          THE DEPARTMENT OF DEFENSE’S FAILED
PROJECT




          ELECTRONIC HEALTH RECORD
DATE                    BY
          26 FEB 2013        MARK SILVERBERG
Project Overview
HISTORY                                  COMPONENTS
 1988 - DOD begins to acquire an EHR      client-server architecture
 (“Composite Health Care System”)             client-side apps
 1993 - deployed but lacked many              server software/hardware
 features like integration b/w systems        clinical data repository
 and did not use data standards
 “perpetuated the reliance on paper-     DELIVERY
 based record”                            Like CHCS I, development and
                                          implementation contracted out
 1997 - new project (CHCS II) with            26 competitive RFPs which
 nearly identical scope as 1988 but w/        resulted in contracts for T&M & FFP
 emphasis on worldwide, 24/7 access,          11 non-competitive contracts
 common data standards                            later found to be unnecessary
                                                  by FAR guidelines
KEY INPUTS                                2009 - deployment with overwhelming
 requirements were first of many           negative feedback
 problems; delayed multiple times             “Intolerable” - congress hearing
    => delay in creating WBS                  “slow, difficult to use, unreliable”

                                          “EHR Way Ahead” = CHCS III
Challenges
POOR PROJECT PLANNING
  “comprehensive project management plan was not established” - GAO
  “poor planning and execution and a failure to appreciate the ‘significant complexity’
  of the program” - health industry analyst

REQUIREMENTS GATHERING
 Essential to establishing and controlling scope
 End users of the system were only engaged at the beginning and end of the project
 lifecycle so when they did provide feedback at the end, it was too late to inform
 development

LACK OF BUY-IN AND NO FEEDBACK LOOP WITH USERS
 Army’s Surgeon General “faced a near mutiny of our healthcare
 providers, our doctors, our nurse practitioners, physician assistants”
 USAF Deputy Surgeon General: “low productivity and provider
 morale [from] working around the system trying to find new solutions”
 GAO: “[DOD] stopped measuring user satisfaction levels in July 2007
 after overall user satisfaction had declined to its lowest point
 in more than 2 years.”
What Project Management?
Costs were neither minimized nor benefits maximized (or in many cases realized)

                                           $2 BILLION OVER 13 YEARS

Contenu connexe

Similaire à DOD's Failed $2 Billion Electronic Health Record Project

Crafting Infrastructures. Requirements, scenarios and evaluation in the SPICE...
Crafting Infrastructures. Requirements, scenarios and evaluation in the SPICE...Crafting Infrastructures. Requirements, scenarios and evaluation in the SPICE...
Crafting Infrastructures. Requirements, scenarios and evaluation in the SPICE...Luca Galli
 
Fromscrumtokanbantowardlean
FromscrumtokanbantowardleanFromscrumtokanbantowardlean
FromscrumtokanbantowardleanLuca Aliberti
 
6 An Innovative Distributed Project Control
6 An Innovative Distributed Project Control6 An Innovative Distributed Project Control
6 An Innovative Distributed Project Controlpmb25
 
Iaetsd pinpointing performance deviations of subsystems in distributed
Iaetsd pinpointing performance deviations of subsystems in distributedIaetsd pinpointing performance deviations of subsystems in distributed
Iaetsd pinpointing performance deviations of subsystems in distributedIaetsd Iaetsd
 
Computers as data analysis in preclinical development
Computers as data analysis in preclinical developmentComputers as data analysis in preclinical development
Computers as data analysis in preclinical developmentHemantAlhat1
 
Bba 3626, project management overview 1 course learni
 Bba 3626, project management overview 1 course learni Bba 3626, project management overview 1 course learni
Bba 3626, project management overview 1 course learniSALU18
 
Lect2 conventional software management
Lect2 conventional software managementLect2 conventional software management
Lect2 conventional software managementmeena466141
 
Project Name Project CharterVersion 1.0 DraftHealth.docx
Project Name Project CharterVersion 1.0 DraftHealth.docxProject Name Project CharterVersion 1.0 DraftHealth.docx
Project Name Project CharterVersion 1.0 DraftHealth.docxdenneymargareta
 
DEIS: Dependability Engineering Innovation for Cypber-Physical Systems
DEIS: Dependability Engineering Innovation for Cypber-Physical SystemsDEIS: Dependability Engineering Innovation for Cypber-Physical Systems
DEIS: Dependability Engineering Innovation for Cypber-Physical SystemsRan Wei
 
Transf React Proact T&D Ass Management
Transf React Proact T&D Ass ManagementTransf React Proact T&D Ass Management
Transf React Proact T&D Ass ManagementBert Taube
 
SOFTWARE AS A SERVICE – COMMON SERVICE BUS (SAAS-CSB)
SOFTWARE AS A SERVICE – COMMON SERVICE BUS (SAAS-CSB)SOFTWARE AS A SERVICE – COMMON SERVICE BUS (SAAS-CSB)
SOFTWARE AS A SERVICE – COMMON SERVICE BUS (SAAS-CSB)IJCSEA Journal
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contractsGlen Alleman
 
IT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptxIT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptxdjualaja88
 
BBA 3626, Project Management Overview 1 Course Learni
 BBA 3626, Project Management Overview 1 Course Learni BBA 3626, Project Management Overview 1 Course Learni
BBA 3626, Project Management Overview 1 Course LearniMargaritoWhitt221
 

Similaire à DOD's Failed $2 Billion Electronic Health Record Project (20)

Chap 5.pdf
Chap 5.pdfChap 5.pdf
Chap 5.pdf
 
Chap 5.pdf
Chap 5.pdfChap 5.pdf
Chap 5.pdf
 
Crafting Infrastructures. Requirements, scenarios and evaluation in the SPICE...
Crafting Infrastructures. Requirements, scenarios and evaluation in the SPICE...Crafting Infrastructures. Requirements, scenarios and evaluation in the SPICE...
Crafting Infrastructures. Requirements, scenarios and evaluation in the SPICE...
 
Fromscrumtokanbantowardlean
FromscrumtokanbantowardleanFromscrumtokanbantowardlean
Fromscrumtokanbantowardlean
 
6 An Innovative Distributed Project Control
6 An Innovative Distributed Project Control6 An Innovative Distributed Project Control
6 An Innovative Distributed Project Control
 
Iaetsd pinpointing performance deviations of subsystems in distributed
Iaetsd pinpointing performance deviations of subsystems in distributedIaetsd pinpointing performance deviations of subsystems in distributed
Iaetsd pinpointing performance deviations of subsystems in distributed
 
Computers as data analysis in preclinical development
Computers as data analysis in preclinical developmentComputers as data analysis in preclinical development
Computers as data analysis in preclinical development
 
PERIL LIBRARY
PERIL LIBRARYPERIL LIBRARY
PERIL LIBRARY
 
Case study
Case studyCase study
Case study
 
Bba 3626, project management overview 1 course learni
 Bba 3626, project management overview 1 course learni Bba 3626, project management overview 1 course learni
Bba 3626, project management overview 1 course learni
 
Lect2 conventional software management
Lect2 conventional software managementLect2 conventional software management
Lect2 conventional software management
 
Project Name Project CharterVersion 1.0 DraftHealth.docx
Project Name Project CharterVersion 1.0 DraftHealth.docxProject Name Project CharterVersion 1.0 DraftHealth.docx
Project Name Project CharterVersion 1.0 DraftHealth.docx
 
DEIS: Dependability Engineering Innovation for Cypber-Physical Systems
DEIS: Dependability Engineering Innovation for Cypber-Physical SystemsDEIS: Dependability Engineering Innovation for Cypber-Physical Systems
DEIS: Dependability Engineering Innovation for Cypber-Physical Systems
 
Transf React Proact T&D Ass Management
Transf React Proact T&D Ass ManagementTransf React Proact T&D Ass Management
Transf React Proact T&D Ass Management
 
SOFTWARE AS A SERVICE – COMMON SERVICE BUS (SAAS-CSB)
SOFTWARE AS A SERVICE – COMMON SERVICE BUS (SAAS-CSB)SOFTWARE AS A SERVICE – COMMON SERVICE BUS (SAAS-CSB)
SOFTWARE AS A SERVICE – COMMON SERVICE BUS (SAAS-CSB)
 
System lifecycle
System lifecycleSystem lifecycle
System lifecycle
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contracts
 
IT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptxIT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptx
 
2009 ASME final
2009 ASME final2009 ASME final
2009 ASME final
 
BBA 3626, Project Management Overview 1 Course Learni
 BBA 3626, Project Management Overview 1 Course Learni BBA 3626, Project Management Overview 1 Course Learni
BBA 3626, Project Management Overview 1 Course Learni
 

Dernier

Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfRankYa
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostZilliz
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 

Dernier (20)

Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdf
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 

DOD's Failed $2 Billion Electronic Health Record Project

  • 1. 2nd THE DEPARTMENT OF DEFENSE’S FAILED PROJECT ELECTRONIC HEALTH RECORD DATE BY 26 FEB 2013 MARK SILVERBERG
  • 2. Project Overview HISTORY COMPONENTS 1988 - DOD begins to acquire an EHR client-server architecture (“Composite Health Care System”) client-side apps 1993 - deployed but lacked many server software/hardware features like integration b/w systems clinical data repository and did not use data standards “perpetuated the reliance on paper- DELIVERY based record” Like CHCS I, development and implementation contracted out 1997 - new project (CHCS II) with 26 competitive RFPs which nearly identical scope as 1988 but w/ resulted in contracts for T&M & FFP emphasis on worldwide, 24/7 access, 11 non-competitive contracts common data standards later found to be unnecessary by FAR guidelines KEY INPUTS 2009 - deployment with overwhelming requirements were first of many negative feedback problems; delayed multiple times “Intolerable” - congress hearing => delay in creating WBS “slow, difficult to use, unreliable” “EHR Way Ahead” = CHCS III
  • 3. Challenges POOR PROJECT PLANNING “comprehensive project management plan was not established” - GAO “poor planning and execution and a failure to appreciate the ‘significant complexity’ of the program” - health industry analyst REQUIREMENTS GATHERING Essential to establishing and controlling scope End users of the system were only engaged at the beginning and end of the project lifecycle so when they did provide feedback at the end, it was too late to inform development LACK OF BUY-IN AND NO FEEDBACK LOOP WITH USERS Army’s Surgeon General “faced a near mutiny of our healthcare providers, our doctors, our nurse practitioners, physician assistants” USAF Deputy Surgeon General: “low productivity and provider morale [from] working around the system trying to find new solutions” GAO: “[DOD] stopped measuring user satisfaction levels in July 2007 after overall user satisfaction had declined to its lowest point in more than 2 years.”
  • 4. What Project Management? Costs were neither minimized nor benefits maximized (or in many cases realized) $2 BILLION OVER 13 YEARS