PM DeepDive

Project Cost Management
     - Niraj Agarwal




                          May 2011
                            Slide 1
Project Cost Management
Definition

Project Cost Management includes the processes involved in planning
                                                              planning,
estimating, budgeting, and controlling costs so that the project can be
completed within the approved budget.
• Cost Estimating – developing an approximation of the costs of the
monetary resources needed to complete project activities.
• Cost Budgeting – aggregating the estimated costs of individual
activities or work packages t establish a cost b li
  ti iti         k    k     to t bli h       t baseline.
• Cost Control – influencing the factors that create cost variances and
controlling changes to the project budget.




                                                                   May 2011
                                                                     Slide 2
Project Cost Management
Types of Project Costs

• Direct Project Cost - The costs directly attributable to a project
                                                             project,
including all personnel, goods and/or services together with all their
associated costs. E.g. team travel, team wages, training,material,etc.
• Indirect Project Cost - All costs which do not form a part of the final
product, but which are none the less required for the orderly
completion of the project and which may include, but not necessarily be
limited to field administration, direct supervision, incidental tools and
equipment, startup costs, contractor’s fees, insurance, taxes, etc.
• Fixed Project Costs - Those costs which do not change with change in
volume of output E g set-up rental etc
          output. E.g. set-up, rental, etc.

•   Variable Project Costs - Those costs that vary proportionately with
    volume of output. E.g. material cost, supplies, wages, etc.

                                                                    May 2011
                                                                      Slide 3
Project Cost Management
Analogous Estimating

• It means using the actual cost of previous similar projects as the
                                     previous,
basis for estimating the cost of the current project.
• It uses expert judgment.
• This type of estimate is typically done as part of the business case
development or during the early stages of scope planning when there
isn’t a lot of detail on the project.
• An analogous estimate may be done for the project as a whole or for
selected phases or deliverables. It is not typically used to estimate
individual work packages.
• Analogous estimates are the least accurate of all the estimating
techniques but also the least costly.


                                                                       May 2011
                                                                         Slide 4
Project Cost Management
Parametric Estimating

• Same as the technique used in duration estimating
                                         estimating.
• This technique uses a mathematical model to compute costs, and it
most often uses the quantity of work multiplied by the rate.
• Parametric estimating is dependent on the accuracy of the data used
to create the model.




                                                                 May 2011
                                                                   Slide 5
Project Cost Management
Bottom - Up Estimating

• Assigns a cost estimate to each work package on the project
                                                      project.
• The WBS and the project resource requirements are critical inputs
for a bottom - up estimate.
• The idea is that you start at the work package level of the WBS and
calculate the cost of each activity assigned to that work package.
• The sum of all the work package estimates p
                          p    g            provides the estimate of
the total project cost.
• Bottom - up estimates are the most accurate of all the estimating
tec ques,
techniques, but t ey ’re a so t e most t e - consuming to pe o .
                they e also the ost time co su         g perform.




                                                                   May 2011
                                                                     Slide 6
Project Time Management
Three Point Estimates

• Three point estimates used:
  - Most likely(M) : Most likely cost of the schedule activity
  - Optimistic(O) : Activity cost is based on a best-case scenario
  - Pessimistic(P) : Activity cost is based on a worst-case scenario
• Estimating based on 3 formulas:
    i.
    i PERT Activity Cost : C = (P + 4M + O)/6




                                                                       May 2011
                                                                         Slide 7
Project Cost Management
Sample project cost estimate




                               May 2011
                                 Slide 8
Cost Estimating
ITTO




                  May 2011
                    Slide 9
Cost Estimating
ITTO




                  May 2011
                   Slide 10
Project Cost Management
Estimating Tips

• Brainstorm with your project team
• Communicate the type of estimate you are providing & the level of
accuracy they provide.
• Make use of any available templates
• Get estimates from the people doing the work.
• Document any assumptions you have made




                                                                 May 2011
                                                                  Slide 11
Cost Budgeting
Definition

Cost Budgeting is the process of aggregating all the cost estimates and
establishing a cost baseline for the project.
The cost baseline is the total expected cost for the project. Once
approved, it’s
approved it s used throughout the remainder of the project to measure
the overall cost performance.




                                                                    May 2011
                                                                     Slide 12
Cost Budgeting
ITTO




                 May 2011
                  Slide 13
Cost Budgeting
ITTO




                 May 2011
                  Slide 14
Cost Budgeting
Reserves

Contingency Reserves “A separately planned quantity used to allow for
                         A
future situations which may be planned for only in part (sometimes
called ‘known unknowns’). For example, rework is certain, the
amount of rework is not. The contingency fund is usually under the
                                    g   y              y
discretion of the project manager, who controls how these funds are
spent.

Management Reserve “ A separately planned quantity used to allow
                                    l l      d       i     d    ll
for future situations which are impossible to predict (sometimes called
“unknown-Unknowns”). Management reserves may involve cost or
schedule.
schedule Management reserves are intended to reduce the risk of
missing cost or schedule objectives. The management fund is usually
controlled by upper management.


                                                                  May 2011
                                                                   Slide 15
Project Cost Control
Definition

• Project Cost Control is primarily concerned with Controlling Changes
to the project budget
• The processes of gathering, accumulating, analyzing, reporting and
managing the costs on an on going basis
                         on-going basis.
• Includes project procedures, project cost changes, monitoring actual
versus budget, variance analysis, integrated cost/schedule reporting,
progress analysis and corrective actions.
            l i     d       ti      ti




                                                                  May 2011
                                                                   Slide 16
Project Cost Control
Definition

• Project Cost Control is primarily concerned with Controlling Changes
to the project budget
• The processes of gathering, accumulating, analyzing, reporting and
managing the costs on an on going basis
                         on-going basis.
• Includes project procedures, project cost changes, monitoring actual
versus budget, variance analysis, integrated cost/schedule reporting,
progress analysis and corrective actions.
            l i     d       ti      ti




                                                                  May 2011
                                                                   Slide 17
Earned Value Analysis


• Integrates cost, schedule and scope
• Better that comparing projected vs. actual because time and cost are
  analyzed separately
• Terms:
  - PV / BCWS – Budgeted Cost of Work Scheduled /Planned Value
  - EV / BCWP – Budgeted Cost of Work Performed / Earned Value
  - AC /ACWP – Actual Cost of Work Performed / Actual Cost




                                                                  May 2011
                                                                   Slide 18
Earned Value Analysis


• BAC – Budget at Completion (how much did you budget for the total
job)
• EAC – Estimate at Completion (what do we expect the total project to
cost)
• ETC – Estimate to Completion (how much more do we expect to
spend to finish the job)
• VAC – Variance at Completion (how much over/under budget do we
expect to be)




                                                                 May 2011
                                                                  Slide 19
Earned Value Analysis


• Variance = (Plan – Actual)
              (             )
• Cost Variance (CV): EV– AC; -ve is over budget , +ve is under
• Schedule Variance (SV): EV– PV; +ve is behind schedule, +ve is ahead
• Cost Performance Index (CPI): EV/ AC
  - I am only getting x¢ out of every $
• Schedule Performance Index (SPI): EV/ PV
  - I am only progressing x % of the planned rate
• Estimate at Completion (EAC): BAC / CPI
  - As of now we expect the total project to cost x$
• E ti t t C
  Estimate to Complete (ETC) EAC – AC
                     l t (ETC):
  - how much will it cost from now to completion
• Variance at Completion: BAC – EAC; when the project is over how much
more or less did we spend
                                                                 May 2011
                                                                  Slide 20
Earned Value Analysis
Question
                                     Work       Actual   Today is June 30th. —Data
                         Budget
Work Unit
            Completion
                         (in $M)
                                   Performed     Cost    Date
              Date                  (in $M)    (in $M)
                            PV
                                      EV          AC     1. What is the Cost Variance
   A        Jan. 31      10        10          12        2. What is the Schedule
   B        Feb. 8
            F b 28       5         4           5         Variance
   C        Mar. 31      6         8           8         3. What is the CPI
   D        12-May       15        13          12        4. What is the SPI
                                                         5
                                                         5. What is the EAC
   E        30-Jun
            30 Jun       20        20          30
                                                         6. What is the ETC
   F        18-Jul       3         0           0
                                                         7. What is the Percent
   G        Aug. 30      35        0           0
                                                         Complete
   H        Sept.
            Sept 22      22        0           0
                                                         8. What is the Percent Spent
   I        Oct. 29      12        0           0
   J        Nov. 30      9         0           0


                                                                               May 2011
                                                                                Slide 21
Earned Value Analysis
Question
                                     Work               What is the CV ? $55 - $67 =
                         Budget                Actual
Work Unit
            Completion
                         (in $M)
                                   Performed
                                             Cost (in   -$12 (EV AC)
                                                         $12 (EV-AC)
              Date                  (in $M)
                            PV
                                      EV
                                              $M) AC    2. What is the SV ? $55 - $56 =
                                                        -$1 (EV-PV)
   A        Jan. 31      10        10       12          3. What is the CPI? 55/67 =
   B        Feb. 8
            F b 28       5         4        5           .82 (EV/AC)
   C        Mar. 31      6         8        8           4. What is the SPI? 55/56 =
   D        12-May       15        13       12          .98 (EV-PV)
   E        30-Jun
            30 Jun       20        20       30          5.
                                                        5 What is the EAC? 137/ 82 =
                                                                             137/.
   F        18-Jul       3         0        0           $167 (BAC/CPI)
                                                        6. What is the ETC? $167 - $67 =
   G        Aug. 30      35        0        0
                                                        $100 (EAC-AC)
   H        Sept.
            Sept 22      22        0        0           7. What is the Percent
                                                             h      h
   I        Oct. 29      12        0        0           Complete? 55/137 =
   J        Nov. 30      9         0        0           40% (EV/BAC)
                                                        8. What is the Percent Spent?
                                                        67/137 = 49% (AC/BAC)
                                                                               May 2011
                                                                                Slide 22
Pop Quiz
Question 1

You are asked to prepare an estimate for a project business
case to install a new group of servers at a new satellite office.
There is very little detail about this project. What will you use
to compute your estimate?
       p     y
A. The price the client is willing to pay
B. A sophisticated modeling technique
C. The estimate provided by the project sponsor
D. The actual cost of a similar project




                                                             May 2011
                                                              Slide 23
Pop Quiz
Question 2

A discretionary fund used by the project manager to cover the
cost of possible adverse events during the project is known as
which of the following?
A.
A Management reserve
B. Chart of accounts
C. Contingency fund
         g   y
D. Cost baseline




                                                          May 2011
                                                           Slide 24
Pop Quiz
Question 3

You are developing a bottom - up estimate for the first phase of your
project. Which of the following is the most important input to complete
this task?
A.
A Historic data from a similar project
B. Schedule
C. The WBS
D. The scope statement




                                                                  May 2011
                                                                   Slide 25
Pop Quiz
Question 4

What is the most accurate estimate?
A. Analogous estimate
B. Bottom - up estimate
C. Estimates based on expert judgment
D. Parametric estimate




                                        May 2011
                                         Slide 26
Pop Quiz
Question 5

You are the project manager for a large IT project. At the time
you performed your cost estimates, the vendor you ’ re
working with provided you with the following estimates:
Programming estimate = 320 hours at $135/hour
                                    $135/hour.
Project management estimate = 320 hours at $155/hour.
Testing estimate = 150 hours at $85/hour.
      g                            /
What type of estimate are these?
A. Analogous
B. Bottom-up
C. Cost benefit
D.
D Parametric
                                                          May 2011
                                                           Slide 27
Thank You!

Contenu connexe

Tendances

Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
Izah Asmadi
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
Glen Alleman
 

Tendances (18)

Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
COST MANAGEMENT
COST MANAGEMENT COST MANAGEMENT
COST MANAGEMENT
 
Project Cost Management
Project Cost Management Project Cost Management
Project Cost Management
 
Cost management
Cost managementCost management
Cost management
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniques
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 

Similaire à Pm deep dive cost management

Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
ssusercf695b
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
reddvise
 

Similaire à Pm deep dive cost management (20)

Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
PMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost ManagementPMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost Management
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptx
 
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh MahasnehTop Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh Mahasneh
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
cost Management V4
cost Management V4cost Management V4
cost Management V4
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 

Plus de Niraj Agarwal (11)

Pmp refresher know the exam
Pmp refresher   know the examPmp refresher   know the exam
Pmp refresher know the exam
 
Pm deep dive time management
Pm deep dive   time managementPm deep dive   time management
Pm deep dive time management
 
Pm deep dive the processes
Pm deep dive   the processesPm deep dive   the processes
Pm deep dive the processes
 
Pm deep dive the framework
Pm deep dive   the frameworkPm deep dive   the framework
Pm deep dive the framework
 
Pm deep dive risk management
Pm deep dive   risk managementPm deep dive   risk management
Pm deep dive risk management
 
Pm deep dive quality management
Pm deep dive   quality managementPm deep dive   quality management
Pm deep dive quality management
 
Pm deep dive integration management
Pm deep dive   integration managementPm deep dive   integration management
Pm deep dive integration management
 
Pm deep dive hr - comm - procurement - pr
Pm deep dive   hr - comm - procurement - prPm deep dive   hr - comm - procurement - pr
Pm deep dive hr - comm - procurement - pr
 
Pm deep dive scope management
Pm deep dive   scope managementPm deep dive   scope management
Pm deep dive scope management
 
Fundamentals of data structures
Fundamentals of data structuresFundamentals of data structures
Fundamentals of data structures
 
Corporate Etiquette
Corporate EtiquetteCorporate Etiquette
Corporate Etiquette
 

Dernier

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 

Dernier (20)

Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Cyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfCyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdf
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 

Pm deep dive cost management

  • 1. PM DeepDive Project Cost Management - Niraj Agarwal May 2011 Slide 1
  • 2. Project Cost Management Definition Project Cost Management includes the processes involved in planning planning, estimating, budgeting, and controlling costs so that the project can be completed within the approved budget. • Cost Estimating – developing an approximation of the costs of the monetary resources needed to complete project activities. • Cost Budgeting – aggregating the estimated costs of individual activities or work packages t establish a cost b li ti iti k k to t bli h t baseline. • Cost Control – influencing the factors that create cost variances and controlling changes to the project budget. May 2011 Slide 2
  • 3. Project Cost Management Types of Project Costs • Direct Project Cost - The costs directly attributable to a project project, including all personnel, goods and/or services together with all their associated costs. E.g. team travel, team wages, training,material,etc. • Indirect Project Cost - All costs which do not form a part of the final product, but which are none the less required for the orderly completion of the project and which may include, but not necessarily be limited to field administration, direct supervision, incidental tools and equipment, startup costs, contractor’s fees, insurance, taxes, etc. • Fixed Project Costs - Those costs which do not change with change in volume of output E g set-up rental etc output. E.g. set-up, rental, etc. • Variable Project Costs - Those costs that vary proportionately with volume of output. E.g. material cost, supplies, wages, etc. May 2011 Slide 3
  • 4. Project Cost Management Analogous Estimating • It means using the actual cost of previous similar projects as the previous, basis for estimating the cost of the current project. • It uses expert judgment. • This type of estimate is typically done as part of the business case development or during the early stages of scope planning when there isn’t a lot of detail on the project. • An analogous estimate may be done for the project as a whole or for selected phases or deliverables. It is not typically used to estimate individual work packages. • Analogous estimates are the least accurate of all the estimating techniques but also the least costly. May 2011 Slide 4
  • 5. Project Cost Management Parametric Estimating • Same as the technique used in duration estimating estimating. • This technique uses a mathematical model to compute costs, and it most often uses the quantity of work multiplied by the rate. • Parametric estimating is dependent on the accuracy of the data used to create the model. May 2011 Slide 5
  • 6. Project Cost Management Bottom - Up Estimating • Assigns a cost estimate to each work package on the project project. • The WBS and the project resource requirements are critical inputs for a bottom - up estimate. • The idea is that you start at the work package level of the WBS and calculate the cost of each activity assigned to that work package. • The sum of all the work package estimates p p g provides the estimate of the total project cost. • Bottom - up estimates are the most accurate of all the estimating tec ques, techniques, but t ey ’re a so t e most t e - consuming to pe o . they e also the ost time co su g perform. May 2011 Slide 6
  • 7. Project Time Management Three Point Estimates • Three point estimates used: - Most likely(M) : Most likely cost of the schedule activity - Optimistic(O) : Activity cost is based on a best-case scenario - Pessimistic(P) : Activity cost is based on a worst-case scenario • Estimating based on 3 formulas: i. i PERT Activity Cost : C = (P + 4M + O)/6 May 2011 Slide 7
  • 8. Project Cost Management Sample project cost estimate May 2011 Slide 8
  • 9. Cost Estimating ITTO May 2011 Slide 9
  • 10. Cost Estimating ITTO May 2011 Slide 10
  • 11. Project Cost Management Estimating Tips • Brainstorm with your project team • Communicate the type of estimate you are providing & the level of accuracy they provide. • Make use of any available templates • Get estimates from the people doing the work. • Document any assumptions you have made May 2011 Slide 11
  • 12. Cost Budgeting Definition Cost Budgeting is the process of aggregating all the cost estimates and establishing a cost baseline for the project. The cost baseline is the total expected cost for the project. Once approved, it’s approved it s used throughout the remainder of the project to measure the overall cost performance. May 2011 Slide 12
  • 13. Cost Budgeting ITTO May 2011 Slide 13
  • 14. Cost Budgeting ITTO May 2011 Slide 14
  • 15. Cost Budgeting Reserves Contingency Reserves “A separately planned quantity used to allow for A future situations which may be planned for only in part (sometimes called ‘known unknowns’). For example, rework is certain, the amount of rework is not. The contingency fund is usually under the g y y discretion of the project manager, who controls how these funds are spent. Management Reserve “ A separately planned quantity used to allow l l d i d ll for future situations which are impossible to predict (sometimes called “unknown-Unknowns”). Management reserves may involve cost or schedule. schedule Management reserves are intended to reduce the risk of missing cost or schedule objectives. The management fund is usually controlled by upper management. May 2011 Slide 15
  • 16. Project Cost Control Definition • Project Cost Control is primarily concerned with Controlling Changes to the project budget • The processes of gathering, accumulating, analyzing, reporting and managing the costs on an on going basis on-going basis. • Includes project procedures, project cost changes, monitoring actual versus budget, variance analysis, integrated cost/schedule reporting, progress analysis and corrective actions. l i d ti ti May 2011 Slide 16
  • 17. Project Cost Control Definition • Project Cost Control is primarily concerned with Controlling Changes to the project budget • The processes of gathering, accumulating, analyzing, reporting and managing the costs on an on going basis on-going basis. • Includes project procedures, project cost changes, monitoring actual versus budget, variance analysis, integrated cost/schedule reporting, progress analysis and corrective actions. l i d ti ti May 2011 Slide 17
  • 18. Earned Value Analysis • Integrates cost, schedule and scope • Better that comparing projected vs. actual because time and cost are analyzed separately • Terms: - PV / BCWS – Budgeted Cost of Work Scheduled /Planned Value - EV / BCWP – Budgeted Cost of Work Performed / Earned Value - AC /ACWP – Actual Cost of Work Performed / Actual Cost May 2011 Slide 18
  • 19. Earned Value Analysis • BAC – Budget at Completion (how much did you budget for the total job) • EAC – Estimate at Completion (what do we expect the total project to cost) • ETC – Estimate to Completion (how much more do we expect to spend to finish the job) • VAC – Variance at Completion (how much over/under budget do we expect to be) May 2011 Slide 19
  • 20. Earned Value Analysis • Variance = (Plan – Actual) ( ) • Cost Variance (CV): EV– AC; -ve is over budget , +ve is under • Schedule Variance (SV): EV– PV; +ve is behind schedule, +ve is ahead • Cost Performance Index (CPI): EV/ AC - I am only getting x¢ out of every $ • Schedule Performance Index (SPI): EV/ PV - I am only progressing x % of the planned rate • Estimate at Completion (EAC): BAC / CPI - As of now we expect the total project to cost x$ • E ti t t C Estimate to Complete (ETC) EAC – AC l t (ETC): - how much will it cost from now to completion • Variance at Completion: BAC – EAC; when the project is over how much more or less did we spend May 2011 Slide 20
  • 21. Earned Value Analysis Question Work Actual Today is June 30th. —Data Budget Work Unit Completion (in $M) Performed Cost Date Date (in $M) (in $M) PV EV AC 1. What is the Cost Variance A Jan. 31 10 10 12 2. What is the Schedule B Feb. 8 F b 28 5 4 5 Variance C Mar. 31 6 8 8 3. What is the CPI D 12-May 15 13 12 4. What is the SPI 5 5. What is the EAC E 30-Jun 30 Jun 20 20 30 6. What is the ETC F 18-Jul 3 0 0 7. What is the Percent G Aug. 30 35 0 0 Complete H Sept. Sept 22 22 0 0 8. What is the Percent Spent I Oct. 29 12 0 0 J Nov. 30 9 0 0 May 2011 Slide 21
  • 22. Earned Value Analysis Question Work What is the CV ? $55 - $67 = Budget Actual Work Unit Completion (in $M) Performed Cost (in -$12 (EV AC) $12 (EV-AC) Date (in $M) PV EV $M) AC 2. What is the SV ? $55 - $56 = -$1 (EV-PV) A Jan. 31 10 10 12 3. What is the CPI? 55/67 = B Feb. 8 F b 28 5 4 5 .82 (EV/AC) C Mar. 31 6 8 8 4. What is the SPI? 55/56 = D 12-May 15 13 12 .98 (EV-PV) E 30-Jun 30 Jun 20 20 30 5. 5 What is the EAC? 137/ 82 = 137/. F 18-Jul 3 0 0 $167 (BAC/CPI) 6. What is the ETC? $167 - $67 = G Aug. 30 35 0 0 $100 (EAC-AC) H Sept. Sept 22 22 0 0 7. What is the Percent h h I Oct. 29 12 0 0 Complete? 55/137 = J Nov. 30 9 0 0 40% (EV/BAC) 8. What is the Percent Spent? 67/137 = 49% (AC/BAC) May 2011 Slide 22
  • 23. Pop Quiz Question 1 You are asked to prepare an estimate for a project business case to install a new group of servers at a new satellite office. There is very little detail about this project. What will you use to compute your estimate? p y A. The price the client is willing to pay B. A sophisticated modeling technique C. The estimate provided by the project sponsor D. The actual cost of a similar project May 2011 Slide 23
  • 24. Pop Quiz Question 2 A discretionary fund used by the project manager to cover the cost of possible adverse events during the project is known as which of the following? A. A Management reserve B. Chart of accounts C. Contingency fund g y D. Cost baseline May 2011 Slide 24
  • 25. Pop Quiz Question 3 You are developing a bottom - up estimate for the first phase of your project. Which of the following is the most important input to complete this task? A. A Historic data from a similar project B. Schedule C. The WBS D. The scope statement May 2011 Slide 25
  • 26. Pop Quiz Question 4 What is the most accurate estimate? A. Analogous estimate B. Bottom - up estimate C. Estimates based on expert judgment D. Parametric estimate May 2011 Slide 26
  • 27. Pop Quiz Question 5 You are the project manager for a large IT project. At the time you performed your cost estimates, the vendor you ’ re working with provided you with the following estimates: Programming estimate = 320 hours at $135/hour $135/hour. Project management estimate = 320 hours at $155/hour. Testing estimate = 150 hours at $85/hour. g / What type of estimate are these? A. Analogous B. Bottom-up C. Cost benefit D. D Parametric May 2011 Slide 27