1. STATUS REPORT OF AS ON
09.02.13
“A”-BLOCK STATUS
1. PCC-Completed
2. Footings-Completed
3. G. Slab-Completed
4. Sub Cellar Slab(-2)-
Completed.
2. STATUS REPORT OF AS ON
09.02.13
“B”-BLOCK STATUS
1. PCC-Completed
2. Footings-Completed
3. G. Slab-Completed
4. Sub Cellar Slab(-2)-
Completed
5. Cellar Slab(-1)Shuttering
work in progress for 1
&2 flats.
3. STATUS REPORT OF AS ON
09.02.13
“C”-BLOCK STATUS
1. PCC-Completed
2. Footings-Completed
3. G. Slab-Completed
4. Sub Cellar – for flat
No:01 completed for flat
No:02 today completed.
4. STATUS REPORT OF AS ON
09.02.13
“D”-BLOCK STATUS
1. PCC-Completed
2. FOOTINGS-Completed
3. G. Slab-Completed
4. Sub Cellar-Completed
5. Cellar Slab Column
work in progress for flat
1 & 2.
5. STATUS REPORT OF AS ON
09.02.13
“E”-BLOCK STATUS
1. PCC-Completed
2. Footings-Completed
3. G. Slab-Completed
4. Sub. Cellar- 40%-
Completed
6. STATUS REPORT OF AS ON
09.02.13
“TOTAL SITE” STATUS
1. All Blocks PCC-
Completed
2. All Block Footings-
Completed
3. All locks G. Slab-
Completed
4. Total Site Sub Cellar-
88%-Completed