SlideShare une entreprise Scribd logo
1  sur  62
Télécharger pour lire hors ligne
Presentation for: 2012 NYSCHSA Summer Conference
                    August 28, 2012
             By: Christopher Sichak, P.E.
Outline
•   Introduction
•   Existing Conditions
•   Environmental Considerations
•   Project Needs
•   Development of Alternatives
•   Project Costs
•   Selection of Preferred Alternative
•   Construction Phase
•   Lessons Learned
•   Summary
•   Learning Assessment
•   Questions
Introduction
Project Location
• NYSDOT Region 4, Orleans County, Town of Ridgeway
• Between Ridge Road (SR 104) and Oak Orchard River Road
• Oak Orchard River upstream of Waterport Pond (Lake Alice)



                               PROJECT
                              ` LOCATION
Introduction
  Project Team
                 Orleans County
Owner’s Group




                 • NYSDOT Region 4
                 • Town of Ridgeway
                 • Federal Highway Administration


                 Clark Patterson Lee / Dewberry-Goodkind, Inc.
 Engineering




                 •   Ravi Engineering & Land Surveying (survey, mapping, environmental, construction inspection)
                 •   SJB, Empire Geo Services, Inc. (geotechnical, construction material testing)
                 •   BME Associates (wetland delineation)
                 •   R K Hite & Co., Inc. (right of way acquisition)


                 Ramsey Constructors, Inc.                            Material Suppliers:
                 •   Clark Rigging (crane work)
                 •   G & J Contracting (reinforcement installation)
                 •                                                    •   Contech Construction Products, Inc.
 Construction




                     Buffalo Barricade (detour signage)
                 •   C & A Pavement Marking (pavement markings)       •   Lakelands Concrete Products, Inc.
                 •   Villager Construction, Inc. (milling)            •   Pavilion Drainage Supply Co., Inc.
                 •   Elderlee, Inc. (guide-rail and signs)            •   Suit-Kote
                 •   Terry Tree (tree removal)                        •   Hanson Aggregates
                                                                      •   Vellano Bros., Inc.
                 •   MJ Dreher Trucking (trucking)
                                                                      •   Kistner Concrete Products, Inc.
                 •   Farrell Landscaping (seeding)
                                                                      •   Keystone Builders Supply
                 •   Fisher Associates (survey and ROW markers)
Introduction
• Bridge Constructed in 1930
• Steel Jack Arch Structure
• Two 40.7’ Spans (85’ total)
• 24’ curb-to-curb
• 27’ out-to-out
• No skew
• Reinforced
  Concrete
  Substructures
Existing Conditions
 2006 Biennial Inspection
• 31 of the 50 (62%) rated elements had poor values (4 or lower)




• NYSDOT Condition Rating = 4.015, FHWA Sufficiency Rating = 39.9, General Rec. = 4
• Structurally Deficient (Condition < 5, significant maintenance to remain in service)
Existing Conditions
 Safety Flags
• Condition presenting a clear and present danger to vehicular or
  pedestrian traffic, but poses no danger of structural failure.




 • Spalling of Concrete Parapets        • Hole in deck near the pier
Existing Conditions
Approach Roadway
• 2 – 11’ travel lanes
• Variable width gravel shoulders




                                    Two way AADT:
                                    • 2000: 944
                                    • 2009: 992
Existing Conditions
Geotechnical Investigations                   Boring Recovery RQD
                                               B-1     81% 51%
 • Shale bedrock below apparent fill soils
                                               B-2     91% 28%




    • RQD (Rock Quality Designation)              RQD
                                                           Rock Mass
                                                             Quality
     length of pieces exceeding 4”
     ____________________                         <25%     very poor
=                                    x 100%      25-50%       poor
         length of core run                      50-75%        fair
                                                 75-90%       good
    •Bearing capacity of 8 tons/sf               90-100%    excellent
Existing Conditions
Utilities
 Electric (National Grid)   Telephone (Verizon)        Water (Town of Ridgeway)

  o Relocate aerial          o Relocate aerial          o Coordinate geometry
    facilities and street      facilities along east      with 8” Direct bored
    light along east side      side of the roadway        watermain along east
    of the roadway                                        side of the roadway
Existing Conditions
Hydraulics
 • History of debris
   snagging on pier

 • Pier erosion and scour

 • Exposed pier footing
Existing Conditions
 Hydraulics
• 48 mile upstream length
• Initiates in Genesee County         PROJECT
                                      LOCATION
• 192 square miles drainage area
• Upstream flow controlled
                      50 Year Flood   `
      Model
                      Elevation (m)
Existing Structure       353.34
Replacement
                         353.27
Option 1
Replacement
                         353.37
Option 2
Environmental Considerations
Archeological Sensitive Area
          SHPO Project Review
          Application completed
2/9/09    detailing previous
                                  Project Location
          disturbance




          SHPO concurrence with
2/24/09   previous disturbance




          FHWA concurrence no
3/13/09   Phase I Cultural
          Resources neccesary
Environmental Considerations
Environmental Screenings and Permitting
  • USACOE Nationwide Permit #3
  • NYSDEC Excavation and Fill in Navigable Waters
  • NYSDEC Water Quality Certification




Endangered Species = Stream Restriction
  • Longear Sunfish (Lepomis Megalotis)
  • June 15 to September 15
Project Needs
Goals




•   Replace existing structure within available funding limits
•   Provide structural service life of 75 years
•   Meet current standards
•   Enhance safety
•   Minimize stream disturbance in accordance with permits
Development of Alternatives
Conceptual Alternatives:
1.   Rehabilitation

2.   Single Span Multigirder Replacement:
     a. Steel
     b. Spread or Adjacent Prestressed Concrete Box Beam
     c. Other Prestressed Concrete Shapes (AASHTO I, New England Bulb Tee)

3.   Single Span Concrete Buried Structure

4.   Two-Span Bridge Replacement (Steel or Concrete Superstructure)

5.   Multi-Span Concrete Buried Structure
Development of Alternatives
Conceptual Alternatives:
1.    Rehabilitation

2.    Single Span Multigirder Replacement:
      a. Steel
      b. Spread or Adjacent Prestressed Concrete Box Beam
      c. Other Prestressed Concrete Shapes (AASHTO I, New England Bulb Tee)

3.    Single Span Concrete Buried Structure

4.    Two-Span Bridge Replacement (Steel or Concrete Superstructure)
     Dropped due to Hydraulic Characteristics
5.    Multi-Span Concrete Buried Structure
Development of Alternatives
1. Rehabilitation
 • Replace the superstructure
 • Repair and reuse the existing substructures
 • Retained existing features
   would continue to
   deteriorate
 • Initial construction cost
 • Anticipated future
   maintenance costs
 • Continued stream
   obstruction from pier
Development of Alternatives
Conceptual Alternatives:
1.   Rehabilitation

2.   Single Span Multigirder Replacement:
     a. Steel
     b. Spread or Adjacent Prestressed Concrete Box Beam
     c. Other Prestressed Concrete Shapes (AASHTO I, New England Bulb Tee)
      Dropped due to Anticipated Costs
3.   Single Span Concrete Buried Structure
Development of Alternatives
2. Adjacent Prestressed Concrete Box Beam Replacement
                                      100’ (+/-)




                                Proposed Elevation

• Lower initial construction cost than steel multigirder
     • deck forming and thickness
• Tall Concrete Abutments and Wingwalls with spread footings on bedrock (25’ – 30’)
Development of Alternatives
3. Single Span Concrete Buried Structure
• Lower maintenance costs           • Arch:
   o Absence of features               o Geometry fits well with
     requiring maintenance:              site topography
       Joints                         o Structurally sound and
       Bearings                         efficient shape
       Deck                           o Most economical
       Primary Members                  foundation size
• Lower construction costs
   o Limited field construction
     (precast)
   o Limited field specialty work
Development of Alternatives
3. Single Span Concrete Buried Structure (Precast Arch)
                         77’-9”




                                  21’-10”
                     Proposed Elevation
 • Detailed as a precast structure
   o Twin leaf structure, headwalls, and wingwalls
   o E78T/0: Contech BEBO (77’ -9” Span x 21’ –10” Rise)
Development of Alternatives
             •LRFD Specifications mandated for bridge design by October 1, 2007
 EI 05-003
             •Exception: LRFD implementation for design of buried structures in 2010



 EI 07-014
EI 07-030    •Release of 2007 (Metric and US) and 2008 (US) LRFD Specifications
EI 08 -042


             •Release of 2010 US Customary LRFD Specifications
 EI 10-013   •Implementation for buried structures if the project’s preliminary
                       engineering design phase begins after October 1, 2010

Design Criteria   Standard Value                                                Existing Value Proposed Value
Structural        HL-93 and NYS Design Permit Vehicle (LRFD Replacement Min.)
                  MS-23 (AASHTO Replacement Min.)                               N/A           MS-23
Capacity          MS-18 (AASHTO Rehabilitation Min.)
Development of Alternatives
Maintenance and Protection of Traffic
 • Traffic maintained via offsite detour
 • NYSDOT Highway Work Permit (PERM 33)


Right of Way
 • 66’ ROW width
 • Single property owner (Erie Boulevard Hydropower) adjacent to structure
 • Temporary easements taken at the four corners of the bridge
   o Constructing wingwalls
   o Placing stone filling
 • Donation streamlined the ROW process and minimized project costs
Project Costs
 Preliminary Engineer’s Estimates
                      Precast Concrete Arch   Single-Span Multigirder
Work Item
                            Replacement            Replacement
Right-of-Way                $ 14,000                 $ 14,000
Structure Removal          $ 225,000                $ 170,000
Bridge Construction        $ 755,800               $ 1,074,400
Highway                    $ 211,000                $ 176,500
M&PT                        $ 21,300                 $ 21,300
Mobilization (4%)           $ 40,100                 $ 51,200
Contingency (10%)          $ 126,800                $ 150,800
Total                     $ 1,394,000              $ 1,658,500
Selection of Preferred Alternative
Preferred Alternative: Precast Concrete Arch Replacement
   • Lowest Initial Construction Cost
   • Precast Components
       o Quality Control During Fabrication
       o Expedited Installation
       o Minimal Environmental Impacts
   • Lowest Maintenance Costs
   • Aesthetics - recreational area during summer months
       oForm liner considered but dropped due to:
           Cost (not federally reimbursable)
           Rural Location
Selection of Preferred Alternative
Preferred Alternative: Precast Concrete Arch Replacement
 Bid, Letting, and Award
     • Advertised on April 14, 2010
          o Delayed due to federal fund availability
          o 75 calendar days from anticipated NTP to completion date
               32 calendar days prior to stream restriction
               51 calendar days post stream restriction

     • Bid opening on May 5, 2010
        o Low Bidder: Ramsey Constructor's, Inc. (4 bidders)
        o 92% Engineers Estimate
Construction Phase
Notice to Proceed
May 13, 2010




                             Existing Bridge Demolition
                          June 3 through June 15, 2010
Construction Phase
                          Precast Arch Concrete Footing
                                             Placement




Completed July 30, 2010
Construction Phase
                                           Precast Concrete
                                              Shop Drawings
                                       Submitted July 2, 2010




Approvals:
Foundation Layout: July 12, 2010
Arch Units: July 27, 2010
Wingwalls/Headwalls: August 11, 2010
Construction Phase
                                   Arch Placement




September 22, 2010
Construction Phase
  Arch
Erection
9/22/10
Construction Phase
  Arch
Erection
9/22/10
Construction Phase
  Arch
Erection
9/22/10
Construction Phase
  Arch
Erection
9/22/10
Construction Phase
Arch Erection 9/22/10
Construction Phase
 Crown
Closure
  Pour
9/27/10
Construction Phase
        Headwall and Wingwall Placement
                   October 7 and 8, 2010
Construction Phase
          Headwall and Wingwall Bracing
Construction Phase
Headwall
   and
Wingwall
 Bracing
Construction Phase
                                    Headwall and
                                        Wingwall
                                      Installation




“Everyone is OK”
Construction Phase
              Headwall and Wingwall
                         Installation
Construction Phase
  Rock
Outcrop
Removal
 10/9/10
    to
10/13/10
Construction Phase
                              Backfill and Geotextile
                                          Installation




Bodkin Bar Connection
Construction Phase
Backfill and
 Geotextile
Installation
Commences
 10/13/10
Construction Phase
  Precast
 Headwall
Installation
 Complete
 10/19/10
Construction Phase
                           Nearing Backfill Completion




October 23, 2010
Construction Phase
New Bridge opened on November 5, 2010




                 • 60 working days utilized
                   to complete project
Construction Phase




        • Average of 9.5 hours per
          working day
Lessons Learned

• Appropriate Geotechnical Explorations
  • Pay attention to surrounding existing features


• Permitting / Stream Restrictions
  • May impact the preferred alternative

• Constructability
  • Utilize input from others to understand the process
Summary
Learning Assessment

Q: What NYSDOT bridge rating typically constitutes a “poor” rating?:

   a) 5: Minor deterioration, but functioning as originally designed.
   b) 4: Between a 5 and a 3 rating.
   c) 3: Serious deterioration, or not functioning as originally designed.
   d) 2: Between a 3 and a 1 rating.
   e) 1: Totally deteriorated, or in failed condition.

A: b) 4
Learning Assessment

Q: Which statement(s) is/are true of a structurally deficient bridge:

     The bridge
          a) doesn't meet current standards for managing traffic volumes.
          b) has a condition rating < 5.
          c) has narrow lanes, no shoulders, or low clearances.
          d) requires significant maintenance to remain in service.
          e) is unsafe or likely to collapse.


A:        b) has a condition rating < 5
                              and
          d) requires significant maintenance to remain in service
Learning Assessment

Q: Which statement is true of a Safety Flag:

a)   Reports a condition presenting a clear and present danger to vehicular or
     pedestrian traffic, but poses no danger of structural failure.
b)   Reports a potentially hazardous structural condition, which if left unattended
     could become a clear and present danger before the next scheduled inspection.
c)   Reports the failure or potential failure of a primary structural component that is
     likely to occur before the next schedule biennial inspection.


A:   a) Reports a condition presenting a clear and present danger to vehicular or
        pedestrian traffic, but poses no danger of structural failure.
Learning Assessment

Q: In geotechnical exploration, what does RQD stand for?




A: Rock Quality Designation
Learning Assessment

Q: (True/False) Meeting the freeboard recommendation is the primary
   concern on all bridge replacement projects over water.




A: False, while true for most projects, other considerations such as
   recurring scour or stream obstacles (pier) need to be taken into
   consideration.
Learning Assessment

Q: (True/False) Structural design criteria currently requires the use of
   AASHTO Standard Specifications (Allowable Stress Design) for Buried
   Structures.




A: False, LRFD specifications are required if the project’s preliminary
   engineering design phase began after October 1, 2010.
Learning Assessment

Q: Identify four conventional bridge elements not contained as part of
   precast concrete buried structures which account for lower
   maintenance costs.




A: 1. Joints
   2. Bearings
   3. Deck
   4. Conventional Primary Members
Learning Assessment

Q: What benefits can be realized during the construction of a precast
   concrete buried structure resulting in minimized construction costs
   and an enhanced finished product?




A: 1. Increased quality control during fabrication.
   2. Expedited installation (lack of forming, pouring, cure times)
   3. Minimization of environmental impacts.
Learning Assessment

Q: What is the name Contech gives to the mechanism which connects the
   geotextile “tabs” cast into the back face of the MSE style walls and the
   Tesar geotextile within the backfill zone?




A: Bodkin Bar
Learning Assessment

Q: (True/False) It is possible to construct a bridge over a stream with a
   restriction during the prime construction season.




A: True.
Questions

Contenu connexe

Tendances

The Hanover Company - 717 Olympic
The Hanover Company - 717 OlympicThe Hanover Company - 717 Olympic
The Hanover Company - 717 OlympicHanh N. Hong
 
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Tonyamis
 
Repair Options for Concrete Roadways
Repair Options for Concrete RoadwaysRepair Options for Concrete Roadways
Repair Options for Concrete RoadwaysJill Reeves
 
Composites_Global_LinkedIn 2015
Composites_Global_LinkedIn 2015Composites_Global_LinkedIn 2015
Composites_Global_LinkedIn 2015Steven Behrens
 
Whitemud Drive Retaining Wall
Whitemud Drive Retaining WallWhitemud Drive Retaining Wall
Whitemud Drive Retaining WallJim McMullan
 
GE Presentation 6th October 2010
GE Presentation 6th October 2010GE Presentation 6th October 2010
GE Presentation 6th October 2010Tonyamis
 
Henn, Ray (LONG) w-o PhD 2014 (NEW)
Henn, Ray  (LONG) w-o PhD 2014 (NEW)Henn, Ray  (LONG) w-o PhD 2014 (NEW)
Henn, Ray (LONG) w-o PhD 2014 (NEW)Raymond Henn
 
Pile Foundation and beams site report
Pile Foundation and beams site reportPile Foundation and beams site report
Pile Foundation and beams site reportskmunazzar
 
Construction methods and equipments
Construction methods and equipmentsConstruction methods and equipments
Construction methods and equipmentsR VIJAYAKUMAR
 
Jefferson County Historical High School
Jefferson County Historical High SchoolJefferson County Historical High School
Jefferson County Historical High SchoolMason Frascona
 
Spectra halfday pdf
Spectra halfday pdfSpectra halfday pdf
Spectra halfday pdfhtrdano
 
special foundation techniques
 special foundation techniques special foundation techniques
special foundation techniquesShrideviAnil
 
2012 9 Philadelphia Museum of Art Construction Project
2012 9 Philadelphia Museum of Art Construction Project2012 9 Philadelphia Museum of Art Construction Project
2012 9 Philadelphia Museum of Art Construction ProjectIAMFA
 
Civil_Structural Engineer, Graham Chambers, December 2015
Civil_Structural Engineer, Graham Chambers, December 2015Civil_Structural Engineer, Graham Chambers, December 2015
Civil_Structural Engineer, Graham Chambers, December 2015Graham Chambers
 
Emin sg sistema dimension caso west hynes tank farm
Emin sg   sistema dimension caso west hynes tank farmEmin sg   sistema dimension caso west hynes tank farm
Emin sg sistema dimension caso west hynes tank farmEMIN Sistemas Geotecnicos
 

Tendances (20)

The Hanover Company - 717 Olympic
The Hanover Company - 717 OlympicThe Hanover Company - 717 Olympic
The Hanover Company - 717 Olympic
 
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
 
Repair Options for Concrete Roadways
Repair Options for Concrete RoadwaysRepair Options for Concrete Roadways
Repair Options for Concrete Roadways
 
BPA Commercial
BPA CommercialBPA Commercial
BPA Commercial
 
Composites_Global_LinkedIn 2015
Composites_Global_LinkedIn 2015Composites_Global_LinkedIn 2015
Composites_Global_LinkedIn 2015
 
Construction Job Story in GeoDrilling International
Construction Job Story in GeoDrilling InternationalConstruction Job Story in GeoDrilling International
Construction Job Story in GeoDrilling International
 
GCS PSU Pegula2
GCS PSU Pegula2GCS PSU Pegula2
GCS PSU Pegula2
 
Whitemud Drive Retaining Wall
Whitemud Drive Retaining WallWhitemud Drive Retaining Wall
Whitemud Drive Retaining Wall
 
GE Presentation 6th October 2010
GE Presentation 6th October 2010GE Presentation 6th October 2010
GE Presentation 6th October 2010
 
Henn, Ray (LONG) w-o PhD 2014 (NEW)
Henn, Ray  (LONG) w-o PhD 2014 (NEW)Henn, Ray  (LONG) w-o PhD 2014 (NEW)
Henn, Ray (LONG) w-o PhD 2014 (NEW)
 
Pile Foundation and beams site report
Pile Foundation and beams site reportPile Foundation and beams site report
Pile Foundation and beams site report
 
Construction methods and equipments
Construction methods and equipmentsConstruction methods and equipments
Construction methods and equipments
 
Jefferson County Historical High School
Jefferson County Historical High SchoolJefferson County Historical High School
Jefferson County Historical High School
 
Spectra halfday pdf
Spectra halfday pdfSpectra halfday pdf
Spectra halfday pdf
 
special foundation techniques
 special foundation techniques special foundation techniques
special foundation techniques
 
Confined masonry
Confined masonryConfined masonry
Confined masonry
 
2012 9 Philadelphia Museum of Art Construction Project
2012 9 Philadelphia Museum of Art Construction Project2012 9 Philadelphia Museum of Art Construction Project
2012 9 Philadelphia Museum of Art Construction Project
 
resume_2015
resume_2015resume_2015
resume_2015
 
Civil_Structural Engineer, Graham Chambers, December 2015
Civil_Structural Engineer, Graham Chambers, December 2015Civil_Structural Engineer, Graham Chambers, December 2015
Civil_Structural Engineer, Graham Chambers, December 2015
 
Emin sg sistema dimension caso west hynes tank farm
Emin sg   sistema dimension caso west hynes tank farmEmin sg   sistema dimension caso west hynes tank farm
Emin sg sistema dimension caso west hynes tank farm
 

En vedette

Seafarer's Center Pedestrian Bridge
Seafarer's Center Pedestrian BridgeSeafarer's Center Pedestrian Bridge
Seafarer's Center Pedestrian BridgeMaha Al Soufi
 
Building a Budget Bridge
Building a Budget BridgeBuilding a Budget Bridge
Building a Budget Bridgebuckburch
 
Implementation of Construction Project with Detailed Contract Documents
Implementation of Construction Project with Detailed Contract DocumentsImplementation of Construction Project with Detailed Contract Documents
Implementation of Construction Project with Detailed Contract DocumentsAye Nyein
 
Smart Sensors for Infrastructure and Structural Health Monitoring
Smart Sensors for Infrastructure and Structural Health MonitoringSmart Sensors for Infrastructure and Structural Health Monitoring
Smart Sensors for Infrastructure and Structural Health MonitoringJeffrey Funk
 
Examples of Design Briefs
Examples of Design BriefsExamples of Design Briefs
Examples of Design BriefsR. Sosa
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 

En vedette (7)

Seafarer's Center Pedestrian Bridge
Seafarer's Center Pedestrian BridgeSeafarer's Center Pedestrian Bridge
Seafarer's Center Pedestrian Bridge
 
Building a Budget Bridge
Building a Budget BridgeBuilding a Budget Bridge
Building a Budget Bridge
 
Implementation of Construction Project with Detailed Contract Documents
Implementation of Construction Project with Detailed Contract DocumentsImplementation of Construction Project with Detailed Contract Documents
Implementation of Construction Project with Detailed Contract Documents
 
Smart Sensors for Infrastructure and Structural Health Monitoring
Smart Sensors for Infrastructure and Structural Health MonitoringSmart Sensors for Infrastructure and Structural Health Monitoring
Smart Sensors for Infrastructure and Structural Health Monitoring
 
Examples of Design Briefs
Examples of Design BriefsExamples of Design Briefs
Examples of Design Briefs
 
Construction process
Construction processConstruction process
Construction process
 
Creating the Perfect Design Brief
Creating the Perfect Design BriefCreating the Perfect Design Brief
Creating the Perfect Design Brief
 

Similaire à Assessing and constructing a cost effective bridge replacement christopher sichak, pe

SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)dgonano
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09zaff69
 
2006 AEG Godwin presentation
2006 AEG Godwin presentation2006 AEG Godwin presentation
2006 AEG Godwin presentationWilliam Godwin
 
05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards Presentation05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards PresentationAISC/NSBA
 
Michalis presentation_2015
Michalis presentation_2015Michalis presentation_2015
Michalis presentation_2015ILIAS MICHALIS
 
module20120PPT.pdf
module20120PPT.pdfmodule20120PPT.pdf
module20120PPT.pdfRakeshH21
 
Portageville Presentation
Portageville PresentationPortageville Presentation
Portageville PresentationJordan Penney
 
Experimental study of shear capacity of reinforced concrete slabs
Experimental study of shear capacity of reinforced concrete slabsExperimental study of shear capacity of reinforced concrete slabs
Experimental study of shear capacity of reinforced concrete slabsEva Lantsoght
 
07 AASHTO Bridge Committee Awards Presentation
07 AASHTO Bridge Committee Awards Presentation07 AASHTO Bridge Committee Awards Presentation
07 AASHTO Bridge Committee Awards PresentationAISC/NSBA
 
Dn tanks prestressed_concretetank
Dn tanks prestressed_concretetankDn tanks prestressed_concretetank
Dn tanks prestressed_concretetankAdrian Frantescu
 
Inspection,Repair and Strengthening of PSC Bridge.
Inspection,Repair and Strengthening of PSC  Bridge.Inspection,Repair and Strengthening of PSC  Bridge.
Inspection,Repair and Strengthening of PSC Bridge.Mohammad Furqan
 
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Rajesh Kolli
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiKrystian Gnysinski
 
Rock engineering-overview
Rock engineering-overviewRock engineering-overview
Rock engineering-overviewAman Bagrecha
 
Innovation - Extending Cast-In-Place Box Culverts with Precast Box Culverts -...
Innovation - Extending Cast-In-Place Box Culverts with Precast Box Culverts -...Innovation - Extending Cast-In-Place Box Culverts with Precast Box Culverts -...
Innovation - Extending Cast-In-Place Box Culverts with Precast Box Culverts -...Jensen Precast
 

Similaire à Assessing and constructing a cost effective bridge replacement christopher sichak, pe (20)

SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09
 
2006 AEG Godwin presentation
2006 AEG Godwin presentation2006 AEG Godwin presentation
2006 AEG Godwin presentation
 
50 years of Innovation in Bridge Design & Construction
50 years of Innovation in Bridge Design & Construction50 years of Innovation in Bridge Design & Construction
50 years of Innovation in Bridge Design & Construction
 
05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards Presentation05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards Presentation
 
Michalis presentation_2015
Michalis presentation_2015Michalis presentation_2015
Michalis presentation_2015
 
module20120PPT.pdf
module20120PPT.pdfmodule20120PPT.pdf
module20120PPT.pdf
 
Portageville Presentation
Portageville PresentationPortageville Presentation
Portageville Presentation
 
Experimental study of shear capacity of reinforced concrete slabs
Experimental study of shear capacity of reinforced concrete slabsExperimental study of shear capacity of reinforced concrete slabs
Experimental study of shear capacity of reinforced concrete slabs
 
07 AASHTO Bridge Committee Awards Presentation
07 AASHTO Bridge Committee Awards Presentation07 AASHTO Bridge Committee Awards Presentation
07 AASHTO Bridge Committee Awards Presentation
 
Dn tanks prestressed_concretetank
Dn tanks prestressed_concretetankDn tanks prestressed_concretetank
Dn tanks prestressed_concretetank
 
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
 
Inspection,Repair and Strengthening of PSC Bridge.
Inspection,Repair and Strengthening of PSC  Bridge.Inspection,Repair and Strengthening of PSC  Bridge.
Inspection,Repair and Strengthening of PSC Bridge.
 
Airport Boulevard Railroad Grade Separation Project
Airport Boulevard Railroad Grade Separation ProjectAirport Boulevard Railroad Grade Separation Project
Airport Boulevard Railroad Grade Separation Project
 
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
 
Newport Marina Presentation March 2015
Newport Marina Presentation March 2015Newport Marina Presentation March 2015
Newport Marina Presentation March 2015
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
Rock engineering-overview
Rock engineering-overviewRock engineering-overview
Rock engineering-overview
 
Precast concrete 101
Precast concrete 101Precast concrete 101
Precast concrete 101
 
Innovation - Extending Cast-In-Place Box Culverts with Precast Box Culverts -...
Innovation - Extending Cast-In-Place Box Culverts with Precast Box Culverts -...Innovation - Extending Cast-In-Place Box Culverts with Precast Box Culverts -...
Innovation - Extending Cast-In-Place Box Culverts with Precast Box Culverts -...
 

Plus de mecocca5

Local Roads Matter Photo Slideshow
Local Roads Matter Photo SlideshowLocal Roads Matter Photo Slideshow
Local Roads Matter Photo Slideshowmecocca5
 
Innovative Retaining Wall Systems
Innovative Retaining Wall SystemsInnovative Retaining Wall Systems
Innovative Retaining Wall Systemsmecocca5
 
Beach Road, Porous Pavement and Then Some
Beach Road, Porous Pavement and Then SomeBeach Road, Porous Pavement and Then Some
Beach Road, Porous Pavement and Then Somemecocca5
 
Subsurface Investigation and Geotechnical Evaluation
Subsurface Investigation and Geotechnical EvaluationSubsurface Investigation and Geotechnical Evaluation
Subsurface Investigation and Geotechnical Evaluationmecocca5
 
The Way We Were -The Way We Are
The Way We Were -The Way We AreThe Way We Were -The Way We Are
The Way We Were -The Way We Aremecocca5
 
Fwd thinking
Fwd thinkingFwd thinking
Fwd thinkingmecocca5
 
Pavement preservation john curley and dane mellon
Pavement preservation john curley and dane mellonPavement preservation john curley and dane mellon
Pavement preservation john curley and dane mellonmecocca5
 
What the complete streets legislation means for you ed stachura
What the complete streets legislation means for you ed stachuraWhat the complete streets legislation means for you ed stachura
What the complete streets legislation means for you ed stachuramecocca5
 
Impacts of energy development on low volume roads paul wilke, pe
Impacts of energy development on low volume roads paul wilke, peImpacts of energy development on low volume roads paul wilke, pe
Impacts of energy development on low volume roads paul wilke, pemecocca5
 
NYS DEC PSRT Program-Tom Blanchard, NYSDEC and Andy Stiles, NYSDOT
NYS DEC PSRT Program-Tom Blanchard, NYSDEC and Andy Stiles, NYSDOTNYS DEC PSRT Program-Tom Blanchard, NYSDEC and Andy Stiles, NYSDOT
NYS DEC PSRT Program-Tom Blanchard, NYSDEC and Andy Stiles, NYSDOTmecocca5
 
What would you do ethical choices questions and responses
What would you do ethical choices questions and responsesWhat would you do ethical choices questions and responses
What would you do ethical choices questions and responsesmecocca5
 
Best Practices for Management of Traffic Signs: Town of Clifton Park as a Cas...
Best Practices for Management of Traffic Signs: Town of Clifton Park as a Cas...Best Practices for Management of Traffic Signs: Town of Clifton Park as a Cas...
Best Practices for Management of Traffic Signs: Town of Clifton Park as a Cas...mecocca5
 
Quality Based Road Program
Quality Based Road ProgramQuality Based Road Program
Quality Based Road Programmecocca5
 
Overcoming the Hurdles of Improving Outdated Vehicle Maintenance Facilities
Overcoming the Hurdles of Improving Outdated Vehicle Maintenance FacilitiesOvercoming the Hurdles of Improving Outdated Vehicle Maintenance Facilities
Overcoming the Hurdles of Improving Outdated Vehicle Maintenance Facilitiesmecocca5
 
Maintaining Compliance with Right to Know Law
Maintaining Compliance with Right to Know LawMaintaining Compliance with Right to Know Law
Maintaining Compliance with Right to Know Lawmecocca5
 
Mechanistic Empirical Pavement Design
Mechanistic Empirical Pavement Design Mechanistic Empirical Pavement Design
Mechanistic Empirical Pavement Design mecocca5
 
Construction Materials Engineering and Testing
Construction Materials Engineering and TestingConstruction Materials Engineering and Testing
Construction Materials Engineering and Testingmecocca5
 
Big Challenge, Big Success
Big Challenge, Big SuccessBig Challenge, Big Success
Big Challenge, Big Successmecocca5
 
Stretching Dollars with Bridge Maintenance
Stretching Dollars with Bridge Maintenance Stretching Dollars with Bridge Maintenance
Stretching Dollars with Bridge Maintenance mecocca5
 
Asset Management - Data Collection, Prioritization, Estimating, Funding
Asset Management - Data Collection, Prioritization, Estimating, FundingAsset Management - Data Collection, Prioritization, Estimating, Funding
Asset Management - Data Collection, Prioritization, Estimating, Fundingmecocca5
 

Plus de mecocca5 (20)

Local Roads Matter Photo Slideshow
Local Roads Matter Photo SlideshowLocal Roads Matter Photo Slideshow
Local Roads Matter Photo Slideshow
 
Innovative Retaining Wall Systems
Innovative Retaining Wall SystemsInnovative Retaining Wall Systems
Innovative Retaining Wall Systems
 
Beach Road, Porous Pavement and Then Some
Beach Road, Porous Pavement and Then SomeBeach Road, Porous Pavement and Then Some
Beach Road, Porous Pavement and Then Some
 
Subsurface Investigation and Geotechnical Evaluation
Subsurface Investigation and Geotechnical EvaluationSubsurface Investigation and Geotechnical Evaluation
Subsurface Investigation and Geotechnical Evaluation
 
The Way We Were -The Way We Are
The Way We Were -The Way We AreThe Way We Were -The Way We Are
The Way We Were -The Way We Are
 
Fwd thinking
Fwd thinkingFwd thinking
Fwd thinking
 
Pavement preservation john curley and dane mellon
Pavement preservation john curley and dane mellonPavement preservation john curley and dane mellon
Pavement preservation john curley and dane mellon
 
What the complete streets legislation means for you ed stachura
What the complete streets legislation means for you ed stachuraWhat the complete streets legislation means for you ed stachura
What the complete streets legislation means for you ed stachura
 
Impacts of energy development on low volume roads paul wilke, pe
Impacts of energy development on low volume roads paul wilke, peImpacts of energy development on low volume roads paul wilke, pe
Impacts of energy development on low volume roads paul wilke, pe
 
NYS DEC PSRT Program-Tom Blanchard, NYSDEC and Andy Stiles, NYSDOT
NYS DEC PSRT Program-Tom Blanchard, NYSDEC and Andy Stiles, NYSDOTNYS DEC PSRT Program-Tom Blanchard, NYSDEC and Andy Stiles, NYSDOT
NYS DEC PSRT Program-Tom Blanchard, NYSDEC and Andy Stiles, NYSDOT
 
What would you do ethical choices questions and responses
What would you do ethical choices questions and responsesWhat would you do ethical choices questions and responses
What would you do ethical choices questions and responses
 
Best Practices for Management of Traffic Signs: Town of Clifton Park as a Cas...
Best Practices for Management of Traffic Signs: Town of Clifton Park as a Cas...Best Practices for Management of Traffic Signs: Town of Clifton Park as a Cas...
Best Practices for Management of Traffic Signs: Town of Clifton Park as a Cas...
 
Quality Based Road Program
Quality Based Road ProgramQuality Based Road Program
Quality Based Road Program
 
Overcoming the Hurdles of Improving Outdated Vehicle Maintenance Facilities
Overcoming the Hurdles of Improving Outdated Vehicle Maintenance FacilitiesOvercoming the Hurdles of Improving Outdated Vehicle Maintenance Facilities
Overcoming the Hurdles of Improving Outdated Vehicle Maintenance Facilities
 
Maintaining Compliance with Right to Know Law
Maintaining Compliance with Right to Know LawMaintaining Compliance with Right to Know Law
Maintaining Compliance with Right to Know Law
 
Mechanistic Empirical Pavement Design
Mechanistic Empirical Pavement Design Mechanistic Empirical Pavement Design
Mechanistic Empirical Pavement Design
 
Construction Materials Engineering and Testing
Construction Materials Engineering and TestingConstruction Materials Engineering and Testing
Construction Materials Engineering and Testing
 
Big Challenge, Big Success
Big Challenge, Big SuccessBig Challenge, Big Success
Big Challenge, Big Success
 
Stretching Dollars with Bridge Maintenance
Stretching Dollars with Bridge Maintenance Stretching Dollars with Bridge Maintenance
Stretching Dollars with Bridge Maintenance
 
Asset Management - Data Collection, Prioritization, Estimating, Funding
Asset Management - Data Collection, Prioritization, Estimating, FundingAsset Management - Data Collection, Prioritization, Estimating, Funding
Asset Management - Data Collection, Prioritization, Estimating, Funding
 

Dernier

Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostZilliz
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfRankYa
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 

Dernier (20)

Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdf
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 

Assessing and constructing a cost effective bridge replacement christopher sichak, pe

  • 1. Presentation for: 2012 NYSCHSA Summer Conference August 28, 2012 By: Christopher Sichak, P.E.
  • 2. Outline • Introduction • Existing Conditions • Environmental Considerations • Project Needs • Development of Alternatives • Project Costs • Selection of Preferred Alternative • Construction Phase • Lessons Learned • Summary • Learning Assessment • Questions
  • 3. Introduction Project Location • NYSDOT Region 4, Orleans County, Town of Ridgeway • Between Ridge Road (SR 104) and Oak Orchard River Road • Oak Orchard River upstream of Waterport Pond (Lake Alice) PROJECT ` LOCATION
  • 4. Introduction Project Team Orleans County Owner’s Group • NYSDOT Region 4 • Town of Ridgeway • Federal Highway Administration Clark Patterson Lee / Dewberry-Goodkind, Inc. Engineering • Ravi Engineering & Land Surveying (survey, mapping, environmental, construction inspection) • SJB, Empire Geo Services, Inc. (geotechnical, construction material testing) • BME Associates (wetland delineation) • R K Hite & Co., Inc. (right of way acquisition) Ramsey Constructors, Inc. Material Suppliers: • Clark Rigging (crane work) • G & J Contracting (reinforcement installation) • • Contech Construction Products, Inc. Construction Buffalo Barricade (detour signage) • C & A Pavement Marking (pavement markings) • Lakelands Concrete Products, Inc. • Villager Construction, Inc. (milling) • Pavilion Drainage Supply Co., Inc. • Elderlee, Inc. (guide-rail and signs) • Suit-Kote • Terry Tree (tree removal) • Hanson Aggregates • Vellano Bros., Inc. • MJ Dreher Trucking (trucking) • Kistner Concrete Products, Inc. • Farrell Landscaping (seeding) • Keystone Builders Supply • Fisher Associates (survey and ROW markers)
  • 5. Introduction • Bridge Constructed in 1930 • Steel Jack Arch Structure • Two 40.7’ Spans (85’ total) • 24’ curb-to-curb • 27’ out-to-out • No skew • Reinforced Concrete Substructures
  • 6. Existing Conditions 2006 Biennial Inspection • 31 of the 50 (62%) rated elements had poor values (4 or lower) • NYSDOT Condition Rating = 4.015, FHWA Sufficiency Rating = 39.9, General Rec. = 4 • Structurally Deficient (Condition < 5, significant maintenance to remain in service)
  • 7. Existing Conditions Safety Flags • Condition presenting a clear and present danger to vehicular or pedestrian traffic, but poses no danger of structural failure. • Spalling of Concrete Parapets • Hole in deck near the pier
  • 8. Existing Conditions Approach Roadway • 2 – 11’ travel lanes • Variable width gravel shoulders Two way AADT: • 2000: 944 • 2009: 992
  • 9. Existing Conditions Geotechnical Investigations Boring Recovery RQD B-1 81% 51% • Shale bedrock below apparent fill soils B-2 91% 28% • RQD (Rock Quality Designation) RQD Rock Mass Quality length of pieces exceeding 4” ____________________ <25% very poor = x 100% 25-50% poor length of core run 50-75% fair 75-90% good •Bearing capacity of 8 tons/sf 90-100% excellent
  • 10. Existing Conditions Utilities Electric (National Grid) Telephone (Verizon) Water (Town of Ridgeway) o Relocate aerial o Relocate aerial o Coordinate geometry facilities and street facilities along east with 8” Direct bored light along east side side of the roadway watermain along east of the roadway side of the roadway
  • 11. Existing Conditions Hydraulics • History of debris snagging on pier • Pier erosion and scour • Exposed pier footing
  • 12. Existing Conditions Hydraulics • 48 mile upstream length • Initiates in Genesee County PROJECT LOCATION • 192 square miles drainage area • Upstream flow controlled 50 Year Flood ` Model Elevation (m) Existing Structure 353.34 Replacement 353.27 Option 1 Replacement 353.37 Option 2
  • 13. Environmental Considerations Archeological Sensitive Area SHPO Project Review Application completed 2/9/09 detailing previous Project Location disturbance SHPO concurrence with 2/24/09 previous disturbance FHWA concurrence no 3/13/09 Phase I Cultural Resources neccesary
  • 14. Environmental Considerations Environmental Screenings and Permitting • USACOE Nationwide Permit #3 • NYSDEC Excavation and Fill in Navigable Waters • NYSDEC Water Quality Certification Endangered Species = Stream Restriction • Longear Sunfish (Lepomis Megalotis) • June 15 to September 15
  • 15. Project Needs Goals • Replace existing structure within available funding limits • Provide structural service life of 75 years • Meet current standards • Enhance safety • Minimize stream disturbance in accordance with permits
  • 16. Development of Alternatives Conceptual Alternatives: 1. Rehabilitation 2. Single Span Multigirder Replacement: a. Steel b. Spread or Adjacent Prestressed Concrete Box Beam c. Other Prestressed Concrete Shapes (AASHTO I, New England Bulb Tee) 3. Single Span Concrete Buried Structure 4. Two-Span Bridge Replacement (Steel or Concrete Superstructure) 5. Multi-Span Concrete Buried Structure
  • 17. Development of Alternatives Conceptual Alternatives: 1. Rehabilitation 2. Single Span Multigirder Replacement: a. Steel b. Spread or Adjacent Prestressed Concrete Box Beam c. Other Prestressed Concrete Shapes (AASHTO I, New England Bulb Tee) 3. Single Span Concrete Buried Structure 4. Two-Span Bridge Replacement (Steel or Concrete Superstructure) Dropped due to Hydraulic Characteristics 5. Multi-Span Concrete Buried Structure
  • 18. Development of Alternatives 1. Rehabilitation • Replace the superstructure • Repair and reuse the existing substructures • Retained existing features would continue to deteriorate • Initial construction cost • Anticipated future maintenance costs • Continued stream obstruction from pier
  • 19. Development of Alternatives Conceptual Alternatives: 1. Rehabilitation 2. Single Span Multigirder Replacement: a. Steel b. Spread or Adjacent Prestressed Concrete Box Beam c. Other Prestressed Concrete Shapes (AASHTO I, New England Bulb Tee) Dropped due to Anticipated Costs 3. Single Span Concrete Buried Structure
  • 20. Development of Alternatives 2. Adjacent Prestressed Concrete Box Beam Replacement 100’ (+/-) Proposed Elevation • Lower initial construction cost than steel multigirder • deck forming and thickness • Tall Concrete Abutments and Wingwalls with spread footings on bedrock (25’ – 30’)
  • 21. Development of Alternatives 3. Single Span Concrete Buried Structure • Lower maintenance costs • Arch: o Absence of features o Geometry fits well with requiring maintenance: site topography  Joints o Structurally sound and  Bearings efficient shape  Deck o Most economical  Primary Members foundation size • Lower construction costs o Limited field construction (precast) o Limited field specialty work
  • 22. Development of Alternatives 3. Single Span Concrete Buried Structure (Precast Arch) 77’-9” 21’-10” Proposed Elevation • Detailed as a precast structure o Twin leaf structure, headwalls, and wingwalls o E78T/0: Contech BEBO (77’ -9” Span x 21’ –10” Rise)
  • 23. Development of Alternatives •LRFD Specifications mandated for bridge design by October 1, 2007 EI 05-003 •Exception: LRFD implementation for design of buried structures in 2010 EI 07-014 EI 07-030 •Release of 2007 (Metric and US) and 2008 (US) LRFD Specifications EI 08 -042 •Release of 2010 US Customary LRFD Specifications EI 10-013 •Implementation for buried structures if the project’s preliminary engineering design phase begins after October 1, 2010 Design Criteria Standard Value Existing Value Proposed Value Structural HL-93 and NYS Design Permit Vehicle (LRFD Replacement Min.) MS-23 (AASHTO Replacement Min.) N/A MS-23 Capacity MS-18 (AASHTO Rehabilitation Min.)
  • 24. Development of Alternatives Maintenance and Protection of Traffic • Traffic maintained via offsite detour • NYSDOT Highway Work Permit (PERM 33) Right of Way • 66’ ROW width • Single property owner (Erie Boulevard Hydropower) adjacent to structure • Temporary easements taken at the four corners of the bridge o Constructing wingwalls o Placing stone filling • Donation streamlined the ROW process and minimized project costs
  • 25. Project Costs Preliminary Engineer’s Estimates Precast Concrete Arch Single-Span Multigirder Work Item Replacement Replacement Right-of-Way $ 14,000 $ 14,000 Structure Removal $ 225,000 $ 170,000 Bridge Construction $ 755,800 $ 1,074,400 Highway $ 211,000 $ 176,500 M&PT $ 21,300 $ 21,300 Mobilization (4%) $ 40,100 $ 51,200 Contingency (10%) $ 126,800 $ 150,800 Total $ 1,394,000 $ 1,658,500
  • 26. Selection of Preferred Alternative Preferred Alternative: Precast Concrete Arch Replacement • Lowest Initial Construction Cost • Precast Components o Quality Control During Fabrication o Expedited Installation o Minimal Environmental Impacts • Lowest Maintenance Costs • Aesthetics - recreational area during summer months oForm liner considered but dropped due to:  Cost (not federally reimbursable)  Rural Location
  • 27. Selection of Preferred Alternative Preferred Alternative: Precast Concrete Arch Replacement Bid, Letting, and Award • Advertised on April 14, 2010 o Delayed due to federal fund availability o 75 calendar days from anticipated NTP to completion date  32 calendar days prior to stream restriction  51 calendar days post stream restriction • Bid opening on May 5, 2010 o Low Bidder: Ramsey Constructor's, Inc. (4 bidders) o 92% Engineers Estimate
  • 28. Construction Phase Notice to Proceed May 13, 2010 Existing Bridge Demolition June 3 through June 15, 2010
  • 29. Construction Phase Precast Arch Concrete Footing Placement Completed July 30, 2010
  • 30. Construction Phase Precast Concrete Shop Drawings Submitted July 2, 2010 Approvals: Foundation Layout: July 12, 2010 Arch Units: July 27, 2010 Wingwalls/Headwalls: August 11, 2010
  • 31. Construction Phase Arch Placement September 22, 2010
  • 32. Construction Phase Arch Erection 9/22/10
  • 33. Construction Phase Arch Erection 9/22/10
  • 34. Construction Phase Arch Erection 9/22/10
  • 35. Construction Phase Arch Erection 9/22/10
  • 38. Construction Phase Headwall and Wingwall Placement October 7 and 8, 2010
  • 39. Construction Phase Headwall and Wingwall Bracing
  • 40. Construction Phase Headwall and Wingwall Bracing
  • 41. Construction Phase Headwall and Wingwall Installation “Everyone is OK”
  • 42. Construction Phase Headwall and Wingwall Installation
  • 43. Construction Phase Rock Outcrop Removal 10/9/10 to 10/13/10
  • 44. Construction Phase Backfill and Geotextile Installation Bodkin Bar Connection
  • 45. Construction Phase Backfill and Geotextile Installation Commences 10/13/10
  • 46. Construction Phase Precast Headwall Installation Complete 10/19/10
  • 47. Construction Phase Nearing Backfill Completion October 23, 2010
  • 48. Construction Phase New Bridge opened on November 5, 2010 • 60 working days utilized to complete project
  • 49. Construction Phase • Average of 9.5 hours per working day
  • 50. Lessons Learned • Appropriate Geotechnical Explorations • Pay attention to surrounding existing features • Permitting / Stream Restrictions • May impact the preferred alternative • Constructability • Utilize input from others to understand the process
  • 52. Learning Assessment Q: What NYSDOT bridge rating typically constitutes a “poor” rating?: a) 5: Minor deterioration, but functioning as originally designed. b) 4: Between a 5 and a 3 rating. c) 3: Serious deterioration, or not functioning as originally designed. d) 2: Between a 3 and a 1 rating. e) 1: Totally deteriorated, or in failed condition. A: b) 4
  • 53. Learning Assessment Q: Which statement(s) is/are true of a structurally deficient bridge: The bridge a) doesn't meet current standards for managing traffic volumes. b) has a condition rating < 5. c) has narrow lanes, no shoulders, or low clearances. d) requires significant maintenance to remain in service. e) is unsafe or likely to collapse. A: b) has a condition rating < 5 and d) requires significant maintenance to remain in service
  • 54. Learning Assessment Q: Which statement is true of a Safety Flag: a) Reports a condition presenting a clear and present danger to vehicular or pedestrian traffic, but poses no danger of structural failure. b) Reports a potentially hazardous structural condition, which if left unattended could become a clear and present danger before the next scheduled inspection. c) Reports the failure or potential failure of a primary structural component that is likely to occur before the next schedule biennial inspection. A: a) Reports a condition presenting a clear and present danger to vehicular or pedestrian traffic, but poses no danger of structural failure.
  • 55. Learning Assessment Q: In geotechnical exploration, what does RQD stand for? A: Rock Quality Designation
  • 56. Learning Assessment Q: (True/False) Meeting the freeboard recommendation is the primary concern on all bridge replacement projects over water. A: False, while true for most projects, other considerations such as recurring scour or stream obstacles (pier) need to be taken into consideration.
  • 57. Learning Assessment Q: (True/False) Structural design criteria currently requires the use of AASHTO Standard Specifications (Allowable Stress Design) for Buried Structures. A: False, LRFD specifications are required if the project’s preliminary engineering design phase began after October 1, 2010.
  • 58. Learning Assessment Q: Identify four conventional bridge elements not contained as part of precast concrete buried structures which account for lower maintenance costs. A: 1. Joints 2. Bearings 3. Deck 4. Conventional Primary Members
  • 59. Learning Assessment Q: What benefits can be realized during the construction of a precast concrete buried structure resulting in minimized construction costs and an enhanced finished product? A: 1. Increased quality control during fabrication. 2. Expedited installation (lack of forming, pouring, cure times) 3. Minimization of environmental impacts.
  • 60. Learning Assessment Q: What is the name Contech gives to the mechanism which connects the geotextile “tabs” cast into the back face of the MSE style walls and the Tesar geotextile within the backfill zone? A: Bodkin Bar
  • 61. Learning Assessment Q: (True/False) It is possible to construct a bridge over a stream with a restriction during the prime construction season. A: True.