My home abhra status report as on 30.05.2014
- 2. MY HOME ABHRA TOWER-”A” AS ON 30.05.14
1.1st
Floor To 17th
Floor Slabs Completed
2.External Brick Work Completed
- 3. MY HOME ABHRA TOWER-”B” AS ON 30.05.14
1.1st
Floor To 17th
Floor Slabs Completed
2.External Brick Work Completed
- 4. MY HOME ABHRA TOWER-”C” AS ON 30.05.14
1.1St
Floor To 17th
Floor Slabs Completed
2.External Brick Work Completed
- 5. MY HOME ABHRA TOWER-”D” AS ON 30.05.14
1.1St
Floor To 17th
Floor Slabs Completed
2.External Brick Work Completed
- 6. MY HOME ABHRA TOWER-”E” AS ON 30.05.14
1.1St
Floor To 17th
Floor Slabs Completed
2.External Brick Work Completed
- 7. MY HOME ABHRA TOWER-”E” AS ON 30.05.14
1.1St
Floor To 17th
Floor Slabs Completed
2.External Brick Work Completed