3. Footer Text
Mission & Goals
MISSION
– Working with others to provide safe and reliable transportation solutions for Texas
GOALS
– Maintain a safe system
– Address congestion
– Connect Texas communities
– Best in class state agency
3
4. Footer Text
100 Most Congested Roadway Segments in Texas
US 290: I-610 to FM 529 - #18
I-610: I-10 to I-45 - #20
US 290: FM 529 to FM 1960 #32
4
5. Footer Text
US 290 Program Overview
US 290: I-610 to FM 2920
– 35 miles ($2.4 billion)
5
Hempstead: I-610 to SH 99
– 24 miles ($2.3 billion)
Record of Decision (ROD) approved 2010
6. Footer Text
Interim Solution
Funding current concept not feasible
Interim partnership solution on US 290 ($1.8 billion)
6
Rehabilitate Hempstead Road (Started August 2013)
Environmental Re-evaluation Document Public Comment Period
ended September 18th, 2013
7. Footer Text
Partnership
Key Funding Partners
– State and Federal Elected Officials – Approval of state and federal funds
– Harris County – Judge, Harris County Commissioners Court, Public Infrastructure Department, Toll
Road Authority
– Houston Galveston Area Council – Transportation Policy Council
Other Partners
– Federal Highway Administration
– Metropolitan Transit Authority of Harris County
– City of Houston
– City of Jersey Village
Community Partners
– Cy-Fair Chamber of Commerce
– West Houston Association
– Near Northwest Management District
– Greater Houston Partnership
7
8. Footer Text
Funding
Original US 290/Hempstead Tollway Program Cost - $4.7
billion
Interim Phased Plan - $1.8 billion
– Harris County - $400 million
– Rider 42 funds/Prop 12 - $168 million
– Other Prop 12 - $440 million
– Prop 14 - $123 million
– Other State - $84 million
– Federal - $646 million
8
9. Footer Text
Memorandum of Understanding
TxDOT and Harris County Toll Road Authority –
executed April 2012
– Partnership to leverage resources and maximize interim congestion relief
Interim US 290 from I-610 to SH 99 (Grand Parkway)
– 4-general purpose lanes each direction
– Reversible 3 to 2 managed lanes in center
– Harris County to operate and maintain managed lanes
• Revenue stays in the region
– Rehabilitate Hempstead Road
9
11. Footer Text
Accelerating Construction
7 project construction contracts awarded
5 projects and Hempstead Tollway remaining to let for construction
11
Estimate/
Bid
$83M $104M$41M $91M $135M $58M $110M $153M $143M $107M (Project J-1)
$142M (Project J-2)
$151M (Project K)
12. Footer Text
Construction
Project K (I-610/US 290 Partial Interchange)
– Congestion relief on I-10, I-610, US 290
– Construction contract awarded May 26, 2011
– $151 million contract; $6.79 million incentives
– Estimated completion 2015
Project J-1 (I-610/US 290 Partial Interchange)
– Construction contract awarded October 25, 2012
– $107 million contract; $5.76 million incentives
– Estimated completion 2016
12
13. Footer Text
Construction
Project G (US 290/Beltway 8 Interchange)
– Congestion relief on US 290, Beltway 8, Sam Houston Tollway
– Significant safety enhancements
– Construction contract awarded September 26, 2012
– $110 million contract; $5 million incentives
– Estimated completion 2016
13
15. Footer Text
Public Information Program
Dedicated Public Information Office and Staff
Brookhollow Central III
2950 North Loop West, Suite 1150
Houston, TX 77092
Website: www.my290.com
@my290Houston
Hotline Number: 1-866-95US290 (1-866-958-7290)
15