3. PROVISION ON PLANT
EQUIPMENT
A) Provision of piling equipment
1) Bringing in and unload 2nos static frame
2) Assembling of piling frame
3) Dismantling of piling frame
4) Load and remove piling frame
5) Allow 15% profit and overhead
B) Maintaining of Plant
1) Moving and handling of equipment
2) Allow 15% profit and overhead
4. 1) Bringing in and unload 2nos static
frame
A) Transportation Cost
-Hiring 5 tonne Lorry 1 day
B) Unloading cost
-Hiring 15 tonne crawler crane 2 hours
C) Labour cost
-2 unskilled labour for 2 hours
5. 2) Assembling of piling frame
A) Unloading Cost
- Hiring of 1 No 15 Tonne crawler crane for 4 hours
B) Labour Cost
- 2 skilled worker
- 2 Unskilled worker
3) Dismantling of piling frame
A) Unloading Cost
- Hiring of 1 No 15 Tonne crawler crane for 4
hours
B) Labour Cost
- 2 skilled worker
- 2 Unskilled worker
6. 4) Load and remove of piling
frame
A) Transportation Cost
-Hiring 5 tonne Lorry 1 day
B) Unloading cost
-Hiring 15 tonne crawler crane 2 hours
C) Labour cost
-2 unskilled labour for 2 hours
7. MOVING AND HANDLING OF
EQUIPMENT
1) Moving and handling 2nos frame
- 1 skilled worker
- 1 unskilled worker
2) Estimated contract period: 2 months
3) Allow 15% profit and overhead