HONG KONG MASS TRANSIT RAILWAY
       A SUCCESS STORY
            PRESENTED BY

      Ir Thomas S K LAI
       CEng, MICE, MIStructE, MHKIE
       Chairman HKIE UK CHAPTER




                                      0
                                          ©
BIRTH & GROWTH OF

HONG KONG MASS TRANSIT RAILWAY

UP TO DATE



                             1
HONG KONG

• LOCATED AT THE PEARL RIVER
  ESTUARY ON THE SOUTHERN
  COAST OF CHINA




                               2
VICTORIA HARBOUR
                   3
August 2003                   77




              HARBOUR FRONT
                                   4
STAR FERRY




August 2003         66




                         5
CULTURAL REVOLUTION

• In 1966 – CULTURAL REVOLUTION
  RAGING IN CHINA
• SPILLED OVER TO HONG KONG
• FARE INCREASE IN STAR FERRY
• RIOTS
• SERIOUS DISRUPTION
  TO PUBLIC TRANSPORT
                                  6
CULTURAL REVOLUTION


      HONG KONG IN

         CRISIS




                      7
CULTURAL REVOLUTION

      HONG KONG IN
         CRISIS

         危    机
 •   Danger   Opportunity



                            8
PLB



     PLB




PUBLIC LIGHT BUS
                   9
PLB

• AVAILABLE - FREQUENT SERVICE

• CONVENIENT - PASSENGERS HOP ON
  AND OFF ANYWHERE ALONG ROUTE

• PREMIUM FOR SERVICE

• POPULAR WITH PASSENGERS
                                   10
HONG KONG GOVERNMENT
 •VIABILITY OF UNDERGROUND RAILWAY SYSTEM


 •CONFIRMED BY CONSULTANT‟S FEASIBILITY STUDY


 •1975 - MASS TRANSIT PROVISIONAL AUTHORITY


 •1976 - MASS TRANSIT RAILWAY CORPORATION


                   MTRC
                                                11
MTRC

THE MASS TRANIST RAILWAY
ORDINANCE




                           12
MTRC

• WHOLLY GOVERNMENT
  OWNED ENTERPRISE




                      13
MTRC
• MANDATED TO BUILD AND
  OPERATE AN UNDERGROUND
  RAILWAY SYSTEM

• ON PRUDENT COMMERCIAL
  PRINCIPLES

• HAVING REGARD TO THE
  REASONABLE REQUIREMENTS OF
  THE PUBLIC TRANSPORT SYSTEM
  OF HONG KONG
                                14
MTRC
HONG KONG GOVERNMENT PUTS IN
INITIAL EQUITY (HK$ 800 M)

MTRC BORROWS REST IN OPEN
MONEY MARKET




                            15
PREFERRED SYSTEM




                   16
INITIAL SYSTEM
LETTER OF INTENT SIGNED WITH JAPANESE
  CONSORTIUM FOR THE INITIAL SYSTEM
 (20 km) AS A SINGLE DESIGN & BUILD CONTRACT




                                               17
INITIAL SYSTEM

OIL CRISIS


CONSORTIUM WITHDREW




                        18
MODIFIED INITIAL SYSTEM

MIS
(15.6 km)
25 CIVIL & 10 E&M
DESIGN AND BUILD
 CONTRACTS




                          19
MIS
GOVERNMENT SET UP MASS
TRANSIT ADVISER (MTA) TO:

• CO-ORDINATE BETWEEN MTRC &
  GOVERNMENT DEPARTMENTS

• FACILITATE TIMELY POLICY MAKING
  & ISSUE RESOLUTION

                                20
MIS

DIFFERENT LEVEL OF COMMITTEES & WORKING
  GROUPS:

• GOVERNMENT / MTR LIAISON COMMITTEE

• GOVERNMENT / MTR PUBLICITY COMMITTEE

• METRO PUBLIC RELATIONS POLICY GROUP



                                          21
MIS
• LAND ACQUISITION CO-ORDINATION COMMITTEE (LACC)

• STATION AND TRANSPORT INTEGRATION COMMITTEE
  (STIC)

• SAFETY AND SECURITY CO-ORDINATION COMMITTEE
  (SSCC)

• TRAFFIC MAMAGEMENT GROUP (TMG)

• UTILITIES CO-ORDINATION GROUP (UCG)



                                                    22
INSPECTORATE OF RAILWAY
         (UK)
 • APPOINTED BY GOVERNMENT AS
   ADVISER ON RAILWAY SAFETY

 • PROVIDES INPUT DURING DESIGN

 • INSPECTS RAILWAY SYSTEM

 • RECOMMENDS OPENING
                                  23
MIS
IMPORTANCE OF PUBLIC RELATIONS


• OBSERVATION WINDOWS ON HOARDINGS


• GROWING FOR YOU



                                 24
MIS
IMPORTANCE OF PUBLIC RELATIONS


• CEREMONIES OF COMMENCEMENT

 & COMPLETION OF WORKS




                                 25
MIS
IMPORTANCE OF PUBLIC RELATIONS


PARTICIPANTS (STAKEHOLDERS) INCLUDE:

  CORPORATION REPRESENTATIVES
  CONTRACTORS
  CONSULTANTS
  GOVERNMENT OFFICIALS
  LEGISLATORS
  DISTRICT COUNCILLORS
  LOCAL DIGNITARIES
                                   26
MIS
IMPORTANCE OF PUBLIC RELATIONS


• TEAM BUILDING

• PUBLICISING PROGRESS OF WORKS




                                 27
MIS

WORK STARTED

• NOVEMBER
  1975



            GROUNDBREAKING CEREMONY
        BY CHAIRMAN SIR NORMAN THOMPSON
                                          28
                  AT KWUN TONG
MIS

• FIRST CHAIRMAN – SIR NORMAN THOMPSON

 DIRECT ACCESS TO THE GOVERNOR
 SIMPLE & CLEAR MESSAGES


• PROJECT MANAGER – HONG KONG &
  SHANGHAI BANK HQ BUILDING


                                   29
MIS

• FIRST M.D. – PROF. TONY RIDLEY

• M.D. – LONDON UNDERGROUND
 MAJOR IMPROVEMENT TO THE SYSTEM


• PROFESSOR – IMPERIAL COLLEGE
  LONDON

                                   30
MIS

• HONG KONG PEOPLE

 – EXCITEMENT

 – EXPECTATION

 – DETERMINATION
                      31
MIS

• HONG KONG PEOPLE

 HIGH DEGREE OF TOLERENCE
      &
 CO-OPERATION




                            32
MIS
PROJECT MANAGEMENT APPROACH:

• QUICK DECISION-MAKING

• REGULAR MONITORING OF EFFECT OF
  CHANGES ON BUDGET & PROGRAMME

• APPROPRIATE DELEGATION OF AUTHORITY

• SHARE RISKS & BENEFITS WITH
  CONTRACTORS
                                    33
MIS
• BASED ON PROVEN TECHNOLOGY

• PROJECT MOTTO:


   IF IT IS ESSENTIAL,
     GET ON WITH IT.

   IF IT IS DESIRABLE,
     FORGET IT.
                               34
MIS
            GOVERNMENT




COMMUNITY                      MTRC

            UNITY IN PURPOSE

                                      35
MIS

GROUND CONDITIONS

 ALLUVIAL DEPOSITS

 GRANITE (VARYING DEGREE OF
  DECOMPOSITION)

 HARD ROCK
                               36
MIS




STATION WALL CONSTRUCTION
                            37
MIS




STATION CONSTRUCTION
                       38
MIS




INSITU HORSESHOE TUNNEL
                          39
MIS




PRECAST CONCRETE TUNNEL
         LINING
                          40
MIS




SGI TUNNEL LINING
                    41
MIS




NGAU TAU KOK STATION &
       VIADUCT
                         42
MIS




KOWLOON BAY DEPOT
                    43
MIS




ADMIRALTY STATION
   EXCAVATION
                    44
MIS




IMMERSED TUBE CASTING
                        45
MIS




IMT
      46
MIS
• FROM KWUN TONG TO CENTRAL
 KWUN TONG TO SHEK KIP MEI
 – OPERATIONAL ON 1 OCTOBER 1979




                                   47
MIS
• FROM KWUN TONG TO CENTRAL
 KWUN TONG TO TSIM SHA TSUI
 – OPERATIONAL ON 31 DECEMBER 1979




                                     48
MIS
• FROM KWUN TONG TO CENTRAL
 KWUN TONG TO CENTRAL
 – OPENED BY PRINCESS ALEXANDRA
   ON 12 FEBRUARY 1980




                                  49
MIS
• FROM KWUN TONG TO CENTRAL

 ON TIME AND WITHIN BUDGET




                              50
MIS

ESTIMATED COST IN 1975               HK$ B
(INCL. 7% p.a. ESCALATION TO 1980)   5.8

CONSTRUCTION COST                    5.6


INCL. INTEREST AND FINANCE COST S    7.3




                                             51
MIS
• NO SMOKING

• NO EATING

• NO DRINKING

• NO MUSIC/RADIO

                      52
MIS
• CLEAN

• QUIET

• EFFICIENT

• RELIABLE

• AIR-CONDITIONED
                    53
MIS


SUCCESS


          54
TSUEN WAN LINE




                 55
TWL

• ENGINEER‟S DESIGN

• CONTRACTOR‟S ALTERNATIVE
  PROPOSALS CONSIDERED &
  ADOPTED


        LAI KING TO KWAI FONG VIADUCT
                                        56
TWL
• SET UP STRONG IN-HOUSE
  PROFESSIONAL PROJECT
  MANAGEMENT TEAM

• HANDS-ON STYLE



                   LAI KING TO KWAI FONG
                        CROSS-OVER
                                       57
TWL
• PROJECT TEAM RESPONSIBLE FOR:

   FEASIBLITY STUDY
   PROPOSAL TO GOVERNMENT
   SPECIFICATION
   APPOINTMENT OF CONSULTANTS
   TENDERING
   CONTRACT AWARD
   DESIGN MANAGEMENT
   CONSTRUCTION MANAGEMENT
   TESTING & COMMISSIONING
   HANDOVER TO OPERATIONS
                                  58
TWL

• TSUEN WAN LINE
 – TSUEN WAN
   TO CENTRAL


 – OPERATIONAL
   10 May 1982
   (AHEAD OF PROGRAMME)

                          59
TWL
ESTIMATED COST IN 1978              HK$ B
(INCL. ESCALATION TO 1982)          4.1

 CONTRACT COSTS              3.7

 CORPORATION COST
 CONSULATANTS‟ FEES
 LAND ACQUISITION
 COMPENSATION                0.7

 FINAL CONSTRUCTION COST            3.9

 INCL. INTEREST AND FINANCE COSTS   5.3

                                            60
ISL




      61
ISL

• ISLAND LINE

  – CHAI WAN TO
    ADMIRALTY
    31 MAY 1985

  – CHAI WAN TO
    SHEUNG WAN
    23 MAY 1986

                        62
ISL
ESTIMATED TOTAL COSTS                HK$ B
AT 1986 PRICES                       10.9
(EXCL. INTEREST AND FINANCE
COSTS)

FINAL COST                           10.0

INCL. INTEREST AND FINANCE COSTS     11.9


              FORTESS HILL STATION
                                             63
ISL
• CHAIRMAN & CEO :
  SIR WILFRID NEWTON
 STRENGTHENED CORPORATION‟S FINANCE
 LAID SOUND FOUNDATION FOR FUTURE
  GROWTH
 RE-ORGANISED HONG KONG STOCK
  EXCHANGE AFTER MARKET COLLAPSE

 DIRECTOR OF HONG KONG & SHANGHAI
  BANKING CORPORATION (HSBC)
 HON. FELLOW - HKIE
 CHAIRMAN – LONDON TRANSPORT
  OVERSAW JUBILEE LINE EXTENSION
                                       64
  CONSTRUCTION
MTR
ARRIVAL & GROWTH OF MTR

COINCIDE WITH :

TRANSFORMATION OF HONG KONG

FROM REGIONAL CITY

TO INTERNATIONAL FINANCIAL CENTRE

                                    65
HONG KONG LEASE
• 99-YEAR LEASE EXPIRES ON 1 JULY 1997

• GOVERNMENT DEPENDS ON SALE OF
  LAND LEASES FOR REVENUE

• NEEDS TO KNOW ITS FUTURE

• NEGOTIATION BETWEEN LONDON &
  BEIJING

                                     66
HONG KONG LEASE
• BRITISH PRIME MINISTER VISITED
  BEIJING

• OFFER TO EXCHANGE
  SOVEREIGNTY FOR
  ADMINSTRATION

• OFFER REJECTED BY CHINA
                                   67
HONG KONG LEASE
BUT AGREED TO:

• SET UP JOINT LIAISON COMMITTEE (JLC)

• CONTINUE NEGOTIATION

• MAINTAIN STABILITY & PROSPERITY OF
  HONG KONG

                                       68
HONG KONG LEASE

• NEGOTIATION NOT GOING WELL

• UNCERTAINTY




                               69
HONG KONG LEASE
• JITTERY & GLOOMY

• INVESTMENTS PUT ON HOLD

• STOCK MARKET CRASH

• PROPERTY BUBBLE BURST

                            70
HONG KONG LEASE

HONG KONG DOLLAR PLUNGES

FROM AROUND HK$ 6 = US$ 1
       TO
OVER HK$ 9 = US$ 1



                            71
HONG KONG LEASE

PEOPLE RUSH TO SUPERMARKET
TO BUY :

RICE




                             72
HONG KONG LEASE

PEOPLE RUSH TO SUPERMARKET
TO BUY :

RICE &

BABY‟S POWDERED MILK

                             73
HONG KONG LEASE

• CURRENCY PEG

 HK$ 7.8 = US$ 1




                       74
HONG KONG LEASE

• CALM THE CITY

• STOP PANIC




                       75
HONG KONG LEASE


• IN 1984 BRITAIN & CHINA SIGNED
  JOINT DECLARATION ON FUTURE OF
  HONG KONG

• CHINA TO REGAIN FULL SOVEREIGNTY
  ON 1 JULY 1997
  August 2003                 85



                                     76
HONG KONG LEASE
PROMISE TO HONG KONG PEOPLE

• HONG KONG PEOPLE GOVERN HONG
  KONG

• WITH HIGH DEGREE OF AUTONOMY

• ONE COUNTRY TWO SYSTEMS

• NO CHANGE FOR 50 YEARS
                                 77
HONG KONG LEASE
•ENSHRINED IN   •LODGED WITH
 BASIC LAW       UNITED NATIONS




                              78
HONG KONG LEASE
• CURRENCY PEG

 HK$ 7.8 = US$ 1

• REMAINS TO THIS DAY




                        79
MTRC

• BORROWING IN US$

• REVENUE IN HK$

• ADVERSE IMPACT BY
  HIGH INTEREST RATE (12%)
  DEVALUATION

                             80
MTRC
• HONG KONG GOVERNMENT TO
  INCREASE EQUITY
  (HK$ 2.5 B ISSUED, 2.5 B ON CALL )

• SHIFT BORROWING TO BE
  HK$ DENOMINATED


                                   81
MTRC

• IN NO POSITION TO FINANCE NEW
  EXTENSIONS




                                  82
EASTERN HARBOUR
    CROSSING




                  83
EHC
• BOT PROJECT BY OTHERS

• LINKING KWUN TONG TO QUARRY BAY

• THIRD CROSS HARBOUR TUNNEL
  CARRYING ROAD AND RAILWAY

• RAIL PORTION LEASED TO MTRC
         EASTERN HARBOUR CROSSING
                 ENTRANCE
                                    84
EHC
MTRC PAYS SEMI-ANNUAL INSTALMENTS FOR
18½ YEARS TOTALLING            HK$ 2.6 B

OTHER CAPITAL INVESTMENT
INCL. ROLLING STOCKS                0.365 B




            IMMERSED TUBE CASTING          85
EHC

OPENED BY PRINCE OF WALES
ON 1 OCTOBER 1989




                            86
AFTER JOINT DECLARATION

• UNCERTAINTY REMOVED

• CONFIDENCE RETURNED




                        LIPPO CENTRE
                                  87
KAI TAK AIRPORT




  CHECKERBOARD IN SIGHT
                          88
KAI TAK AIRPORT




   STEADY AS SHE GOES
                        89
KAI TAK AIRPORT




 DO YOUR WINDOW SHOPPING
     BEFORE YOU LAND
                           90
KAI TAK AIRPORT




 SEE....I LAND IT ON THE ROOF
                                91
KAI TAK AIRPORT




  HARD RIGHT TURN AND DIVE
                             92
KAI TAK AIRPORT




    BUT LANDING ON THE
  RUNWAY...... IS NOT ALWAYS
                               93
             EASY
KAI TAK AIRPORT




 SOMETIMES.... ENDED UP IN THE
           WATER
                                 94
AIRPORT CORE PROJECTS




RELOCATE AIRPORT FROM KAI TAK TO CHEK LAP KOK

                                            95
AIRPORT CORE PROJECTS

• APPROVED BY BEIJING
  & LONDON




                        96
AIRPORT CORE PROJECTS

• OBJECTIVES:

 – TO STIMULATE ECONOMY
 – TO FACILITATE FUTURE GROWTH
 – TO ELIMINATE AVIATION HAZARD

 – TO BE COMPLETED IN TIME FOR
   HANDOVER
                                  97
ACP

• AIRPORT AT CHEK LAP KOK

• TSING MA BRIDGE

• LANTAU & AIRPORT RAILWAY

                             98
ACP

•   KAP SHUI MUN BRIDGE
•   TING KAU BRIDGE
•   HIGHWAYS
•   RECLAMATIONS
•   THIRD CROSS HARBOUR ROAD
    TUNNEL (WESTERN HARBOUR CROSSING)
                                        99
ACP

• HK$ 127 BILLION    £ 10 BILLION




                                    100
ACP

CHINA‟S CONCERN:

• ROSE GARDEN PROJECT

• EMPTY TREASURY

• HIGH DEBT
                        101
ACP
AGREEMENT REACHED TO:

• LEAVE HK$ 25 B MIN. IN TREASURY

• CAP GOVERNMENT BORROWING
  AT HK$ 5 B UNLESS AGREED
  OTHERWISE

• CAP ANNUAL LAND SALE
  NO MORE THAN 50 ha /year
                                    102
ACP

• ESSENTIAL TO HAVE CHINA‟S
  AGREEMENT AND SUPPORT TO
  ASSURE INVESTORS

• WRANGLING OVER FINANCIAL DATA
  DELAYED PROJECT START


                              103
ACP


 AT TIME OF HANDOVER
 ON 30 JUNE/1 JULY 1997




• CHINESE PRESIDENT ARRIVED BY PLANE AT
  THE NEW AIRPORT

• LAST BRITISH GOVERNOR LEFT ON ROYAL
  YACHT BRITANNIA
                                          104
ACP

PROJECT COMPLETED IN 1998




                            105
HONG KONG INTERNATIONAL
       AIRPORT
                          106
TSING MA BRIDGE
  (ROAD + RAIL)
                  107
LANTAU & AIRPORT LINE




                        108
LAL
AIRPORT EXPRESS LINE
(AEL)



AIRPORT – HONG KONG

23 MINUTES JOURNEY

IN-TOWN-CHECK-IN

                       109
LAL

TUNG CHUNG LINE
(ON SHARED TRACK WITH AEL)


TUNG CHUNG - HONG KONG
COMMUTER LINE

ALSO PROVIDES RELIEF
TO NATHAN ROAD CONGESTION


                             110
LAL

FINANCIAL SUPPORT AGREEMENT (FSA)
WITH GOVERNMENT

• HK$ 23.7 B ADDITIONAL EQUITY BY
  GOVERNMENT
• 62 ha LAND FOR DEVELOPMENT
• DEFERRAL OF DIVIDENDS UNTIL 2001
• REVENUE DEFICIENCY PAYMENTS
  (80% FOR NO MORE THAN 2 YEARS
   IF DELAYED BY OTHERS)

                                     111
LAL

• EXTENSIVE APPLICATION OF
  VALUE ENGINEERING

• INTRODUCE PARTNERING




                             112
TUNG CHUNG LINE




  NO MORE SLIDING SEATS
                          113
AIRPORT EXPRESS
• SPACIOUS SEATING

• PLEASANT AMBIENCE

• BUSINESS CLASS
  COMFORT

 FROM PLANE,
 THROUGH TRAIN,
 TO HOTEL          AEL TRAIN
                               114
LAL
TCL
OPERATIONAL ON 22 JUNE 1998
AEL
OPERATIONAL ON 6 JULY 1998




                              115
LAL
                                   HK$ B

PROJECT COST                        35.1
(INCLUDING CAPITALISED INTEREST)

FINANCED BY:

EQUITY                              23.7
DEBT                                11.4



                                      116
TSEUNG KWAN O LINE




                     117
TKL

• TSEUNG KWUN O LINE

 – COMMUTER LINE

 – FROM PO LAM TO NORTH POINT

 – OPERATIONAL ON 17 AUGUST 2002
                                   118
TKL

I st JULY – 1997
ASIAN FINANCIAL CRISIS

MAJOR REVIEW OF THE
PROJECT

                         119
TKL

INITIAL CAPITAL COST ESTIMATE     HK$ B
INCL. CAPITALISED INTEREST        30.5

FINAL COST                        16.0




               HANG HAU STATION
                                         120
TKL




NORTH POINT CAVERN
                     121
DISNEYLAND RESORT LINE




                         122
DISNEYLAND RESORT LINE




                         123
DRL

• DISNEYLAND RESORT
  LINE

 – FROM SUNNY BAY TO
   DISNEYLAND

 – OPERATIONAL ON
  12 SEPTEMBER 2005
                       124
ASIAWORLD-EXPO STATION




                         125
ASIAWORLD-EXPO STATION




                         126
ASIAWORLD-EXPO STATION
 AIR STATION –
 ASIAWORLD-EXPO

 OPERATIONAL ON
 20 DECEMBER 2005




                         127
NGONG PING 360




                 128
NGONG PING 360




                 129
NGONG PING 360




                 130
NGONG PING 360




                 131
NGONG PING 360




AIRPORT ISLAND STATION    TUNG CHUNG TERMINAL
                                          132
NGONG PING 360

• MATERIAL DELIVERY

 – HELICOPTERS
 – MULES




                      133
NGONG PING 360
SCHEDULED OPENING   24 JUNE 2006
OPERATIONAL         18 SEPT 2006
OFFICIAL OPENING     9 NOV 2006




                             134
NGONG PING 360
OPERATION SUSPENDED     11 JUNE 2007
OPERATION RESUMED        31 DEC 2007
SUBSIDIARY COMPANY SET UP TO
MANAGE & OPERATE THE SYSTEM




                                  135
MTR CORPORATION

AN OUTSTANDINGLY SUCCESSFUL
         ENTERPRISE




                              136
MTRC
SUCCESSES PROFILERATING

 PROJECT MANAGEMENT

 RAILWAY OPERATION

 FINANCIAL EXPERTISE


 TRAINING & DEVELOPMENT

 PROPERTY

 AUTOMATIC FARE COLLECTION
                              137
MTRC
• INVEST HEAVILY IN STAFF TRAINING &
  DEVELOPMENT

• CORE VALUES :

 CUSTOMER SERVICE

 RESPECT FOR THE INDIVIDUAL

 ON TIME AND WITHIN BUDGET
                                       138
MTRC

• PROVIDES PROFESSIONAL
  TRAINING SERVICES TO OTHER
  RAILWAYS IN:

 – MAINLAND CHINA

 – SOUTHEAST ASIA

                               139
PROPERTY DEVELOPMENT
     & MANAGEMENT
• GOVERNMENT ALLOCATE LAND AT
  FULL MARKET VALUE ALONG THE
  RAILWAY FOR DEVELOPMENT




                                140
PROPERTY DEVELOPMENT
     & MANAGEMENT
• MAJOR & REPUTABLE
  PROPERTY DEVELOPER
  AND MANAGER IN
  TOWN

• JOINT VENTURES

  –   RESIDENTIAL
  –   RETAIL
  –   OFFICES
  –   HOTEL             141
PROPERTY DEVELOPMENT
    & MANAGEMENT

• SUBSTANTIAL CONTRIBUTION
  TOWARDS COST OF RAILWAY

• CAPTURED PASSENGERS
  (FORMING PART OF 2.4 M DAILY
  RIDERSHIP)


                                 142
PROPERTY DEVELOPMENT
    & MANAGEMENT
 PROCEEDS FROM DEVELOPMENTS
 HELP TO:

• KEEP FARES AT REASONABLE
  LEVEL

• MAINTAIN & EXTEND RAIL
  NETWORK
                             143
PROPERTY DEVELOPMENT
    & MANAGEMENT




                       144
PROPERTY DEVELOPMENT
    & MANAGEMENT




        TELFORD GARDEN
                         145
PROPERTY DEVELOPMENT
    & MANAGEMENT




         PARK VIEW
                       146
PROPERTY DEVELOPMENT
    & MANAGEMENT




       CENTRAL STATION RETAIL
                                147
PROPERTY DEVELOPMENT
    & MANAGEMENT




        TELFORD PLAZA
                        148
PROPERTY DEVELOPMENT
    & MANAGEMENT




       MARITIME SQUARE
                         149
PROPERTY DEVELOPMENT
    & MANAGEMENT




         ELEMENTS      150
2 INTERNATIONAL FINANCE
        CENTRE




            2IFC
                          151
UNION SQUARE




               152
INTERNATIONAL COMMERCE
        CENTRE
 • 118 FLOORS

 • 490 METRES HIGH

 • THIRD TALLEST
   BUILDING IN THE
   WORLD
                 ICC
                         153
ICC




ICC
      154
GATEWAY TOWERS




                 155
CHINA – BEIJING

• PROPERTY OPEARATIONS
         & MANAGEMENT




             GINZA MALL
                          156
PROPERTY DEVELOPMENT
    & MANAGEMENT
AS AT END 2010:

Investment properties :
• 12 shopping malls + 18 floors at 2 IFC
• 277,942 sq.m in Hong Kong

Managed properties:
• 81,962 residential units in Hong Kong
• 744,214 sq.m commercial properties in Hong Kong
• 776,402 sq.m in Mainland China
                                                    157
AUTOMATIC FARE COLLECTION


• ELECTRO-MAGNETIC CARD

• STORED VALUE CARD

• CONTACTLESS SMART CARD



                             158
AUTOMATIC FARE COLLECTION

ELECTRO-MAGNETIC CARD

•   PLASTIC
•   RE-USABLE
•   NO LITTER
•   ISSUED BY MACHINE / HAND
•   FIXED VALUE
•   ELECTRO-MAGNETIC
•   SINGLE JOURNEY




                                 159
MIS
• NO SMOKING

• NO EATING

• NO DRINKING

• NO MUSIC/RADIO

• NO TICKET FLICKING   160
AUTOMATIC FARE COLLECTION
STORED VALUE
•   PLASTIC
•   RE-USABLE
•   NO LITTER
•   ISSUED BY MACHINE / HAND
•   FIXED VALUE
•   ELECTRO-MAGNETIC
•   MULTIPLE JOURNEYS
•   UNRESTRICTED LAST JOURNEY
•   ADVANCE REVENUE COLLECTION
•   REDUCTION IN CASH HANDLING


                                 161
AUTOMATIC FARE COLLECTION
OCTOPUS CONTACTLESS SMART CARD

•   PLASTIC
•   ISSUED BY MACHINE / HAND
•   RE-USABLE
•   NO LITTER
•   MULTIPLE JOURNEYS
•   ADVANCE REVENUE
•   RADIO FREQUENCY IDENTIFICATION (RFID)
•   NO CONTACT AT TURNSTILE
•   TOP UP VALUE
•   FURTHER REDUCTION IN CASH HANDLING
•   ACCEPTED BY BUSINESS PARTNERS

                                            162
OCTOPUS CONTACTLESS
     SMART CARD
• RELIABLE TICKETING

• LABOUR SAVING

• DATA FOR:

  OPERATIONAL PLANNIN INCLUDING PRICING



                                          163
OCTOPUS CONTACTLESS
    SMART CARD
• FORERUNNER OF:

• EZ-LINK – SINGAPORE
• OYSTER CARD – LONDON
• EASYCARD - TAIPEI



                         164
OCTOPUS CONTACTLESS
      SMART CARD
OTHER USES:

 PUBLIC TRANSPORTS
 CAR PARKS
 ACCESS CONTROL TO BUILDINGS
 CONFIRMATION OF STUDENTS‟
  ATTENDANCE AT SCHOOL



                                165
OCTOPUS CONTACTLESS
         SMART CARD

AT END OF JUNE 2011:

• 24.3 MILLION CARDS ISSUED (18.7 MILLION ACTIVE)

• 11.7 MILLION DAILY TRANSACTIONS

• HK$ 112.7 MILLION PER DAY

• ADOPTED BY OVER 3000 SERVICE PROVIDERS

                                                166
MTR CORPORATION LTD

LISTED ON THE HONG KONG
EXCHANGE

ON 5 OCTOBER 2000




                          167
MTRCL
EXPANSION

NEW VISION :

• TO BE A WORLD CLASS ENTERPRISE
• GROWING IN HONG KONG & BEYOND
• FOCUSING ON RAIL, PROPERTY &
  RELATED BUSINESS

                                   168
MTRCL

• NEW MISSION :

• EXCELLENT VALUE FOR CUSTOMERS
• OPPORTUNITIES FOR STAFF
• DEVELOP RAILWAY NETWORK AS
  BACKBONE OF PUBLIC TRANSPORT IN
  HONG KONG
• GROW IN MAINLAND CHINA & CAPTURE
  OPPORTUNITIES IN EUROPE
                                     169
MTRCL

• NEW CORE VALUES :

EXCELLENT SERVICE
VALUE CREATION
MUTUAL RESPECT
ENTERPRISING SPIRIT

                       170
MERGER

• HONG KONG GOVERNMENT ANNOUNCED
  MERGER PROPOSAL BETWEEN MTRCL & KCRC
  ON 11 APRIL 2006




                                     171
MERGER

• KCRC

• ORIGINALLY A GOVERNMENT DEPARTMENT
• TURNED INTO A WHOLLY GOVERNMENT
  OWNED PUBLIC CORPORATION
• CHARGED TO OPERATE AND DEVELOP
  DOMESTIC, CROSS-BOUNDARY AND INTERCITY
  RAILWAY SERVICES
• IN A PRUDENT COMMERCIAL MANNER
                                      172
MERGER
KCRC

• OPERATES:
  – EAST RAIL
  – WEST RAIL
  – LIGHT RAIL
  – INTERCITY TO
    GUANGZHOU
  – FREIGHT TO
    INTERIOR OF
    MAINLAND CHINA

                        173
MERGER
KCRC



• PROPERTY DEVELOPMENT
       &
  MANAGEMENT



                         174
MERGER

• HONG KONG GOVERNMENT ANNOUNCED MERGER
  PROPOSAL BETWEEN MTRCL & KCRC ON 11 APRIL 2006

• MTRCL SIGNED MEMORANDUM OF UNDERSTANDING
  (MOU) WITH HK GOVERNMENT




                                                   175
MERGER
MOU PROVIDES FOR:

• REDUCED FARE
• ABOLITION OF SECOND BOARDING CHARGE
• FURTHER DISCOUNTS FOR MEDIUM & LONG DISTANCE
  JOURNEYS
• INTRODUCTION OF AN OBJECTIVE, TRANSPARENT &
  PREDICTABLE FARE ADJUSTMENT MECHANISM (FAM)
• FULLY INTEGRATED INTERCHANGE STATIONS FOR
  SHATIN TO CENTRAL LINK
• IMPROVEMENT ON EXISTING INTERCHANGE
  ARRANGEMENTS IN THE SHORT TERM
• PROVISION OF SEAMLESS INTERCHANGE
  ARRANGEMENTS WITH FUTURE EXTENSIONS

                                                 176
MERGER

MOU PROVIDES FOR

• JOB SECURITY FOR ALL FRONTLINE STAFF




                                         177
MERGER

DEAL TERMS

• PROVIDE A BALANCED PACKAGE FAIR TO ALL
  STAKEHOLDERS




                                           178
MERGER
DEAL TERMS

• ACQUISITION OF RENEWABLE OPERATIONAL RIGHT OF
  KCR FOR 50 YEARS
   – UPFRONT PAYMENT OF HK$4.25 BILLION FOR SERVICE
     CONCESSION AND TO PURCHASE CERTAIN RAIL ASSETS
   – HK$7.79 BILLION FOR A PROPERTY PACKAGE
   – FIXED ANNUAL PAYMENT OF HK$750 MILLION
   – VARIABLE ANNUAL PAYMENT BASED ON REVENUES
     GENERATED FROM KCR‟S RAIL AND RAIL-RELATED
     OPERATIONS
• EXPECTED TO BE EPS & NPV ACCRETIVE FOR MTRCL


                                                 179
MERGER

MEET THE GOVERNMENT‟S FIVE PARAMETERS

1. ADOPTION OF A MORE OBJECTIVE AND TRANSPARENT
   FAM
2. ABOLITION OF THE SECOND BOARDING CHARGE &
   REVIEW FARE STRUCTURE TO REDUCE FARES
3. EARLY RESOLUTION OF INTERCHANGE ARRANGEMENTS
   FOR RAIL PROJECTS UNDER PLANNING, NOTABLY THE
   SHATIN TO CENTRAL LINK
4. ENSURE JOB SECURITY FOR FRONTLINE STAFF
5. PROVISION OF SEAMLESS INTERCHANGE
   ARRANGEMENTS IN THE LONG TERM

                                               180
MERGER

BENEFITS

•   SYNERGY
•   ECONOMIES OF SCALE
•   COST EFFICIENCY
•   INTEGRATED RAIL SYSTEM




                             181
MERGER
TRANSITION - ONE YEAR OR MORE

SHARE PRICE JUMPED 5.3%
 (FROM HK$19 TO 20)

RAIL MERGER BILL APPROVED BY LegCo
 on 8 JUNE 2007

OUTLOOK - BRIGHT
                                     182
MERGED

• COMPLETED ON
  2 DECEMBER
  2007



• 香港鐵路有限公司
       ONE COMPANY ONE TEAM
                              183
MERGED




         184
MERGED
•   211 Km ROUTE LENGTH
•   82 STATIONS
•   9 COMMUTER LINES
•   AIRPORT EXPRESS
•   LIGHT RAIL
•   DISNEYLAND RESORT LINE
•   FEEDER BUS SERVICE
•   CABLE CAR
•   INTERCITY PASSENGER SERVICE
•   INTERCITY FREIGHT SERVICE
•   3 MILLION DAILY PASSENGERS
                                  185
MERGED
•   ONE COMPANY, ONE TEAM




      STAFF INTEGRATION     186
MTR CORPORATION LTD




    GROWTH MOMENTUM




                      187
DUBAI




        188
DUBAI




METRO & AIRPORT LINES
                        189
DUBAI
CONSULTANCY

TO REVIEW DESIGN PROPOSALS IN
 RESPECT OF :

OPERATION &
MAINTENANCE


          VIADUCT CONSTRUCTION
                                 190
INDIA

Delhi Airport Metro
 Express Line
 (AMEL)

• Major engineering &
  project management
  contract
                        191
UK BUSINESS




    BIDS
              192
UK BUSINESS
    LORO      (MTR/LAING )


FRANCHISE TO OPERATE

NORTH & EAST LONDON
 OVERGROUND LINES

 FROM 11 NOVEMBE 2007
 FOR 7 YEARS

 WITH OPTION FOR 2 FURTHER YEARS
                                   SUCCESS
                                             193
UK BUSINESS
LOROL      (MTR/DEUTSCHE BAHN)

ACTION ON DAY ONE

• OYSTER TICKETING SYSTEM

• NEW TICKETING MACHINES

• STATIONS GATED

                                 194
UK BUSINESS
               (MTR/DEUTSCHE BAHN)

• IMPROVEMENT IN:

  1.   SERVICE OPERATION
  2.   PUNCTUALITY
  3.   SAFETY
  4.   SECURITY

• TICKETLESS TRAVEL DOWN

• REVENUE UP
                                     195
UK BUSINESS
                (MTR/DEUTSCHE BAHN)


PROGRAMME FOR:

•   CUSTOMER SERVICE TRAINING
•   STATION CLEANING AND REPAIR
•   STATION REFURBISHEMENT
•   STATION REMODELLING
•   NEW EXTENSIONS


                                      196
UK BUSINESS
                   (MTR/DEUTSCHE BAHN)



• “….so gradually all suburban rail services in London
  can be brought up to the standard of London
  Overground.”

Ken Livingstone
Mayor of London


                                                     197
EUROPE BUSINESS
STOCKHOLM UNDERGROUND

TOOK OVER OPERATION 2 NOVEMBER 2009
(FOR 8 YEARS MINIMUM)




                                      198
AUSTRALIAN BUSINESS

METRO TRAINS MELBOURNE

TOOK OVER OPERATION ON 30 NOVEMBER 2009
(FOR INITIAL PERIOD OF 8 YEARS)




                                          199
CHINA BUSINESS




                 200
CHINA BUSINESS

SHANGHAI

TOGETHER WITH ITS JOINT VENTURE PARTNER,
  APPOINTED AS:

 OWNER‟S REPRESENTATIVE TO PROJECT MANAGE
  DESIGN AND CONSTRUCTION OF LINE 9

 OWNER‟S ADVISOR OF LINE 8 & LINE 11


                                             201
CHINA BUSINESS
BEIJING LINE 4
 – INITIALLED IN FEBRUARY 2005
 – COMPANY FORMED IN JANUARY 2006
 – AGREEMENT SIGNED ON 12 APRIL 2006




                                202
CHINA BUSINESS
BEIJING LINE 4
– PPP
– 30-YEAR CONCESSION AGREEMENT WITH BEIJING
  MUNICIPAL GOVERNMENT
– FOR INVESTMENT, CONSTRUCTION & OPERATION
OPENED 28 SEPTEMBER 2009



DAXING LINE
OPENED 30 DECEMBER 2010



                                              203
CHINA BUSINESS

SHENZHEN LINE 4
– 30-YEAR BOT PROJECT
– CONCESSION AGREEMENT WITH
  SHENZHEN MUNICIPAL GOVERNMENT
– „RAIL + PROPERTY‟
– INITIALLED IN MAY 2005
– PHASE 1 TAKEN OVER 01 JULY 2010
– PHASE 2 OPENED 16 JUNE 2011




                                    204
BUSINESS OUTSIDE HONG KONG


COMPANY                                          SHARE
BEIJING MTR CORPORATION LTD. (BJMTR)             49%
MTR CORPORATION ( SHENZHEN) LTD. (SZMTR)         100%
METRO TRAINS MELBOURNE PTY. LTD. (MTM)           60%
MTR STOCKHOLM AB (MTRS)                          100%
TUNNELBANAN TEKNIK STOCKHOLM AB (TBT)            50%
LONDON OVERGROUND RAIL OPERATIONS LTD. (LOROL)   50%
MTR HANGZHOU LINE 1 INVESTMENT CO. LTD.          100%




                                                        205
MTRCL
• PROFITABLE
    HK$B
    16
               14.2
    14
                          Turnover
    12
                   10.7
    10
                          Operating profit
     8             8.6    before depreciation
                          (after property
     6                    development profit)
                          Net profit excluding
     4                    investment property
                          revaluation
     2

     0




                                                 206
MTRCL




        207
MTRCL




        208
MTRCL
 CONSOLIDATED P & L A/C
(YEAR ENDED 31 December 2010)               HK$ M


• REVENUE                                   29,500
• PROFIT ON PROPERTY DEVELOPMENTS            4,034
• OPERATING PROFIT BEFORE DEPRECIATION      10,917

• NET PROFIT ATTRIBUTABLE TO SHAREHOLDERS   12,059




                                              209
MTRCL

AS AT END 2010:

PATRONAGE ( million)

Yearly                 1,564

Daily                     4.5


                               210
HONG KONG GOVERNMENT
    INFRASTRUCTURE INVESTMENT

• 2007-2008 POLICY ADDRESS
  ANNOUNCES TEN MAJOR
  INFRASTRUCTURE PROJECTS

• ANNUAL EXPENDITURE OF
  HK$ 50 BILLION (£ 4 BILLION)
  IN COMING YEARS


                                 211
HONG KONG GOVERNMENT
       INFRASTRUCTURE INVESTMENT
•     Transport Infrastructure
1.    South Island MTR Line
2.    The Sha Tin to Central MTR Link
3.    The Tuen Mun Western Bypass and Tuen Mun-Chek Lap Kok
      Link

•     Cross-boundary Infrastructure Projects
4.    The Guangzhou-Shenzhen-HK Express Rail Link
5.    HK-Shenzhen Airport Co-operation
6.    HK-Zhuhai-Macao Bridge
7.    HK-Shenzhen Joint Development of the Lok Ma Chau Loop

•     New Urban Development Areas
8.    West Kowloon Cultural District
9.    Kai Tak Development Plan
10.   New Development Areas (NDAs)                            212
RAILWAY EXTENSIONS




                     213
RAILWAY EXTENSIONS




        XRL          214
RAILWAY EXTENSIONS




        WIL          215
RAILWAY EXTENSIONS




        KTE          216
RAILWAY EXTENSIONS




        SCL          217
RAILWAY EXTENSIONS




                     218
       SIL(E)
RAILWAY EXTENSIONS
EXTENSION   PROJECT FUNDING
XRL         SERVICE CONCESSION
            (GOVERNMENT CAPITAL + MTRCL OPERATIONS)
WIL         CAPITAL GRANT
KTE         RAIL + PROPERTY
SCL         SERVICE CONCESSION
SIL(E)      RAIL + PROPERTY




                                                      219
RAILWAY BUILDING
    & MANAGEMENT
FEASIBILITY

IDENTIFY TRANSPORT NEEDS
FEASIBILITY STUDY
ROUTE PROTECTION
PROPOSAL TO GOVERNMENT




                            220
RAILWAY BUILDING
        & MANAGEMENT
PRE-CONTRACT

 PREPARATION OF CONTRACT DOCUMENTS
     DESIGN STANDARDS MANUAL
     MATERIALS & WORKMANSHIP SPECIFICATION
     CONDITIONS OF CONTRACT
     BILLS OF QUANTITIES
 APPOINTMENT OF CONSULTANTS
 TENDERING
 CONTRACT AWARD

                                          221
RAILWAY BUILDING
     & MANAGEMENT
CONSTRUCTION

DESIGN MANAGEMENT
CONSTRUCTION MANAGEMENT
PROTECTION OF ADJACENT PROPERTIES
TESTING & COMMISSIONING
APPROVAL BY RAILWAY INSPECTORATE
HANDOVER TO OPERATIONS

                                 222
RAILWAY BUILDING
        & MANAGEMENT
IN SERVICE
 IMPROVEMENTS:
     NEW INTEGRATED ENTRANCES
     ENTRANCE UPGRADE
     RETROFITS - PLATFORM SCREEN DOORS
     FACILITIES FOR THE PHYSICALLY IMPAIRED
     KIOSKS
 CONDITION MONITORING
 MAINTENANCE
 RAILWAY PROTECTION

                                               223
MTRCL


      A STORY
         OF
OUTSTANDING SUCCESS


                      224
MTRCL

        HONG KONG PEOPLE


ENGINEERS               MTR STAFF




     HAVE REASON TO BE PROUD

                                225
This presentation is dedicated to :

          All my friends

  Especially those of the MTR

                                      226
227
BBC NEWS

19 APRIL 2006

                228

More Related Content

Similar to Mtr a success story 07.11.2011 v4

Aricle in Irish Trucker Magazine
Aricle in Irish Trucker MagazineAricle in Irish Trucker Magazine
Aricle in Irish Trucker MagazineTony O Neill
 
Community liason-group-presentation-10-02-2015
Community liason-group-presentation-10-02-2015Community liason-group-presentation-10-02-2015
Community liason-group-presentation-10-02-2015Auckland Transport
 
Integrated transport - investing in Auckland's future
Integrated transport - investing in Auckland's futureIntegrated transport - investing in Auckland's future
Integrated transport - investing in Auckland's futureAuckland Transport
 
July 24, 2013 City Council Freeway Aesthetic Concepts Presentation
July 24, 2013 City Council Freeway Aesthetic Concepts PresentationJuly 24, 2013 City Council Freeway Aesthetic Concepts Presentation
July 24, 2013 City Council Freeway Aesthetic Concepts PresentationCity of Corona
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewCrosstown TO
 
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...IEI GSC
 
high performance concrete
high performance concretehigh performance concrete
high performance concretebeerappa143
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Crosstown TO
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
Gabions in civil engineering ppt presentation
Gabions in civil engineering  ppt presentationGabions in civil engineering  ppt presentation
Gabions in civil engineering ppt presentationBnkvvnnnjn
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Crosstown TO
 
Deep South Resources Inc.
Deep South Resources Inc.Deep South Resources Inc.
Deep South Resources Inc.MomentumPR
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentationATUL SHUKLA
 
Karachi npp siting a violation
Karachi npp siting  a violationKarachi npp siting  a violation
Karachi npp siting a violationakhtar ali
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 
Reconstruction Of Veterans Lane Revised Mayhew
Reconstruction Of Veterans Lane Revised MayhewReconstruction Of Veterans Lane Revised Mayhew
Reconstruction Of Veterans Lane Revised Mayhewmayhew50
 
Presentation - Métropolis - Englis version
Presentation - Métropolis - Englis versionPresentation - Métropolis - Englis version
Presentation - Métropolis - Englis versionLouis-Alexandre Cazal
 

Similar to Mtr a success story 07.11.2011 v4 (20)

Aricle in Irish Trucker Magazine
Aricle in Irish Trucker MagazineAricle in Irish Trucker Magazine
Aricle in Irish Trucker Magazine
 
Community liason-group-presentation-10-02-2015
Community liason-group-presentation-10-02-2015Community liason-group-presentation-10-02-2015
Community liason-group-presentation-10-02-2015
 
Public Private Partnership
Public Private PartnershipPublic Private Partnership
Public Private Partnership
 
Integrated transport - investing in Auckland's future
Integrated transport - investing in Auckland's futureIntegrated transport - investing in Auckland's future
Integrated transport - investing in Auckland's future
 
July 24, 2013 City Council Freeway Aesthetic Concepts Presentation
July 24, 2013 City Council Freeway Aesthetic Concepts PresentationJuly 24, 2013 City Council Freeway Aesthetic Concepts Presentation
July 24, 2013 City Council Freeway Aesthetic Concepts Presentation
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design Review
 
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
 
high performance concrete
high performance concretehigh performance concrete
high performance concrete
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Gabions in civil engineering ppt presentation
Gabions in civil engineering  ppt presentationGabions in civil engineering  ppt presentation
Gabions in civil engineering ppt presentation
 
Team Downtown: Part One
Team Downtown: Part OneTeam Downtown: Part One
Team Downtown: Part One
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
Deep South Resources Inc.
Deep South Resources Inc.Deep South Resources Inc.
Deep South Resources Inc.
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentation
 
Karachi npp siting a violation
Karachi npp siting  a violationKarachi npp siting  a violation
Karachi npp siting a violation
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
LeBreton - Public Board Presentation
LeBreton - Public Board Presentation LeBreton - Public Board Presentation
LeBreton - Public Board Presentation
 
Reconstruction Of Veterans Lane Revised Mayhew
Reconstruction Of Veterans Lane Revised MayhewReconstruction Of Veterans Lane Revised Mayhew
Reconstruction Of Veterans Lane Revised Mayhew
 
Presentation - Métropolis - Englis version
Presentation - Métropolis - Englis versionPresentation - Métropolis - Englis version
Presentation - Métropolis - Englis version
 

More from laitsk

Hkie uk chapter hk land-of_opportunities_icl.10.03.2014
Hkie uk chapter   hk land-of_opportunities_icl.10.03.2014Hkie uk chapter   hk land-of_opportunities_icl.10.03.2014
Hkie uk chapter hk land-of_opportunities_icl.10.03.2014laitsk
 
Chinese language
Chinese languageChinese language
Chinese languagelaitsk
 
Chinese language
Chinese languageChinese language
Chinese languagelaitsk
 
Jts.vts memories
Jts.vts   memoriesJts.vts   memories
Jts.vts memorieslaitsk
 
Jts.vts memories
Jts.vts   memoriesJts.vts   memories
Jts.vts memorieslaitsk
 
Hktc memories of old hong kong technical college buildings v1
Hktc   memories of old hong kong technical college buildings v1Hktc   memories of old hong kong technical college buildings v1
Hktc memories of old hong kong technical college buildings v1laitsk
 
Hktc memories of old hong kong technical college buildings v1
Hktc   memories of old hong kong technical college buildings v1Hktc   memories of old hong kong technical college buildings v1
Hktc memories of old hong kong technical college buildings v1laitsk
 
Memories of old hong kong technical college buildings
Memories of old hong kong technical college buildingsMemories of old hong kong technical college buildings
Memories of old hong kong technical college buildingslaitsk
 

More from laitsk (8)

Hkie uk chapter hk land-of_opportunities_icl.10.03.2014
Hkie uk chapter   hk land-of_opportunities_icl.10.03.2014Hkie uk chapter   hk land-of_opportunities_icl.10.03.2014
Hkie uk chapter hk land-of_opportunities_icl.10.03.2014
 
Chinese language
Chinese languageChinese language
Chinese language
 
Chinese language
Chinese languageChinese language
Chinese language
 
Jts.vts memories
Jts.vts   memoriesJts.vts   memories
Jts.vts memories
 
Jts.vts memories
Jts.vts   memoriesJts.vts   memories
Jts.vts memories
 
Hktc memories of old hong kong technical college buildings v1
Hktc   memories of old hong kong technical college buildings v1Hktc   memories of old hong kong technical college buildings v1
Hktc memories of old hong kong technical college buildings v1
 
Hktc memories of old hong kong technical college buildings v1
Hktc   memories of old hong kong technical college buildings v1Hktc   memories of old hong kong technical college buildings v1
Hktc memories of old hong kong technical college buildings v1
 
Memories of old hong kong technical college buildings
Memories of old hong kong technical college buildingsMemories of old hong kong technical college buildings
Memories of old hong kong technical college buildings
 

Recently uploaded

Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...JojoEDelaCruz
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
Presentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxPresentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxRosabel UA
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operationalssuser3e220a
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Projectjordimapav
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
Dust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSEDust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSEaurabinda banchhor
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 

Recently uploaded (20)

Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
Presentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxPresentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptx
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operational
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Project
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
Dust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSEDust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSE
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 

Mtr a success story 07.11.2011 v4

  • 1. HONG KONG MASS TRANSIT RAILWAY A SUCCESS STORY PRESENTED BY Ir Thomas S K LAI CEng, MICE, MIStructE, MHKIE Chairman HKIE UK CHAPTER 0 ©
  • 2. BIRTH & GROWTH OF HONG KONG MASS TRANSIT RAILWAY UP TO DATE 1
  • 3. HONG KONG • LOCATED AT THE PEARL RIVER ESTUARY ON THE SOUTHERN COAST OF CHINA 2
  • 5. August 2003 77 HARBOUR FRONT 4
  • 7. CULTURAL REVOLUTION • In 1966 – CULTURAL REVOLUTION RAGING IN CHINA • SPILLED OVER TO HONG KONG • FARE INCREASE IN STAR FERRY • RIOTS • SERIOUS DISRUPTION TO PUBLIC TRANSPORT 6
  • 8. CULTURAL REVOLUTION HONG KONG IN CRISIS 7
  • 9. CULTURAL REVOLUTION HONG KONG IN CRISIS 危 机 • Danger Opportunity 8
  • 10. PLB PLB PUBLIC LIGHT BUS 9
  • 11. PLB • AVAILABLE - FREQUENT SERVICE • CONVENIENT - PASSENGERS HOP ON AND OFF ANYWHERE ALONG ROUTE • PREMIUM FOR SERVICE • POPULAR WITH PASSENGERS 10
  • 12. HONG KONG GOVERNMENT •VIABILITY OF UNDERGROUND RAILWAY SYSTEM •CONFIRMED BY CONSULTANT‟S FEASIBILITY STUDY •1975 - MASS TRANSIT PROVISIONAL AUTHORITY •1976 - MASS TRANSIT RAILWAY CORPORATION MTRC 11
  • 13. MTRC THE MASS TRANIST RAILWAY ORDINANCE 12
  • 14. MTRC • WHOLLY GOVERNMENT OWNED ENTERPRISE 13
  • 15. MTRC • MANDATED TO BUILD AND OPERATE AN UNDERGROUND RAILWAY SYSTEM • ON PRUDENT COMMERCIAL PRINCIPLES • HAVING REGARD TO THE REASONABLE REQUIREMENTS OF THE PUBLIC TRANSPORT SYSTEM OF HONG KONG 14
  • 16. MTRC HONG KONG GOVERNMENT PUTS IN INITIAL EQUITY (HK$ 800 M) MTRC BORROWS REST IN OPEN MONEY MARKET 15
  • 18. INITIAL SYSTEM LETTER OF INTENT SIGNED WITH JAPANESE CONSORTIUM FOR THE INITIAL SYSTEM (20 km) AS A SINGLE DESIGN & BUILD CONTRACT 17
  • 20. MODIFIED INITIAL SYSTEM MIS (15.6 km) 25 CIVIL & 10 E&M DESIGN AND BUILD CONTRACTS 19
  • 21. MIS GOVERNMENT SET UP MASS TRANSIT ADVISER (MTA) TO: • CO-ORDINATE BETWEEN MTRC & GOVERNMENT DEPARTMENTS • FACILITATE TIMELY POLICY MAKING & ISSUE RESOLUTION 20
  • 22. MIS DIFFERENT LEVEL OF COMMITTEES & WORKING GROUPS: • GOVERNMENT / MTR LIAISON COMMITTEE • GOVERNMENT / MTR PUBLICITY COMMITTEE • METRO PUBLIC RELATIONS POLICY GROUP 21
  • 23. MIS • LAND ACQUISITION CO-ORDINATION COMMITTEE (LACC) • STATION AND TRANSPORT INTEGRATION COMMITTEE (STIC) • SAFETY AND SECURITY CO-ORDINATION COMMITTEE (SSCC) • TRAFFIC MAMAGEMENT GROUP (TMG) • UTILITIES CO-ORDINATION GROUP (UCG) 22
  • 24. INSPECTORATE OF RAILWAY (UK) • APPOINTED BY GOVERNMENT AS ADVISER ON RAILWAY SAFETY • PROVIDES INPUT DURING DESIGN • INSPECTS RAILWAY SYSTEM • RECOMMENDS OPENING 23
  • 25. MIS IMPORTANCE OF PUBLIC RELATIONS • OBSERVATION WINDOWS ON HOARDINGS • GROWING FOR YOU 24
  • 26. MIS IMPORTANCE OF PUBLIC RELATIONS • CEREMONIES OF COMMENCEMENT & COMPLETION OF WORKS 25
  • 27. MIS IMPORTANCE OF PUBLIC RELATIONS PARTICIPANTS (STAKEHOLDERS) INCLUDE: CORPORATION REPRESENTATIVES CONTRACTORS CONSULTANTS GOVERNMENT OFFICIALS LEGISLATORS DISTRICT COUNCILLORS LOCAL DIGNITARIES 26
  • 28. MIS IMPORTANCE OF PUBLIC RELATIONS • TEAM BUILDING • PUBLICISING PROGRESS OF WORKS 27
  • 29. MIS WORK STARTED • NOVEMBER 1975 GROUNDBREAKING CEREMONY BY CHAIRMAN SIR NORMAN THOMPSON 28 AT KWUN TONG
  • 30. MIS • FIRST CHAIRMAN – SIR NORMAN THOMPSON  DIRECT ACCESS TO THE GOVERNOR  SIMPLE & CLEAR MESSAGES • PROJECT MANAGER – HONG KONG & SHANGHAI BANK HQ BUILDING 29
  • 31. MIS • FIRST M.D. – PROF. TONY RIDLEY • M.D. – LONDON UNDERGROUND MAJOR IMPROVEMENT TO THE SYSTEM • PROFESSOR – IMPERIAL COLLEGE LONDON 30
  • 32. MIS • HONG KONG PEOPLE – EXCITEMENT – EXPECTATION – DETERMINATION 31
  • 33. MIS • HONG KONG PEOPLE HIGH DEGREE OF TOLERENCE & CO-OPERATION 32
  • 34. MIS PROJECT MANAGEMENT APPROACH: • QUICK DECISION-MAKING • REGULAR MONITORING OF EFFECT OF CHANGES ON BUDGET & PROGRAMME • APPROPRIATE DELEGATION OF AUTHORITY • SHARE RISKS & BENEFITS WITH CONTRACTORS 33
  • 35. MIS • BASED ON PROVEN TECHNOLOGY • PROJECT MOTTO: IF IT IS ESSENTIAL, GET ON WITH IT. IF IT IS DESIRABLE, FORGET IT. 34
  • 36. MIS GOVERNMENT COMMUNITY MTRC UNITY IN PURPOSE 35
  • 37. MIS GROUND CONDITIONS  ALLUVIAL DEPOSITS  GRANITE (VARYING DEGREE OF DECOMPOSITION)  HARD ROCK 36
  • 43. MIS NGAU TAU KOK STATION & VIADUCT 42
  • 45. MIS ADMIRALTY STATION EXCAVATION 44
  • 47. MIS IMT 46
  • 48. MIS • FROM KWUN TONG TO CENTRAL KWUN TONG TO SHEK KIP MEI – OPERATIONAL ON 1 OCTOBER 1979 47
  • 49. MIS • FROM KWUN TONG TO CENTRAL KWUN TONG TO TSIM SHA TSUI – OPERATIONAL ON 31 DECEMBER 1979 48
  • 50. MIS • FROM KWUN TONG TO CENTRAL KWUN TONG TO CENTRAL – OPENED BY PRINCESS ALEXANDRA ON 12 FEBRUARY 1980 49
  • 51. MIS • FROM KWUN TONG TO CENTRAL ON TIME AND WITHIN BUDGET 50
  • 52. MIS ESTIMATED COST IN 1975 HK$ B (INCL. 7% p.a. ESCALATION TO 1980) 5.8 CONSTRUCTION COST 5.6 INCL. INTEREST AND FINANCE COST S 7.3 51
  • 53. MIS • NO SMOKING • NO EATING • NO DRINKING • NO MUSIC/RADIO 52
  • 54. MIS • CLEAN • QUIET • EFFICIENT • RELIABLE • AIR-CONDITIONED 53
  • 57. TWL • ENGINEER‟S DESIGN • CONTRACTOR‟S ALTERNATIVE PROPOSALS CONSIDERED & ADOPTED LAI KING TO KWAI FONG VIADUCT 56
  • 58. TWL • SET UP STRONG IN-HOUSE PROFESSIONAL PROJECT MANAGEMENT TEAM • HANDS-ON STYLE LAI KING TO KWAI FONG CROSS-OVER 57
  • 59. TWL • PROJECT TEAM RESPONSIBLE FOR:  FEASIBLITY STUDY  PROPOSAL TO GOVERNMENT  SPECIFICATION  APPOINTMENT OF CONSULTANTS  TENDERING  CONTRACT AWARD  DESIGN MANAGEMENT  CONSTRUCTION MANAGEMENT  TESTING & COMMISSIONING  HANDOVER TO OPERATIONS 58
  • 60. TWL • TSUEN WAN LINE – TSUEN WAN TO CENTRAL – OPERATIONAL 10 May 1982 (AHEAD OF PROGRAMME) 59
  • 61. TWL ESTIMATED COST IN 1978 HK$ B (INCL. ESCALATION TO 1982) 4.1 CONTRACT COSTS 3.7 CORPORATION COST CONSULATANTS‟ FEES LAND ACQUISITION COMPENSATION 0.7 FINAL CONSTRUCTION COST 3.9 INCL. INTEREST AND FINANCE COSTS 5.3 60
  • 62. ISL 61
  • 63. ISL • ISLAND LINE – CHAI WAN TO ADMIRALTY 31 MAY 1985 – CHAI WAN TO SHEUNG WAN 23 MAY 1986 62
  • 64. ISL ESTIMATED TOTAL COSTS HK$ B AT 1986 PRICES 10.9 (EXCL. INTEREST AND FINANCE COSTS) FINAL COST 10.0 INCL. INTEREST AND FINANCE COSTS 11.9 FORTESS HILL STATION 63
  • 65. ISL • CHAIRMAN & CEO : SIR WILFRID NEWTON  STRENGTHENED CORPORATION‟S FINANCE  LAID SOUND FOUNDATION FOR FUTURE GROWTH  RE-ORGANISED HONG KONG STOCK EXCHANGE AFTER MARKET COLLAPSE  DIRECTOR OF HONG KONG & SHANGHAI BANKING CORPORATION (HSBC)  HON. FELLOW - HKIE  CHAIRMAN – LONDON TRANSPORT OVERSAW JUBILEE LINE EXTENSION 64 CONSTRUCTION
  • 66. MTR ARRIVAL & GROWTH OF MTR COINCIDE WITH : TRANSFORMATION OF HONG KONG FROM REGIONAL CITY TO INTERNATIONAL FINANCIAL CENTRE 65
  • 67. HONG KONG LEASE • 99-YEAR LEASE EXPIRES ON 1 JULY 1997 • GOVERNMENT DEPENDS ON SALE OF LAND LEASES FOR REVENUE • NEEDS TO KNOW ITS FUTURE • NEGOTIATION BETWEEN LONDON & BEIJING 66
  • 68. HONG KONG LEASE • BRITISH PRIME MINISTER VISITED BEIJING • OFFER TO EXCHANGE SOVEREIGNTY FOR ADMINSTRATION • OFFER REJECTED BY CHINA 67
  • 69. HONG KONG LEASE BUT AGREED TO: • SET UP JOINT LIAISON COMMITTEE (JLC) • CONTINUE NEGOTIATION • MAINTAIN STABILITY & PROSPERITY OF HONG KONG 68
  • 70. HONG KONG LEASE • NEGOTIATION NOT GOING WELL • UNCERTAINTY 69
  • 71. HONG KONG LEASE • JITTERY & GLOOMY • INVESTMENTS PUT ON HOLD • STOCK MARKET CRASH • PROPERTY BUBBLE BURST 70
  • 72. HONG KONG LEASE HONG KONG DOLLAR PLUNGES FROM AROUND HK$ 6 = US$ 1 TO OVER HK$ 9 = US$ 1 71
  • 73. HONG KONG LEASE PEOPLE RUSH TO SUPERMARKET TO BUY : RICE 72
  • 74. HONG KONG LEASE PEOPLE RUSH TO SUPERMARKET TO BUY : RICE & BABY‟S POWDERED MILK 73
  • 75. HONG KONG LEASE • CURRENCY PEG HK$ 7.8 = US$ 1 74
  • 76. HONG KONG LEASE • CALM THE CITY • STOP PANIC 75
  • 77. HONG KONG LEASE • IN 1984 BRITAIN & CHINA SIGNED JOINT DECLARATION ON FUTURE OF HONG KONG • CHINA TO REGAIN FULL SOVEREIGNTY ON 1 JULY 1997 August 2003 85 76
  • 78. HONG KONG LEASE PROMISE TO HONG KONG PEOPLE • HONG KONG PEOPLE GOVERN HONG KONG • WITH HIGH DEGREE OF AUTONOMY • ONE COUNTRY TWO SYSTEMS • NO CHANGE FOR 50 YEARS 77
  • 79. HONG KONG LEASE •ENSHRINED IN •LODGED WITH BASIC LAW UNITED NATIONS 78
  • 80. HONG KONG LEASE • CURRENCY PEG HK$ 7.8 = US$ 1 • REMAINS TO THIS DAY 79
  • 81. MTRC • BORROWING IN US$ • REVENUE IN HK$ • ADVERSE IMPACT BY HIGH INTEREST RATE (12%) DEVALUATION 80
  • 82. MTRC • HONG KONG GOVERNMENT TO INCREASE EQUITY (HK$ 2.5 B ISSUED, 2.5 B ON CALL ) • SHIFT BORROWING TO BE HK$ DENOMINATED 81
  • 83. MTRC • IN NO POSITION TO FINANCE NEW EXTENSIONS 82
  • 84. EASTERN HARBOUR CROSSING 83
  • 85. EHC • BOT PROJECT BY OTHERS • LINKING KWUN TONG TO QUARRY BAY • THIRD CROSS HARBOUR TUNNEL CARRYING ROAD AND RAILWAY • RAIL PORTION LEASED TO MTRC EASTERN HARBOUR CROSSING ENTRANCE 84
  • 86. EHC MTRC PAYS SEMI-ANNUAL INSTALMENTS FOR 18½ YEARS TOTALLING HK$ 2.6 B OTHER CAPITAL INVESTMENT INCL. ROLLING STOCKS 0.365 B IMMERSED TUBE CASTING 85
  • 87. EHC OPENED BY PRINCE OF WALES ON 1 OCTOBER 1989 86
  • 88. AFTER JOINT DECLARATION • UNCERTAINTY REMOVED • CONFIDENCE RETURNED LIPPO CENTRE 87
  • 89. KAI TAK AIRPORT CHECKERBOARD IN SIGHT 88
  • 90. KAI TAK AIRPORT STEADY AS SHE GOES 89
  • 91. KAI TAK AIRPORT DO YOUR WINDOW SHOPPING BEFORE YOU LAND 90
  • 92. KAI TAK AIRPORT SEE....I LAND IT ON THE ROOF 91
  • 93. KAI TAK AIRPORT HARD RIGHT TURN AND DIVE 92
  • 94. KAI TAK AIRPORT BUT LANDING ON THE RUNWAY...... IS NOT ALWAYS 93 EASY
  • 95. KAI TAK AIRPORT SOMETIMES.... ENDED UP IN THE WATER 94
  • 96. AIRPORT CORE PROJECTS RELOCATE AIRPORT FROM KAI TAK TO CHEK LAP KOK 95
  • 97. AIRPORT CORE PROJECTS • APPROVED BY BEIJING & LONDON 96
  • 98. AIRPORT CORE PROJECTS • OBJECTIVES: – TO STIMULATE ECONOMY – TO FACILITATE FUTURE GROWTH – TO ELIMINATE AVIATION HAZARD – TO BE COMPLETED IN TIME FOR HANDOVER 97
  • 99. ACP • AIRPORT AT CHEK LAP KOK • TSING MA BRIDGE • LANTAU & AIRPORT RAILWAY 98
  • 100. ACP • KAP SHUI MUN BRIDGE • TING KAU BRIDGE • HIGHWAYS • RECLAMATIONS • THIRD CROSS HARBOUR ROAD TUNNEL (WESTERN HARBOUR CROSSING) 99
  • 101. ACP • HK$ 127 BILLION £ 10 BILLION 100
  • 102. ACP CHINA‟S CONCERN: • ROSE GARDEN PROJECT • EMPTY TREASURY • HIGH DEBT 101
  • 103. ACP AGREEMENT REACHED TO: • LEAVE HK$ 25 B MIN. IN TREASURY • CAP GOVERNMENT BORROWING AT HK$ 5 B UNLESS AGREED OTHERWISE • CAP ANNUAL LAND SALE NO MORE THAN 50 ha /year 102
  • 104. ACP • ESSENTIAL TO HAVE CHINA‟S AGREEMENT AND SUPPORT TO ASSURE INVESTORS • WRANGLING OVER FINANCIAL DATA DELAYED PROJECT START 103
  • 105. ACP AT TIME OF HANDOVER ON 30 JUNE/1 JULY 1997 • CHINESE PRESIDENT ARRIVED BY PLANE AT THE NEW AIRPORT • LAST BRITISH GOVERNOR LEFT ON ROYAL YACHT BRITANNIA 104
  • 107. HONG KONG INTERNATIONAL AIRPORT 106
  • 108. TSING MA BRIDGE (ROAD + RAIL) 107
  • 109. LANTAU & AIRPORT LINE 108
  • 110. LAL AIRPORT EXPRESS LINE (AEL) AIRPORT – HONG KONG 23 MINUTES JOURNEY IN-TOWN-CHECK-IN 109
  • 111. LAL TUNG CHUNG LINE (ON SHARED TRACK WITH AEL) TUNG CHUNG - HONG KONG COMMUTER LINE ALSO PROVIDES RELIEF TO NATHAN ROAD CONGESTION 110
  • 112. LAL FINANCIAL SUPPORT AGREEMENT (FSA) WITH GOVERNMENT • HK$ 23.7 B ADDITIONAL EQUITY BY GOVERNMENT • 62 ha LAND FOR DEVELOPMENT • DEFERRAL OF DIVIDENDS UNTIL 2001 • REVENUE DEFICIENCY PAYMENTS (80% FOR NO MORE THAN 2 YEARS IF DELAYED BY OTHERS) 111
  • 113. LAL • EXTENSIVE APPLICATION OF VALUE ENGINEERING • INTRODUCE PARTNERING 112
  • 114. TUNG CHUNG LINE NO MORE SLIDING SEATS 113
  • 115. AIRPORT EXPRESS • SPACIOUS SEATING • PLEASANT AMBIENCE • BUSINESS CLASS COMFORT FROM PLANE, THROUGH TRAIN, TO HOTEL AEL TRAIN 114
  • 116. LAL TCL OPERATIONAL ON 22 JUNE 1998 AEL OPERATIONAL ON 6 JULY 1998 115
  • 117. LAL HK$ B PROJECT COST 35.1 (INCLUDING CAPITALISED INTEREST) FINANCED BY: EQUITY 23.7 DEBT 11.4 116
  • 118. TSEUNG KWAN O LINE 117
  • 119. TKL • TSEUNG KWUN O LINE – COMMUTER LINE – FROM PO LAM TO NORTH POINT – OPERATIONAL ON 17 AUGUST 2002 118
  • 120. TKL I st JULY – 1997 ASIAN FINANCIAL CRISIS MAJOR REVIEW OF THE PROJECT 119
  • 121. TKL INITIAL CAPITAL COST ESTIMATE HK$ B INCL. CAPITALISED INTEREST 30.5 FINAL COST 16.0 HANG HAU STATION 120
  • 125. DRL • DISNEYLAND RESORT LINE – FROM SUNNY BAY TO DISNEYLAND – OPERATIONAL ON 12 SEPTEMBER 2005 124
  • 128. ASIAWORLD-EXPO STATION AIR STATION – ASIAWORLD-EXPO OPERATIONAL ON 20 DECEMBER 2005 127
  • 133. NGONG PING 360 AIRPORT ISLAND STATION TUNG CHUNG TERMINAL 132
  • 134. NGONG PING 360 • MATERIAL DELIVERY – HELICOPTERS – MULES 133
  • 135. NGONG PING 360 SCHEDULED OPENING 24 JUNE 2006 OPERATIONAL 18 SEPT 2006 OFFICIAL OPENING 9 NOV 2006 134
  • 136. NGONG PING 360 OPERATION SUSPENDED 11 JUNE 2007 OPERATION RESUMED 31 DEC 2007 SUBSIDIARY COMPANY SET UP TO MANAGE & OPERATE THE SYSTEM 135
  • 137. MTR CORPORATION AN OUTSTANDINGLY SUCCESSFUL ENTERPRISE 136
  • 138. MTRC SUCCESSES PROFILERATING  PROJECT MANAGEMENT  RAILWAY OPERATION  FINANCIAL EXPERTISE  TRAINING & DEVELOPMENT  PROPERTY  AUTOMATIC FARE COLLECTION 137
  • 139. MTRC • INVEST HEAVILY IN STAFF TRAINING & DEVELOPMENT • CORE VALUES :  CUSTOMER SERVICE  RESPECT FOR THE INDIVIDUAL  ON TIME AND WITHIN BUDGET 138
  • 140. MTRC • PROVIDES PROFESSIONAL TRAINING SERVICES TO OTHER RAILWAYS IN: – MAINLAND CHINA – SOUTHEAST ASIA 139
  • 141. PROPERTY DEVELOPMENT & MANAGEMENT • GOVERNMENT ALLOCATE LAND AT FULL MARKET VALUE ALONG THE RAILWAY FOR DEVELOPMENT 140
  • 142. PROPERTY DEVELOPMENT & MANAGEMENT • MAJOR & REPUTABLE PROPERTY DEVELOPER AND MANAGER IN TOWN • JOINT VENTURES – RESIDENTIAL – RETAIL – OFFICES – HOTEL 141
  • 143. PROPERTY DEVELOPMENT & MANAGEMENT • SUBSTANTIAL CONTRIBUTION TOWARDS COST OF RAILWAY • CAPTURED PASSENGERS (FORMING PART OF 2.4 M DAILY RIDERSHIP) 142
  • 144. PROPERTY DEVELOPMENT & MANAGEMENT PROCEEDS FROM DEVELOPMENTS HELP TO: • KEEP FARES AT REASONABLE LEVEL • MAINTAIN & EXTEND RAIL NETWORK 143
  • 145. PROPERTY DEVELOPMENT & MANAGEMENT 144
  • 146. PROPERTY DEVELOPMENT & MANAGEMENT TELFORD GARDEN 145
  • 147. PROPERTY DEVELOPMENT & MANAGEMENT PARK VIEW 146
  • 148. PROPERTY DEVELOPMENT & MANAGEMENT CENTRAL STATION RETAIL 147
  • 149. PROPERTY DEVELOPMENT & MANAGEMENT TELFORD PLAZA 148
  • 150. PROPERTY DEVELOPMENT & MANAGEMENT MARITIME SQUARE 149
  • 151. PROPERTY DEVELOPMENT & MANAGEMENT ELEMENTS 150
  • 152. 2 INTERNATIONAL FINANCE CENTRE 2IFC 151
  • 153. UNION SQUARE 152
  • 154. INTERNATIONAL COMMERCE CENTRE • 118 FLOORS • 490 METRES HIGH • THIRD TALLEST BUILDING IN THE WORLD ICC 153
  • 155. ICC ICC 154
  • 157. CHINA – BEIJING • PROPERTY OPEARATIONS & MANAGEMENT GINZA MALL 156
  • 158. PROPERTY DEVELOPMENT & MANAGEMENT AS AT END 2010: Investment properties : • 12 shopping malls + 18 floors at 2 IFC • 277,942 sq.m in Hong Kong Managed properties: • 81,962 residential units in Hong Kong • 744,214 sq.m commercial properties in Hong Kong • 776,402 sq.m in Mainland China 157
  • 159. AUTOMATIC FARE COLLECTION • ELECTRO-MAGNETIC CARD • STORED VALUE CARD • CONTACTLESS SMART CARD 158
  • 160. AUTOMATIC FARE COLLECTION ELECTRO-MAGNETIC CARD • PLASTIC • RE-USABLE • NO LITTER • ISSUED BY MACHINE / HAND • FIXED VALUE • ELECTRO-MAGNETIC • SINGLE JOURNEY 159
  • 161. MIS • NO SMOKING • NO EATING • NO DRINKING • NO MUSIC/RADIO • NO TICKET FLICKING 160
  • 162. AUTOMATIC FARE COLLECTION STORED VALUE • PLASTIC • RE-USABLE • NO LITTER • ISSUED BY MACHINE / HAND • FIXED VALUE • ELECTRO-MAGNETIC • MULTIPLE JOURNEYS • UNRESTRICTED LAST JOURNEY • ADVANCE REVENUE COLLECTION • REDUCTION IN CASH HANDLING 161
  • 163. AUTOMATIC FARE COLLECTION OCTOPUS CONTACTLESS SMART CARD • PLASTIC • ISSUED BY MACHINE / HAND • RE-USABLE • NO LITTER • MULTIPLE JOURNEYS • ADVANCE REVENUE • RADIO FREQUENCY IDENTIFICATION (RFID) • NO CONTACT AT TURNSTILE • TOP UP VALUE • FURTHER REDUCTION IN CASH HANDLING • ACCEPTED BY BUSINESS PARTNERS 162
  • 164. OCTOPUS CONTACTLESS SMART CARD • RELIABLE TICKETING • LABOUR SAVING • DATA FOR: OPERATIONAL PLANNIN INCLUDING PRICING 163
  • 165. OCTOPUS CONTACTLESS SMART CARD • FORERUNNER OF: • EZ-LINK – SINGAPORE • OYSTER CARD – LONDON • EASYCARD - TAIPEI 164
  • 166. OCTOPUS CONTACTLESS SMART CARD OTHER USES:  PUBLIC TRANSPORTS  CAR PARKS  ACCESS CONTROL TO BUILDINGS  CONFIRMATION OF STUDENTS‟ ATTENDANCE AT SCHOOL 165
  • 167. OCTOPUS CONTACTLESS SMART CARD AT END OF JUNE 2011: • 24.3 MILLION CARDS ISSUED (18.7 MILLION ACTIVE) • 11.7 MILLION DAILY TRANSACTIONS • HK$ 112.7 MILLION PER DAY • ADOPTED BY OVER 3000 SERVICE PROVIDERS 166
  • 168. MTR CORPORATION LTD LISTED ON THE HONG KONG EXCHANGE ON 5 OCTOBER 2000 167
  • 169. MTRCL EXPANSION NEW VISION : • TO BE A WORLD CLASS ENTERPRISE • GROWING IN HONG KONG & BEYOND • FOCUSING ON RAIL, PROPERTY & RELATED BUSINESS 168
  • 170. MTRCL • NEW MISSION : • EXCELLENT VALUE FOR CUSTOMERS • OPPORTUNITIES FOR STAFF • DEVELOP RAILWAY NETWORK AS BACKBONE OF PUBLIC TRANSPORT IN HONG KONG • GROW IN MAINLAND CHINA & CAPTURE OPPORTUNITIES IN EUROPE 169
  • 171. MTRCL • NEW CORE VALUES : EXCELLENT SERVICE VALUE CREATION MUTUAL RESPECT ENTERPRISING SPIRIT 170
  • 172. MERGER • HONG KONG GOVERNMENT ANNOUNCED MERGER PROPOSAL BETWEEN MTRCL & KCRC ON 11 APRIL 2006 171
  • 173. MERGER • KCRC • ORIGINALLY A GOVERNMENT DEPARTMENT • TURNED INTO A WHOLLY GOVERNMENT OWNED PUBLIC CORPORATION • CHARGED TO OPERATE AND DEVELOP DOMESTIC, CROSS-BOUNDARY AND INTERCITY RAILWAY SERVICES • IN A PRUDENT COMMERCIAL MANNER 172
  • 174. MERGER KCRC • OPERATES: – EAST RAIL – WEST RAIL – LIGHT RAIL – INTERCITY TO GUANGZHOU – FREIGHT TO INTERIOR OF MAINLAND CHINA 173
  • 176. MERGER • HONG KONG GOVERNMENT ANNOUNCED MERGER PROPOSAL BETWEEN MTRCL & KCRC ON 11 APRIL 2006 • MTRCL SIGNED MEMORANDUM OF UNDERSTANDING (MOU) WITH HK GOVERNMENT 175
  • 177. MERGER MOU PROVIDES FOR: • REDUCED FARE • ABOLITION OF SECOND BOARDING CHARGE • FURTHER DISCOUNTS FOR MEDIUM & LONG DISTANCE JOURNEYS • INTRODUCTION OF AN OBJECTIVE, TRANSPARENT & PREDICTABLE FARE ADJUSTMENT MECHANISM (FAM) • FULLY INTEGRATED INTERCHANGE STATIONS FOR SHATIN TO CENTRAL LINK • IMPROVEMENT ON EXISTING INTERCHANGE ARRANGEMENTS IN THE SHORT TERM • PROVISION OF SEAMLESS INTERCHANGE ARRANGEMENTS WITH FUTURE EXTENSIONS 176
  • 178. MERGER MOU PROVIDES FOR • JOB SECURITY FOR ALL FRONTLINE STAFF 177
  • 179. MERGER DEAL TERMS • PROVIDE A BALANCED PACKAGE FAIR TO ALL STAKEHOLDERS 178
  • 180. MERGER DEAL TERMS • ACQUISITION OF RENEWABLE OPERATIONAL RIGHT OF KCR FOR 50 YEARS – UPFRONT PAYMENT OF HK$4.25 BILLION FOR SERVICE CONCESSION AND TO PURCHASE CERTAIN RAIL ASSETS – HK$7.79 BILLION FOR A PROPERTY PACKAGE – FIXED ANNUAL PAYMENT OF HK$750 MILLION – VARIABLE ANNUAL PAYMENT BASED ON REVENUES GENERATED FROM KCR‟S RAIL AND RAIL-RELATED OPERATIONS • EXPECTED TO BE EPS & NPV ACCRETIVE FOR MTRCL 179
  • 181. MERGER MEET THE GOVERNMENT‟S FIVE PARAMETERS 1. ADOPTION OF A MORE OBJECTIVE AND TRANSPARENT FAM 2. ABOLITION OF THE SECOND BOARDING CHARGE & REVIEW FARE STRUCTURE TO REDUCE FARES 3. EARLY RESOLUTION OF INTERCHANGE ARRANGEMENTS FOR RAIL PROJECTS UNDER PLANNING, NOTABLY THE SHATIN TO CENTRAL LINK 4. ENSURE JOB SECURITY FOR FRONTLINE STAFF 5. PROVISION OF SEAMLESS INTERCHANGE ARRANGEMENTS IN THE LONG TERM 180
  • 182. MERGER BENEFITS • SYNERGY • ECONOMIES OF SCALE • COST EFFICIENCY • INTEGRATED RAIL SYSTEM 181
  • 183. MERGER TRANSITION - ONE YEAR OR MORE SHARE PRICE JUMPED 5.3% (FROM HK$19 TO 20) RAIL MERGER BILL APPROVED BY LegCo on 8 JUNE 2007 OUTLOOK - BRIGHT 182
  • 184. MERGED • COMPLETED ON 2 DECEMBER 2007 • 香港鐵路有限公司 ONE COMPANY ONE TEAM 183
  • 185. MERGED 184
  • 186. MERGED • 211 Km ROUTE LENGTH • 82 STATIONS • 9 COMMUTER LINES • AIRPORT EXPRESS • LIGHT RAIL • DISNEYLAND RESORT LINE • FEEDER BUS SERVICE • CABLE CAR • INTERCITY PASSENGER SERVICE • INTERCITY FREIGHT SERVICE • 3 MILLION DAILY PASSENGERS 185
  • 187. MERGED • ONE COMPANY, ONE TEAM STAFF INTEGRATION 186
  • 188. MTR CORPORATION LTD GROWTH MOMENTUM 187
  • 189. DUBAI 188
  • 190. DUBAI METRO & AIRPORT LINES 189
  • 191. DUBAI CONSULTANCY TO REVIEW DESIGN PROPOSALS IN RESPECT OF : OPERATION & MAINTENANCE VIADUCT CONSTRUCTION 190
  • 192. INDIA Delhi Airport Metro Express Line (AMEL) • Major engineering & project management contract 191
  • 193. UK BUSINESS BIDS 192
  • 194. UK BUSINESS LORO (MTR/LAING ) FRANCHISE TO OPERATE NORTH & EAST LONDON OVERGROUND LINES FROM 11 NOVEMBE 2007 FOR 7 YEARS WITH OPTION FOR 2 FURTHER YEARS SUCCESS 193
  • 195. UK BUSINESS LOROL (MTR/DEUTSCHE BAHN) ACTION ON DAY ONE • OYSTER TICKETING SYSTEM • NEW TICKETING MACHINES • STATIONS GATED 194
  • 196. UK BUSINESS (MTR/DEUTSCHE BAHN) • IMPROVEMENT IN: 1. SERVICE OPERATION 2. PUNCTUALITY 3. SAFETY 4. SECURITY • TICKETLESS TRAVEL DOWN • REVENUE UP 195
  • 197. UK BUSINESS (MTR/DEUTSCHE BAHN) PROGRAMME FOR: • CUSTOMER SERVICE TRAINING • STATION CLEANING AND REPAIR • STATION REFURBISHEMENT • STATION REMODELLING • NEW EXTENSIONS 196
  • 198. UK BUSINESS (MTR/DEUTSCHE BAHN) • “….so gradually all suburban rail services in London can be brought up to the standard of London Overground.” Ken Livingstone Mayor of London 197
  • 199. EUROPE BUSINESS STOCKHOLM UNDERGROUND TOOK OVER OPERATION 2 NOVEMBER 2009 (FOR 8 YEARS MINIMUM) 198
  • 200. AUSTRALIAN BUSINESS METRO TRAINS MELBOURNE TOOK OVER OPERATION ON 30 NOVEMBER 2009 (FOR INITIAL PERIOD OF 8 YEARS) 199
  • 202. CHINA BUSINESS SHANGHAI TOGETHER WITH ITS JOINT VENTURE PARTNER, APPOINTED AS:  OWNER‟S REPRESENTATIVE TO PROJECT MANAGE DESIGN AND CONSTRUCTION OF LINE 9  OWNER‟S ADVISOR OF LINE 8 & LINE 11 201
  • 203. CHINA BUSINESS BEIJING LINE 4 – INITIALLED IN FEBRUARY 2005 – COMPANY FORMED IN JANUARY 2006 – AGREEMENT SIGNED ON 12 APRIL 2006 202
  • 204. CHINA BUSINESS BEIJING LINE 4 – PPP – 30-YEAR CONCESSION AGREEMENT WITH BEIJING MUNICIPAL GOVERNMENT – FOR INVESTMENT, CONSTRUCTION & OPERATION OPENED 28 SEPTEMBER 2009 DAXING LINE OPENED 30 DECEMBER 2010 203
  • 205. CHINA BUSINESS SHENZHEN LINE 4 – 30-YEAR BOT PROJECT – CONCESSION AGREEMENT WITH SHENZHEN MUNICIPAL GOVERNMENT – „RAIL + PROPERTY‟ – INITIALLED IN MAY 2005 – PHASE 1 TAKEN OVER 01 JULY 2010 – PHASE 2 OPENED 16 JUNE 2011 204
  • 206. BUSINESS OUTSIDE HONG KONG COMPANY SHARE BEIJING MTR CORPORATION LTD. (BJMTR) 49% MTR CORPORATION ( SHENZHEN) LTD. (SZMTR) 100% METRO TRAINS MELBOURNE PTY. LTD. (MTM) 60% MTR STOCKHOLM AB (MTRS) 100% TUNNELBANAN TEKNIK STOCKHOLM AB (TBT) 50% LONDON OVERGROUND RAIL OPERATIONS LTD. (LOROL) 50% MTR HANGZHOU LINE 1 INVESTMENT CO. LTD. 100% 205
  • 207. MTRCL • PROFITABLE HK$B 16 14.2 14 Turnover 12 10.7 10 Operating profit 8 8.6 before depreciation (after property 6 development profit) Net profit excluding 4 investment property revaluation 2 0 206
  • 208. MTRCL 207
  • 209. MTRCL 208
  • 210. MTRCL CONSOLIDATED P & L A/C (YEAR ENDED 31 December 2010) HK$ M • REVENUE 29,500 • PROFIT ON PROPERTY DEVELOPMENTS 4,034 • OPERATING PROFIT BEFORE DEPRECIATION 10,917 • NET PROFIT ATTRIBUTABLE TO SHAREHOLDERS 12,059 209
  • 211. MTRCL AS AT END 2010: PATRONAGE ( million) Yearly 1,564 Daily 4.5 210
  • 212. HONG KONG GOVERNMENT INFRASTRUCTURE INVESTMENT • 2007-2008 POLICY ADDRESS ANNOUNCES TEN MAJOR INFRASTRUCTURE PROJECTS • ANNUAL EXPENDITURE OF HK$ 50 BILLION (£ 4 BILLION) IN COMING YEARS 211
  • 213. HONG KONG GOVERNMENT INFRASTRUCTURE INVESTMENT • Transport Infrastructure 1. South Island MTR Line 2. The Sha Tin to Central MTR Link 3. The Tuen Mun Western Bypass and Tuen Mun-Chek Lap Kok Link • Cross-boundary Infrastructure Projects 4. The Guangzhou-Shenzhen-HK Express Rail Link 5. HK-Shenzhen Airport Co-operation 6. HK-Zhuhai-Macao Bridge 7. HK-Shenzhen Joint Development of the Lok Ma Chau Loop • New Urban Development Areas 8. West Kowloon Cultural District 9. Kai Tak Development Plan 10. New Development Areas (NDAs) 212
  • 215. RAILWAY EXTENSIONS XRL 214
  • 216. RAILWAY EXTENSIONS WIL 215
  • 217. RAILWAY EXTENSIONS KTE 216
  • 218. RAILWAY EXTENSIONS SCL 217
  • 219. RAILWAY EXTENSIONS 218 SIL(E)
  • 220. RAILWAY EXTENSIONS EXTENSION PROJECT FUNDING XRL SERVICE CONCESSION (GOVERNMENT CAPITAL + MTRCL OPERATIONS) WIL CAPITAL GRANT KTE RAIL + PROPERTY SCL SERVICE CONCESSION SIL(E) RAIL + PROPERTY 219
  • 221. RAILWAY BUILDING & MANAGEMENT FEASIBILITY IDENTIFY TRANSPORT NEEDS FEASIBILITY STUDY ROUTE PROTECTION PROPOSAL TO GOVERNMENT 220
  • 222. RAILWAY BUILDING & MANAGEMENT PRE-CONTRACT  PREPARATION OF CONTRACT DOCUMENTS  DESIGN STANDARDS MANUAL  MATERIALS & WORKMANSHIP SPECIFICATION  CONDITIONS OF CONTRACT  BILLS OF QUANTITIES  APPOINTMENT OF CONSULTANTS  TENDERING  CONTRACT AWARD 221
  • 223. RAILWAY BUILDING & MANAGEMENT CONSTRUCTION DESIGN MANAGEMENT CONSTRUCTION MANAGEMENT PROTECTION OF ADJACENT PROPERTIES TESTING & COMMISSIONING APPROVAL BY RAILWAY INSPECTORATE HANDOVER TO OPERATIONS 222
  • 224. RAILWAY BUILDING & MANAGEMENT IN SERVICE  IMPROVEMENTS:  NEW INTEGRATED ENTRANCES  ENTRANCE UPGRADE  RETROFITS - PLATFORM SCREEN DOORS  FACILITIES FOR THE PHYSICALLY IMPAIRED  KIOSKS  CONDITION MONITORING  MAINTENANCE  RAILWAY PROTECTION 223
  • 225. MTRCL A STORY OF OUTSTANDING SUCCESS 224
  • 226. MTRCL HONG KONG PEOPLE ENGINEERS MTR STAFF HAVE REASON TO BE PROUD 225
  • 227. This presentation is dedicated to : All my friends Especially those of the MTR 226
  • 228. 227
  • 229. BBC NEWS 19 APRIL 2006 228