SlideShare une entreprise Scribd logo
1  sur  28
Submitted by: Submitted to:
Mayank Sharma(10EJCEE032) Mr. S.N. Jhanwar
VIIIth Sem. H.O.D.(EE Dept.)
J.E.C.R.C.,Jaipur
Introduction:
 The electrical load schedule is an estimate of the
instantaneous electrical loads operating in a facility, in
terms of active, reactive and apparent power (measured in
kW, kVAR and kVA respectively).
 The load schedule is usually categorised by switchboard
or occasionally by sub-facility / area.
 A key feature of this divisible load distribution scheduling
theory (known as DLT) is that it uses a linear
mathematical model.
Need Of load Scheduling:
 Essential for some of the key electrical design activities
(such as equipment sizing and power system studies)
 It provides the preliminary details of process / building /
Organisation Load.
 The electrical load schedule can typically be started with a
preliminary key single line diagram (or at least an idea of
the main voltage levels in the system)
Procedure to calculate the load
Scheduling:
 Step 1: Collect a list of the expected electrical loads in the
facility
 Step 2: For each load, collect the electrical parameters,
e.g. nominal / absorbed ratings, power factor, efficiency,
etc
 Step 3: Classify each of the loads in terms of switchboard
location, load duty and load criticality
 Step 4: For each load, calculate the expected consumed
load
 Step 5: For each switchboard and the overall system,
calculate operating, peak and design load
Step 1: Collect list of loads
 Process loads - are the loads that are directly relevant to
the facility.
Example-Motors, Heaters, Compressors, Conveyors.
• Non-process loads - are the auxiliary loads that are
necessary to run the facility.
• Example-lighting, utility systems (power and water),
DCS/PLC control systems, fire safety systems
Step 2: Collect electrical load
parameters
 Rated power is the full load or nameplate rating of the load
and represents the maximum continuous power output of the
load. For motor loads, the rated power corresponds to the
standard motor size (e.g. 11kW, 37kW, 75kW, etc).
 Absorbed power is the expected power that will be drawn by
the load.
 Power factor of the load is necessary to determine the reactive
components of the load schedule. Typically 0.85 for motor
loads >7.5kW, 1.0 for heater loads and 0.8 for all other loads).
 Efficiency accounts for the losses incurred when converting
electrical energy to mechanical energy. Typically 0.85 or 0.9 is
used when efficiencies are unknown.
Step 3: Classify the loads
 Voltage Level :What voltage level and which switchboard
should the load be located?
Loads <150kW-LV System (400V - 690V)
150KW<Load<10 MW- MV System (3.3kV - 6.6kV)
Loads >10MW-HV Distribution System (11kV - 33kV)
 Load duty-
Continuous loads -are those that normally operate
continuously over a 24 hour period.eg. process loads,
control systems, lighting and small power distribution
boards, UPS systems.
Step 3(2):
Intermittent loads -only operate a fraction of a 24 hour period,
e.g. intermittent pumps and process loads, automatic doors and
gates.
Standby loads -are those that are on standby or rarely operate
under normal conditions, e.g. standby loads, emergency systems.
 Load criticality-
Normal loads-run under normal operating conditions.
Essential loads are those necessary under emergency conditions,
when the main power supply is disconnected and the system is
being supported by an emergency generator, e.g. emergency
lighting, key process loads that operate during emergency
conditions, fire and safety systems
Critical Loads-are those critical for the operation of safety systems
and normally supplied through a U.P.S. Battery.eg. Escape
lightning .
Step 4: Calculate consumed load
 The consumed load is the quantity of electrical power that
the load is expected to consume. For each load, calculate
the consumed active and reactive loading, derived as
follows:
;
Step 5: Calculate operating, peak
and design loads
 Operating load -The operating load is the expected
load during normal operation.
Peak load -The peak load is the expected maximum
load during normal operation.
Step 5(2):
 Design load -The design load is the load to be used for
the design for equipment sizing, electrical studies.
or
Parts of Load Scheduling:
Coordination
(Yearly,Monthly
Or Weekly)
Unit Commitment
(Weekly Or Daily)
Economic Load
Dispatch
(Hourly)
Hydrothermal Coordination
problem:
 It is the first stage in the solution of the hydrothermal
generation scheduling problem. The HCP consists of
determining the optimal amounts of hydro and
thermal generation to be used during a scheduling
period .The HCP is also decomposed in three Parts.
depending on the reservoirs storage capacity.
1.Long Term
2.Mid Term
3.Short Term
Unit Commitment-
 The electrical unit commitment problem is the
problem of deciding which electricity generating units
should be running in each period so as to satisfy
predictibly varying demand of electricity.
 Load of power system varies through out of the
demand reaches a different peak value from one day to
another. so which generator to start up and the
sequence in which units should be operate and for
how long.The computational procedure for making
such decision is called unit commitment
Economic Load Dispatch
 In power generation our main aim is to generate the
required amount of power with minimum cost.
 Economic load dispatch means that the generator’s
real and reactive power are allowed to vary within
certain limits so as to meet a particular load demand
with minimum fuel cost
 This allocation of loads are based on some
constraints.
DIFFERENT CONSTRAINTS IN
ECONOMIC LOAD DISPATCH
 INEQUALITY CONSTRAINTS
 Voltage constraints
Vmin ≤ V ≤ Vmax ,
δmin ≤ δ ≤ δmax
 Generator constraints
KVA loading of generator should not exceed prescribed
value
Pmin ≤ P ≤ Pmax
Qmin ≤ Q ≤ Qmax
 Running spare capacity constraints
This constraints are needed to meet forced outage of
one or more alternators in the system and also
unexpected load on the system
 Transmission line constraints
flow of power through transmission line should less
than its thermal capacity
 Transformer tap set
for autotransformer tap t should between 0 & 1
For two winding transformer – between 0& k
 Equality constraints
 Real power
Pp= Vp Σ Ypq Vq cos(θpq-(δp+δq))
 Reactive power
Qp= Vp Σ Ypq Vq sin(θpq-(δp+δq))
OPERATING COST OF THERMAL
PLANT
 The factors influencing power generation at minimum
cost are operating efficiencies of generators, fuel cost,
and transmission losses.
 The most efficient generator in the system does not
guarantee minimum cost as it may be located in an
area where fuel cost is high.
 If the plant is located far from the load center,
transmission losses may be considerably higher and
hence the plant may be overly uneconomical.
 The input to the thermal plant is generally measured
in Btu/h, and the output is measured in MW
 In all practical cases, the fuel cost of generator can be
represented as a quadratic function of real power
generation
a) Heat rate curve b) Fuel cost curve
• By plotting the derivative of the fuel-cost curve versus
the real power we get the incremental fuel-cost curve
Incremental fuel-cost curve
The incremental fuel-cost curve is a measure of how
costly it will be to produce the next increment of
power.
ECONOMIC DISPATCH NEGLECTING
LOSSES
 It is the simplest economic dispatch problem
 Assume that the system is only one bus with all
generation and loads connected to it
 A cost function Ci is assumed to be known for each
plant
 The problem is to find the real power generation for
each plant such that the objective function (i.e., total
production cost) as defined by the equation
Is minimum ,subjected to the constraints
 when losses are neglected with no generator limits, for
most economic operation. all plants must operate at
equal incremental production cost
 Production from each plant can be found by
This equation is known as the coordination equation
For analytic solution we can find λ by
REFERENCES
 Power System Analysis - Hadi Saadat
 Power system Analysis - Nagrath and Kothari
 Openelectrical.org/load scheduling
THANKS

Contenu connexe

Tendances

Electric traction
Electric tractionElectric traction
Electric tractionDipak Meher
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relayCS V
 
Unit 2 Reactive Power Management
Unit 2 Reactive Power ManagementUnit 2 Reactive Power Management
Unit 2 Reactive Power ManagementSANTOSH GADEKAR
 
Loading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission LinesLoading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission LinesRaja Adapa
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Deviceskhemraj298
 
Power system stability
Power system stabilityPower system stability
Power system stabilityBalaram Das
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal schedulingASHIRBAD BARIK
 
Over current Relays
Over current RelaysOver current Relays
Over current RelaysASWANTH6270
 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch centerddxdharmesh
 
ENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORSENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORSArigela Harika
 
Generation shift factor and line outage factor
Generation shift factor and line outage factorGeneration shift factor and line outage factor
Generation shift factor and line outage factorViren Pandya
 
Economic dispatch
Economic dispatch  Economic dispatch
Economic dispatch Hussain Ali
 
Unit 4 Automatic Generation Control
Unit 4 Automatic Generation ControlUnit 4 Automatic Generation Control
Unit 4 Automatic Generation ControlSANTOSH GADEKAR
 
Inter Connected Power System(Turbine Speed Governing Mechanism )
Inter Connected Power System(Turbine Speed Governing Mechanism)Inter Connected Power System(Turbine Speed Governing Mechanism)
Inter Connected Power System(Turbine Speed Governing Mechanism )Raviraj solanki
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flowAhmed M. Elkholy
 
EE8701-High Voltage Engineering (1).pptx
EE8701-High Voltage Engineering (1).pptxEE8701-High Voltage Engineering (1).pptx
EE8701-High Voltage Engineering (1).pptxsai karthick
 
Unit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentUnit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentSANTOSH GADEKAR
 

Tendances (20)

Electric traction
Electric tractionElectric traction
Electric traction
 
Load flow analysis of radial distribution system
Load flow analysis of radial distribution system Load flow analysis of radial distribution system
Load flow analysis of radial distribution system
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relay
 
Unit 2 Reactive Power Management
Unit 2 Reactive Power ManagementUnit 2 Reactive Power Management
Unit 2 Reactive Power Management
 
Load flow studies 19
Load flow studies 19Load flow studies 19
Load flow studies 19
 
Loading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission LinesLoading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission Lines
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Devices
 
Power system stability
Power system stabilityPower system stability
Power system stability
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal scheduling
 
Over current Relays
Over current RelaysOver current Relays
Over current Relays
 
Gauss seidel method
Gauss seidel methodGauss seidel method
Gauss seidel method
 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch center
 
ENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORSENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORS
 
Generation shift factor and line outage factor
Generation shift factor and line outage factorGeneration shift factor and line outage factor
Generation shift factor and line outage factor
 
Economic dispatch
Economic dispatch  Economic dispatch
Economic dispatch
 
Unit 4 Automatic Generation Control
Unit 4 Automatic Generation ControlUnit 4 Automatic Generation Control
Unit 4 Automatic Generation Control
 
Inter Connected Power System(Turbine Speed Governing Mechanism )
Inter Connected Power System(Turbine Speed Governing Mechanism)Inter Connected Power System(Turbine Speed Governing Mechanism)
Inter Connected Power System(Turbine Speed Governing Mechanism )
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
 
EE8701-High Voltage Engineering (1).pptx
EE8701-High Voltage Engineering (1).pptxEE8701-High Voltage Engineering (1).pptx
EE8701-High Voltage Engineering (1).pptx
 
Unit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentUnit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit Commitment
 

En vedette

Ohm’s law
Ohm’s lawOhm’s law
Ohm’s lawaichikun
 
Ohms law
Ohms lawOhms law
Ohms laww1nds
 
Electrical symbols
Electrical symbolsElectrical symbols
Electrical symbolsSolas Lagua
 
Iec symbol reference
Iec symbol referenceIec symbol reference
Iec symbol referenceVamsi Krishna
 
Nation and State in the Age of Globalization
Nation and State in the Age of GlobalizationNation and State in the Age of Globalization
Nation and State in the Age of GlobalizationKent Saldaña
 
Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Vijay Kumar
 
Electricity and ohm’s law
Electricity and ohm’s lawElectricity and ohm’s law
Electricity and ohm’s lawitutor
 
2 History of Philippine Art
2 History of Philippine Art2 History of Philippine Art
2 History of Philippine ArtOphelynn Cano
 
Electric load patterns for (residential/commercial /industrial) usage
Electric load patterns for (residential/commercial /industrial) usageElectric load patterns for (residential/commercial /industrial) usage
Electric load patterns for (residential/commercial /industrial) usageMuhammad Abdulhadi
 
Preliminary electrical load calculation course share
Preliminary electrical load calculation course sharePreliminary electrical load calculation course share
Preliminary electrical load calculation course shareAli Hassan
 
Philippine Contemporary Arts
Philippine Contemporary ArtsPhilippine Contemporary Arts
Philippine Contemporary ArtsKent Saldaña
 

En vedette (20)

Load list calculation
Load list calculationLoad list calculation
Load list calculation
 
Energy calculation
Energy calculationEnergy calculation
Energy calculation
 
Ohm’s law
Ohm’s lawOhm’s law
Ohm’s law
 
Ohms law
Ohms lawOhms law
Ohms law
 
electrical symbol v2
electrical  symbol v2electrical  symbol v2
electrical symbol v2
 
Electrical symbols
Electrical symbolsElectrical symbols
Electrical symbols
 
Iec symbol reference
Iec symbol referenceIec symbol reference
Iec symbol reference
 
Electrical symbols
Electrical symbolsElectrical symbols
Electrical symbols
 
Climate change
Climate changeClimate change
Climate change
 
Nation and State in the Age of Globalization
Nation and State in the Age of GlobalizationNation and State in the Age of Globalization
Nation and State in the Age of Globalization
 
Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings
 
Day 7 6.25
Day 7 6.25Day 7 6.25
Day 7 6.25
 
Ohm's Law
Ohm's Law Ohm's Law
Ohm's Law
 
Electricity and ohm’s law
Electricity and ohm’s lawElectricity and ohm’s law
Electricity and ohm’s law
 
2 History of Philippine Art
2 History of Philippine Art2 History of Philippine Art
2 History of Philippine Art
 
Day 2.6.13.16
Day 2.6.13.16Day 2.6.13.16
Day 2.6.13.16
 
Electric load patterns for (residential/commercial /industrial) usage
Electric load patterns for (residential/commercial /industrial) usageElectric load patterns for (residential/commercial /industrial) usage
Electric load patterns for (residential/commercial /industrial) usage
 
Preliminary electrical load calculation course share
Preliminary electrical load calculation course sharePreliminary electrical load calculation course share
Preliminary electrical load calculation course share
 
Philippine Contemporary Arts
Philippine Contemporary ArtsPhilippine Contemporary Arts
Philippine Contemporary Arts
 
Day 1. 6.12.16
Day 1. 6.12.16Day 1. 6.12.16
Day 1. 6.12.16
 

Similaire à Optimal load scheduling

Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptxPoojaAnupGarg
 
Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01vikram anand
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfTheBlank5
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingBIJAY NAYAK
 
UPS_Sizing_Calculation__170450556677.pdf
UPS_Sizing_Calculation__170450556677.pdfUPS_Sizing_Calculation__170450556677.pdf
UPS_Sizing_Calculation__170450556677.pdfFarukPatel9
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)inventionjournals
 
Importance of Power Factor.pptx
Importance of Power Factor.pptxImportance of Power Factor.pptx
Importance of Power Factor.pptxVineet Shekhar
 
Module1-Power-System-operation and-control
Module1-Power-System-operation and-controlModule1-Power-System-operation and-control
Module1-Power-System-operation and-controlkvvbapiraju2
 
REACTIVE POWER
REACTIVE POWERREACTIVE POWER
REACTIVE POWERJeetDatta3
 
Reactive Power : Problems and Solutions
Reactive Power : Problems and SolutionsReactive Power : Problems and Solutions
Reactive Power : Problems and SolutionsAbhinav Dubey
 
Battery Aware Dynamic Scheduling for Periodic Task Graphs
Battery Aware Dynamic Scheduling for Periodic Task GraphsBattery Aware Dynamic Scheduling for Periodic Task Graphs
Battery Aware Dynamic Scheduling for Periodic Task GraphsNicolas Navet
 

Similaire à Optimal load scheduling (20)

Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptx
 
Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdf
 
Unit 5.pptx
Unit 5.pptxUnit 5.pptx
Unit 5.pptx
 
UPS Sizing
UPS SizingUPS Sizing
UPS Sizing
 
Economic dipatch
Economic dipatch Economic dipatch
Economic dipatch
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load shedding
 
UPS_Sizing_Calculation__170450556677.pdf
UPS_Sizing_Calculation__170450556677.pdfUPS_Sizing_Calculation__170450556677.pdf
UPS_Sizing_Calculation__170450556677.pdf
 
Power system planing and operation (pce5312) chapter five
Power system planing and operation (pce5312) chapter fivePower system planing and operation (pce5312) chapter five
Power system planing and operation (pce5312) chapter five
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
UNIT-4-PPT.ppt
UNIT-4-PPT.pptUNIT-4-PPT.ppt
UNIT-4-PPT.ppt
 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
 
Power System Review
Power System ReviewPower System Review
Power System Review
 
Economic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdfEconomic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdf
 
Importance of Power Factor.pptx
Importance of Power Factor.pptxImportance of Power Factor.pptx
Importance of Power Factor.pptx
 
Module1-Power-System-operation and-control
Module1-Power-System-operation and-controlModule1-Power-System-operation and-control
Module1-Power-System-operation and-control
 
REACTIVE POWER
REACTIVE POWERREACTIVE POWER
REACTIVE POWER
 
Reactive Power : Problems and Solutions
Reactive Power : Problems and SolutionsReactive Power : Problems and Solutions
Reactive Power : Problems and Solutions
 
Battery Aware Dynamic Scheduling for Periodic Task Graphs
Battery Aware Dynamic Scheduling for Periodic Task GraphsBattery Aware Dynamic Scheduling for Periodic Task Graphs
Battery Aware Dynamic Scheduling for Periodic Task Graphs
 
White paper
White paperWhite paper
White paper
 

Dernier

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 

Dernier (20)

Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 

Optimal load scheduling

  • 1. Submitted by: Submitted to: Mayank Sharma(10EJCEE032) Mr. S.N. Jhanwar VIIIth Sem. H.O.D.(EE Dept.) J.E.C.R.C.,Jaipur
  • 2. Introduction:  The electrical load schedule is an estimate of the instantaneous electrical loads operating in a facility, in terms of active, reactive and apparent power (measured in kW, kVAR and kVA respectively).  The load schedule is usually categorised by switchboard or occasionally by sub-facility / area.  A key feature of this divisible load distribution scheduling theory (known as DLT) is that it uses a linear mathematical model.
  • 3. Need Of load Scheduling:  Essential for some of the key electrical design activities (such as equipment sizing and power system studies)  It provides the preliminary details of process / building / Organisation Load.  The electrical load schedule can typically be started with a preliminary key single line diagram (or at least an idea of the main voltage levels in the system)
  • 4. Procedure to calculate the load Scheduling:  Step 1: Collect a list of the expected electrical loads in the facility  Step 2: For each load, collect the electrical parameters, e.g. nominal / absorbed ratings, power factor, efficiency, etc  Step 3: Classify each of the loads in terms of switchboard location, load duty and load criticality  Step 4: For each load, calculate the expected consumed load  Step 5: For each switchboard and the overall system, calculate operating, peak and design load
  • 5. Step 1: Collect list of loads  Process loads - are the loads that are directly relevant to the facility. Example-Motors, Heaters, Compressors, Conveyors. • Non-process loads - are the auxiliary loads that are necessary to run the facility. • Example-lighting, utility systems (power and water), DCS/PLC control systems, fire safety systems
  • 6. Step 2: Collect electrical load parameters  Rated power is the full load or nameplate rating of the load and represents the maximum continuous power output of the load. For motor loads, the rated power corresponds to the standard motor size (e.g. 11kW, 37kW, 75kW, etc).  Absorbed power is the expected power that will be drawn by the load.  Power factor of the load is necessary to determine the reactive components of the load schedule. Typically 0.85 for motor loads >7.5kW, 1.0 for heater loads and 0.8 for all other loads).  Efficiency accounts for the losses incurred when converting electrical energy to mechanical energy. Typically 0.85 or 0.9 is used when efficiencies are unknown.
  • 7. Step 3: Classify the loads  Voltage Level :What voltage level and which switchboard should the load be located? Loads <150kW-LV System (400V - 690V) 150KW<Load<10 MW- MV System (3.3kV - 6.6kV) Loads >10MW-HV Distribution System (11kV - 33kV)  Load duty- Continuous loads -are those that normally operate continuously over a 24 hour period.eg. process loads, control systems, lighting and small power distribution boards, UPS systems.
  • 8. Step 3(2): Intermittent loads -only operate a fraction of a 24 hour period, e.g. intermittent pumps and process loads, automatic doors and gates. Standby loads -are those that are on standby or rarely operate under normal conditions, e.g. standby loads, emergency systems.  Load criticality- Normal loads-run under normal operating conditions. Essential loads are those necessary under emergency conditions, when the main power supply is disconnected and the system is being supported by an emergency generator, e.g. emergency lighting, key process loads that operate during emergency conditions, fire and safety systems Critical Loads-are those critical for the operation of safety systems and normally supplied through a U.P.S. Battery.eg. Escape lightning .
  • 9. Step 4: Calculate consumed load  The consumed load is the quantity of electrical power that the load is expected to consume. For each load, calculate the consumed active and reactive loading, derived as follows: ;
  • 10. Step 5: Calculate operating, peak and design loads  Operating load -The operating load is the expected load during normal operation. Peak load -The peak load is the expected maximum load during normal operation.
  • 11. Step 5(2):  Design load -The design load is the load to be used for the design for equipment sizing, electrical studies. or
  • 12. Parts of Load Scheduling: Coordination (Yearly,Monthly Or Weekly) Unit Commitment (Weekly Or Daily) Economic Load Dispatch (Hourly)
  • 13. Hydrothermal Coordination problem:  It is the first stage in the solution of the hydrothermal generation scheduling problem. The HCP consists of determining the optimal amounts of hydro and thermal generation to be used during a scheduling period .The HCP is also decomposed in three Parts. depending on the reservoirs storage capacity. 1.Long Term 2.Mid Term 3.Short Term
  • 14. Unit Commitment-  The electrical unit commitment problem is the problem of deciding which electricity generating units should be running in each period so as to satisfy predictibly varying demand of electricity.  Load of power system varies through out of the demand reaches a different peak value from one day to another. so which generator to start up and the sequence in which units should be operate and for how long.The computational procedure for making such decision is called unit commitment
  • 15. Economic Load Dispatch  In power generation our main aim is to generate the required amount of power with minimum cost.  Economic load dispatch means that the generator’s real and reactive power are allowed to vary within certain limits so as to meet a particular load demand with minimum fuel cost  This allocation of loads are based on some constraints.
  • 16. DIFFERENT CONSTRAINTS IN ECONOMIC LOAD DISPATCH  INEQUALITY CONSTRAINTS  Voltage constraints Vmin ≤ V ≤ Vmax , δmin ≤ δ ≤ δmax  Generator constraints KVA loading of generator should not exceed prescribed value Pmin ≤ P ≤ Pmax Qmin ≤ Q ≤ Qmax
  • 17.  Running spare capacity constraints This constraints are needed to meet forced outage of one or more alternators in the system and also unexpected load on the system  Transmission line constraints flow of power through transmission line should less than its thermal capacity  Transformer tap set for autotransformer tap t should between 0 & 1 For two winding transformer – between 0& k
  • 18.  Equality constraints  Real power Pp= Vp Σ Ypq Vq cos(θpq-(δp+δq))  Reactive power Qp= Vp Σ Ypq Vq sin(θpq-(δp+δq))
  • 19. OPERATING COST OF THERMAL PLANT  The factors influencing power generation at minimum cost are operating efficiencies of generators, fuel cost, and transmission losses.  The most efficient generator in the system does not guarantee minimum cost as it may be located in an area where fuel cost is high.  If the plant is located far from the load center, transmission losses may be considerably higher and hence the plant may be overly uneconomical.
  • 20.  The input to the thermal plant is generally measured in Btu/h, and the output is measured in MW  In all practical cases, the fuel cost of generator can be represented as a quadratic function of real power generation a) Heat rate curve b) Fuel cost curve
  • 21. • By plotting the derivative of the fuel-cost curve versus the real power we get the incremental fuel-cost curve Incremental fuel-cost curve The incremental fuel-cost curve is a measure of how costly it will be to produce the next increment of power.
  • 22. ECONOMIC DISPATCH NEGLECTING LOSSES  It is the simplest economic dispatch problem  Assume that the system is only one bus with all generation and loads connected to it  A cost function Ci is assumed to be known for each plant
  • 23.  The problem is to find the real power generation for each plant such that the objective function (i.e., total production cost) as defined by the equation Is minimum ,subjected to the constraints
  • 24.
  • 25.
  • 26.  when losses are neglected with no generator limits, for most economic operation. all plants must operate at equal incremental production cost  Production from each plant can be found by This equation is known as the coordination equation For analytic solution we can find λ by
  • 27. REFERENCES  Power System Analysis - Hadi Saadat  Power system Analysis - Nagrath and Kothari  Openelectrical.org/load scheduling