable at all time during the switchout in case the ESB Networks need to switch the line back on. 5. Diversion of Overhead Lines Where diversion of the line is a practical option, contact with ESB Networks must be made as early as possible, e.g. at the planning stage as suggested above. Time spans for the diversion of LV/l0kV/20kV lines can ( be up to a few months due to wayleave serving, work load, etc., and that for higher voltages lines can be as much as one year due to planning permission submissions, wayleave serving, workload, etc. In certain circumstances it is impossible to
  • 10. overhead 23/11/04 2:28 PM Page 10 Page 8 of 20 design a suitable line diversion due to the lack of an alternative route. In addition, if the work in proximity to a line is of a particular nature, e.g. not involving the erection of permanent structures over ground, a line diversion would not be an appropriate or justifiable means of dealing with the problem. Generally diversions of high voltage lines are not feasible. 6. Working in Proximity to Overhead lines Where switching out the line or diverting the line, as discussed under 4. and 5. above is not practicable, the precautions required to prevent accidents involving LIVE overhead lines depend on the nature of the work. There are three broad categories of work on site. (a) Sites where there will be no work or passage of plant under a live line. Here barriers are required to prevent close approach. (b) Sites where plant will pass under a live line. Here, defined passageways under the line must be made. (c) Sites where work will be done beneath a live line. Here further precautions must be taken in addition to the provision of barriers and passageways. 7. Sites where there will be no work or passage of plant under a Live Overhead Line (all work outside the ‘at risk zone’) On sites where machinery or plant may accidentally come in contact with a live overhead line the Contractor should erect a barrier on the work side (limit of ‘at
  • 11. overhead 23/11/04 2:28 PM Page 11 Page 9 of 20 risk zone’) at a minimum distance from the line. The barrier should run parallel to the overhead at a minimum distance of 6 metres from the nearest conductor of a low voltage, 10kV, 20kV and 38kV lines. This distance should be increased to a minimum of 10 metres for voltage of 110kV, 220kV and 400kV. The distance should be measured from the outer conductor to the barrier and not from the centre of the pole or mast. Consult ESB Networks to confirm the voltage of the line. These distances may be increased depending on the nature, frequency and duration of the work. The barrier should consist of fixed post fencing, steel drums painted red and white and filled with rubble, spaced 1.5 metres apart or other means approved by a Health and Safety Authority Inspector. The barrier should be supplemented by notice boards indicating: "DANGER LIVE OVERHEAD LINES", which should be spaced at intervals of not more then 20 metres apart along the route. Where a crane, tipper truck or other high equipment is operating in the vicinity of a live line then the barrier should be further supplemented. This can be done with a line of bunting or other approved means of highlighting the hazard at a minimum height of 3 metres immediately over the barrier, see Figure 1 and Figure 6. Figure 1
  • 12. overhead 23/11/04 2:28 PM Page 12 Page 10 of 20 8. Sites where plant will pass under a live Overhead Line Where movement of plant is necessary under a live overhead line the Contractor should erect wooden or other non conducting material goal posts at the entrance to the passage on each side of the line. The goal posts should be in line with the protection barrier as detailed in 7 above, and the wooden cross- bar should be set at a height determined in consultation with ESB Networks. The passageway should be as narrow as possible and should not exceed 10 metres in width and should be fenced or have steel drums on either side. Two large warning notice boards indicating "DANGER LIVE OVERHEAD LINES" should be placed near the goal posts at each entrance to the passage. The goal posts should be marked in red and white stripes, See Figure 2. Figure 2.
  • 13. overhead 23/11/04 2:28 PM Page 13 Page 11 of 20 9. Sites where work will be done within the ‘at risk zone’ of an Overhead Line In general when work has to be carried out close to (within the ‘at risk zone) of a live line, ESB Networks insists on the line being switched out for the duration of such work. In some situations, due to continuity of supply considerations, ESB Networks may be forced to permit work underneath a live line, but only after detailed consultation with them and with the understanding that strict safety precautions will be employed. In addition to the precautions outlined in 7 and 8, it will be necessary for the Contractor to erect a safety barrier underneath the line. This barrier may be made of timber or an earthed steel net and placed at a height determined by ESB Networks. It must be erected under the supervision of ESB Networks so as to avoid danger of contact with the overhead line. Generally, mobile and fixed cranes should be located in such a position that loads cannot be slewn over live lines. If there is a need to slew over power lines, always contact ESB Networks in advance to ensure that agreed precautions are put in place before the slewing operation. 10. Maintenance of barriers and warning notices In all cases covered under 7 and 8 and 9 above, a care and maintenance system must be introduced by the Contractor in order to ensure that barriers and warning notices remain effective for the duration of the work. 11. Special Precautions • Always remember that, in common with electrical utilities worldwide, ESB Network's overhead electrical lines are bare conductors. In the rare
  • 14. overhead 23/11/04 2:28 PM Page 14 Page 12 of 20 situations where one finds covered conductors this covering is largely for mechanical protection of the overhead line and is not a fully rated insulation and must be treated with the same precautions as bare conductor. • ESB Networks must be contacted whenever it is proposed to work in the vicinity of their overhead electrical lines. • Contact with or coming close to overhead electrical lines can be lethal whether they are carrying voltages as high as 400,000 volts or as low as 220 volts. High voltages in particular can arc across a distance in air, and this makes it hazardous to come close to high voltage lines ranging from 10kV to 400kV. • Clearance from overhead electrical lines should not be reduced by the dumping or tipping of waste material, by landscaping operations or by the creation of storage areas under these lines. • Pre-planning of safe working procedures is essential. • Liaison with ESB Networks should be continued until the construction work has been completed. • Access for plant and materials and the working of plant should be under direct supervision of a responsible person appointed by the Contractor to ensure that the safety precautions are observed. • Self-adhesive danger stickers (obtainable free from ESB Networks) that warn machinery operators of the hazards of working in close proximity to overhead electrical lines should be placed on the cab window, doors or
  • 15. overhead 23/11/04 2:28 PM Page 15 Page 13 of 20 dash of machines and vehicles. • Before starting work in the vicinity of overhead electrical lines, machinery operators in particular, should be briefed by their responsible supervisors on the dangers existing and the precautions to be observed. • In the absence of specific information provided by ESB Networks, it must be assumed at all times that an overhead electrical line is live. • Should a vehicle accidentally come in contact with an overhead line, stay in the cab if the vehicle is not on fire. If there is a danger of fire, you should jump clear, stay clear and keep everyone else clear until ESB Networks arrive. On no account should you return to the vehicle. • It is your responsibility to enure that any machinery or equipment (eg. ladders, cranes, scaffolding etc.) set up outside the ‘at risk zone’ (see section 7) is stable and that precautions are put in place to prevent them from falling into the ‘at risk zone’. 12. Communicating the Safety Message • ESB Networks advertise regularly on television and newspapers on the dangers of working near overhead lines in an effort to ensure that contractors and high machinery operators are fully aware of the hazards. • In addition to this booklet, a safety poster giving brief details and illustrations of the precautions required when working near overhead lines is available from ESB Networks. The poster is entitled “AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES”
  • 16. overhead 23/11/04 2:28 PM Page 16 Page 14 of 20 AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD LINES At the planning stage and before starting work near an overhead line consult your local ESB office. THERE ARE TWO GENERAL CASES SITE WHERE THERE WILL BE NO WORK OR PASSAGE OF PLANT UNDER A LIVE OVERHEAD LINE • A barrier should run parallel to the line. (See below for distance from line) • This may be fixed post fencing or steel drums filled with rubble spaced 1.5 metres apart. • If cranes are in use a line of bunting at a height of 3 metres should supplement the barriers. (See below for distance from line) • Danger notice stating “Danger Live Overhead Line” should be spaced at intervals. SITE WHERE PLANT WILL PASS UNDER A LIVE OVERHEAD LINE • In addition to the above, Goal Posts should be erected as shown Dimensions as follows: Height of goalposts - As advised by ESB Width of Goalposts - Max. 10 metres. Height of bunting - 3 metres Distance between steel drums - 1.5 metres Distance between danger notices - 20 metres Horizontal distance of barrier to outside conductor on line - 6 metres minimum for LV, 10kV, 20kV, 38kV. - 10 metres minimum for 110kV, 220kV, 400kV. In general if work is to be undertaken directly under the line, ESB will insist that the line is switched off for the duration of the work. ESB may permit working under a live line only if special agreed precautions are put in place. Booklet (ESB Code 9803203) also available which gives greater detail. Figure 3.
  • 17. overhead 23/11/04 2:28 PM Page 17 Page 15 of 20 • Cab stickers, For Tipper Trucks, Cranes, Diggers and Tractors are also available from ESB Networks. These should be stuck on a prominent place on the vehicle and are a reminder to the Driver/Operator of the hazards associated with the machine coming in contact with overhead lines. All cab stickers contain the following safety message: “IF YOUR MACHINE CONTACTS AN ESB Networks LINE, JUMP CLEAR AND KEEP OTHERS CLEAR” ESB Code 9803052 ESB Code 9803128 9806636 9806634 9806635 9806637 9806632 9806633 Figure 4.
  • 18. overhead 23/11/04 2:28 PM Page 18 Page 16 of 20 • Two videos are also available which cover the hazards associated with electricity. These are entitled Lifelines Avoiding Accidents “Lifelines” and “Power2Shock”. The “Lifelines” video recreates 6 from Overhead accidents caused by machinery Lines & coming in contact with overhead Underground lines and underground cables. The Cables 6 accident scenarios depicted are based on real situations where people have lost their lives in the past and involve the following: Tipper Truck, Mobile Crane, Wheeled Digger, Painters ESB Code 9803503 Scaffolding, Cement Truck and Tractor coming in contact with overhead lines or underground cables. The “Power2Shock“ video cover the following 4 accident scenarios: Mini Pillar Vandalism, Tree Cutting, Elevated Platform and Mini Digger All of the above are available from ESB Networks free of charge to interested parties. Bunting and danger signs can usually be sourced locally from danger sign manufacturers. ESB Code 9803509 Figure 5.
  • 19. overhead 23/11/04 2:28 PM Page 19 Page 19 of 20 Example of Rigid Goalposts and Barriers Goalposts (rigid, not conductive) ‘At Risk Zone’ Dimensions A - height to be specified by electricity supplier B - width to e determined by site conditions (max 10m) C - height 3-6m D - 6m (maximum) E - 6m (minimum) Figure 6.
  • 20. overhead 23/11/04 2:28 PM Page 20 Page 18 of 20 ESB Networks EMERGENCY CONTACT NUMBER 1850-372 999 FOR TECHNICAL INFORMATION AND SUPPORT CONTACT ANY OF THE FOLLOWING NUMBERS IN YOUR LOCATION 071-914 9349 046-9066770 Head Office 091-741923 01-702 6119 Dublin Central South and North 01-604 2807 061-430552 058-42449 021-484 4313
  • 21. overhead 23/11/04 2:28 PM Page 21 Page 19 of 20 Acknowledgement of Receipt of Avoidance of Electrical Hazards when Working Near Overhead Electric Lines I have received on the date under my signature ______ copies of the above booklet.. Please detach this page and return to the ESB Networks member of staff who supplied the booklet(s) Only necessary to return one signed sheet, irrespective of the number of booklets received. You may wish to keep local records in a similar manner, for the booklets which you issue onwards to your staff or contractors Signed: _______________________________________________ Date: _______________________________________________ Company Name: _______________________________________________ Address: _______________________________________________ _______________________________________________ _______________________________________________
  • 22. overhead 23/11/04 2:28 PM Page 22 Page 20 of 20 Beware of buried cables • Check for the presence of underground cables when planning any dig or excavation. Contact ESB Networks at 1850 372 757 for details. • Make sure that your staff and sub-contractors are made aware of the presence of any cables and that they observe safe digging and excavating practices. • Remember, contact or even slight damage or movement can cause a cable to explode. Take particular care with: ✓ Excavators ✓ Mini-diggers ✓ Rock hammers ✓ Concrete saws ✓ Hand digging Supporting Safety in the Construction Industry. ELECTRICITY IS A GREAT FORCE OF NATURE. RESPECT ITS POWER.