PROJECT RISK MANAGEMENT
 Example: Company Trip
 Identify
 Response
 Owner
1
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
PROJECT RISK MANAGEMENT
 Risk is an uncertain event or condition that, if occurs, has an
effect on at least one project objective.
 Issue is a point or matter in question or in dispute.
 Threat: Negative risks
 Opportunities: Positive risks
 Risk management objectives:
 increase the probability and impact of positive events
(opportunities).
 decrease the probability and impact of negative events
(threat).
2
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
PROJECT RISK MANAGEMENT
 Risk Attitudes
 Risk Averse: people are not comfortable with risks; they are
willing to avoid the risks, doesn’t like risk.
 Risk Neutral: people manage risks based on their expected
value, that is, probability times impact. In other words, their
decisions towards risks are not biased by any other factors,
except for the risks’ expected value.
 Risk Seeker: people see risks as challenges and feel exciting
dealing with them.
 Risk Tolerant: people are indifferent about risks. This means
they do not pay much attention to risks, until these risks
become real problems.
3
PROJECT RISK MANAGEMENT
 11.1 Plan Risk Management
 11.2 Identify Risks
 11.3 Perform Qualitative Risk
Analysis
 11.4 Perform Quantitative Risk
Analysis
 11.5 Plan Risk Responses
 11.6 Control Risks
4
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
PROJECT RISK MANAGEMENT
5
Knowledge
Area
Process
Initiating Planning Executing
Monitoring &
Contol
Closing
Project Risk
Management
11.1 Plan Risk
Management
11.2 Identify Risks
11.3 Perform
Qualitative Risk
Analysis
11.4 Perform
Quantitative Risk
Analysis
11.5 Plan Risk
Responses
11.6 Control
Risks
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.1 PLAN RISK MANAGEMENT
 Plan Risk Management is the process of defining how to conduct
risk management activities for a project.
 Risk Management Plan include:
 Methodology.
 Roles and responsibilities.
 Budgeting.
 Timing.
 Risk categories.
 …
6
Inputs Tool&Techniques Outputs
.1 Project management plan
.2 Project charter
.3 Stakeholder register
.4 EEFs
.5 OPAs
.1 Analytical techniques
.2 Expert judgment
.3 Meetings
.1 Risk management plan
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.1 PLAN RISK MANAGEMENT
 Risk categories: Provide a means for grouping potential causes of risk.
Several approaches can be used, for example, a structure based on
project objectives by category
Example of a Risk Breakdown Structure (RBS)
7
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.2 IDENTIFY RISKS
 Identify Risks is the process of determining which risks may affect
the project and documenting their characteristics.
8
Inputs Tool&Techniques Outputs
.1 Risk management plan
.2 Cost management plan
.3 Schedule management plan
.4 Quality management plan
.5 Human resource management
plan
.6 Scope baseline
.7 Activity cost estimates
.8 Activity duration estimates
.9 Stakeholder register
.10 Project documents
.11 Procurement documents
.12 EEFs
.13 OPAs
.1 Documentation reviews
.2 Information gathering
techniques
.3 Checklist analysis
.4 Assumptions analysis
.5 Diagramming techniques
.6 SWOT analysis
.7 Expert judgment
.1 Risk register
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.2 IDENTIFY RISKS
 SWOT Analysis: This analysis looks at the project to identify its strengths and
weaknesses and thereby identify risks (opportunities and threats).
9
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.2 IDENTIFY RISKS
 Risk Register
10
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.3 PERFORM QUALITATIVE RISK ANALYSIS
 Perform Qualitative Risk Analysis is the process of
prioritizing risks for further analysis or action by
assessing and combining their probability of occurrence
and impact.
11
Inputs Tool&Techniques Outputs
.1 Risk management plan
.2 Scope baseline
.3 Risk register
.4 EEFs
.5 OPAs
.1 Risk probability and
impact assessment
.2 Probability and impact
matrix
.3 Risk data quality
assessment
.4 Risk categorization
.5 Risk urgency assessment
.6 Expert judgment
.1 Project documents
updates
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.3 PERFORM QUALITATIVE RISK ANALYSIS
 Probability and Impact Matrix
12
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.4 PERFORM QUANTITATIVE RISK ANALYSIS
 Perform Quantitative Risk Analysis is the process of
numerically analyzing the effect of identified risks on
overall project objectives.
13
Inputs Tool&Techniques Outputs
.1 Risk management plan
.2 Cost management plan
.3 Schedule management
plan
.4 Risk register
.5 EEFs
.6 OPAs
.1 Data gathering and
representation
techniques
.2 Quantitative risk
analysis
and modeling techniques
.3 Expert judgment
.1 Project documents
updates
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.4 PERFORM QUANTITATIVE RISK ANALYSIS
 Expected monetary value analysis
 Expected monetary value (EMV) = Probability * Impact
14
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.5 PLAN RISK RESPONSES
 Plan Risk Responses is the process of developing
options and actions to enhance opportunities and to
reduce threats to project objectives.
15
Inputs Tool&Techniques Outputs
.1 Risk management plan
.2 Risk register
.1 Strategies for negative
risks or threats
.2 Strategies for positive
risks or opportunities
.3 Contingent response
strategies
.4 Expert judgment
.1 Project management
plan
updates
.2 Project documents
updates
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.5 PLAN RISK RESPONSES
 Strategies for Negative Risks or Threats
 Avoid: Changing the project management plan to eliminate
the threat entirely: extending the schedule, changing the
strategy, or reducing scope
 Transfer: Make another party responsible for the risk by
purchasing insurance, performance bonds, warranties, or
guarantees or by outsourcing the work.
 Mitigate: Taking early action to reduce the probability and/or
impact of a threat
 Accept: Do nothing and say, “If it happens, it happens:”
16
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.5 PLAN RISK RESPONSES
 Strategies for Positive Risks or Opportunities
 Exploit: Add work or change the project to make sure the
opportunity occurs.
 Enhance: Increase the likelihood (probability) and/or positive
impacts of the risk event.
 Share: Allocate ownership of the opportunity to a third party
(forming a partnership, team, or joint venture) that is best
able to achieve the opportunity
 Accept: Do nothing and say, “If it happens, it happens:”
17
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.5 PLAN RISK RESPONSES
 Contingency plans are plans describing the specific actions that
will be taken if the opportunity or threat occurs.
 Secondary risks that arise as a direct outcome of implementing a
risk response.
 Residual risks These are the risks that remain after risk response
planning.
 Fallback plans These plans are specific actions that will be taken if
the contingency plan is not effective.
 Contingency reserves that are calculated based on the
quantitative risk analysis of the project and the organization’s risk
thresholds.
 Risk response owners A key concept in risk response planning is
that the project manager does not have to do it all and neither
does the team.
18
SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013
11.6 CONTROL RISKS
 Control Risks is the process of implementing risk
response plans, tracking identified risks, monitoring
residual risks, identifying new risks, and evaluating risk
process effectiveness throughout the project.
19
Inputs Tool&Techniques Outputs
.1 Project management plan
.2 Risk register
.3 Work performance data
.4 Work performance
reports
.1 Risk reassessment
.2 Risk audits
.3 Variance and trend
analysis
.4 Technical
performance
measurement
.5 Reserve analysis
.6 Meetings
.1 Work performance
information
.2 Change requests
.3 Project management plan
updates
.4 Project documents
updates
.5 Organizational process
assets updates

Contenu connexe

Tendances

Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3Nam Trung
 
Smsvn pmp training_slides_chapter_9
Smsvn pmp training_slides_chapter_9Smsvn pmp training_slides_chapter_9
Smsvn pmp training_slides_chapter_9Nam Trung
 
Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1Nam Trung
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPTbletindia
 
Pmp(project management professional ) presentation
Pmp(project management professional ) presentationPmp(project management professional ) presentation
Pmp(project management professional ) presentationgokula kannan
 
Mb0049 project management
Mb0049   project managementMb0049   project management
Mb0049 project managementsmumbahelp
 
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...Mubashir Ali
 
Anosha jamshed projectmanager
Anosha jamshed projectmanagerAnosha jamshed projectmanager
Anosha jamshed projectmanageranosha jamshed
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slidesDoreen Yeo
 

Tendances (20)

Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3
 
Smsvn pmp training_slides_chapter_9
Smsvn pmp training_slides_chapter_9Smsvn pmp training_slides_chapter_9
Smsvn pmp training_slides_chapter_9
 
Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPT
 
Free PMP® Exam Sample Question
Free PMP® Exam Sample QuestionFree PMP® Exam Sample Question
Free PMP® Exam Sample Question
 
Pmp(project management professional ) presentation
Pmp(project management professional ) presentationPmp(project management professional ) presentation
Pmp(project management professional ) presentation
 
Mb0049 project management
Mb0049   project managementMb0049   project management
Mb0049 project management
 
Pmi rmp-2020 - v6
Pmi rmp-2020 - v6Pmi rmp-2020 - v6
Pmi rmp-2020 - v6
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
PMP Exam Prep Plus: Why E-Learning?
PMP Exam Prep Plus: Why E-Learning?PMP Exam Prep Plus: Why E-Learning?
PMP Exam Prep Plus: Why E-Learning?
 
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Certified Project Consultant
Certified Project Consultant  Certified Project Consultant
Certified Project Consultant
 
Anosha jamshed projectmanager
Anosha jamshed projectmanagerAnosha jamshed projectmanager
Anosha jamshed projectmanager
 
Certified Planning Engineer CPE
Certified Planning Engineer CPE Certified Planning Engineer CPE
Certified Planning Engineer CPE
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slides
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
PMP Exam Notes
PMP Exam NotesPMP Exam Notes
PMP Exam Notes
 
PMP Study Guides
PMP Study GuidesPMP Study Guides
PMP Study Guides
 

En vedette

Smsvn conflicts
Smsvn conflictsSmsvn conflicts
Smsvn conflictsNam Trung
 
Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3Highmark Health
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Saad Merie
 
Pmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterPmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterYudha Pratama, PMP
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1Craig Brown
 
Oil and Gas Project Management Training Solutions
Oil and Gas Project Management Training SolutionsOil and Gas Project Management Training Solutions
Oil and Gas Project Management Training SolutionsESI14
 
Integration Management Presentation
Integration Management Presentation Integration Management Presentation
Integration Management Presentation TDAKINS319
 
Project Management: Initiating Process Group - Lesson 1
Project Management: Initiating Process Group - Lesson 1 Project Management: Initiating Process Group - Lesson 1
Project Management: Initiating Process Group - Lesson 1 JMBOKAcademy
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk managementPMC Mentor
 
Smsvn quality attitude
Smsvn quality attitudeSmsvn quality attitude
Smsvn quality attitudeNam Trung
 

En vedette (13)

Smsvn conflicts
Smsvn conflictsSmsvn conflicts
Smsvn conflicts
 
Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
Pmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterPmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charter
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1
 
Project management
Project managementProject management
Project management
 
Oil and Gas Project Management Training Solutions
Oil and Gas Project Management Training SolutionsOil and Gas Project Management Training Solutions
Oil and Gas Project Management Training Solutions
 
Integration Management Presentation
Integration Management Presentation Integration Management Presentation
Integration Management Presentation
 
Project Management: Initiating Process Group - Lesson 1
Project Management: Initiating Process Group - Lesson 1 Project Management: Initiating Process Group - Lesson 1
Project Management: Initiating Process Group - Lesson 1
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk management
 
Smsvn quality attitude
Smsvn quality attitudeSmsvn quality attitude
Smsvn quality attitude
 

Similaire à Smsvn pmp training_slides_chapter_11

Schwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.pptSchwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.pptAyidAlmgati
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentationRaven Morgan
 
12 Project RISK and ISSUES Management.pdf
12 Project RISK and ISSUES Management.pdf12 Project RISK and ISSUES Management.pdf
12 Project RISK and ISSUES Management.pdfmebratuhailu674
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskMuzette Charles, PMP
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1reddvise
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5Future Managers
 
For Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptxFor Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptxAbhinavRJ1
 
Risk mgmt
Risk mgmtRisk mgmt
Risk mgmtOliver
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”Ary Jamil
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship AliAbbas390458
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazMohamed Saeed
 

Similaire à Smsvn pmp training_slides_chapter_11 (20)

Schwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.pptSchwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.ppt
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
11 risk management
11 risk management11 risk management
11 risk management
 
12 Project RISK and ISSUES Management.pdf
12 Project RISK and ISSUES Management.pdf12 Project RISK and ISSUES Management.pdf
12 Project RISK and ISSUES Management.pdf
 
Ch_1_PRM.pdf
Ch_1_PRM.pdfCh_1_PRM.pdf
Ch_1_PRM.pdf
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Manage risks
Manage risksManage risks
Manage risks
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
PMP Preparation - 11 Risk Management
PMP Preparation - 11 Risk ManagementPMP Preparation - 11 Risk Management
PMP Preparation - 11 Risk Management
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5
 
Pmp risk management
Pmp risk managementPmp risk management
Pmp risk management
 
For Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptxFor Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptx
 
PPT SE SACHIN.ppt
PPT SE SACHIN.pptPPT SE SACHIN.ppt
PPT SE SACHIN.ppt
 
Risk mgmt
Risk mgmtRisk mgmt
Risk mgmt
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbaz
 
Risk management process
Risk management  processRisk management  process
Risk management process
 

Dernier

FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 

Dernier (20)

FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 

Smsvn pmp training_slides_chapter_11

  • 1. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 PROJECT RISK MANAGEMENT  Example: Company Trip  Identify  Response  Owner 1
  • 2. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 PROJECT RISK MANAGEMENT  Risk is an uncertain event or condition that, if occurs, has an effect on at least one project objective.  Issue is a point or matter in question or in dispute.  Threat: Negative risks  Opportunities: Positive risks  Risk management objectives:  increase the probability and impact of positive events (opportunities).  decrease the probability and impact of negative events (threat). 2
  • 3. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 PROJECT RISK MANAGEMENT  Risk Attitudes  Risk Averse: people are not comfortable with risks; they are willing to avoid the risks, doesn’t like risk.  Risk Neutral: people manage risks based on their expected value, that is, probability times impact. In other words, their decisions towards risks are not biased by any other factors, except for the risks’ expected value.  Risk Seeker: people see risks as challenges and feel exciting dealing with them.  Risk Tolerant: people are indifferent about risks. This means they do not pay much attention to risks, until these risks become real problems. 3
  • 4. PROJECT RISK MANAGEMENT  11.1 Plan Risk Management  11.2 Identify Risks  11.3 Perform Qualitative Risk Analysis  11.4 Perform Quantitative Risk Analysis  11.5 Plan Risk Responses  11.6 Control Risks 4
  • 5. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 PROJECT RISK MANAGEMENT 5 Knowledge Area Process Initiating Planning Executing Monitoring & Contol Closing Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Control Risks
  • 6. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.1 PLAN RISK MANAGEMENT  Plan Risk Management is the process of defining how to conduct risk management activities for a project.  Risk Management Plan include:  Methodology.  Roles and responsibilities.  Budgeting.  Timing.  Risk categories.  … 6 Inputs Tool&Techniques Outputs .1 Project management plan .2 Project charter .3 Stakeholder register .4 EEFs .5 OPAs .1 Analytical techniques .2 Expert judgment .3 Meetings .1 Risk management plan
  • 7. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.1 PLAN RISK MANAGEMENT  Risk categories: Provide a means for grouping potential causes of risk. Several approaches can be used, for example, a structure based on project objectives by category Example of a Risk Breakdown Structure (RBS) 7
  • 8. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.2 IDENTIFY RISKS  Identify Risks is the process of determining which risks may affect the project and documenting their characteristics. 8 Inputs Tool&Techniques Outputs .1 Risk management plan .2 Cost management plan .3 Schedule management plan .4 Quality management plan .5 Human resource management plan .6 Scope baseline .7 Activity cost estimates .8 Activity duration estimates .9 Stakeholder register .10 Project documents .11 Procurement documents .12 EEFs .13 OPAs .1 Documentation reviews .2 Information gathering techniques .3 Checklist analysis .4 Assumptions analysis .5 Diagramming techniques .6 SWOT analysis .7 Expert judgment .1 Risk register
  • 9. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.2 IDENTIFY RISKS  SWOT Analysis: This analysis looks at the project to identify its strengths and weaknesses and thereby identify risks (opportunities and threats). 9
  • 10. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.2 IDENTIFY RISKS  Risk Register 10
  • 11. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.3 PERFORM QUALITATIVE RISK ANALYSIS  Perform Qualitative Risk Analysis is the process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact. 11 Inputs Tool&Techniques Outputs .1 Risk management plan .2 Scope baseline .3 Risk register .4 EEFs .5 OPAs .1 Risk probability and impact assessment .2 Probability and impact matrix .3 Risk data quality assessment .4 Risk categorization .5 Risk urgency assessment .6 Expert judgment .1 Project documents updates
  • 12. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.3 PERFORM QUALITATIVE RISK ANALYSIS  Probability and Impact Matrix 12
  • 13. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.4 PERFORM QUANTITATIVE RISK ANALYSIS  Perform Quantitative Risk Analysis is the process of numerically analyzing the effect of identified risks on overall project objectives. 13 Inputs Tool&Techniques Outputs .1 Risk management plan .2 Cost management plan .3 Schedule management plan .4 Risk register .5 EEFs .6 OPAs .1 Data gathering and representation techniques .2 Quantitative risk analysis and modeling techniques .3 Expert judgment .1 Project documents updates
  • 14. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.4 PERFORM QUANTITATIVE RISK ANALYSIS  Expected monetary value analysis  Expected monetary value (EMV) = Probability * Impact 14
  • 15. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.5 PLAN RISK RESPONSES  Plan Risk Responses is the process of developing options and actions to enhance opportunities and to reduce threats to project objectives. 15 Inputs Tool&Techniques Outputs .1 Risk management plan .2 Risk register .1 Strategies for negative risks or threats .2 Strategies for positive risks or opportunities .3 Contingent response strategies .4 Expert judgment .1 Project management plan updates .2 Project documents updates
  • 16. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.5 PLAN RISK RESPONSES  Strategies for Negative Risks or Threats  Avoid: Changing the project management plan to eliminate the threat entirely: extending the schedule, changing the strategy, or reducing scope  Transfer: Make another party responsible for the risk by purchasing insurance, performance bonds, warranties, or guarantees or by outsourcing the work.  Mitigate: Taking early action to reduce the probability and/or impact of a threat  Accept: Do nothing and say, “If it happens, it happens:” 16
  • 17. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.5 PLAN RISK RESPONSES  Strategies for Positive Risks or Opportunities  Exploit: Add work or change the project to make sure the opportunity occurs.  Enhance: Increase the likelihood (probability) and/or positive impacts of the risk event.  Share: Allocate ownership of the opportunity to a third party (forming a partnership, team, or joint venture) that is best able to achieve the opportunity  Accept: Do nothing and say, “If it happens, it happens:” 17
  • 18. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.5 PLAN RISK RESPONSES  Contingency plans are plans describing the specific actions that will be taken if the opportunity or threat occurs.  Secondary risks that arise as a direct outcome of implementing a risk response.  Residual risks These are the risks that remain after risk response planning.  Fallback plans These plans are specific actions that will be taken if the contingency plan is not effective.  Contingency reserves that are calculated based on the quantitative risk analysis of the project and the organization’s risk thresholds.  Risk response owners A key concept in risk response planning is that the project manager does not have to do it all and neither does the team. 18
  • 19. SMSVN – PMP Training Course 2013 – Chapter 11 Prepared by Nguyen Quy Son - 20/08/2013 11.6 CONTROL RISKS  Control Risks is the process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project. 19 Inputs Tool&Techniques Outputs .1 Project management plan .2 Risk register .3 Work performance data .4 Work performance reports .1 Risk reassessment .2 Risk audits .3 Variance and trend analysis .4 Technical performance measurement .5 Reserve analysis .6 Meetings .1 Work performance information .2 Change requests .3 Project management plan updates .4 Project documents updates .5 Organizational process assets updates