1. The Royal Navy: JIT based ship spares provisioning
Alan Fowler
Introduction
JIT methods are commonly associated with mass production industries, for example car
manufacturing, in which investment in developing and implementing radical new processes can be
justified against savings in large volume turnover. However, Womack and Jones1 identified several
successful applications of this practice in different industries around the world, and claimed that it
could be applied in low volume operations and office activities as well as in mass production on the
scale typically found in the automotive industry. The question therefore arises as to whether these
methods can yield cost-effective benefits in the small quantities that are turned over in industries
such as defence. Spares provisioning for the Royal Navy typifies such a requirement where, in
addition to potential concerns about higher set-up costs for small batch production, development
costs are high relative to material costs. For a service that is becoming increasingly aware of the
need to reduce costs, whilst simultaneously maintaining a high level of operational availability,
JIT based methods of spares provisioning appear potentially promising.
Contending models for warship spares provisioning
Traditionally, spares support for warships, as depicted schematically in Figure 32.1, can be divided
into two categories: Forward Support, including carried-on-board (COB) spares, and Base Support
(base spares). Ships carry a limited range of spare parts, mechanical and electrical, so that repairs
and some maintenance can be performed whilst at sea. The range of COB spares is limited by the
ability to conduct the related maintenance at sea while the quantity is determined by stock-out risk
(SOR) criteria. This is typically set at 95 per cent which means that the warship crew can be 95 per
cent confident that they will not run out of spares during a standard mission (for example 90 days).
This calculation assumes constant random failure rates for all equipment (no account is taken of
wear-out rates within this simplified assumption). In practice this is a reasonable assumption, since
it is generally true for the electronic products which comprise the largest population of COB spares.
Conversely, the rate of demand for mechanical items is so low as to make the required spares
quantities insensitive to the inaccuracies of this assumption.
Figure 32.1 Conventional warship spares provisioning system
2. The majority of maintenance and repair work, other than emergencies at sea, is performed at the
dockside by a ‘prime contractor’ working for the MOD/Navy (the MOD Support Organisation).
When a warship returns to base, any COB spares used on deployment must be replaced. Further
spares may also be required for base maintenance. These are drawn from stores, either held at the
shore base or at a central depot. Currently, the level of spares inventory for each ‘Line Replaceable
Unit’ (LRU), sometimes called a ‘spareable’ item, is again determined by a SOR criterion for some
initial period of the warship’s operational life. By definition, the stock-out risk criterion is
demanding: almost twice as many spares are held as are expected to be needed, just in case. The
rationale for this is that the Royal Navy is charged with the defence of the nation, implying that
operational availability is crucial and should not be jeopardised by lack of spares. The situation is
exacerbated by MOD’s requirement for insurance spares. These are required since occasionally
damage is incurred to warships through fire, accident or combat. Under these circumstances spares
may be required on a range and scale that would not normally be anticipated. These often include
large quantities or high-value items that represent a significant cost.
The prime contractor is supplied by original equipment manufacturers (OEM) who, in turn, are
supplied by component manufacturers comprising the ‘spares supply chain’. Collectively, this
comprises the supplier support organisation, depicted in Figure 32.1. Finally, Figure 32.1, also
alludes to the current state of relationships within the supply chain which may be characterised by
an ‘over the wall’ mentality involving limited integration and transparency. Currently the MOD is
beginning to contract with prime contractors to provide the Support Organization for a Contractor
Logistic Support (CLS) period (Tasker and Willcox2) which corresponds to the period for initial
support. During this initial period the actual spares demand is monitored and further spares are
ordered as required. However, there are some fundamental problems with this existing system. For
example, the initial support period is not long enough to determine future demand; too much stock
is procured initially; shortages develop quickly; obsolescence problems arise and excessive
inventory costs are incurred.
Process reconfiguration drawing on JIT principles
Figure 32.2 illustrates how a JIT approach to replenishment could enable base-spares inventory to
be reduced to give an equivalent SOR but with a shorter replacement lead-time. First, it should be
noted that there is no real change at the COB end of the spectrum, except a stronger emphasis on
providing timely information when a failure occurs which necessitates a call on spares. Notably the
MOD shore base stores are reduced and responsibility for provisioning is passed further back
upstream, moving from a just-in-case to a JIT concept. The system therefore depends upon a
fundamental change in the relationship and associated contract with the supplier. This entails
arrangement for replacement of spares in a guaranteed lead-time with fixed prices. By adopting this
approach based on JIT principles, featuring a shorter replacement lead-time, it may be possible to
reduce base-spares inventory and tackle the problems outlined above, whilst continuing to provide
an equivalent SOR. This also allows insurance spares to be largely eliminated by making alternative
arrange ments
3. for timely replacements in the event that they are needed. This would be achieved by changing the
structure of the contract with the supplier whereby instead of a one-off buy of equipment and
spares, the supplier would be contracted to provide a service level commitment for a specified
period of time. Reduced bureaucracy should also characterise this system. Currently, when
defective items are returned to industry for repair or refurbishment, there is a protracted contractual
debate about whether it is economical to repair the item, how much this should cost and how long it
should take. This debate can often take place between the MOD and several tiers within the supply
chain.
Consequently it is disproportionately expensive and time-consuming. With the JIT concept, all
defective items are simply returned directly to the supplier who then takes the decision on repair
independently. Since the supplier is already contracted to provide a replacement in a guaranteed
lead-time at a fixed unit price, the customer can be indifferent to the decision outcome. However,
the supplier must also provide information on the diagnosis of the failure and any repair activity
carried out to maintain ‘Corrective Actions’ and ‘Configuration Management’ records. Since it is
envisioned that a fixed price would be paid for this service, then the supplier should be motivated to
take the most cost-effective decision to maintain margins. Indeed, by assessing the expected
number of items that will be capable of repair, and the likely repair costs, the fixed unit price for
replacements can be negotiated to a weighted average of new build and repair costs with an agreed
margin. This means that the aggregate unit price for spares could be less than that paid for the
original equipment. Under such a system, the supplier would also be motivated to improve the
reliability of its equipment, since this is the other way in which margins can be maintained or
improved.
In contemplating the potential of such a system, there are a number of current developments which
illustrate the trend towards alternative approaches. For example, there is notable evidence that many
in the defence industry are attracted to the idea of moving spares stock from the customer’s
premises to those of the suppliers. This view, which appears to be gaining popularity, is referred to
4. as ‘vendor managed inventory’ (Walmsley3 and Coles4). The benefits are seen as reducing the cost
of holding the inventory and enabling suppliers to manage inventory levels. However, suppliers
naturally expect to be paid for providing this service and taking on additional risk. Furthermore,
Coles alludes to doubts over the sincerity of industry in its espoused willingness to participate in
such projects:
‘Only those in industry can truly know whether they are prepared to work in this way, and there is
still some way to go before we can confidently predict what the exact result will be.’ These
initiatives have the potential to facilitate more rapid introduction of new technology into service
since the switch to upgrades can render large spares inventories obsolete overnight. However, the
most significant factor impacting on the more rapid introduction of new technology is the adoption
of commercial off-the-shelf (COTS) components. This is because commercial development moves
at a rapid pace and is supported by a much larger market. Use of COTS, therefore, enables the
MOD to take advantage of new technologies as they emerge without the time and cost penalties of
developing bespoke military equipment.
Conversely, there are penalties associated with having to accept commercial specifications, which
may require concessions on military requirements such as shock resistance. Design must also be
modular to allow frequent upgrades in components to be accepted without affecting form, fit or
function. However, on balance, the policies of increasing use of COTS and vendor managed
inventory would appear to be entirely complementary with JIT spares provisioning. For example,
JIT may be seen to facilitate the more rapid introduction of COTS upgrades by maintaining the
supply chain and reducing inventory while COTS components will be more suitable for JIT
provisioning because of the larger manufacturing base and expanded production volumes. These
smart procurement policies are mostly enablers for defence projects to achieve greater efficiencies
through modern information systems, streamlined bureaucracy and clear data standards. All are
potentially significant contributors towards the development of a JIT spares provisioning system,
although amongst the various approaches proposed RAMP (rapid acquisition of manufactured
parts) appears to be the most relevant. This envisages the holding of electronic parts data and/or
partially manufactured components at the suppliers’ premises so that they can be completed and
shipped quickly when required. In this way, the long leadtimes and risks associated with process
planning, sourcing exotic materials and elaborate forgings, and organising complex manufacturing
processes can be managed upstream, leaving the relatively straightforward stages of manufacture to
be completed when the parts are required. The MOD pays for the extent of the work completed plus
a fee for storage and only completes the balance when the part is actually delivered.
Some issues of concern
Although the JIT system potentially has several advantages, it is also necessary to sound a
cautionary note. The JIT model may work in situations where the accounting trade-off between the
risk of losing a sale, due to the absence of immediate availability, can be balanced with the cost of
inventory. The question is, does this logic transfer directly to the case of the defence industry? The
MOD is charged with the defence of the realm. What higher priority can there be, and what price
can be placed on success? Understandably, the MOD is preoccupied with operational availability as
well as cost. A simple trade-off between the costs of the traditional system and those of a JIT
system may not be sufficient to justify a change in policy. Additionally, JIT production is usually
considered to depend on predictable demand and level scheduling, but both factors are significantly
absent in the context of spares provisioning. Also, there is the broader issue of whether JIT really
eliminates cost from the supply chain or just moves the costs to some point upstream. For example,
some evidence indicates that only those suppliers who themselves also implement JIT
manufacturing and purchasing techniques are able to supply JIT without increases in raw material
and/or finished goods inventory (Germain and Droge5). Furthermore, some would say that only
where manufacturing lead-time is less than the required response time can increases in finished
goods inventory be avoided. This highlights the main threat to the application of JIT in the low-
5. volume operations of the Royal Navy. Short response times are required at irregular and
unpredictable intervals for the supply of high-value, complex equipment with long manufacturing
lead-times. The implication is that this can only be achieved through holding finished goods
inventory.
In summary, it is essential to remember that still the most significant issue for the MOD, which
differentiates it from much of industry, is the importance of operational availability. Achieving a
trade-off between inventory cost and availability is a difficult problem to solve.
Cost modelling of the spares provisioning process
Financial viability is a primary consideration in contemplating a transition to JIT based spares
provisioning. Towards this end, a limited modelling exercise may be readily conducted using
available suppliers’ data on component cost, reliability and production lead-time. Extending this
context, it is also important to ask the question: What happens after the initial in-service support
period? With the conventional approach, the stock level would be topped up to restore the desired
SOR for some follow-on period, taking account of the actual demand rate experienced during the
initial in-service support period. For analysis to proceed, it would have to be assumed that the
predicted failure rate is accurate so that the predicted demand rate, after the initial period, can be
expected to remain unchanged. JIT replacements would then continue to be provided, as before,
with prices assumed to remain stable. Furthermore, the advantage of the JIT based approach could
actually be enhanced further when factors such as obsolescence and technology upgrading are taken
into account. This is because with JIT, accommodating changes to the inservice equipment
configuration is easier, quicker and cheaper because there is less inventory to become obsolete.
Finally, it must always be emphasised that the operational availability of vessels is of paramount
importance to the MOD. Consequently, it is imperative when comparing the resulting spares
availability under the two competing policies, to bear in mind that the availability of spares must
remain at least as good as it is at present and, ideally, should actually be improved following the
implementation of a JIT policy.
A comparative illustration of a typical spares provisioning situation
Presented below is a snapshot of some typical data pertaining to spares provisioning for warships.
The Royal Navy is considering the alternative JIT based approach as a means of potentially
reducing the cost of spares inventory and is using, as an example, the case of a particular high-tech
part for a radar system. This is supplied by a single supplier who does not supply anything else to
the Navy. Under the existing arrangements, the Navy carries two years’ stock whilst also
subscribing to the 95 per cent stock-out risk criterion (this means that there is a 95 per cent
confidence of not running out of spares). Alternatively, this may be thought of as a 95 per cent
‘stock-held’ confidence criterion. In addition, Naval operational requirements dictate that,
irrespective of risk criteria based on probability, there should be a minimum inventory level of one
item to provide for immediate availability. Under the alternative JIT based spares policy that is
being considered, the customer (the Navy/MOD in this case) will hold reduced stock at its shore
base, while still achieving 95 per cent SOR against a guarantee of delivery on demand to the Navy,
within five days, at a fixed unit price. The supplier will also maintain additional buffer stock, at an
agreed level, to achieve 95 per cent SOR against its manufacturing lead-time, to maintain
availability (replacing any parts drawn down by the Navy during the support period). This service
will be provided, in return for a fixed fee to be agreed between customer and supplier. It is assumed
that any failed parts will be discarded.
For the purpose of calculation, the following customer data is available:
● There is one of these parts fitted on each of 10 ships.
● The anticipated utilisation is 1000 operating hours per year for each part.
6. ● The mean time between failure (MTBF) of these parts is 10 000 operating hours. The
following supplier data is also available:
● The supplier has a manufacturing lead-time of 90 days.
● The cost of each part to the supplier is £100 000. This is marked up by 10 per cent for sale
to the Navy.
● The supplier proposes to charge a fee of £35 000 per annum to the Navy for providing the
JIT type service, plus the initial cost of setting up the buffer stock.
● The contract will run for two years (to be directly comparable with the existing
arrangements).
In comparing the JIT based proposal with the existing arrangements, the following
questions thereby arise:
(a) What is the cost to the Navy in the existing, traditional arrangement, when there is a
need to carry two years’ stock in accordance with the 95 per cent stock-out risk criterion?
(b) Under the alternative JIT arrangement, what level of stock needs to be carried by the
Navy and by the supplier respectively? What will this arrangement cost the Navy, in total?
(c) Is the propose d JIT arrangement financially advantageous to both the Navy and the
supplier (that is, what are the respective profits/benefits)?
(d) Suppose that a sensitivity analysis is also to be performed in which the mean time
between failure is assumed to be respectively:
– 1000 operating hours.
– 20000 operating hours.
How does this affect the predictions of benefits/deficits accruing to the respective parties?
(e) Are there any other sensitivities that should be considered and how influential are they
with respect to the viability of the proposal?
In performing the above analysis it should be assumed that cumulative Poisson probability
data will be used to assess the value of the stock-out risk criterion for different scenarios. In
performing your calculations you may choose, for convenience, to use the cumulative
Poisson function provided in the standard Excel spreadsheet facility.
Questions
In addition to consideration of the financial and operational advantages that might accrue when
implementing the changes suggested above, it is inevitable that political, cultural, social and
economic issues will also impact on, and influence, the potential success of the JIT based proposal.
A full analysis should therefore focus on a number of questions which may be summarised as
follows:
1 How does the proposed JIT system compare with/differ from the existing conventional spares
provisioning process?
2 What are the qualitative benefits that might accrue, based on the data made available in the case
study?
3 The stakeholders involved in implementing this proposal may be broadly grouped into three
categories: the MOD/Navy, the prime contractors (organisations who provide first-line and
dockyard services to the MOD) and subcontractors (the organisations in the industries that supply
and support the prime contractors). What do you believe the issues/problems would be in applying
JIT principles to spares provisioning from the perspective of each of these groups respectively?
4 Based on the illustrative numerical data presented above, how attractive is the JIT proposition
from a financial perspective, assuming this simplified quantitative example is typical of others
(work through the calculations to produce your answer).
5 Weighing all the evidence available, do you believe that it would be feasible and advantageous to
move towards a JIT based system for spares provisioning to Royal Navy warships? Explain your
reasoning.