SlideShare une entreprise Scribd logo
1  sur  23
Télécharger pour lire hors ligne
TSX : AXY
1 DEC 2011    COMPANY PRESENTATION
Forward-Looking Information



    This Presentation contains certain “forward-looking information” within the meaning of Canadian securities laws, which may include, but is
    not limited to, statements with respect to future events or future performance, management’s expectations regarding Alterra’s production
    capacity, results of operations, cash flows, revenues and requirements for capital, future demand for and prices of electricity, and Alterra’s
    business prospects and opportunities.

    These statements reflect the current views of Alterra with respect to future events and are necessarily based upon a number of
    assumptions and estimates that, while considered reasonable by Alterra, are inherently subject to significant business, economic, political
    and social uncertainties and contingencies. Many factors, both known and unknown, could cause Alterra’s actual results, performance or
    achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such
    forward-looking statements contained in this presentation, and Alterra has made assumptions based on or related to many of these
    factors. Such factors include, without limitation: fluctuations in currency markets (particularly with respect to the Icelandic krona, the U.S.
    dollar and Canadian dollar); risks related to the technological and operational nature of Alterra’s business; changes in national or regional
    governments, legislation, regulation, permitting or taxation; political or economic developments in Canada, the United States, Iceland or
    other countries where Alterra may carry on business; risks and hazards associated with the business of renewable energy generation;
    risks relating to the creditworthiness and financial condition of suppliers and other parties which Alterra will deal with; inadequate
    insurance or inability to obtain insurance to cover these risks and hazards; employee relations; relationships with and claims by local
    communities and First Nations; availability and costs of equipment and labour; litigation; the success and timely completion of planned
    expansion and development programs; the growth rate in net electricity consumption; support and demand for renewable energy;
    government initiatives to support the development of renewable energy generation; the reliability of technical data and capital expenditure
    estimates; and availability of capital to fund development and expansion programs. Forward-looking information and statements are also
    based upon the assumption that none of the identified risk factors that could cause actual results to differ materially from the forward-
    looking information and statements will occur.

    Although Alterra has attempted to identify important factors that could cause actual results to differ materially, there may be other factors
    that cause results not to be as anticipated, estimated, described or intended. There can be no assurance that the forward-looking
    information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information.
    Accordingly, prospective investors should not place undue reliance on forward-looking information. Other than as required by applicable
    securities laws, Alterra does not assume any obligation to update or revise such forward-looking information to reflect new events or
    circumstances.




2
Alterra Power – Strategy and Assets

    Our mission: to be a leading global renewable energy company

    Clean energy: permanent, stable cash flow with zero fuel cost/exposure
       Incentives are great (USA, Chile, Europe) but not essential (Iceland)
       Core infrastructure business – once built, permanent value

    Our assets today:
       Generation:

                   Hydro     Two large run-of-river plants in BC - 235 MW (40% Alterra)
                    Wind     BC’s largest wind farm - 144 MW (51% Alterra)
             Geothermal      Two power plants in Iceland - 175 MW (75% Alterra)
                             One power plant in Nevada - 16 MW (100% Alterra)

       Pipeline: 509 MW development pipeline in wind, hydro, geothermal
       Balance Sheet: $1.1 billion total assets
       Management Team: Deep experience in wind, hydro, geothermal


3
Recent Growth Metrics

                    Magma Energy (founded 2008) acquired Plutonic Power in 2011; name
                    changed to Alterra Power Corp

                          CAPACITY   (end of year)                                          PRODUCTION
                   350                                                              1,800
                                                                                    1,600
                   300
                                                                                    1,400
                   250
                                                                                    1,200
                   200                                                              1,000




                                                                     GWh
    MW




                   150                                                               800
                                                                                     600
                   100
                                                                                     400
                    50                                                               200
                     0                                                                 0
                          2009    2010           2011e       2012e                          2009     2010   2011e   2012e


                          REVENUE                                                           EBITDA
                   $120                                                              $70
                                                                                     $60
                   $100
                                                                                     $50
    Millions USD




                    $80
                                                                     Millions USD    $40
                    $60                                                              $30
                                                                                     $20
                    $40
                                                                                     $10
                    $20
                                                                                       $-
                     $-                                                             $(10)
                           2009   2010               2011e   2012e                          2009     2010   2011e   2012e


4
Balanced Portfolio - Global Exploration and Operations

                        ICELAND:
                            2 geothermal power plants with 175 MW capacity (75% Alterra)
                            Additional 130 MW of defined expansion plans
                            80 MW of expansions underway


                        WESTERN CANADA:
                            Toba-Montrose hydro plants with 235 MW capacity (40% Alterra)
                            Dokie wind farm with 144 MW capacity (51% Alterra)
                            124 MW Upper Toba expansion and 156 MW Dokie 2 expansion


                        WESTERN USA:
                            16 MW geothermal power plant with expansion potential
                            Excellent government support for geothermal projects
                            6 other early stage properties


                        CHILE
                            Very large (320 MW) inferred resource discovered at low cost
                            Emerging renewable power markets with world-class potential
                            Strong government support for geothermal projects
                            Active exploration concessions covering in excess of 158,000 ha

                        FURTHER GROWTH ASSETS IN ONTARIO, BC, ITALY AND PERU

5
Assets and Pipeline

                                                         Capacity
                      Project                        Gross   AXY Share   Technology

                      Operating (2011)

                      Soda Lake                       16 MW     16 MW    Geothermal

                      Svartsengi                      75 MW     56 MW    Geothermal

                      Reykjanes 1 & 2                100 MW     75 MW    Geothermal
                      East Toba &
                                                     235 MW     94 MW    Hydro
                      Montrose
                      Dokie 1                        144 MW     73 MW    Wind

                      Total Capacity                570 MW     315 MW
                      Annual Net Generation 1,529 GWh

                      Operating Additions (2016)

                      Upper Toba                     124 MW    62 MW     Hydro

                      Ontario Solar                   50 MW     5 MW     Solar

                      Reykjanes 3 & 4                 80 MW    60 MW     Geothermal

                      Dokie 2                        156 MW    80 MW     Wind

                      McCoy                           15 MW    15 MW     Geothermal

                      Mariposa                        50 MW    50 MW     Geothermal

                      Eldvörp                         50 MW    38 MW     Geothermal

                      Other (e.g. Chile, Iceland)    200 MW    200 MW    Geothermal
                      Pipeline Total                 725 MW    509 MW
                      Total Capacity                1,295 MW   824 MW



6
Outstanding Developer Track Record

    Successful developer track record across renewable
    technologies
        Proven ability to develop and deliver large new assets at
         greenfield locations
        Development teams from all these projects remain
         substantially intact

    Recent project successes

    Wind              Dokie               144 MW        2011 COD
    Hydro             Toba Montrose       236 MW        2010 COD
    Geothermal        Reykjanes           100 MW        2006 COD


    Near term organic growth - all near existing operations

    Wind              Dokie 2             156 MW       COD 2014E
    Hydro             Upper Toba          124 MW       COD 2015E
    Geothermal        Reykjanes 3/4        80 MW       COD 2013-14E




7
Leading Growth Profile

                   Alterra has one of Canada’s largest clean energy development pipelines
             900                                                                                                        6,000

             800
                                                                                                               153      5,000
             700

             600                                                                                               156      4,000
                                                                                                      153
    Net MW




             500




                                                                                                                                GWh
                                                                                                                        3,000
             400
                                                                                   153                156

             300                                                      73                                                2,000
                                         73         73
                                                                                    94                         510
                             94                                       94
             200                         94         94
                                                                                                      295               1,000
             100          191                                        185           207
                                        147        147

              0                                                                                                         0
                         2010          2011        2012              2013          2014           2015         2016
                                   GEOTHERMAL             HYDRO             WIND              SOLAR


                        Existing Generation     Capacity Additions


                   Soda Lake          Dokie 1   ABW Solar         Reykjanes 3   Reykjanes 4     Eldvörp      Pipeline
                   HS Orka                                                      Dokie 2         Maule
                   Toba Montrose                                                                Upper Toba




8
Analyst Coverage and Capital Structure

 C APITAL S TRUCTURE :       PRO- FORMA NET INTEREST

MARKET CAPITALIZATION (30 NOV 2011)                                           C$ 184 MM

CASH (30 SEP 2011)                                                           US$ 41 MM

TOTAL ASSETS (30 SEP 2011)                                                  US$ 907 MM

LONG TERM DEBT (30 SEP 2011)                                                US$ 513 MM



FIRM                              CONTACT              EMAIL
Canaccord Genuity                 Jared Alexander      jalexander@canaccordgenuity.com
Cormark Securities                MacMurray Whale      mwhale@cormark.com
Jacob Securities                  John McIlveen        jmcilveen@jacobsecurities.com
Mackie Research Capital           Matthew Gowing       matthew.gowing@researchcapital.com
Mirabaud Securities               Gus Hochschild       gus.hochschild@mirabaud.co.uk
National Bank Financial           Jeremy Mersereau     jeremy.mersereau@nbfinancial.com
Pritchard Capital Partners        Veny Aleksandrov     valeksandrov@pritchardcapital.com
Raymond James Securities          Steven Li            steven.li@raymondjames.ca
Salman Partners                   Mike Plaster         mplaster@salmanpartners.com
INDEX COVERAGE
Ardour Global Alternative Energy Index
S&P/TSX Clean Technology Index
RENIXX Renewable Energy Industrial Index




9
Value Proposition Summary / Next Milestones

VALUE PROPOSITION

     Core Producing Assets - long term, stable cash flow

     Diversified Assets - by geography & generation type

     Larger Size - better liquidity, lower cost of capital

     Outstanding Project Pipeline - geothermal, hydro, wind assets
     could triple output by 2016

     Exceptional operating, financial and development teams



NEXT MILESTONES

     Iceland PPA and financing for next 130 MW expansion

     Chile partner financing and next phase of drilling at Maule

     Exploration of new Peruvian and Italian concessions

     Continuing expansion at Soda Lake and US assets

     Advancement of Dokie 2 and Upper Toba projects

     Ongoing M&A opportunities




10
TSX : AXY
11 DEC 2011   www.alterrapower.ca
TSX : AXY
12 DEC 2011   www.alterrapower.ca
Senior Management

     Outstanding development, financial and operations expertise

                 Ross Beaty: Executive Chairman
                 Geologist and resource company entrepreneur with 40 years experience in the international minerals industry. In early 2008,
                 Mr. Beaty founded Magma Energy Corp to focus on international geothermal energy development. In 2011 Magma and
                 Plutonic Power merged to create Alterra Power. Mr. Beaty is the Director of the Nature Trust B.C. and patron of the Beaty
                 Biodiversity Center at the University of B.C. Recipient of numerous awards, including the prestigious Viola Macmillan Award.


                 Donald McInnes: Executive Vice-Chairman
                 Mr. McInnes was the founder, Vice-Chair and CEO of Plutonic Power Corp. He currently serves as Vice-Chair of the Clean
                 Energy Association of British Columbia and is a director of Prostate Cancer Canada, the Powell River Economic
                 Development Society, the Duke of Edinburgh's Award-British Columbia and Yukon Division and is a governor of the British
                 Columbia Business Council.

                 John Carson: Chief Executive Officer
                 Mr. Carson is a highly experienced renewable energy business leader with a core expertise in structuring and leading
                 financial transactions. His financing experience includes senior positions held with GE Energy Financial Services, Terra-Gen
                 Power and Noble Environmental Power. He has closed over US$2 billion of transactions, primarily in the renewable energy
                 space, including geothermal, wind and hydro transactions.

                 Bruce Ripley: Chief Operating Officer
                 Mr. Ripley has 30 years of engineering experience in the hydroelectric and heavy civil industries, including 16 years with BC
                 Hydro where he was Vice President of Engineering. He oversees all technical and commercial work at Alterra’s assets
                 including operations and exploration. He has worked on development, design, construction, operations and maintenance
                 projects in Canada, USA, China, Philippines and Australia.

                 Peter Wong: Chief Financial Officer
                 Mr. Wong joined the Company in 2005; over the last 18 years he has held a number of progressive senior financial
                 management positions with publicly listed mining and technology companies at the venture, development and operational
                 stages. Mr. Wong articled with the accounting firm of Deloitte and Touche and obtained his CA designation in 1992. He is a
                 current member of the Institute of Chartered Accountants of BC and holds a B.Comm. from the University of B.C.



13
Board of Directors

Ross Beaty                   Mr. Beaty is a geologist and resource company entrepreneur with more than 40 years of experience in the international
                              minerals industry, Founder and chair of Magma Energy Corp and Pan American Silver (TSX: PAA, NASDAQ: PAAS) and
Executive Chairman            several other resource companies that were successfully built and divested.

Donald A. McInnes            Mr. McInnes was the Founder, Vice-Chair and CEO of Plutonic Power Corporation. He currently serves as Vice-Chair of the
                              Clean Energy Association of British Columbia and is a director of Prostate Cancer Canada, the Powell River Economic
Executive Vice-Chairman       Development Society, the Duke of Edinburgh's Award-British Columbia and Yukon Division and is a governor of the British
                              Columbia Business Council.

David Cornhill               Mr. Cornhill is the founder, Chairman and Chief Executive Officer of AltaGas Income Trust, one of Canada's largest energy
                              infrastructure groups, focused on gas and power infrastructure and renewable energy (wind and hydro). With more than 25
Director                      years of experience in the energy industry, Mr. Cornhill also sits on several private and public boards including AltaGas Utility
                              Group and Ivey Business School.

David O’Brien                Mr. O'Brien is retired as President and Chief Executive Officer, Toronto Hydro Corporation where he served between 2004-
                              2009. Mr. O'Brien was previously with Ontario's Ministry of Energy, initially as Associate Deputy Minister of Energy and
Director                      subsequently as Deputy Minister. Mr. O'Brien has also served as President and Chief Executive Officer of Enersource
                              Corporation, the parent company of Hydro Mississauga. Mr. O'Brien is a member of the Board of OMERS, Apex Co-Vantage
                              and the Summerhill Group, as well as a strategic advisor on energy matters to a number of other companies.

Donald Shumka                Mr. Shumka is Managing Director of Walden Management Ltd., a financial consulting firm. Mr. Shumka received a Master of
                              Business Administration from Harvard University. From 1966 to 1979 he worked in a variety of positions in the forest industry,
Director                      from 1979 to 1989 he was Vice President and Chief Financial Officer of West Fraser Timber Co. Ltd. and from 1989 to 2004
                              he headed the Forest Products Group for two Canadian investment banks. Other public company boards include Eldorado
                              Gold Corp and Paladin Energy Ltd.

Paul Sweeney                 Mr. Sweeney has over 30 years experience in financial management of mining and renewable energy companies. From
                              2007-2010, he was Executive Vice President, Corporate Development, of Plutonic Power Corporation. He has served as
Director                      CFO of a number of successful mineral resource companies including Canico Resources, Sutton Resources and Gibraltar
                              Mines and is a director of several resource companies including Pan American Silver Corp. where he chairs the audit
                              committee.

Walter Segsworth             Mr. Segsworth recently served as Chairman of Plutonic Power Corporation. He is past President and Director of Westmin
                              Resources. Upon the takeover of Westmin by Boliden in 1998, Mr. Segsworth joined Homestake Mining Company of
Director                      California where he was subsequently appointed President, Director and Chief Operating Officer and served until the merger
                              with Barrick in early 2002. He is past Chairman of both the Mining Associations of BC and Canada and was named BC's
                              Mining Person of the Year in 1996.



14
Overview - Toba Montrose in B.C.

     Alterra owns a 40% economic interest in two recently completed run of river
     hydroelectric generation facilities in southwestern British Columbia

 Facilities            East Toba River and Montrose Creek


 Capacity &
                       236 MW generating 727 GWh / year
 Production


                       60% - GE EFS
 Ownership
                       40% - Alterra


 Start of Operation    2010


 Power Purchase
                       EPA to 2045 with BC Hydro
 Agreement


                       $470 MM total project debt with 35 year amortization and
 Project Debt
                        6.4% effective interest rate

                       2011E project revenue of $74 MM
 Revenue
                          • Includes $10/MWh ecoEnergy Program incentive

                       2011E project EBITDA of $60 MM
 EBITDA
                          • $24 MM net EBITDA to Alterra



15
Overview - Dokie Wind in B.C.

     Alterra owns a 51% economic interest in the recently completed Dokie Wind
     Farm, located in northern British Columbia

 Facilities            Dokie Wind Farm


 Capacity &
                       144 MW generating 330 GWh annually
 Production

                       51% - Alterra
 Ownership
                       49% - GE EFS


 Start of Operation    March 2, 2011


 Power Purchase
                       EPA to 2036 with BC Hydro
 Agreement


                       $175 MM total project debt with 20 year amortization and
 Project Debt
                        7.2% effective interest rate

                       Annual project revenue of $35 - $40 MM
 Revenue
                         • Includes $10/MWh ecoEnergy Program incentive

                       Annual project EBITDA of $27 MM
 EBITDA
                         • $14 MM net EBITDA to Alterra



16
Overview - Svartsengi and Reykjanes in Iceland

     Alterra’s 75% - owned subsidiary HS Orka owns two geothermal power plants in
     southwestern Iceland

 Facilities            Svartsengi and Reykjanes


 Capacity &            175 MW generating 1,315 GWh /year
 Production            Thermal (hot water) production 150 MW th

                       75% - Alterra
 Ownership
                       25% - Jarôvarmi (Icelandic Pension Funds)


 Start of Operation    1978 for Svartsengi and 2006 for Reykjanes


                       Four PPAs with terms expiring from 2011 to 2026;
 Power Purchase         additional power sold on one-year contracts
 Agreements
                       46% of power sales paid in USD and linked to aluminum price

                       $170 MM total company debt with average 9 years to maturity
 Project Debt
                        and average 2.645% effective current interest rate


 Revenue               2011E project revenue of $64 MM



 EBITDA                2011E project EBITDA of $20 MM




17
Overview - Soda Lake in Nevada

     Alterra owns a 23 MW geothermal power plant near Fallon in northern Nevada



 Facilities            Soda Lake 1 and Soda Lake 2


 Capacity &            23 MW, currently operating at 16 MW gross and generating
 Production             84 GWh /year


 Ownership             100% - Alterra



 Start of Operation    1987 & 1991


 Power Purchase
                       Two PPAs to 2020 with NV Energy
 Agreement


 Project Debt          None



 Revenue               2011E project revenue of $5 MM



 EBITDA                2011E project EBITDA of $1 MM




18
Overview - ABW Solar in Ontario

     Alterra has an option to acquire a 10% interest in a portfolio of solar facilities
     from First Solar, to be built in southern Ontario


 Facility              3 solar facilities in southwestern Ontario


                       Amherstburg – 10 MW
 Capacity              Belmont – 20 MW
                       Walpole – 20 MW


 Proposed              90% - GE EFS
 Ownership             10% - Alterra


                       Mid 2012 E
 Start of Operation
                       Construction to start in 4Q 2011


 Power Purchase
                       20 year EPA with Ontario Power Authority
 Agreement



 Project Debt          TBD



 EBITDA                $3 MM net annual EBITDA to Alterra




19
Overview - Upper Toba Expansion Project in B.C.

     A power purchase agreement and permitting are in place for additional run of
     river hydro plants near the Toba Montrose facilities in southwestern B.C.

                      Jimmie Creek and Upper Toba River
 Locations
                      In the close vicinity to existing Toba Montrose facility

 Capacity &
                      124 MW generating 316 GWh annually
 Production

                      50% - Alterra
 Ownership
                      50% - GE EFS

                      Environmental Assessment Certificate granted and Water
 Permitting
                       Licence pending

 Power Purchase
 Agreement            In place with BC Hydro



Begin Construction    1Q 2013 E



On Line               2Q 2015 E


                      Completion of preliminary engineering & cost estimation
Notes                  targeted for end of 2011
                      Utilizes existing transmission and road infrastructure


20
Overview - Reykjanes 3 & 4 Expansion Project in Iceland

     The Reykjanes geothermal power plant in southwestern Iceland has substantial
     existing well capacity and is permitted for an expansion of production

 Location             Existing Reykjanes facility and steam field


 Capacity &
                      80 MW generating 687 GWh annually
 Production

                      75% - Alterra
 Ownership
                      25% - Jarôvarmi (Icelandic Pension Funds)


 Permitting           Completed


 Power Purchase
 Agreement            H1 2012 E



Begin Construction    H2 2012 E


                      Reykjanes 3 - 50 MW in H2 2013 E
On Line
                      Reykjanes 4 - 30 MW in H1 2014 E

                      High pressure 50 MW turbine for Reykjanes 3 already on site
Notes                 Reykjanes 4 will run on existing well field output in a 30 MW
                       low pressure turbine


21
Overview - Dokie 2 Expansion Project in B.C.

     The Dokie Wind Farm in northern B.C. is permitted for a 156 MW expansion



 Location             Undeveloped ridgelines within Dokie Wind Farm area


 Capacity &
                      156 MW generating 357 GWh annually
 Production

                      51% - Alterra
 Ownership
                      49% - GE EFS


 Permitting           Existing permitting allows total with Dokie 1 of 300 MW


 Power Purchase
 Agreement            Opportunity to discuss with BC Hydro and other off-takers



Begin Construction    1Q 2013 E



On Line               3Q 2014 E


                      Wind assessment, turbine layout, infrastructure and financial
Notes                  studies in progress




22
Overview - Mariposa Development Project in Chile

     The Mariposa geothermal field in Chile has an inferred-level capacity of 320 MW


                   In the Andes Mountains in south-central Chile, approximately
 Location
                    300 km south of Santiago

                   320 MW inferred resource with promising characteristics
 Capacity &
 Production
                   Exploitation Concession granted for first phase of 50 MW
                   Permanent production concession at Laguna del Maule
 Ownership         Resource area continues on adjacent Pellado concession
                   Alterra has a third adjacent concession at Los Cristales

                   Letter authorizing first round of exploratory holes
 Permitting
                   Baseline prepared for subsequent permitting

 Exploration &     Access road and infrastructure advanced - 2010
 Development       Three slim holes completed by core drilling - Nov 2010


Next Phase         Deep rotary and wide diameter drilling planned - 2012 E        BRAZIL




On Line            2016 E


                   Recent volcanism and hot springs near concession
Notes
                   Seeking investment partner for next phase



23

Contenu connexe

Tendances

Corporate presentation april
Corporate presentation   aprilCorporate presentation   april
Corporate presentation aprilMPX_RI
 
MMX 2011 result webcast
MMX 2011 result webcastMMX 2011 result webcast
MMX 2011 result webcastmmxriweb
 
Tses Plass Presentation
Tses Plass PresentationTses Plass Presentation
Tses Plass PresentationSimon Kapenda
 
01 edwin koot - solarplaza
01   edwin koot - solarplaza01   edwin koot - solarplaza
01 edwin koot - solarplazaLinea Trovata
 
Rio grande valley past present future
Rio grande valley past present futureRio grande valley past present future
Rio grande valley past present futureFirstAmericanRealty
 
Goldman Sachs Fourth Annual Global Steel CEO Forum
 	 Goldman Sachs Fourth Annual Global Steel CEO Forum  	 Goldman Sachs Fourth Annual Global Steel CEO Forum
Goldman Sachs Fourth Annual Global Steel CEO Forum finance15
 
International Markets & Policy on Renewable Energy
International Markets & Policy on Renewable EnergyInternational Markets & Policy on Renewable Energy
International Markets & Policy on Renewable Energyreeep
 
Market Research Report : Renewable Energy Market in Norway 2009
Market Research Report :  Renewable Energy Market in Norway 2009Market Research Report :  Renewable Energy Market in Norway 2009
Market Research Report : Renewable Energy Market in Norway 2009Netscribes, Inc.
 
CMD 2012: Supply and Trade Focus (Alvin Rosvoll)
CMD 2012: Supply and Trade Focus (Alvin Rosvoll)CMD 2012: Supply and Trade Focus (Alvin Rosvoll)
CMD 2012: Supply and Trade Focus (Alvin Rosvoll)Yara International
 
Obama FY2010 Budget
Obama FY2010 BudgetObama FY2010 Budget
Obama FY2010 BudgetRobert Bluey
 
Bruce yandle-chc-january
Bruce yandle-chc-januaryBruce yandle-chc-january
Bruce yandle-chc-januaryMercatus Center
 
AREVA, business & strategy overview - January 2009 - Appendix 7
AREVA, business & strategy overview - January 2009 - Appendix 7AREVA, business & strategy overview - January 2009 - Appendix 7
AREVA, business & strategy overview - January 2009 - Appendix 7AREVA
 
Us silver corporate presentation november 2011
Us silver corporate presentation november 2011Us silver corporate presentation november 2011
Us silver corporate presentation november 2011ussilver
 
Session 2A - Les Shephard
Session 2A - Les ShephardSession 2A - Les Shephard
Session 2A - Les ShephardReenergize
 

Tendances (20)

Guyana -Trade Profile [UWI's Shridath Ramphal Centre]
Guyana -Trade Profile [UWI's Shridath Ramphal Centre]Guyana -Trade Profile [UWI's Shridath Ramphal Centre]
Guyana -Trade Profile [UWI's Shridath Ramphal Centre]
 
Exxon Mobil 2012 Energy Outlook
Exxon Mobil 2012 Energy OutlookExxon Mobil 2012 Energy Outlook
Exxon Mobil 2012 Energy Outlook
 
Corporate presentation april
Corporate presentation   aprilCorporate presentation   april
Corporate presentation april
 
MMX 2011 result webcast
MMX 2011 result webcastMMX 2011 result webcast
MMX 2011 result webcast
 
Tses Plass Presentation
Tses Plass PresentationTses Plass Presentation
Tses Plass Presentation
 
The Bahamas - Trade Profile UWI's Shridath Ramphal Centre
The Bahamas - Trade Profile UWI's Shridath Ramphal CentreThe Bahamas - Trade Profile UWI's Shridath Ramphal Centre
The Bahamas - Trade Profile UWI's Shridath Ramphal Centre
 
01 edwin koot - solarplaza
01   edwin koot - solarplaza01   edwin koot - solarplaza
01 edwin koot - solarplaza
 
Haiti - Trade Profile [UWI's Shridath Ramphal Centre]
Haiti  - Trade Profile [UWI's Shridath Ramphal Centre]Haiti  - Trade Profile [UWI's Shridath Ramphal Centre]
Haiti - Trade Profile [UWI's Shridath Ramphal Centre]
 
Rio grande valley past present future
Rio grande valley past present futureRio grande valley past present future
Rio grande valley past present future
 
Goldman Sachs Fourth Annual Global Steel CEO Forum
 	 Goldman Sachs Fourth Annual Global Steel CEO Forum  	 Goldman Sachs Fourth Annual Global Steel CEO Forum
Goldman Sachs Fourth Annual Global Steel CEO Forum
 
Dominican Republic -Trade Profile UWI's Shridath Ramphal Centre
Dominican Republic -Trade Profile UWI's Shridath Ramphal CentreDominican Republic -Trade Profile UWI's Shridath Ramphal Centre
Dominican Republic -Trade Profile UWI's Shridath Ramphal Centre
 
International Markets & Policy on Renewable Energy
International Markets & Policy on Renewable EnergyInternational Markets & Policy on Renewable Energy
International Markets & Policy on Renewable Energy
 
Market Research Report : Renewable Energy Market in Norway 2009
Market Research Report :  Renewable Energy Market in Norway 2009Market Research Report :  Renewable Energy Market in Norway 2009
Market Research Report : Renewable Energy Market in Norway 2009
 
Changing Donor Priorities and Strategies for Agricultural R&D in Developing C...
Changing Donor Priorities and Strategies for Agricultural R&D in Developing C...Changing Donor Priorities and Strategies for Agricultural R&D in Developing C...
Changing Donor Priorities and Strategies for Agricultural R&D in Developing C...
 
CMD 2012: Supply and Trade Focus (Alvin Rosvoll)
CMD 2012: Supply and Trade Focus (Alvin Rosvoll)CMD 2012: Supply and Trade Focus (Alvin Rosvoll)
CMD 2012: Supply and Trade Focus (Alvin Rosvoll)
 
Obama FY2010 Budget
Obama FY2010 BudgetObama FY2010 Budget
Obama FY2010 Budget
 
Bruce yandle-chc-january
Bruce yandle-chc-januaryBruce yandle-chc-january
Bruce yandle-chc-january
 
AREVA, business & strategy overview - January 2009 - Appendix 7
AREVA, business & strategy overview - January 2009 - Appendix 7AREVA, business & strategy overview - January 2009 - Appendix 7
AREVA, business & strategy overview - January 2009 - Appendix 7
 
Us silver corporate presentation november 2011
Us silver corporate presentation november 2011Us silver corporate presentation november 2011
Us silver corporate presentation november 2011
 
Session 2A - Les Shephard
Session 2A - Les ShephardSession 2A - Les Shephard
Session 2A - Les Shephard
 

En vedette

NWACC EMPACTS Serves Up Soup for the Poor
NWACC EMPACTS Serves Up Soup for the PoorNWACC EMPACTS Serves Up Soup for the Poor
NWACC EMPACTS Serves Up Soup for the PoorBarbara Rademacher
 
NWACC EMPACTS Students Help Canine Rescue
NWACC EMPACTS Students Help Canine RescueNWACC EMPACTS Students Help Canine Rescue
NWACC EMPACTS Students Help Canine RescueBarbara Rademacher
 
NWACC EMPACTS BA Students Collect Food for Haiti
NWACC EMPACTS BA Students Collect Food for HaitiNWACC EMPACTS BA Students Collect Food for Haiti
NWACC EMPACTS BA Students Collect Food for HaitiBarbara Rademacher
 
NWACC EMPACTS Helps Helping Hands
NWACC EMPACTS Helps Helping HandsNWACC EMPACTS Helps Helping Hands
NWACC EMPACTS Helps Helping HandsBarbara Rademacher
 
NWACC EMPACTS BA Students Help Horse Rescue
NWACC EMPACTS BA Students Help Horse RescueNWACC EMPACTS BA Students Help Horse Rescue
NWACC EMPACTS BA Students Help Horse RescueBarbara Rademacher
 
NWACC EMPACTS Students Help TASC
NWACC EMPACTS Students Help TASCNWACC EMPACTS Students Help TASC
NWACC EMPACTS Students Help TASCBarbara Rademacher
 
Alterra Presentation August 2012
Alterra Presentation August 2012Alterra Presentation August 2012
Alterra Presentation August 2012Alterra Power Corp.
 
Constructivism: How to Use It to Improve YOUR Teaching and Learning
Constructivism:  How to Use It to Improve YOUR Teaching and LearningConstructivism:  How to Use It to Improve YOUR Teaching and Learning
Constructivism: How to Use It to Improve YOUR Teaching and LearningBarbara Rademacher
 

En vedette (19)

Axy 7 July
Axy 7 JulyAxy 7 July
Axy 7 July
 
Alterra presentation oct
Alterra presentation   octAlterra presentation   oct
Alterra presentation oct
 
Alterra presentation Nov
Alterra presentation   NovAlterra presentation   Nov
Alterra presentation Nov
 
NWACC EMPACTS Serves Up Soup for the Poor
NWACC EMPACTS Serves Up Soup for the PoorNWACC EMPACTS Serves Up Soup for the Poor
NWACC EMPACTS Serves Up Soup for the Poor
 
Alterra Presentation - MAY 2012
Alterra Presentation -  MAY 2012Alterra Presentation -  MAY 2012
Alterra Presentation - MAY 2012
 
NWACC EMPACTS Students Help Canine Rescue
NWACC EMPACTS Students Help Canine RescueNWACC EMPACTS Students Help Canine Rescue
NWACC EMPACTS Students Help Canine Rescue
 
Magma presentation-feb 21-2011
Magma presentation-feb 21-2011Magma presentation-feb 21-2011
Magma presentation-feb 21-2011
 
Magma presentation feb-1_2011
Magma presentation feb-1_2011Magma presentation feb-1_2011
Magma presentation feb-1_2011
 
Gb52
Gb52Gb52
Gb52
 
Magma presentation-jan 2011
Magma presentation-jan 2011Magma presentation-jan 2011
Magma presentation-jan 2011
 
NWACC EMPACTS BA Students Collect Food for Haiti
NWACC EMPACTS BA Students Collect Food for HaitiNWACC EMPACTS BA Students Collect Food for Haiti
NWACC EMPACTS BA Students Collect Food for Haiti
 
NWACC EMPACTS Helps Helping Hands
NWACC EMPACTS Helps Helping HandsNWACC EMPACTS Helps Helping Hands
NWACC EMPACTS Helps Helping Hands
 
NWACC EMPACTS BA Students Help Horse Rescue
NWACC EMPACTS BA Students Help Horse RescueNWACC EMPACTS BA Students Help Horse Rescue
NWACC EMPACTS BA Students Help Horse Rescue
 
AXY Aug 2011
AXY Aug 2011AXY Aug 2011
AXY Aug 2011
 
Magma presentation-nov17
Magma presentation-nov17Magma presentation-nov17
Magma presentation-nov17
 
NWACC EMPACTS Students Help TASC
NWACC EMPACTS Students Help TASCNWACC EMPACTS Students Help TASC
NWACC EMPACTS Students Help TASC
 
Alterra Presentation August 2012
Alterra Presentation August 2012Alterra Presentation August 2012
Alterra Presentation August 2012
 
Alterra presentation sep
Alterra presentation    sepAlterra presentation    sep
Alterra presentation sep
 
Constructivism: How to Use It to Improve YOUR Teaching and Learning
Constructivism:  How to Use It to Improve YOUR Teaching and LearningConstructivism:  How to Use It to Improve YOUR Teaching and Learning
Constructivism: How to Use It to Improve YOUR Teaching and Learning
 

Similaire à Alterra presentation DEC

Alterra Presentation May 29 - 2012
Alterra Presentation May 29 - 2012Alterra Presentation May 29 - 2012
Alterra Presentation May 29 - 2012Alterra Power Corp.
 
Magma - Corporate Presenation - October 2010
Magma - Corporate Presenation - October 2010Magma - Corporate Presenation - October 2010
Magma - Corporate Presenation - October 2010Alterra Power Corp.
 
January 2013 - Presentation
January 2013 - PresentationJanuary 2013 - Presentation
January 2013 - PresentationPotashRidge
 
Development Bank of Jamaica Presentation by Alexander Ochs
Development Bank of Jamaica Presentation by Alexander OchsDevelopment Bank of Jamaica Presentation by Alexander Ochs
Development Bank of Jamaica Presentation by Alexander OchsWorldwatchEn
 
January 2013 - Presentation
January 2013 - PresentationJanuary 2013 - Presentation
January 2013 - PresentationPotashRidge
 
February 2013 - Presentation
February 2013 - PresentationFebruary 2013 - Presentation
February 2013 - PresentationPotashRidge
 
Presentation feb12013
Presentation feb12013Presentation feb12013
Presentation feb12013PotashRidge
 
Avion Corporate Presentation, April 2010
Avion Corporate Presentation, April 2010Avion Corporate Presentation, April 2010
Avion Corporate Presentation, April 2010Avion Gold Corp
 
Magma presentation-feb-16 -2011
Magma presentation-feb-16 -2011Magma presentation-feb-16 -2011
Magma presentation-feb-16 -2011Intact
 
Magma presentation-feb 17-2011-
Magma presentation-feb 17-2011-Magma presentation-feb 17-2011-
Magma presentation-feb 17-2011-Intact
 
Claude Resources Inc. PDAC 2013 Presentation
Claude Resources Inc. PDAC 2013 PresentationClaude Resources Inc. PDAC 2013 Presentation
Claude Resources Inc. PDAC 2013 PresentationClaude Resources Inc.
 
Full Steam Ahead For Philippine Geothermal Energy
Full Steam Ahead For Philippine Geothermal EnergyFull Steam Ahead For Philippine Geothermal Energy
Full Steam Ahead For Philippine Geothermal EnergyFernando Penarroyo
 
Smart Grid Solutions in India - Arvind Patravali
Smart Grid Solutions in India - Arvind PatravaliSmart Grid Solutions in India - Arvind Patravali
Smart Grid Solutions in India - Arvind PatravaliBoston University
 
Magma Energy Corp. - Corporate Presentation - July 2010
Magma Energy Corp. - Corporate Presentation - July 2010Magma Energy Corp. - Corporate Presentation - July 2010
Magma Energy Corp. - Corporate Presentation - July 2010Alterra Power Corp.
 

Similaire à Alterra presentation DEC (20)

Alterra presentation sep
Alterra presentation   sepAlterra presentation   sep
Alterra presentation sep
 
Alterra Presentation May 29 - 2012
Alterra Presentation May 29 - 2012Alterra Presentation May 29 - 2012
Alterra Presentation May 29 - 2012
 
Magma - Corporate Presenation - October 2010
Magma - Corporate Presenation - October 2010Magma - Corporate Presenation - October 2010
Magma - Corporate Presenation - October 2010
 
Magma presentation-jan 2011
Magma presentation-jan 2011Magma presentation-jan 2011
Magma presentation-jan 2011
 
January 2013 - Presentation
January 2013 - PresentationJanuary 2013 - Presentation
January 2013 - Presentation
 
Development Bank of Jamaica Presentation by Alexander Ochs
Development Bank of Jamaica Presentation by Alexander OchsDevelopment Bank of Jamaica Presentation by Alexander Ochs
Development Bank of Jamaica Presentation by Alexander Ochs
 
Magma presentation-dec
Magma presentation-decMagma presentation-dec
Magma presentation-dec
 
January 2013 - Presentation
January 2013 - PresentationJanuary 2013 - Presentation
January 2013 - Presentation
 
February 2013 - Presentation
February 2013 - PresentationFebruary 2013 - Presentation
February 2013 - Presentation
 
Presentation feb12013
Presentation feb12013Presentation feb12013
Presentation feb12013
 
Avion Corporate Presentation, April 2010
Avion Corporate Presentation, April 2010Avion Corporate Presentation, April 2010
Avion Corporate Presentation, April 2010
 
Uintah Basin Energy and Transportation Study
Uintah Basin Energy and Transportation StudyUintah Basin Energy and Transportation Study
Uintah Basin Energy and Transportation Study
 
Magma presentation-feb-16 -2011
Magma presentation-feb-16 -2011Magma presentation-feb-16 -2011
Magma presentation-feb-16 -2011
 
Magma presentation-feb-15 -2011
Magma presentation-feb-15 -2011Magma presentation-feb-15 -2011
Magma presentation-feb-15 -2011
 
Magma presentation-feb 17-2011-
Magma presentation-feb 17-2011-Magma presentation-feb 17-2011-
Magma presentation-feb 17-2011-
 
Claude Resources Inc. PDAC 2013 Presentation
Claude Resources Inc. PDAC 2013 PresentationClaude Resources Inc. PDAC 2013 Presentation
Claude Resources Inc. PDAC 2013 Presentation
 
Barrack
BarrackBarrack
Barrack
 
Full Steam Ahead For Philippine Geothermal Energy
Full Steam Ahead For Philippine Geothermal EnergyFull Steam Ahead For Philippine Geothermal Energy
Full Steam Ahead For Philippine Geothermal Energy
 
Smart Grid Solutions in India - Arvind Patravali
Smart Grid Solutions in India - Arvind PatravaliSmart Grid Solutions in India - Arvind Patravali
Smart Grid Solutions in India - Arvind Patravali
 
Magma Energy Corp. - Corporate Presentation - July 2010
Magma Energy Corp. - Corporate Presentation - July 2010Magma Energy Corp. - Corporate Presentation - July 2010
Magma Energy Corp. - Corporate Presentation - July 2010
 

Dernier

WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 

Dernier (20)

WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 

Alterra presentation DEC

  • 1. TSX : AXY 1 DEC 2011 COMPANY PRESENTATION
  • 2. Forward-Looking Information This Presentation contains certain “forward-looking information” within the meaning of Canadian securities laws, which may include, but is not limited to, statements with respect to future events or future performance, management’s expectations regarding Alterra’s production capacity, results of operations, cash flows, revenues and requirements for capital, future demand for and prices of electricity, and Alterra’s business prospects and opportunities. These statements reflect the current views of Alterra with respect to future events and are necessarily based upon a number of assumptions and estimates that, while considered reasonable by Alterra, are inherently subject to significant business, economic, political and social uncertainties and contingencies. Many factors, both known and unknown, could cause Alterra’s actual results, performance or achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements contained in this presentation, and Alterra has made assumptions based on or related to many of these factors. Such factors include, without limitation: fluctuations in currency markets (particularly with respect to the Icelandic krona, the U.S. dollar and Canadian dollar); risks related to the technological and operational nature of Alterra’s business; changes in national or regional governments, legislation, regulation, permitting or taxation; political or economic developments in Canada, the United States, Iceland or other countries where Alterra may carry on business; risks and hazards associated with the business of renewable energy generation; risks relating to the creditworthiness and financial condition of suppliers and other parties which Alterra will deal with; inadequate insurance or inability to obtain insurance to cover these risks and hazards; employee relations; relationships with and claims by local communities and First Nations; availability and costs of equipment and labour; litigation; the success and timely completion of planned expansion and development programs; the growth rate in net electricity consumption; support and demand for renewable energy; government initiatives to support the development of renewable energy generation; the reliability of technical data and capital expenditure estimates; and availability of capital to fund development and expansion programs. Forward-looking information and statements are also based upon the assumption that none of the identified risk factors that could cause actual results to differ materially from the forward- looking information and statements will occur. Although Alterra has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated, described or intended. There can be no assurance that the forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, prospective investors should not place undue reliance on forward-looking information. Other than as required by applicable securities laws, Alterra does not assume any obligation to update or revise such forward-looking information to reflect new events or circumstances. 2
  • 3. Alterra Power – Strategy and Assets Our mission: to be a leading global renewable energy company Clean energy: permanent, stable cash flow with zero fuel cost/exposure  Incentives are great (USA, Chile, Europe) but not essential (Iceland)  Core infrastructure business – once built, permanent value Our assets today:  Generation: Hydro Two large run-of-river plants in BC - 235 MW (40% Alterra) Wind BC’s largest wind farm - 144 MW (51% Alterra) Geothermal Two power plants in Iceland - 175 MW (75% Alterra) One power plant in Nevada - 16 MW (100% Alterra)  Pipeline: 509 MW development pipeline in wind, hydro, geothermal  Balance Sheet: $1.1 billion total assets  Management Team: Deep experience in wind, hydro, geothermal 3
  • 4. Recent Growth Metrics Magma Energy (founded 2008) acquired Plutonic Power in 2011; name changed to Alterra Power Corp CAPACITY (end of year) PRODUCTION 350 1,800 1,600 300 1,400 250 1,200 200 1,000 GWh MW 150 800 600 100 400 50 200 0 0 2009 2010 2011e 2012e 2009 2010 2011e 2012e REVENUE EBITDA $120 $70 $60 $100 $50 Millions USD $80 Millions USD $40 $60 $30 $20 $40 $10 $20 $- $- $(10) 2009 2010 2011e 2012e 2009 2010 2011e 2012e 4
  • 5. Balanced Portfolio - Global Exploration and Operations ICELAND:  2 geothermal power plants with 175 MW capacity (75% Alterra)  Additional 130 MW of defined expansion plans  80 MW of expansions underway WESTERN CANADA:  Toba-Montrose hydro plants with 235 MW capacity (40% Alterra)  Dokie wind farm with 144 MW capacity (51% Alterra)  124 MW Upper Toba expansion and 156 MW Dokie 2 expansion WESTERN USA:  16 MW geothermal power plant with expansion potential  Excellent government support for geothermal projects  6 other early stage properties CHILE  Very large (320 MW) inferred resource discovered at low cost  Emerging renewable power markets with world-class potential  Strong government support for geothermal projects  Active exploration concessions covering in excess of 158,000 ha FURTHER GROWTH ASSETS IN ONTARIO, BC, ITALY AND PERU 5
  • 6. Assets and Pipeline Capacity Project Gross AXY Share Technology Operating (2011) Soda Lake 16 MW 16 MW Geothermal Svartsengi 75 MW 56 MW Geothermal Reykjanes 1 & 2 100 MW 75 MW Geothermal East Toba & 235 MW 94 MW Hydro Montrose Dokie 1 144 MW 73 MW Wind Total Capacity 570 MW 315 MW Annual Net Generation 1,529 GWh Operating Additions (2016) Upper Toba 124 MW 62 MW Hydro Ontario Solar 50 MW 5 MW Solar Reykjanes 3 & 4 80 MW 60 MW Geothermal Dokie 2 156 MW 80 MW Wind McCoy 15 MW 15 MW Geothermal Mariposa 50 MW 50 MW Geothermal Eldvörp 50 MW 38 MW Geothermal Other (e.g. Chile, Iceland) 200 MW 200 MW Geothermal Pipeline Total 725 MW 509 MW Total Capacity 1,295 MW 824 MW 6
  • 7. Outstanding Developer Track Record Successful developer track record across renewable technologies  Proven ability to develop and deliver large new assets at greenfield locations  Development teams from all these projects remain substantially intact Recent project successes Wind Dokie 144 MW 2011 COD Hydro Toba Montrose 236 MW 2010 COD Geothermal Reykjanes 100 MW 2006 COD Near term organic growth - all near existing operations Wind Dokie 2 156 MW COD 2014E Hydro Upper Toba 124 MW COD 2015E Geothermal Reykjanes 3/4 80 MW COD 2013-14E 7
  • 8. Leading Growth Profile Alterra has one of Canada’s largest clean energy development pipelines 900 6,000 800 153 5,000 700 600 156 4,000 153 Net MW 500 GWh 3,000 400 153 156 300 73 2,000 73 73 94 510 94 94 200 94 94 295 1,000 100 191 185 207 147 147 0 0 2010 2011 2012 2013 2014 2015 2016 GEOTHERMAL HYDRO WIND SOLAR Existing Generation Capacity Additions Soda Lake Dokie 1 ABW Solar Reykjanes 3 Reykjanes 4 Eldvörp Pipeline HS Orka Dokie 2 Maule Toba Montrose Upper Toba 8
  • 9. Analyst Coverage and Capital Structure C APITAL S TRUCTURE : PRO- FORMA NET INTEREST MARKET CAPITALIZATION (30 NOV 2011) C$ 184 MM CASH (30 SEP 2011) US$ 41 MM TOTAL ASSETS (30 SEP 2011) US$ 907 MM LONG TERM DEBT (30 SEP 2011) US$ 513 MM FIRM CONTACT EMAIL Canaccord Genuity Jared Alexander jalexander@canaccordgenuity.com Cormark Securities MacMurray Whale mwhale@cormark.com Jacob Securities John McIlveen jmcilveen@jacobsecurities.com Mackie Research Capital Matthew Gowing matthew.gowing@researchcapital.com Mirabaud Securities Gus Hochschild gus.hochschild@mirabaud.co.uk National Bank Financial Jeremy Mersereau jeremy.mersereau@nbfinancial.com Pritchard Capital Partners Veny Aleksandrov valeksandrov@pritchardcapital.com Raymond James Securities Steven Li steven.li@raymondjames.ca Salman Partners Mike Plaster mplaster@salmanpartners.com INDEX COVERAGE Ardour Global Alternative Energy Index S&P/TSX Clean Technology Index RENIXX Renewable Energy Industrial Index 9
  • 10. Value Proposition Summary / Next Milestones VALUE PROPOSITION Core Producing Assets - long term, stable cash flow Diversified Assets - by geography & generation type Larger Size - better liquidity, lower cost of capital Outstanding Project Pipeline - geothermal, hydro, wind assets could triple output by 2016 Exceptional operating, financial and development teams NEXT MILESTONES Iceland PPA and financing for next 130 MW expansion Chile partner financing and next phase of drilling at Maule Exploration of new Peruvian and Italian concessions Continuing expansion at Soda Lake and US assets Advancement of Dokie 2 and Upper Toba projects Ongoing M&A opportunities 10
  • 11. TSX : AXY 11 DEC 2011 www.alterrapower.ca
  • 12. TSX : AXY 12 DEC 2011 www.alterrapower.ca
  • 13. Senior Management Outstanding development, financial and operations expertise Ross Beaty: Executive Chairman Geologist and resource company entrepreneur with 40 years experience in the international minerals industry. In early 2008, Mr. Beaty founded Magma Energy Corp to focus on international geothermal energy development. In 2011 Magma and Plutonic Power merged to create Alterra Power. Mr. Beaty is the Director of the Nature Trust B.C. and patron of the Beaty Biodiversity Center at the University of B.C. Recipient of numerous awards, including the prestigious Viola Macmillan Award. Donald McInnes: Executive Vice-Chairman Mr. McInnes was the founder, Vice-Chair and CEO of Plutonic Power Corp. He currently serves as Vice-Chair of the Clean Energy Association of British Columbia and is a director of Prostate Cancer Canada, the Powell River Economic Development Society, the Duke of Edinburgh's Award-British Columbia and Yukon Division and is a governor of the British Columbia Business Council. John Carson: Chief Executive Officer Mr. Carson is a highly experienced renewable energy business leader with a core expertise in structuring and leading financial transactions. His financing experience includes senior positions held with GE Energy Financial Services, Terra-Gen Power and Noble Environmental Power. He has closed over US$2 billion of transactions, primarily in the renewable energy space, including geothermal, wind and hydro transactions. Bruce Ripley: Chief Operating Officer Mr. Ripley has 30 years of engineering experience in the hydroelectric and heavy civil industries, including 16 years with BC Hydro where he was Vice President of Engineering. He oversees all technical and commercial work at Alterra’s assets including operations and exploration. He has worked on development, design, construction, operations and maintenance projects in Canada, USA, China, Philippines and Australia. Peter Wong: Chief Financial Officer Mr. Wong joined the Company in 2005; over the last 18 years he has held a number of progressive senior financial management positions with publicly listed mining and technology companies at the venture, development and operational stages. Mr. Wong articled with the accounting firm of Deloitte and Touche and obtained his CA designation in 1992. He is a current member of the Institute of Chartered Accountants of BC and holds a B.Comm. from the University of B.C. 13
  • 14. Board of Directors Ross Beaty  Mr. Beaty is a geologist and resource company entrepreneur with more than 40 years of experience in the international minerals industry, Founder and chair of Magma Energy Corp and Pan American Silver (TSX: PAA, NASDAQ: PAAS) and Executive Chairman several other resource companies that were successfully built and divested. Donald A. McInnes  Mr. McInnes was the Founder, Vice-Chair and CEO of Plutonic Power Corporation. He currently serves as Vice-Chair of the Clean Energy Association of British Columbia and is a director of Prostate Cancer Canada, the Powell River Economic Executive Vice-Chairman Development Society, the Duke of Edinburgh's Award-British Columbia and Yukon Division and is a governor of the British Columbia Business Council. David Cornhill  Mr. Cornhill is the founder, Chairman and Chief Executive Officer of AltaGas Income Trust, one of Canada's largest energy infrastructure groups, focused on gas and power infrastructure and renewable energy (wind and hydro). With more than 25 Director years of experience in the energy industry, Mr. Cornhill also sits on several private and public boards including AltaGas Utility Group and Ivey Business School. David O’Brien  Mr. O'Brien is retired as President and Chief Executive Officer, Toronto Hydro Corporation where he served between 2004- 2009. Mr. O'Brien was previously with Ontario's Ministry of Energy, initially as Associate Deputy Minister of Energy and Director subsequently as Deputy Minister. Mr. O'Brien has also served as President and Chief Executive Officer of Enersource Corporation, the parent company of Hydro Mississauga. Mr. O'Brien is a member of the Board of OMERS, Apex Co-Vantage and the Summerhill Group, as well as a strategic advisor on energy matters to a number of other companies. Donald Shumka  Mr. Shumka is Managing Director of Walden Management Ltd., a financial consulting firm. Mr. Shumka received a Master of Business Administration from Harvard University. From 1966 to 1979 he worked in a variety of positions in the forest industry, Director from 1979 to 1989 he was Vice President and Chief Financial Officer of West Fraser Timber Co. Ltd. and from 1989 to 2004 he headed the Forest Products Group for two Canadian investment banks. Other public company boards include Eldorado Gold Corp and Paladin Energy Ltd. Paul Sweeney  Mr. Sweeney has over 30 years experience in financial management of mining and renewable energy companies. From 2007-2010, he was Executive Vice President, Corporate Development, of Plutonic Power Corporation. He has served as Director CFO of a number of successful mineral resource companies including Canico Resources, Sutton Resources and Gibraltar Mines and is a director of several resource companies including Pan American Silver Corp. where he chairs the audit committee. Walter Segsworth  Mr. Segsworth recently served as Chairman of Plutonic Power Corporation. He is past President and Director of Westmin Resources. Upon the takeover of Westmin by Boliden in 1998, Mr. Segsworth joined Homestake Mining Company of Director California where he was subsequently appointed President, Director and Chief Operating Officer and served until the merger with Barrick in early 2002. He is past Chairman of both the Mining Associations of BC and Canada and was named BC's Mining Person of the Year in 1996. 14
  • 15. Overview - Toba Montrose in B.C. Alterra owns a 40% economic interest in two recently completed run of river hydroelectric generation facilities in southwestern British Columbia Facilities  East Toba River and Montrose Creek Capacity &  236 MW generating 727 GWh / year Production  60% - GE EFS Ownership  40% - Alterra Start of Operation  2010 Power Purchase  EPA to 2045 with BC Hydro Agreement  $470 MM total project debt with 35 year amortization and Project Debt 6.4% effective interest rate  2011E project revenue of $74 MM Revenue • Includes $10/MWh ecoEnergy Program incentive  2011E project EBITDA of $60 MM EBITDA • $24 MM net EBITDA to Alterra 15
  • 16. Overview - Dokie Wind in B.C. Alterra owns a 51% economic interest in the recently completed Dokie Wind Farm, located in northern British Columbia Facilities  Dokie Wind Farm Capacity &  144 MW generating 330 GWh annually Production  51% - Alterra Ownership  49% - GE EFS Start of Operation  March 2, 2011 Power Purchase  EPA to 2036 with BC Hydro Agreement  $175 MM total project debt with 20 year amortization and Project Debt 7.2% effective interest rate  Annual project revenue of $35 - $40 MM Revenue • Includes $10/MWh ecoEnergy Program incentive  Annual project EBITDA of $27 MM EBITDA • $14 MM net EBITDA to Alterra 16
  • 17. Overview - Svartsengi and Reykjanes in Iceland Alterra’s 75% - owned subsidiary HS Orka owns two geothermal power plants in southwestern Iceland Facilities  Svartsengi and Reykjanes Capacity &  175 MW generating 1,315 GWh /year Production  Thermal (hot water) production 150 MW th  75% - Alterra Ownership  25% - Jarôvarmi (Icelandic Pension Funds) Start of Operation  1978 for Svartsengi and 2006 for Reykjanes  Four PPAs with terms expiring from 2011 to 2026; Power Purchase additional power sold on one-year contracts Agreements  46% of power sales paid in USD and linked to aluminum price  $170 MM total company debt with average 9 years to maturity Project Debt and average 2.645% effective current interest rate Revenue  2011E project revenue of $64 MM EBITDA  2011E project EBITDA of $20 MM 17
  • 18. Overview - Soda Lake in Nevada Alterra owns a 23 MW geothermal power plant near Fallon in northern Nevada Facilities  Soda Lake 1 and Soda Lake 2 Capacity &  23 MW, currently operating at 16 MW gross and generating Production 84 GWh /year Ownership  100% - Alterra Start of Operation  1987 & 1991 Power Purchase  Two PPAs to 2020 with NV Energy Agreement Project Debt  None Revenue  2011E project revenue of $5 MM EBITDA  2011E project EBITDA of $1 MM 18
  • 19. Overview - ABW Solar in Ontario Alterra has an option to acquire a 10% interest in a portfolio of solar facilities from First Solar, to be built in southern Ontario Facility  3 solar facilities in southwestern Ontario  Amherstburg – 10 MW Capacity  Belmont – 20 MW  Walpole – 20 MW Proposed  90% - GE EFS Ownership  10% - Alterra  Mid 2012 E Start of Operation  Construction to start in 4Q 2011 Power Purchase  20 year EPA with Ontario Power Authority Agreement Project Debt  TBD EBITDA  $3 MM net annual EBITDA to Alterra 19
  • 20. Overview - Upper Toba Expansion Project in B.C. A power purchase agreement and permitting are in place for additional run of river hydro plants near the Toba Montrose facilities in southwestern B.C.  Jimmie Creek and Upper Toba River Locations  In the close vicinity to existing Toba Montrose facility Capacity &  124 MW generating 316 GWh annually Production  50% - Alterra Ownership  50% - GE EFS  Environmental Assessment Certificate granted and Water Permitting Licence pending Power Purchase Agreement  In place with BC Hydro Begin Construction  1Q 2013 E On Line  2Q 2015 E  Completion of preliminary engineering & cost estimation Notes targeted for end of 2011  Utilizes existing transmission and road infrastructure 20
  • 21. Overview - Reykjanes 3 & 4 Expansion Project in Iceland The Reykjanes geothermal power plant in southwestern Iceland has substantial existing well capacity and is permitted for an expansion of production Location  Existing Reykjanes facility and steam field Capacity &  80 MW generating 687 GWh annually Production  75% - Alterra Ownership  25% - Jarôvarmi (Icelandic Pension Funds) Permitting  Completed Power Purchase Agreement  H1 2012 E Begin Construction  H2 2012 E  Reykjanes 3 - 50 MW in H2 2013 E On Line  Reykjanes 4 - 30 MW in H1 2014 E  High pressure 50 MW turbine for Reykjanes 3 already on site Notes  Reykjanes 4 will run on existing well field output in a 30 MW low pressure turbine 21
  • 22. Overview - Dokie 2 Expansion Project in B.C. The Dokie Wind Farm in northern B.C. is permitted for a 156 MW expansion Location  Undeveloped ridgelines within Dokie Wind Farm area Capacity &  156 MW generating 357 GWh annually Production  51% - Alterra Ownership  49% - GE EFS Permitting  Existing permitting allows total with Dokie 1 of 300 MW Power Purchase Agreement  Opportunity to discuss with BC Hydro and other off-takers Begin Construction  1Q 2013 E On Line  3Q 2014 E  Wind assessment, turbine layout, infrastructure and financial Notes studies in progress 22
  • 23. Overview - Mariposa Development Project in Chile The Mariposa geothermal field in Chile has an inferred-level capacity of 320 MW  In the Andes Mountains in south-central Chile, approximately Location 300 km south of Santiago  320 MW inferred resource with promising characteristics Capacity & Production  Exploitation Concession granted for first phase of 50 MW  Permanent production concession at Laguna del Maule Ownership  Resource area continues on adjacent Pellado concession  Alterra has a third adjacent concession at Los Cristales  Letter authorizing first round of exploratory holes Permitting  Baseline prepared for subsequent permitting Exploration &  Access road and infrastructure advanced - 2010 Development  Three slim holes completed by core drilling - Nov 2010 Next Phase  Deep rotary and wide diameter drilling planned - 2012 E BRAZIL On Line  2016 E  Recent volcanism and hot springs near concession Notes  Seeking investment partner for next phase 23