Guidelines to set Priority for Requirements / Task
Value: Requirement /Task that creates value to the customer (Rating Scale: 1 to 10, where 10 is highest & 1 is Lowest)
Effort: The amount of Estimated effort in Hours
Priority :The higher the priority points, the higher the priority.
Value
Effort
Priority
Goal: 1. To deliver the most value to the customer for the smallest amount of effort.
2. Effective Time management.
3. Guidelines to set Priority for Requirements / Task
Sample
# Requiremen/Task/ Work
Value
Creation for Customer Effort(hrs) Priority Which Req/Task to start with
1 R001 8 20 -12 9th
2 R002 8 5 3 3rd
3 R003 5 20 -15 10th
4 R004 10 1 9 1st
5 R005 9 10 -1 6th
6 R006 6 4 2 4th
7 R007 7 10 -3 8th
8 R008 4 5 -1 7th
9 R009 10 3 7 2nd
10 R010 6 5 1 5th
Scale 1 to 10 Value – Effort = Priority