BHARAT HEAVY
ELECTRICALS
LIMITED
Industrial Training
Presentation By:Omkar manav
10H51A0395
CMRCET COLLEGE
Flow of the presentation











Over view
Vision, Mission & Values
Bhel products
Sector details
Financial Analysis
Bhel ramachandrapuram
Steam turbine classifications
Tc &gt producton activities
Machine shop
Machining of steam turbine casing
Overview of BHEL
 BHEL was established in 1964.
 BHEL is one of the only 7 Public Sector Undertakings (PSUs) of

India clubbed under the esteemed 'Maharatna' status. On 1st
February 2013, the Government of India granted Maharatna status
to BHEL.
 BHEL has a share of 59% in India’s total installed generating
capacity contributing 69% (approx.) to the total power generated
from utility sets (excluding non-conventional capacity) as of March
31, 2012.
 BHEL is engaged in the design, engineering, manufacture,
construction, testing, commissioning and servicing of a wide range of
products and services for the core sectors of the economy, viz.
Power, Transmission, Industry, Transportation (Railway), Renewable
Energy, Oil & Gas and defence.
 BHEL has 15 manufacturing divisions, two repair units, four regional
offices, eight service centers and 15 regional centers and currently
operate at more than 150 project sites across India and abroad.
Main Manufacturing Units
BHEL Bhopal (Madhya Pradesh )
BHEL Ramachandrapuram, Hyderabad (Andhra Pradesh)
Transformer Plant, BHEL Jhansi(Uttar Pradesh)
High Pressure Boiler Plant and Seamless Steel Tube Plant,
Tiruchirapalli(Tamil Nadu)
5. Boiler Auxiliaries Plant, Ranipet (Tamil Nadu)
6. ElectronicsDivision and Electro Porcelain Division,
Bangalore(Karnataka
7. Jagdishpur (Uttar Pradesh)
8. Rudrapur (Uttrakhand)
9. Industrial ValvesPlant, Goindwal (Punjab)
10. BHEL Ranipur, Haridwar (Uttarakhand)
11. Bharat Heavy Plates and Vessels Limited(Vizag)
1.
2.
3.
4.













SERVICE GROUPS OF BHEL
Steam turbines, compressors and gas turbines
Common services
Heat exchangers and pulverizes
Pumps
Electrical machines
Quality services
Switch gears
Finance and accounts
Township administration
Project manager
Material management.
Product Range
Products


















Boiler(stream generator)
Gas Generator
Hydro Generator
Steam turbine
Gas turbine
Hydro turbine
Transportation Equipments
Traction Machines
Transformer
Switchgear
Oil field equipments OFE
Boiler drum
Water wall panel
Wind mill
Valve
Electro-static Precipitator
sR & D products
Generator:
 Operating Principle: The rotor is

mounted on a shaft driven by
mechanical prime mover.
 A field winding (rotating ) carries
a DC current to produce a
constant magnetic field. An AC
voltage is induced in the 3phase stator winding (stationary)
to produce electrical Power.
 The electrical frequency of the
3-phase output depends upon
the mechanical speed and the
number of poles.
 3-phases output is directly
connected to load.
Steam Turbine
 A steam turbine is a

device that
extracts thermal
energy from
pressurized steam and
uses it to do mechanical
work on a rotating output
shaft.
 The steam turbine is a
form of heat engine that
derives much of its
improvement in
thermodynamic
efficiency from the use of
multiple stages in the
expansion of the steam,
which results in a closer
approach to the ideal
reversible expansion
Pulverizer
 The coal is put in the boiler after pulverization. For

this pulverizer is used.
 A pulverizer is a device for grinding coal for
combustion in a furnace in a power plant.
 Types of Pulverizers:
i)Ball and Tube Mill
ii) Ring and Ball
Boiler
 Boiler is an enclosed vessel in




1.
2.
3.
4.

which water is heated and
circulated until the water is turned
in to steam at the required
pressure.
Coal is burned inside the
combustion chamber of boiler.
The products of combustion are
nothing but gases. These gases
which are at high temperature
vaporize the water inside the
boiler to steam.
Boilers are classified as:
Fire tube boilers
Water tube boilers
Superheater
Reheater
Condenser
 Steam after rotating steam turbine comes to condenser.

Condenser refers here to the shell and tube heat
exchanger (or surface condenser) installed at the outlet
of every steam turbine in Thermal power stations of utility
companies.
 The purpose is to condense the outlet (or exhaust) steam
from steam turbine to obtain maximum efficiency and
also to get the condensed steam in the form of pure
water, otherwise known as condensate, back to steam
generator or (boiler) as boiler feed water.
 Condensers are classified as:
i)Jet condensers or contact condensers,
ii)Surface condensers.
Cooling Towers
 The condensate (water)

formed in the condenser after
condensation is initially at
high temperature. This hot
water is passed to cooling
towers.
 It is a tower- or building-like
device in which atmospheric
air (the heat receiver)
circulates in direct or indirect
contact with warmer water
(the heat source) and the
water is thereby cooled.
 Types Of Cooling Tower1. Wet cooling tower
2. Dry cooling tower
Economizer
 Flue gases coming out of the

boiler carry lot of heat. Function
of economizer is to recover
some of the heat from the heat
carried away in the flue gases
up the chimney and utilize for
heating the feed water to the
boiler.
 It is placed in the passage of
flue gases in between the exit
from the boiler and the entry to
the chimney.
 The use of economizer results
in saving in coal consumption,
increase in steaming rate and
high boiler efficiency but needs
extra investment and increase
in maintenance costs and floor
area required for the plant.
Electrostatic Precipitator
 It is a device which removes dust or
other finely divided particles from flue
gases by charging the particles

inductively with an electric field, then
attracting them to highly charged
collector plates.
 Some of the usual applications are:
 (1) Removal of dirt from flue gases in
steam plants
 (2) Cleaning of air to remove fungi and
bacteria in
establishments producing
antibiotics and
other drugs, and in
operating rooms
 (3) Cleaning of air in ventilation and air
conditioning systems
 (4) Removal of oil mists in machine
shops and acid mists in chemical
process plants
 (5) Cleaning of blast furnace gases
 (6) Recovery of valuable materials such
Alternator
 An alternator is an electromechanical device that

converts mechanical energy to alternating current
electrical energy. Most alternators use a rotating
magnetic field. Different geometries - such as a
linear alternator for use with sterling engines - are
also occasionally used. In principle, any AC
generator can be called an alternator, but usually the
word refers to small rotating machines driven by
automotive and other internal combustion engines.
Transformers
 It is a device that transfers electric

energy from one alternating-current
circuit to one or more other circuits,
either increasing (stepping up) or
reducing (stepping down) the voltage.
 Uses for transformers include reducing
the line voltage to operate low-voltage
devices (doorbells or toy electric
trains) and raising the voltage from
electric generators so that electric
power can be transmitted over long
distances.
 Transformers act through
electromagnetic induction; current in
the primary coil induces current in the
secondary coil. The secondary voltage
is calculated by multiplying the primary
voltage by the ratio of the number of
turns in the secondary coil to that in
the primary.
Sector Details
 Power transmission sector, high voltage direct current (HVDC)









technology. It manufactures a vast range of transformers,
instrument transformers, thyristor valves, and associated control
equipment.
Industrial equipment sector, BHEL supplies a wide variety of
electrical, electronic and mechanical equipment to a host of
industries, viz. fertilizers, petrochemicals, refineries, coal, steel
etc.
Oil and Gas, BHEL has designed, manufactured and serviced
various types of on-shore deep drilling rigs, super-deep drilling
rigs, mobile rigs and desert rigs with matching draw works and
hoisting equipment
Telecommunication area BHEL has manufactured electronic
private automatic branch exchanges (PABXs) and rural
automatic exchanges (RAXs) for India
Non-conventional energy, BHEL has contributed by way of
manufacturing equipment like solar water heating systems, solar
photo-voltaic systems and wind electric generators
 Transportation sector, over 66% of the Indian Railways, is

equipped with traction equipment by BHEL. Kolkata Metro is
equipped with BHEL drives and controls.
Other products in the sector include traction generators/
alternators, transformers, sub-station equipment, vacuum circuit
breakers, locomotive bogies, smoothing tractors, exciters,
converters, inverters,
 Technological Strategy
 Research and Development Strategy
 Work-Culture and Philosophy
 Vendor Development
 Quality Strategy
 Manufacturing Strategy
 Flexible Manufacturing Technology
 Share Point Portal Server
 Other strategies
BHEL:
Financials
BHEL Ramachandrapuram
Unit
 BHEL Ramachandrapuram Unit has acquired considerable experience in the

design and manufacture of various important types of pumps required for the
thermal power plants
 designed and manufactured for 60 MW, 110 MW and 210 MW under
technical collaboration with M/s. Sigma Lutin of Czechoslovakia.
 In order to meet the requirements of higher efficiency pumps for 210 MW
units and large capacity pumps for 500 MW units, collaboration was entered
in 1980 with M/s. Wier Pumps Limited, U.K., who are acknowledged as one
of the leading manufacturers of pumps in the world.

 In 2007, BHEL Hyderabad has entered into collaboration with M/s. Mitsubishi
Heavy Industries, Japan to manufacture pumps for super-critical thermal
power plants up to 1000 MW


















PRODUCT AND PROCESSES
Turbine & Compressors shop.
Steam Turbines Compressors.
Gas Turbines Compressors.
Turbo Generators.
Steam Generators.
Gas Generators.
Switch Gears.
Ferrous Foundry.
Non-Ferrous Foundry.
Heat Exchangers.
Tool Room.
Heat Treatment.
Pattern shop.
Spares Manufacturing.
Coal pulverizes.
Pumps.
Steam turbines
manufactured

 STEAM TURBINES MANUFACTURED IN BHEL –HYD

 Various types of SIEMENS model turbines are manufactured at BHEL – Hyderabad
according to the requirement of any customer to suit his boiler steam parameters.
 They are:
 Type Turbine
 G - Back pressure type
 EG - Extraction back pressure type
 EHG - Extraction back pressure type with high inlet parameters
 HG - Back pressure type with high inlet parameters
 K - Condensing type
 EK - Extraction condensing type
 WK - Double flow condensing type
 EMG - Electrochemically machined rotor of back pressure type
 EHNK - Extraction condensing with inlet parameters and high speed type
 NK - Straight condensing with high speed type

Catogaries in steam turbine
 Industrial steam turbine are categorized into different

series like
 -2 series
 -3 series
 -4 series
2 SERIES
TURBINES

 standard type and have been

designed for the best efficiency
for range parameters.
 Designs being the standard
further based on then steam flow
quantities size of the turbine is
selected
 in these series of turbines the
fixed blade grooves are
machined directly in the outer
casing and guide blades are
inserted
 Different sizes of -2 types of turbines are:
 G250-2 EK/K 600-2
 G300-2 EK/K 800-2
 G400-2 EK/K 1000-2
 G500-2 EK/K 1100-2

 G800-2 EK/K 1400-2
 “G” stands for back pressure turbine
 “K” stands for condensing turbines
 “E” stands for controlled extraction
-3 SERIES
TURBINE:

 Based on customer‟s requirements
and steps involved in design, the
turbine is divided into different
sections: inlet section, transition,
exhaust or condensing section

 the size of the section is geometrically
graded in the ratio to 1.25 to form
different sizes of section
TURBINES
:

 These types of series are called as
centre admission steam turbines with
counter flow
 range of power, between 30MW to 150
MW
 The steam reverses the direction on the
reaching the end of inner casing to flow
around inner casing and expands
towards the rear end of the turbine
 This process of reverse flow of steam
helps in control the axial thrust to a large
extent.
 These turbines are directly coupled to
the generator. The valve blocks in these
turbines are separate
TC&GT PRODUCTION
ACTIVITIES
Machine shops
 Bay 0
 Maintenance and service dept /
Heavy duty CNC machines / Steam
turbine 150 MW Assembly shop
 Bay 1
 Heavy duty CNC machines / Gas
turbine rotor Assembly
 Bay 2

 Heavy machine shop withHeavy
duty CNC and conventional
machines
 Bay 3
 Blade shop
 Bay 4
 Heavy duty CNC Lathe machines
and steam turbine rotor assembly




Bay 5
 Impeller shop / Light machine shop / Gas
turbine wheel Assembly
Bay 6
Medium machine shop
 Bay 7
 Gas turbine machine shop / Steam turbine
Regulation Assembly
QiQihar CNC horizontal boring machines 2 nos
Tacchi CNC lathes 2 nos
QiQihar CNC horizontal boring
machines 2 nos
Tacchi CNC lathes 2 nos
INNSE Horizontal CNC machine :
Mario Carnaghi Gantry type machine :
Gas turbine Rotor Balancing machine
Tacchi heavy duty CNC lathe:
machine :

Short cut t o inse23.lnk
 This machine is provided with Sinumerik
840C CNC system
Mario Carnaghi Gantry type
machine :
 Rough machining of heavy

 Rough machining of heavy

casings of 120 MW design is
carried out on this machine.
Both top and bottom casings
 can be placed side by side on
the table with the parting plane
up for machining.

casings of 120 MW design is
carried out on this machine.
Both top and bottom casings
 can be placed side by side on
the table with the parting plane
up for machining.


Gas turbine Rotor Balancing machine
:

 The rotors are balanced

individually and as a unit rotor
also for its unbalance before
lowering into the gas Gas
turbine Rotor Balancing
machine :
 Machining of heavy rotors,
drilling, reaming of Coupling
holes on turbine rotor and load
coupling of gas turbine also
carried out in this shop
Tacchi heavy duty CNC lathe:
Tacchi heavy duty CNC lathe:

 Machining of heavy duty rotors

are carried out on this machine.
The max weight carrying
capacity of the machine is 80 T.
This machine is provided with
Sinumerik 840 D CNC system.

 Gas turbines of Fr5, Fr6 and

Fr9 flange to flange assembly
is carried out here.
Bay 2
Heavy machine shop withHeavy duty CNC
and conventional machines
 withHeavy duty CNC and
conventional machinesHeavy
machine shop


 Machining of peripheral

details and grinding of
parting planes of
casings are carried put
in this shop. The
important machines in
this bay are Plano
grinding machine etc
Radial drilling machines
etc

 Heavy duty CNC machines:
 Mitsubishi Horizontal boring
machine :
 DorriesVeritical CNC lathe:
 Skoda Horizontal boring machine:
 Skoda Vertical CNC lathe:
Mitsubishi Horizontal boring machine
:
 Fir tree blade root machining

on steam turbine rotor is
carried out on this machine
 Fanuc 9 CNC system.
Skoda Horizontal boring
machine
 Machining of combustion bores

on gas turbine casings,
peripheral details on steam
turbine casings are carried out
on this machine
Skoda Vertical CNC lathe:

 Finishing machining casings

including guide blade grooves
are carried out in vertical
position on this lathe. The
machine is provided with 840-C
CNC system.
Bay 4
Heavy duty CNC Lathe machines and steam
turbine rotor assembly
 Heavy duty CNC Lathe machines and
steam turbine rotor assembly

 Functions of bay





Steam Turbine rotor Assembly :
Sealing fins drawing machine
LP drilling Machine :
A-Wheel drilling Machine (Impulse blade
drilling machine
CASING SHELL OR
CYLINDER
Casing Materials
 ASTM A 356 Grade 1

for cast carbon steel
 Nodular Cast Iron
GGG40
 The reason is that cast
carbon steel is weld
repairable(LP turbine
inner casing rings,)
 Properties
 1-2 cr mo steels –low

 applications as they

temperature steam
 Cast 9 Cr 1 –Mo- V –Nb
alloys
 9-12-cr martensite
/ferrite steel

offer useful
 combination of high
temperature mechanical
 properties and
corrosion/oxidation
resistance
Casing bolts
Bolting material

properties

Nimonic 80A
Inconel 740
Allvac 718 plus (super alloy )

 High resistance to stress

relaxation
 Creep relaxation behaviour
 offering excellent
mechanical properties,
 increased temperature
capability, good fabricability
and moderate cost
 Unstable states arising during
start-ups, shutdowns and load
changes give rise to unsteady
temperature distribution with time

in steam turbine innercasing
(HP/IP), which results in nonuniform strain and stress
distribution
The rapid increase of temperature
during starts-ups, especially,
causes susceptible to failure and
reduction of expected life for steam
turbine components. Thus accurate
knowledge of thermal stresses is
required for the integrity and
lifetime assessment for the turbine
 MACHINING

SEQUENCE
UNDERGONE BY STEAM
TURBINE
-3 CASING:
Casing
 Lower half

 Upper half
 1)Marking on both lower half and upper half
of casing with machine allowance
 Or
 Punching on cnc machine during machining
with allowances
 2)Skin cut on connecting flang face of lower
half by positioning the parting plane
downwards this process is repeated for
upper half also
 (INNSE MACHINE )

 3)Now the loading the lower half in vertical
position by the help of bearing and clamps
 4)Repeat the process for upper half as well
 5)Parting plane present in both upper half and
lower half are rough milled and then are

followed by finish milling by positioning the
job in vertically with inner part facing the
milling cutter (INNSE)
 Parting plane in lower and upper half are
drilled and threaded as per the drawing
provided
 While providing reses the job is still in
vertical position

 Eccentric pin holes packets machining
followed by pin holes drilling and finish
boring is operation is done only in lower half
 10)Drain holes drilling and slots milling done
only in lower half
 11)Guide blade carriers shoulders
machining only in lower half
 12)Guide blade carriers guides are done
rough milling
 13)Steam chest area machining is done
only in upper half
 14)Job position is changed and clamped in
vertical positonie the casing is placed
backside towards the spindle of machine
 Now the casing is moved to next machine for

further operation

 ( TOS KURIM)
 Parting plane holes done backcounter boring in






both lower and upper half
Eccentric pin holes are back counter bored and
holes are positioned this is done only in lower
half
18)Steam valve spindle boring drilling and finish
boring is done only in upper half
19)Resting paws are milled in upper half
20)Job position is changed and loaded as
combined part on an hydraulic box and
tightened with studs and capnut for stiffness
 21)combined position is loaded on machine














table
22)Job in combined position is performed with
finish boring of guide blade carriers and
connecting flange
23)Connecting flange holes are drilled and
provided with threading
24)Now the combined part is rotated by 180
25)Front gland is rough milled
26)The combined job is sent for inspection
27)After inspecting the job is dismantled
28)Now the job is loaded in vertical position
with parting plane facing the spindle of machine
29)Rough and finish machining of balance
piston gland is done by vertical attachment
30)Job is inspected
31)Stop valve body finish boaring in upper half
32)Diffuser bore finishing bores finish boring
and inspection
Machining for peripheral holes

 a)Peripherial holes radial drilling
both inside and outside of casing

 h)Focing off screw holes

 b)Flange fixing holes

 34)Blue matching both the halves

 c)Wall temperature measurement
holes

to ensure parting plane contact
area by 90% to 100%
 35)If not performing a) scraping
b)deburing
 36)Hydraulic pressure testing
 37) sent for assembly

 d)Thermoelement holes
 e)Pressure test holes (hydraulic
pressure tasting holes)

 f)Tapper pin holes
 g)Guide pinning holes

 i)Main steam inlet flange holes
BHEL Ramachandrapuram Unit's Steam Turbine Manufacturing

Contenu connexe

Tendances

Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineManohar Tatwawadi
 
Steam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptSteam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptBiswajit Mohanty
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its typesSanila Khalid
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsSHIVAJI CHOUDHURY
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing SystemSalil Vaidya
 
[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam TurbineSumit Sharma
 
Study and Analysis of Tube Failure in Water Tube boiler
Study and Analysis of Tube Failure in Water Tube boilerStudy and Analysis of Tube Failure in Water Tube boiler
Study and Analysis of Tube Failure in Water Tube boilerArunMalanthara
 
Steam turbine
Steam turbineSteam turbine
Steam turbineNathan
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~ihaxxo24
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heaterSHIVAJI CHOUDHURY
 
general awareness in steam turbine manufacturing
general awareness in steam turbine manufacturinggeneral awareness in steam turbine manufacturing
general awareness in steam turbine manufacturingGaurav Sharma
 
centrifugal compressors overview
centrifugal compressors overviewcentrifugal compressors overview
centrifugal compressors overviewUsman Ali
 
Calculation of Turbine Efficiency
Calculation of Turbine EfficiencyCalculation of Turbine Efficiency
Calculation of Turbine EfficiencyJahanzeb Khan
 
High pressure boiler
High pressure boilerHigh pressure boiler
High pressure boilerAmol Kokare
 

Tendances (20)

Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
 
Boiler turbe failores
Boiler turbe failoresBoiler turbe failores
Boiler turbe failores
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
 
Power Plant Operations.pdf
Power Plant Operations.pdfPower Plant Operations.pdf
Power Plant Operations.pdf
 
Steam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptSteam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance ppt
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its types
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plants
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing System
 
[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam Turbine
 
Study and Analysis of Tube Failure in Water Tube boiler
Study and Analysis of Tube Failure in Water Tube boilerStudy and Analysis of Tube Failure in Water Tube boiler
Study and Analysis of Tube Failure in Water Tube boiler
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Steam generator part 2
Steam generator part 2Steam generator part 2
Steam generator part 2
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
 
general awareness in steam turbine manufacturing
general awareness in steam turbine manufacturinggeneral awareness in steam turbine manufacturing
general awareness in steam turbine manufacturing
 
centrifugal compressors overview
centrifugal compressors overviewcentrifugal compressors overview
centrifugal compressors overview
 
Calculation of Turbine Efficiency
Calculation of Turbine EfficiencyCalculation of Turbine Efficiency
Calculation of Turbine Efficiency
 
High pressure boiler
High pressure boilerHigh pressure boiler
High pressure boiler
 
Gas turbine course
Gas turbine courseGas turbine course
Gas turbine course
 

Similaire à BHEL Ramachandrapuram Unit's Steam Turbine Manufacturing

Industrial Training BHEL
Industrial Training BHELIndustrial Training BHEL
Industrial Training BHELLalit Kumar
 
INDUSTRIAL TRAINING REPORT.docx 1 (1)
INDUSTRIAL TRAINING REPORT.docx 1 (1)INDUSTRIAL TRAINING REPORT.docx 1 (1)
INDUSTRIAL TRAINING REPORT.docx 1 (1)Soham De
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportAditya Shekhar
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportAditya Shekhar
 
Kota super thermal power station, kota
Kota super thermal power station, kotaKota super thermal power station, kota
Kota super thermal power station, kotaSourabh Chourasiya
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 2
Principles of Power Systems V.K Mehta Complete Book - Chapter 2Principles of Power Systems V.K Mehta Complete Book - Chapter 2
Principles of Power Systems V.K Mehta Complete Book - Chapter 2Power System Operation
 
thermal-plant-report-mechatronics.pdf
thermal-plant-report-mechatronics.pdfthermal-plant-report-mechatronics.pdf
thermal-plant-report-mechatronics.pdfFarzanMehmood
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Stationsagnikchoudhury
 
Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurChandra veer singh
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC KantiTarun Kumar
 
BHELreport
BHELreportBHELreport
BHELreportVinay R
 
Three major inputs of ptps
Three major inputs of ptpsThree major inputs of ptps
Three major inputs of ptps4067HimanshuEE5
 
Overview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCOverview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCNITISHKHALKHO
 
16 MW PRAN Power Stations
16 MW PRAN Power Stations16 MW PRAN Power Stations
16 MW PRAN Power StationsSalim Bhuiyan
 
Mejia Thermal power Station(Seminar)
Mejia Thermal power Station(Seminar)Mejia Thermal power Station(Seminar)
Mejia Thermal power Station(Seminar)Debanjan Kishore Roy
 
Thermal Power Plant PPT
Thermal Power Plant PPTThermal Power Plant PPT
Thermal Power Plant PPTparmod saharan
 
Ntpc ppt complete
Ntpc ppt completeNtpc ppt complete
Ntpc ppt completeVikas Singh
 

Similaire à BHEL Ramachandrapuram Unit's Steam Turbine Manufacturing (20)

Industrial Training BHEL
Industrial Training BHELIndustrial Training BHEL
Industrial Training BHEL
 
INDUSTRIAL TRAINING REPORT.docx 1 (1)
INDUSTRIAL TRAINING REPORT.docx 1 (1)INDUSTRIAL TRAINING REPORT.docx 1 (1)
INDUSTRIAL TRAINING REPORT.docx 1 (1)
 
MTPS Bappa main
MTPS Bappa mainMTPS Bappa main
MTPS Bappa main
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
 
Kota super thermal power station, kota
Kota super thermal power station, kotaKota super thermal power station, kota
Kota super thermal power station, kota
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 2
Principles of Power Systems V.K Mehta Complete Book - Chapter 2Principles of Power Systems V.K Mehta Complete Book - Chapter 2
Principles of Power Systems V.K Mehta Complete Book - Chapter 2
 
thermal-plant-report-mechatronics.pdf
thermal-plant-report-mechatronics.pdfthermal-plant-report-mechatronics.pdf
thermal-plant-report-mechatronics.pdf
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Station
 
Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E Jaipur
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
BHELreport
BHELreportBHELreport
BHELreport
 
Three major inputs of ptps
Three major inputs of ptpsThree major inputs of ptps
Three major inputs of ptps
 
Overview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCOverview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVC
 
16 MW PRAN Power Stations
16 MW PRAN Power Stations16 MW PRAN Power Stations
16 MW PRAN Power Stations
 
Mejia Thermal power Station(Seminar)
Mejia Thermal power Station(Seminar)Mejia Thermal power Station(Seminar)
Mejia Thermal power Station(Seminar)
 
Thermal Power Plant PPT
Thermal Power Plant PPTThermal Power Plant PPT
Thermal Power Plant PPT
 
MAJOR PROJECT
MAJOR PROJECTMAJOR PROJECT
MAJOR PROJECT
 
final report
final reportfinal report
final report
 
Ntpc ppt complete
Ntpc ppt completeNtpc ppt complete
Ntpc ppt complete
 

Dernier

INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxCulture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxPoojaSen20
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
FILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinoFILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinojohnmickonozaleda
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 

Dernier (20)

INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxCulture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
FILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinoFILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipino
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 

BHEL Ramachandrapuram Unit's Steam Turbine Manufacturing

  • 1.
  • 2. BHARAT HEAVY ELECTRICALS LIMITED Industrial Training Presentation By:Omkar manav 10H51A0395 CMRCET COLLEGE
  • 3. Flow of the presentation           Over view Vision, Mission & Values Bhel products Sector details Financial Analysis Bhel ramachandrapuram Steam turbine classifications Tc &gt producton activities Machine shop Machining of steam turbine casing
  • 4. Overview of BHEL  BHEL was established in 1964.  BHEL is one of the only 7 Public Sector Undertakings (PSUs) of India clubbed under the esteemed 'Maharatna' status. On 1st February 2013, the Government of India granted Maharatna status to BHEL.  BHEL has a share of 59% in India’s total installed generating capacity contributing 69% (approx.) to the total power generated from utility sets (excluding non-conventional capacity) as of March 31, 2012.  BHEL is engaged in the design, engineering, manufacture, construction, testing, commissioning and servicing of a wide range of products and services for the core sectors of the economy, viz. Power, Transmission, Industry, Transportation (Railway), Renewable Energy, Oil & Gas and defence.  BHEL has 15 manufacturing divisions, two repair units, four regional offices, eight service centers and 15 regional centers and currently operate at more than 150 project sites across India and abroad.
  • 5.
  • 6. Main Manufacturing Units BHEL Bhopal (Madhya Pradesh ) BHEL Ramachandrapuram, Hyderabad (Andhra Pradesh) Transformer Plant, BHEL Jhansi(Uttar Pradesh) High Pressure Boiler Plant and Seamless Steel Tube Plant, Tiruchirapalli(Tamil Nadu) 5. Boiler Auxiliaries Plant, Ranipet (Tamil Nadu) 6. ElectronicsDivision and Electro Porcelain Division, Bangalore(Karnataka 7. Jagdishpur (Uttar Pradesh) 8. Rudrapur (Uttrakhand) 9. Industrial ValvesPlant, Goindwal (Punjab) 10. BHEL Ranipur, Haridwar (Uttarakhand) 11. Bharat Heavy Plates and Vessels Limited(Vizag) 1. 2. 3. 4.
  • 7.             SERVICE GROUPS OF BHEL Steam turbines, compressors and gas turbines Common services Heat exchangers and pulverizes Pumps Electrical machines Quality services Switch gears Finance and accounts Township administration Project manager Material management.
  • 9. Products                  Boiler(stream generator) Gas Generator Hydro Generator Steam turbine Gas turbine Hydro turbine Transportation Equipments Traction Machines Transformer Switchgear Oil field equipments OFE Boiler drum Water wall panel Wind mill Valve Electro-static Precipitator sR & D products
  • 10. Generator:  Operating Principle: The rotor is mounted on a shaft driven by mechanical prime mover.  A field winding (rotating ) carries a DC current to produce a constant magnetic field. An AC voltage is induced in the 3phase stator winding (stationary) to produce electrical Power.  The electrical frequency of the 3-phase output depends upon the mechanical speed and the number of poles.  3-phases output is directly connected to load.
  • 11. Steam Turbine  A steam turbine is a device that extracts thermal energy from pressurized steam and uses it to do mechanical work on a rotating output shaft.  The steam turbine is a form of heat engine that derives much of its improvement in thermodynamic efficiency from the use of multiple stages in the expansion of the steam, which results in a closer approach to the ideal reversible expansion
  • 12. Pulverizer  The coal is put in the boiler after pulverization. For this pulverizer is used.  A pulverizer is a device for grinding coal for combustion in a furnace in a power plant.  Types of Pulverizers: i)Ball and Tube Mill ii) Ring and Ball
  • 13. Boiler  Boiler is an enclosed vessel in   1. 2. 3. 4. which water is heated and circulated until the water is turned in to steam at the required pressure. Coal is burned inside the combustion chamber of boiler. The products of combustion are nothing but gases. These gases which are at high temperature vaporize the water inside the boiler to steam. Boilers are classified as: Fire tube boilers Water tube boilers Superheater Reheater
  • 14. Condenser  Steam after rotating steam turbine comes to condenser. Condenser refers here to the shell and tube heat exchanger (or surface condenser) installed at the outlet of every steam turbine in Thermal power stations of utility companies.  The purpose is to condense the outlet (or exhaust) steam from steam turbine to obtain maximum efficiency and also to get the condensed steam in the form of pure water, otherwise known as condensate, back to steam generator or (boiler) as boiler feed water.  Condensers are classified as: i)Jet condensers or contact condensers, ii)Surface condensers.
  • 15. Cooling Towers  The condensate (water) formed in the condenser after condensation is initially at high temperature. This hot water is passed to cooling towers.  It is a tower- or building-like device in which atmospheric air (the heat receiver) circulates in direct or indirect contact with warmer water (the heat source) and the water is thereby cooled.  Types Of Cooling Tower1. Wet cooling tower 2. Dry cooling tower
  • 16. Economizer  Flue gases coming out of the boiler carry lot of heat. Function of economizer is to recover some of the heat from the heat carried away in the flue gases up the chimney and utilize for heating the feed water to the boiler.  It is placed in the passage of flue gases in between the exit from the boiler and the entry to the chimney.  The use of economizer results in saving in coal consumption, increase in steaming rate and high boiler efficiency but needs extra investment and increase in maintenance costs and floor area required for the plant.
  • 17. Electrostatic Precipitator  It is a device which removes dust or other finely divided particles from flue gases by charging the particles inductively with an electric field, then attracting them to highly charged collector plates.  Some of the usual applications are:  (1) Removal of dirt from flue gases in steam plants  (2) Cleaning of air to remove fungi and bacteria in establishments producing antibiotics and other drugs, and in operating rooms  (3) Cleaning of air in ventilation and air conditioning systems  (4) Removal of oil mists in machine shops and acid mists in chemical process plants  (5) Cleaning of blast furnace gases  (6) Recovery of valuable materials such
  • 18. Alternator  An alternator is an electromechanical device that converts mechanical energy to alternating current electrical energy. Most alternators use a rotating magnetic field. Different geometries - such as a linear alternator for use with sterling engines - are also occasionally used. In principle, any AC generator can be called an alternator, but usually the word refers to small rotating machines driven by automotive and other internal combustion engines.
  • 19. Transformers  It is a device that transfers electric energy from one alternating-current circuit to one or more other circuits, either increasing (stepping up) or reducing (stepping down) the voltage.  Uses for transformers include reducing the line voltage to operate low-voltage devices (doorbells or toy electric trains) and raising the voltage from electric generators so that electric power can be transmitted over long distances.  Transformers act through electromagnetic induction; current in the primary coil induces current in the secondary coil. The secondary voltage is calculated by multiplying the primary voltage by the ratio of the number of turns in the secondary coil to that in the primary.
  • 20. Sector Details  Power transmission sector, high voltage direct current (HVDC)     technology. It manufactures a vast range of transformers, instrument transformers, thyristor valves, and associated control equipment. Industrial equipment sector, BHEL supplies a wide variety of electrical, electronic and mechanical equipment to a host of industries, viz. fertilizers, petrochemicals, refineries, coal, steel etc. Oil and Gas, BHEL has designed, manufactured and serviced various types of on-shore deep drilling rigs, super-deep drilling rigs, mobile rigs and desert rigs with matching draw works and hoisting equipment Telecommunication area BHEL has manufactured electronic private automatic branch exchanges (PABXs) and rural automatic exchanges (RAXs) for India Non-conventional energy, BHEL has contributed by way of manufacturing equipment like solar water heating systems, solar photo-voltaic systems and wind electric generators
  • 21.  Transportation sector, over 66% of the Indian Railways, is equipped with traction equipment by BHEL. Kolkata Metro is equipped with BHEL drives and controls. Other products in the sector include traction generators/ alternators, transformers, sub-station equipment, vacuum circuit breakers, locomotive bogies, smoothing tractors, exciters, converters, inverters,
  • 22.  Technological Strategy  Research and Development Strategy  Work-Culture and Philosophy  Vendor Development  Quality Strategy  Manufacturing Strategy  Flexible Manufacturing Technology  Share Point Portal Server  Other strategies
  • 23.
  • 25.
  • 26. BHEL Ramachandrapuram Unit  BHEL Ramachandrapuram Unit has acquired considerable experience in the design and manufacture of various important types of pumps required for the thermal power plants  designed and manufactured for 60 MW, 110 MW and 210 MW under technical collaboration with M/s. Sigma Lutin of Czechoslovakia.  In order to meet the requirements of higher efficiency pumps for 210 MW units and large capacity pumps for 500 MW units, collaboration was entered in 1980 with M/s. Wier Pumps Limited, U.K., who are acknowledged as one of the leading manufacturers of pumps in the world.  In 2007, BHEL Hyderabad has entered into collaboration with M/s. Mitsubishi Heavy Industries, Japan to manufacture pumps for super-critical thermal power plants up to 1000 MW
  • 27.
  • 28.                  PRODUCT AND PROCESSES Turbine & Compressors shop. Steam Turbines Compressors. Gas Turbines Compressors. Turbo Generators. Steam Generators. Gas Generators. Switch Gears. Ferrous Foundry. Non-Ferrous Foundry. Heat Exchangers. Tool Room. Heat Treatment. Pattern shop. Spares Manufacturing. Coal pulverizes. Pumps.
  • 29. Steam turbines manufactured   STEAM TURBINES MANUFACTURED IN BHEL –HYD   Various types of SIEMENS model turbines are manufactured at BHEL – Hyderabad according to the requirement of any customer to suit his boiler steam parameters.  They are:  Type Turbine  G - Back pressure type  EG - Extraction back pressure type  EHG - Extraction back pressure type with high inlet parameters  HG - Back pressure type with high inlet parameters  K - Condensing type  EK - Extraction condensing type  WK - Double flow condensing type  EMG - Electrochemically machined rotor of back pressure type  EHNK - Extraction condensing with inlet parameters and high speed type  NK - Straight condensing with high speed type 
  • 30. Catogaries in steam turbine  Industrial steam turbine are categorized into different series like  -2 series  -3 series  -4 series
  • 31. 2 SERIES TURBINES  standard type and have been designed for the best efficiency for range parameters.  Designs being the standard further based on then steam flow quantities size of the turbine is selected  in these series of turbines the fixed blade grooves are machined directly in the outer casing and guide blades are inserted
  • 32.  Different sizes of -2 types of turbines are:  G250-2 EK/K 600-2  G300-2 EK/K 800-2  G400-2 EK/K 1000-2  G500-2 EK/K 1100-2  G800-2 EK/K 1400-2  “G” stands for back pressure turbine  “K” stands for condensing turbines  “E” stands for controlled extraction
  • 33. -3 SERIES TURBINE:  Based on customer‟s requirements and steps involved in design, the turbine is divided into different sections: inlet section, transition, exhaust or condensing section  the size of the section is geometrically graded in the ratio to 1.25 to form different sizes of section
  • 34. TURBINES :  These types of series are called as centre admission steam turbines with counter flow  range of power, between 30MW to 150 MW  The steam reverses the direction on the reaching the end of inner casing to flow around inner casing and expands towards the rear end of the turbine  This process of reverse flow of steam helps in control the axial thrust to a large extent.  These turbines are directly coupled to the generator. The valve blocks in these turbines are separate
  • 36. Machine shops  Bay 0  Maintenance and service dept / Heavy duty CNC machines / Steam turbine 150 MW Assembly shop  Bay 1  Heavy duty CNC machines / Gas turbine rotor Assembly  Bay 2  Heavy machine shop withHeavy duty CNC and conventional machines  Bay 3  Blade shop  Bay 4  Heavy duty CNC Lathe machines and steam turbine rotor assembly   Bay 5  Impeller shop / Light machine shop / Gas turbine wheel Assembly Bay 6 Medium machine shop  Bay 7  Gas turbine machine shop / Steam turbine Regulation Assembly
  • 37. QiQihar CNC horizontal boring machines 2 nos Tacchi CNC lathes 2 nos
  • 38. QiQihar CNC horizontal boring machines 2 nos
  • 40. INNSE Horizontal CNC machine : Mario Carnaghi Gantry type machine : Gas turbine Rotor Balancing machine Tacchi heavy duty CNC lathe:
  • 41. machine : Short cut t o inse23.lnk
  • 42.  This machine is provided with Sinumerik 840C CNC system
  • 43. Mario Carnaghi Gantry type machine :  Rough machining of heavy  Rough machining of heavy casings of 120 MW design is carried out on this machine. Both top and bottom casings  can be placed side by side on the table with the parting plane up for machining. casings of 120 MW design is carried out on this machine. Both top and bottom casings  can be placed side by side on the table with the parting plane up for machining. 
  • 44. Gas turbine Rotor Balancing machine :  The rotors are balanced individually and as a unit rotor also for its unbalance before lowering into the gas Gas turbine Rotor Balancing machine :  Machining of heavy rotors, drilling, reaming of Coupling holes on turbine rotor and load coupling of gas turbine also carried out in this shop
  • 45.
  • 46. Tacchi heavy duty CNC lathe:
  • 47. Tacchi heavy duty CNC lathe:  Machining of heavy duty rotors are carried out on this machine. The max weight carrying capacity of the machine is 80 T. This machine is provided with Sinumerik 840 D CNC system.   Gas turbines of Fr5, Fr6 and Fr9 flange to flange assembly is carried out here.
  • 48. Bay 2 Heavy machine shop withHeavy duty CNC and conventional machines  withHeavy duty CNC and conventional machinesHeavy machine shop   Machining of peripheral details and grinding of parting planes of casings are carried put in this shop. The important machines in this bay are Plano grinding machine etc Radial drilling machines etc  Heavy duty CNC machines:  Mitsubishi Horizontal boring machine :  DorriesVeritical CNC lathe:  Skoda Horizontal boring machine:  Skoda Vertical CNC lathe:
  • 49. Mitsubishi Horizontal boring machine :  Fir tree blade root machining on steam turbine rotor is carried out on this machine  Fanuc 9 CNC system.
  • 50. Skoda Horizontal boring machine  Machining of combustion bores on gas turbine casings, peripheral details on steam turbine casings are carried out on this machine
  • 51. Skoda Vertical CNC lathe:  Finishing machining casings including guide blade grooves are carried out in vertical position on this lathe. The machine is provided with 840-C CNC system.
  • 52. Bay 4 Heavy duty CNC Lathe machines and steam turbine rotor assembly  Heavy duty CNC Lathe machines and steam turbine rotor assembly  Functions of bay     Steam Turbine rotor Assembly : Sealing fins drawing machine LP drilling Machine : A-Wheel drilling Machine (Impulse blade drilling machine
  • 54. Casing Materials  ASTM A 356 Grade 1 for cast carbon steel  Nodular Cast Iron GGG40  The reason is that cast carbon steel is weld repairable(LP turbine inner casing rings,)
  • 55.  Properties  1-2 cr mo steels –low  applications as they temperature steam  Cast 9 Cr 1 –Mo- V –Nb alloys  9-12-cr martensite /ferrite steel offer useful  combination of high temperature mechanical  properties and corrosion/oxidation resistance
  • 56. Casing bolts Bolting material properties Nimonic 80A Inconel 740 Allvac 718 plus (super alloy )  High resistance to stress relaxation  Creep relaxation behaviour  offering excellent mechanical properties,  increased temperature capability, good fabricability and moderate cost
  • 57.  Unstable states arising during start-ups, shutdowns and load changes give rise to unsteady temperature distribution with time in steam turbine innercasing (HP/IP), which results in nonuniform strain and stress distribution The rapid increase of temperature during starts-ups, especially, causes susceptible to failure and reduction of expected life for steam turbine components. Thus accurate knowledge of thermal stresses is required for the integrity and lifetime assessment for the turbine
  • 58.  MACHINING SEQUENCE UNDERGONE BY STEAM TURBINE -3 CASING:
  • 60.  Lower half  Upper half
  • 61.  1)Marking on both lower half and upper half of casing with machine allowance  Or  Punching on cnc machine during machining with allowances  2)Skin cut on connecting flang face of lower half by positioning the parting plane downwards this process is repeated for upper half also  (INNSE MACHINE )  3)Now the loading the lower half in vertical position by the help of bearing and clamps  4)Repeat the process for upper half as well  5)Parting plane present in both upper half and lower half are rough milled and then are followed by finish milling by positioning the job in vertically with inner part facing the milling cutter (INNSE)
  • 62.  Parting plane in lower and upper half are drilled and threaded as per the drawing provided  While providing reses the job is still in vertical position  Eccentric pin holes packets machining followed by pin holes drilling and finish boring is operation is done only in lower half  10)Drain holes drilling and slots milling done only in lower half  11)Guide blade carriers shoulders machining only in lower half  12)Guide blade carriers guides are done rough milling  13)Steam chest area machining is done only in upper half  14)Job position is changed and clamped in vertical positonie the casing is placed backside towards the spindle of machine
  • 63.  Now the casing is moved to next machine for further operation  ( TOS KURIM)  Parting plane holes done backcounter boring in     both lower and upper half Eccentric pin holes are back counter bored and holes are positioned this is done only in lower half 18)Steam valve spindle boring drilling and finish boring is done only in upper half 19)Resting paws are milled in upper half 20)Job position is changed and loaded as combined part on an hydraulic box and tightened with studs and capnut for stiffness
  • 64.  21)combined position is loaded on machine            table 22)Job in combined position is performed with finish boring of guide blade carriers and connecting flange 23)Connecting flange holes are drilled and provided with threading 24)Now the combined part is rotated by 180 25)Front gland is rough milled 26)The combined job is sent for inspection 27)After inspecting the job is dismantled 28)Now the job is loaded in vertical position with parting plane facing the spindle of machine 29)Rough and finish machining of balance piston gland is done by vertical attachment 30)Job is inspected 31)Stop valve body finish boaring in upper half 32)Diffuser bore finishing bores finish boring and inspection
  • 65. Machining for peripheral holes  a)Peripherial holes radial drilling both inside and outside of casing  h)Focing off screw holes  b)Flange fixing holes  34)Blue matching both the halves  c)Wall temperature measurement holes to ensure parting plane contact area by 90% to 100%  35)If not performing a) scraping b)deburing  36)Hydraulic pressure testing  37) sent for assembly  d)Thermoelement holes  e)Pressure test holes (hydraulic pressure tasting holes)  f)Tapper pin holes  g)Guide pinning holes  i)Main steam inlet flange holes