TP
1. Navteq POI - Sri Lanka
Project Lead: Prashant Tyagi
2. A) Briefing:
Capture the POIs in Sri Lanka* which includes Banks, Hotels,
Restaurants & Hospitals etc. and update the POI Database. Post
Quality Check on Ground and Database, the Project will be delivered
to the Client in Shape File format.
Total POIs :45000 (Expected)
B) Resources:
Surveyors :15 (In Sri Lanka)
Operator & Surveyor :1 Operator, 1 Surveyor ( from India)
Quality Check :1 (Project Lead)
Equipments/System Requirements :2 Laptops, 1 PDA
(Trimble Juno) and 1 Garmin GPS
Device.
C) Timelines: : 1st May 2012-15th June 2012
*In Sri Lanka, for cities described in the slides later.
3. Capture The POI (Point Of Interest ) e.g Banks, Hotels, Hospitals & Restaurants etc.
After capturing the POI By Ground, update the POI Data Base.
Check all category code as created by self.
Check all category code by QC team.
After checking all category then run category fill program(as received).