SlideShare une entreprise Scribd logo
1  sur  40
Slide 1 of 18 Schedule Risk Analysis(SRA)Pedram DaneshmandAssociate DirectorBlue Visions Management Pty Ltd
Slide 2 of 18 Content Project Time Management Risk & Opportunities Project Risk Management Schedule Risk Analysis Results Review Action Plan
Project Time ManagementHistory Every project must be managed against a schedule; Project Scheduling has been around a long time; Scheduling is one of the most widely practiced project management disciplines (Archibald and Villoria 1967).    Slide 3 of 18 Project Time Management includes the processes required to accomplish timely completion of the project (PMBOK, 2004).
Project Time ManagementProcess Activity Definition Activity Sequencing (logic) Activity Resource Estimating Activity Duration Estimating Schedule Development Schedule Control (PMBOK, 2004) Slide 4 of 18
Project Time ManagementSchedule Development The Schedule Development process includes selecting a scheduling Method, scheduling Tool, incorporating project specific data within that scheduling tool to develop project specific schedule Model, and generating Project Schedule. (PMI-PS for Scheduling, 2007) Slide 5 of 18
Schedule DevelopmentMethods Logic-based Scheduling Methods (LSM) Deterministic Techniques E.g. Critical Path Method (CPM), Resource Optimisation, Critical Chain Method (CCM), etc. Stochastic Techniques E.g. Probabilistic Evaluation and Review Technique (PERT), PNET, Monte Carlo Simulation (MCS), etc. Repetitive Scheduling Methods (RSM) Line of Balance (LOB) Flowline Method Slide 6 of 18
Schedule Development Inputs Planners develop the project schedule by using: Available templates; Available quantities, resources and productivity rates; Available work/scope statements; Available construction logic; and Other assumptions/documents e.g. calendars, PMP, etc. Slide 7 of 18 All these add uncertainties to schedule and reduce the confidence level. What about risks and opportunities in the schedule?
Schedule Development Outputs The outputs of Schedule Development process are: (Deterministic) Project Schedule; (Deterministic) Schedule Model Data (Deterministic) Schedule Baseline (Deterministic) Resource Requirements Slide 8 of 18 With all those uncertainties in the inputs and the possible risks and opportunities in the schedule, the question is, how confident we are in this schedule?
Schedule Development Major Challenges Uncertainties due to assumptions; Logic, constraints, resources, calendars and activity durations are not always clear and agreed; What-If Scenarios; and Risks and Opportunities    Slide 9 of 18 To have a realistic schedule, Schedule Development process should be improved by using Schedule Risk Analysis.  In other words Project Time Management and Project Risk Management need to be integrated!
Schedule DevelopmentRisks & Opportunities  Every schedule has uncertainties/assumptions. Every schedule has risks and opportunities. Slide 10 of 18 Effect on project (positive or negative) Time Scope So, Risks and Opportunities should be managed effectively to minimize the surprises!! Cost Quality
Project Risk Management Process Slide 11 of 18 Establish Context MONITOR AND REVIEW COMMUNICATE AND CONSULT Identify Risks Analyse Risks RISK ASSESSMENT Evaluate Risks Treat Risks AS/NZS ISO 31000:2009
Project Risk ManagementRisk Assessment Risk Assessment include Risk Identification (both Uncertainties and Events) Risk Analysis Qualitative Quantitative (Schedule Risk Analysis or SRA) Risk Evaluation Slide 12 of 18 The goal is to have a better understanding of risks / opportunities and their overall impact on project completion date.  This will bridges the gap between traditional CPM schedule and the REAL project.
Project Risk ManagementRisk Analysis Risk Analysis is the process to comprehend the nature of risks (or opportunities) and to determine the level of risks (or opportunities) in the schedule Risk analysis provides the basis for risk evaluation and decisions about risk treatment; and Risk Analysis includes risk estimation. Slide 13 of 18 By Schedule Risk Analysis (SRA), we model the risks and opportunities (uncertainties and events) within the complexity of the interrelationships between the various tasks of the schedule.
Schedule Risk Analysis(SRA) SRA is a probabilistic analysis to quantify the impacts to a project, program or portfolio as a result of carrying uncertainties and/or risks and opportunities or to simulate the possible what-if scenarios.  Slide 14 of 18 Relying on a accurate most likely schedule as a base, SRA takes the project time management to the next level of accuracy and confidence.
Schedule Risk AnalysisOverview Available data gathering Schedule Review Technical Research Risks & Opportunities Register Both Uncertainties and Events Schedule Risk Model Simulation Results and Discussions Slide 15 of 18
Schedule Risk Analysis Data Gathering Required information for a SRA Well-developed project scope; Quality estimate excluding contingency and escalation; Schedule reflecting the estimate; Risk management policy/processes in your organisation; Risk checklist presenting typical risks and opportunities; Risk & Opportunities Template; Schedule Risk Templates/Models; and Sample report of the process and recommendations. Slide 16 of 18
Schedule Risk Analysis Schedule Review How to review the deterministic schedule? Validation of all quantities (most likely); Validation of all productivity rates (most likely); Validation of all durations (most likely); Minimum number of constraints; Complete logic network; Reasonable duration for tasks; and Reasonable Critical Path. Slide 17 of 18
SRA – Schedule ReviewSample Report Slide 18 of 20 Confidential
Schedule Risk Analysis Technical Research When the team is confident that the project deterministic schedule reflects the most likely case, the technical research can begin. Historical data research Interviews Internet searches, etc. Slide 19 of 18 Issues may include items such as site access, Environmental Approvals, inclement weather, construction productivity concerns, construction modifications, equipment and material deliver, etc.
Schedule Risk Analysis Risk Register The Technical Research will enable the schedule risk analyst to complete the Risk Register file: The identified risks & opportunities Likelihood of the identified risks and opportunities Impacted activities Schedule and/or Cost Impact/s Schedule and/or Cost Variations Correlation of risks and opportunities to one another Notes, etc. Slide 20 of 18
Schedule Risk Analysis Risk Register (Sample) Slide 21 of 18 Confidential
SRA – Risk Register (Sample)Rain details Slide 22 of 18
SRA – Risk RegisterQuality Check Major risks and opportunities been identified; The likelihood and impacts been assessed; Risk Matrix aligned with the company’s risk management policy; Impacts checked against the allocated calendars; Correlations between risks been identified; Stage the opportunities if required; and Duplications are minimised and addressed.   Slide 23 of 18
SRA – Schedule Risk ModelUncertainties & Events  Developing the Schedule Risk Model involves modelling the potential impacts and the likelihood of the risks and opportunities on the project and then applying those to the schedule. Two aspects of the risks and opportunities should be modelled within the schedule: Estimate Uncertainties (Optimistic, Most Likely and Pessimistic) Events including probabilistic branching  (probability and the impacts)  Slide 24 of 18
SRA – Schedule Risk ModelProbability Distributions Probability Distribution is a way to indicate the likelihood of values between the optimistic and pessimistic values.  Probability Distribution can be: Uniform (flat), Normal (bell shaped), Beta (skinny bell shaped), Triangle (pyramid shaped), or Customised (user defined). Slide 25 of 18
SRA – Schedule Risk ModelProbability Distributions Slide 26 of 18
SRA – Schedule Risk ModelSpecial Conditions  Special conditions which needs extra attention: Probabilistic Branching – which considers the situation where the outcome of an event can cause in two or multiple possible courses of activities. Correlation between risks Positive Correlation: occurs when one risk goes higher, so must the other. Negative or Adverse Correlation: occurs when one risk increases, the other must decrease.  Inclement Weather or other external influences Slide 27 of 18
SRA – Schedule Risk ModelInclement Weather Inclement Weather can be a significant factor in a project schedule. Very often there is good data available but understanding the impact on the schedule is challenging. A proper modelling will allow the team to define risk assessment criteria for inclement weather conditions in the schedule, and include these uncertain weather conditions in the risk analysis. Slide 28 of 18
SRA – Schedule Risk ModelInclement Weather There are two distinct ways of defining inclement weather events: Event with results in an uncertain number of non working days scattered throughout a period, e.g. rain or snow. Event with results in a single block of non working time with a probability of occurrence, e.g. chance of a hurricane in a period. Slide 29 of 18
Schedule Risk Analysis Simulation Methods  The SRA performs multiple simulations of the project using random samplings of the relevant risks and opportunities considering their probability and impact. Two popular methods: Monte Carlo Simulation (MCS) – faster method but has a larger possibility of sampling error Latin Hypercube Sampling (LHS) – slower method but less sampling errors Slide 30 of 18
Schedule Risk Analysis Simulation Process  Analysis does the simulation through multiple samplings or iterations. Each iteration is picking one sample point from each activity and calculating the project outcome.  User defines the number of iteration (e.g. 1000, 5000, etc) depending on the complexity of the project and its risk model. Slide 31 of 18
Schedule Risk Analysis Simulation Tools  Main tools been widely used for simulation are: Primavera Risk Analysis (previously known as Pertmaster) @Risk for Project Crystal Ball Slide 32 of 18 The next slides are presenting results from simulations by using  Primavera Risk Analysis.
Schedule Risk Analysis Sample Programme Slide 33 of 18 Confidential Confidential
Schedule Risk Analysis Finish Date Histogram  Slide 34 of 18 Confidential
Schedule Risk Analysis Histogram & Statistics  Slide 35 of 18 Confidential
Schedule Risk Analysis Criticality Index Tornado Slide 36 of 18 Confidential The Criticality Index of an activity is the proportion of the iterations in which the activity was critical. Usually more attention will be given to the activities with Criticality Index of more than 50%.
Schedule Risk Analysis Criticality Path Report Slide 37 of 18 The Criticality Path Report highlights the path through the project containing the tasks with the highest Criticality Index values. Percent Criticality is the probability that an activity will be on the critical path; this indicates the relative importance of the activity to other activities in the programme. Confidential
Schedule Risk Analysis Criticality Distribution Profile Slide 38 of 18 Criticality Distribution Profile plots the spread of Criticality Index in a project which gives an indication of the number and threat of near to critical path. A high percentage (more than 40%) indicates a relatively tight programme. Confidential
Schedule Risk Analysis Action Plan The accuracy of the SRA outcomes should be improved through a number of iterations of this process. Based on the initial results, the team should: Review the risk register and make modifications where require; Make changes to the risk model accordingly; Run the simulation again and repeat the process to achieve the most cost-effective risk mitigation plan; Finalise the Risk Action Plan as well as the Contingency Plan; and Communicate this schedule with the team and then monitor it. Slide 39 of 18
About the Author Pedram Daneshmand, Associate Director Blue Visions Management 	Pedram is a civil engineer with over 15 years experience in the construction industry. He is highly skilled and technically proficient in many aspects of construction including Programming, Programme Performance Measurement, Quantitative Risk Analysis, Contract Management, Schedule Risk Analysis (SRA), Cost Risk Analysis (CRA), Project Monitoring & Controls (PMC) Systems, Earned Value Performance Measurement technique (EVPM) and POW (Program of Work) Planning & Controls. 	As an industry innovation award winner for his programming and risk analysis skills, Pedram is currently an Associate Director with Blue Visions Management leading a team of planning and controls professionals within the infrastructure sector. With more than 15 articles in the professional conferences/journals, he is been regularly invited to the technical presentations as one of the industry leaders in his field. Slide 40 of 18

Contenu connexe

Tendances

Construction scheduling
Construction schedulingConstruction scheduling
Construction schedulingZTE Nepal
 
2. project initiation
2. project initiation2. project initiation
2. project initiationMad Jutt
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementMohamed Loey
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptxHafixFarhan
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisp6academy
 
Risk Management Framework - Dr. Mustafa Degerli
Risk Management Framework - Dr. Mustafa DegerliRisk Management Framework - Dr. Mustafa Degerli
Risk Management Framework - Dr. Mustafa DegerliDr. Mustafa Değerli
 
Project risk management focus on risk identification techniques
Project risk management   focus on risk identification techniquesProject risk management   focus on risk identification techniques
Project risk management focus on risk identification techniquesMarco De Santis, PMP, CFPP
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)PM Majik
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project ResourcesToyin Osunlaja
 

Tendances (20)

Construction scheduling
Construction schedulingConstruction scheduling
Construction scheduling
 
2. project initiation
2. project initiation2. project initiation
2. project initiation
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
 
Risk Management Framework - Dr. Mustafa Degerli
Risk Management Framework - Dr. Mustafa DegerliRisk Management Framework - Dr. Mustafa Degerli
Risk Management Framework - Dr. Mustafa Degerli
 
Project risk management focus on risk identification techniques
Project risk management   focus on risk identification techniquesProject risk management   focus on risk identification techniques
Project risk management focus on risk identification techniques
 
Pmo final 1
Pmo final 1Pmo final 1
Pmo final 1
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Awareness iso 22301 danang suryo
Awareness iso 22301 danang suryoAwareness iso 22301 danang suryo
Awareness iso 22301 danang suryo
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 

En vedette

Schedule Risk Analysis
Schedule Risk AnalysisSchedule Risk Analysis
Schedule Risk AnalysisGd Suryawan
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskAcumen
 
Omaha SPUG - Use SharePoint to Manage ERM Objectives
Omaha SPUG - Use SharePoint to Manage ERM ObjectivesOmaha SPUG - Use SharePoint to Manage ERM Objectives
Omaha SPUG - Use SharePoint to Manage ERM ObjectivesKerry Dirks MCPS MS
 
Overview of Enterprise Risk Management (ERM)
Overview of Enterprise Risk Management (ERM)Overview of Enterprise Risk Management (ERM)
Overview of Enterprise Risk Management (ERM)Segun Ogunwale
 
GRI ERM Roadmap - Program Overview
GRI ERM Roadmap - Program OverviewGRI ERM Roadmap - Program Overview
GRI ERM Roadmap - Program OverviewDenise Robinson
 
Understanding risk analysis and risk management with net zealous llc services...
Understanding risk analysis and risk management with net zealous llc services...Understanding risk analysis and risk management with net zealous llc services...
Understanding risk analysis and risk management with net zealous llc services...NetZealous LLC
 
Mba 1 me u 4 profit management & risk analysis
Mba 1 me u 4  profit management & risk analysisMba 1 me u 4  profit management & risk analysis
Mba 1 me u 4 profit management & risk analysisRai University
 
Course offeringem
Course offeringemCourse offeringem
Course offeringemRaza Naqvi
 
Risk Analysis In Business Continuity Management - Jeremy Wong
Risk Analysis In Business Continuity Management - Jeremy WongRisk Analysis In Business Continuity Management - Jeremy Wong
Risk Analysis In Business Continuity Management - Jeremy WongBCM Institute
 
How performance management can improve client satisfaction
How performance management can improve client satisfactionHow performance management can improve client satisfaction
How performance management can improve client satisfactionSkanska USA
 
Risk Analysis & Risk Management
Risk Analysis & Risk ManagementRisk Analysis & Risk Management
Risk Analysis & Risk ManagementGrafic.guru
 
Total construction quality management by leading ICT technology
Total construction quality management by leading ICT technologyTotal construction quality management by leading ICT technology
Total construction quality management by leading ICT technologyStephen Au
 
La gestion de risque pour combler l’écart entre la tactique et la stratégie
La gestion de risque pour combler l’écart entre la tactique et la stratégieLa gestion de risque pour combler l’écart entre la tactique et la stratégie
La gestion de risque pour combler l’écart entre la tactique et la stratégiePMI-Montréal
 
IBM Cloud Solution - Blue Box
IBM Cloud Solution - Blue BoxIBM Cloud Solution - Blue Box
IBM Cloud Solution - Blue BoxDaniele Bolletta
 
Web 2.0 threats, vulnerability analysis,secure web 2.0 application developmen...
Web 2.0 threats, vulnerability analysis,secure web 2.0 application developmen...Web 2.0 threats, vulnerability analysis,secure web 2.0 application developmen...
Web 2.0 threats, vulnerability analysis,secure web 2.0 application developmen...Marco Morana
 
Risk Analysis of Geological Hazards and Disaster Management
Risk Analysis of Geological Hazards and Disaster ManagementRisk Analysis of Geological Hazards and Disaster Management
Risk Analysis of Geological Hazards and Disaster ManagementClaudio Ferreira
 

En vedette (20)

Schedule Risk Analysis
Schedule Risk AnalysisSchedule Risk Analysis
Schedule Risk Analysis
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Omaha SPUG - Use SharePoint to Manage ERM Objectives
Omaha SPUG - Use SharePoint to Manage ERM ObjectivesOmaha SPUG - Use SharePoint to Manage ERM Objectives
Omaha SPUG - Use SharePoint to Manage ERM Objectives
 
Overview of Enterprise Risk Management (ERM)
Overview of Enterprise Risk Management (ERM)Overview of Enterprise Risk Management (ERM)
Overview of Enterprise Risk Management (ERM)
 
GRI ERM Roadmap - Program Overview
GRI ERM Roadmap - Program OverviewGRI ERM Roadmap - Program Overview
GRI ERM Roadmap - Program Overview
 
Agile and the DoD
Agile and the DoDAgile and the DoD
Agile and the DoD
 
Understanding risk analysis and risk management with net zealous llc services...
Understanding risk analysis and risk management with net zealous llc services...Understanding risk analysis and risk management with net zealous llc services...
Understanding risk analysis and risk management with net zealous llc services...
 
Mba 1 me u 4 profit management & risk analysis
Mba 1 me u 4  profit management & risk analysisMba 1 me u 4  profit management & risk analysis
Mba 1 me u 4 profit management & risk analysis
 
112 risk management
112 risk management112 risk management
112 risk management
 
Course offeringem
Course offeringemCourse offeringem
Course offeringem
 
Risk Analysis In Business Continuity Management - Jeremy Wong
Risk Analysis In Business Continuity Management - Jeremy WongRisk Analysis In Business Continuity Management - Jeremy Wong
Risk Analysis In Business Continuity Management - Jeremy Wong
 
How performance management can improve client satisfaction
How performance management can improve client satisfactionHow performance management can improve client satisfaction
How performance management can improve client satisfaction
 
Risk Analysis & Risk Management
Risk Analysis & Risk ManagementRisk Analysis & Risk Management
Risk Analysis & Risk Management
 
Risk management
Risk managementRisk management
Risk management
 
Total construction quality management by leading ICT technology
Total construction quality management by leading ICT technologyTotal construction quality management by leading ICT technology
Total construction quality management by leading ICT technology
 
La gestion de risque pour combler l’écart entre la tactique et la stratégie
La gestion de risque pour combler l’écart entre la tactique et la stratégieLa gestion de risque pour combler l’écart entre la tactique et la stratégie
La gestion de risque pour combler l’écart entre la tactique et la stratégie
 
IBM Cloud Solution - Blue Box
IBM Cloud Solution - Blue BoxIBM Cloud Solution - Blue Box
IBM Cloud Solution - Blue Box
 
Web 2.0 threats, vulnerability analysis,secure web 2.0 application developmen...
Web 2.0 threats, vulnerability analysis,secure web 2.0 application developmen...Web 2.0 threats, vulnerability analysis,secure web 2.0 application developmen...
Web 2.0 threats, vulnerability analysis,secure web 2.0 application developmen...
 
Pert master risk analysis tool
Pert master   risk analysis toolPert master   risk analysis tool
Pert master risk analysis tool
 
Risk Analysis of Geological Hazards and Disaster Management
Risk Analysis of Geological Hazards and Disaster ManagementRisk Analysis of Geological Hazards and Disaster Management
Risk Analysis of Geological Hazards and Disaster Management
 

Similaire à Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011

Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Pedram Danesh-Mand
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - PaperDaniel Ackermann
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleGlen Alleman
 
Project risk management model based on prince2 and scrum frameworks
Project risk management model based on prince2 and scrum frameworksProject risk management model based on prince2 and scrum frameworks
Project risk management model based on prince2 and scrum frameworksijseajournal
 
project risk management
project risk managementproject risk management
project risk managementAshima Thakur
 
Increasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementIncreasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementGlen Alleman
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Glen Alleman
 
1Risk ReportingRisk ReportingRique Gidde.docx
1Risk ReportingRisk ReportingRique Gidde.docx1Risk ReportingRisk ReportingRique Gidde.docx
1Risk ReportingRisk ReportingRique Gidde.docxfelicidaddinwoodie
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxMehediHasan636262
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMarkos Mulat G
 
Building Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleBuilding Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleGlen Alleman
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesIRJET Journal
 
Beyond PMP: Risk Management
Beyond PMP: Risk ManagementBeyond PMP: Risk Management
Beyond PMP: Risk Managementabhinayverma
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxGeorgeKabongah2
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaPankaj K Sinha
 

Similaire à Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011 (20)

Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - Paper
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master schedule
 
Planning
PlanningPlanning
Planning
 
Project risk management model based on prince2 and scrum frameworks
Project risk management model based on prince2 and scrum frameworksProject risk management model based on prince2 and scrum frameworks
Project risk management model based on prince2 and scrum frameworks
 
project risk management
project risk managementproject risk management
project risk management
 
Increasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementIncreasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk Management
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)
 
1Risk ReportingRisk ReportingRique Gidde.docx
1Risk ReportingRisk ReportingRique Gidde.docx1Risk ReportingRisk ReportingRique Gidde.docx
1Risk ReportingRisk ReportingRique Gidde.docx
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Building Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleBuilding Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and Schedule
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction Industries
 
Beyond PMP: Risk Management
Beyond PMP: Risk ManagementBeyond PMP: Risk Management
Beyond PMP: Risk Management
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K Sinha
 

Plus de Pedram Danesh-Mand

Risk Management & Contingency Guideline Training Workshop
Risk Management & Contingency Guideline Training WorkshopRisk Management & Contingency Guideline Training Workshop
Risk Management & Contingency Guideline Training WorkshopPedram Danesh-Mand
 
EA Create Magazine Nov 2016 - Pedram Danesh Mand
EA Create Magazine Nov 2016 - Pedram Danesh MandEA Create Magazine Nov 2016 - Pedram Danesh Mand
EA Create Magazine Nov 2016 - Pedram Danesh MandPedram Danesh-Mand
 
Risk Engineering Society RISK 2016 Conference
Risk Engineering Society RISK 2016 ConferenceRisk Engineering Society RISK 2016 Conference
Risk Engineering Society RISK 2016 ConferencePedram Danesh-Mand
 
RES Risk 2016 Conference brochure - 18-20 May 2016, Sydney
RES Risk 2016 Conference brochure - 18-20 May 2016, SydneyRES Risk 2016 Conference brochure - 18-20 May 2016, Sydney
RES Risk 2016 Conference brochure - 18-20 May 2016, SydneyPedram Danesh-Mand
 
CGBrochure_L6040_L6039_ConstructionCostControl_BrisPer
CGBrochure_L6040_L6039_ConstructionCostControl_BrisPerCGBrochure_L6040_L6039_ConstructionCostControl_BrisPer
CGBrochure_L6040_L6039_ConstructionCostControl_BrisPerPedram Danesh-Mand
 
Safety in Design & Multicultural Teams - National Safety Convention - PDM pre...
Safety in Design & Multicultural Teams - National Safety Convention - PDM pre...Safety in Design & Multicultural Teams - National Safety Convention - PDM pre...
Safety in Design & Multicultural Teams - National Safety Convention - PDM pre...Pedram Danesh-Mand
 
Planning, Risks and Delays - Risks, Rewards and Relationships Workshop 03-Dec...
Planning, Risks and Delays - Risks, Rewards and Relationships Workshop 03-Dec...Planning, Risks and Delays - Risks, Rewards and Relationships Workshop 03-Dec...
Planning, Risks and Delays - Risks, Rewards and Relationships Workshop 03-Dec...Pedram Danesh-Mand
 
Effective Contingency Management - Contractor Management Forum - PD July 2013
Effective Contingency Management - Contractor Management Forum - PD July 2013Effective Contingency Management - Contractor Management Forum - PD July 2013
Effective Contingency Management - Contractor Management Forum - PD July 2013Pedram Danesh-Mand
 
Aquenta Risk management Capability Statement (short) 2013
Aquenta Risk management Capability Statement (short) 2013Aquenta Risk management Capability Statement (short) 2013
Aquenta Risk management Capability Statement (short) 2013Pedram Danesh-Mand
 
Monte Calrimulation and Inclement Weather Risk Assessment
Monte Calrimulation and Inclement Weather Risk AssessmentMonte Calrimulation and Inclement Weather Risk Assessment
Monte Calrimulation and Inclement Weather Risk AssessmentPedram Danesh-Mand
 
Assessing EPC Contract Risk by using integrated systems
Assessing EPC Contract Risk by using integrated systemsAssessing EPC Contract Risk by using integrated systems
Assessing EPC Contract Risk by using integrated systemsPedram Danesh-Mand
 
Contract Risk Assessment by using integrated systems
Contract Risk Assessment by using integrated systemsContract Risk Assessment by using integrated systems
Contract Risk Assessment by using integrated systemsPedram Danesh-Mand
 
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...Pedram Danesh-Mand
 

Plus de Pedram Danesh-Mand (14)

Risk Management & Contingency Guideline Training Workshop
Risk Management & Contingency Guideline Training WorkshopRisk Management & Contingency Guideline Training Workshop
Risk Management & Contingency Guideline Training Workshop
 
EA Create Magazine Nov 2016 - Pedram Danesh Mand
EA Create Magazine Nov 2016 - Pedram Danesh MandEA Create Magazine Nov 2016 - Pedram Danesh Mand
EA Create Magazine Nov 2016 - Pedram Danesh Mand
 
2016-06 RES Newsletter FINAL
2016-06 RES Newsletter FINAL2016-06 RES Newsletter FINAL
2016-06 RES Newsletter FINAL
 
Risk Engineering Society RISK 2016 Conference
Risk Engineering Society RISK 2016 ConferenceRisk Engineering Society RISK 2016 Conference
Risk Engineering Society RISK 2016 Conference
 
RES Risk 2016 Conference brochure - 18-20 May 2016, Sydney
RES Risk 2016 Conference brochure - 18-20 May 2016, SydneyRES Risk 2016 Conference brochure - 18-20 May 2016, Sydney
RES Risk 2016 Conference brochure - 18-20 May 2016, Sydney
 
CGBrochure_L6040_L6039_ConstructionCostControl_BrisPer
CGBrochure_L6040_L6039_ConstructionCostControl_BrisPerCGBrochure_L6040_L6039_ConstructionCostControl_BrisPer
CGBrochure_L6040_L6039_ConstructionCostControl_BrisPer
 
Safety in Design & Multicultural Teams - National Safety Convention - PDM pre...
Safety in Design & Multicultural Teams - National Safety Convention - PDM pre...Safety in Design & Multicultural Teams - National Safety Convention - PDM pre...
Safety in Design & Multicultural Teams - National Safety Convention - PDM pre...
 
Planning, Risks and Delays - Risks, Rewards and Relationships Workshop 03-Dec...
Planning, Risks and Delays - Risks, Rewards and Relationships Workshop 03-Dec...Planning, Risks and Delays - Risks, Rewards and Relationships Workshop 03-Dec...
Planning, Risks and Delays - Risks, Rewards and Relationships Workshop 03-Dec...
 
Effective Contingency Management - Contractor Management Forum - PD July 2013
Effective Contingency Management - Contractor Management Forum - PD July 2013Effective Contingency Management - Contractor Management Forum - PD July 2013
Effective Contingency Management - Contractor Management Forum - PD July 2013
 
Aquenta Risk management Capability Statement (short) 2013
Aquenta Risk management Capability Statement (short) 2013Aquenta Risk management Capability Statement (short) 2013
Aquenta Risk management Capability Statement (short) 2013
 
Monte Calrimulation and Inclement Weather Risk Assessment
Monte Calrimulation and Inclement Weather Risk AssessmentMonte Calrimulation and Inclement Weather Risk Assessment
Monte Calrimulation and Inclement Weather Risk Assessment
 
Assessing EPC Contract Risk by using integrated systems
Assessing EPC Contract Risk by using integrated systemsAssessing EPC Contract Risk by using integrated systems
Assessing EPC Contract Risk by using integrated systems
 
Contract Risk Assessment by using integrated systems
Contract Risk Assessment by using integrated systemsContract Risk Assessment by using integrated systems
Contract Risk Assessment by using integrated systems
 
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
 

Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011

  • 1. Slide 1 of 18 Schedule Risk Analysis(SRA)Pedram DaneshmandAssociate DirectorBlue Visions Management Pty Ltd
  • 2. Slide 2 of 18 Content Project Time Management Risk & Opportunities Project Risk Management Schedule Risk Analysis Results Review Action Plan
  • 3. Project Time ManagementHistory Every project must be managed against a schedule; Project Scheduling has been around a long time; Scheduling is one of the most widely practiced project management disciplines (Archibald and Villoria 1967). Slide 3 of 18 Project Time Management includes the processes required to accomplish timely completion of the project (PMBOK, 2004).
  • 4. Project Time ManagementProcess Activity Definition Activity Sequencing (logic) Activity Resource Estimating Activity Duration Estimating Schedule Development Schedule Control (PMBOK, 2004) Slide 4 of 18
  • 5. Project Time ManagementSchedule Development The Schedule Development process includes selecting a scheduling Method, scheduling Tool, incorporating project specific data within that scheduling tool to develop project specific schedule Model, and generating Project Schedule. (PMI-PS for Scheduling, 2007) Slide 5 of 18
  • 6. Schedule DevelopmentMethods Logic-based Scheduling Methods (LSM) Deterministic Techniques E.g. Critical Path Method (CPM), Resource Optimisation, Critical Chain Method (CCM), etc. Stochastic Techniques E.g. Probabilistic Evaluation and Review Technique (PERT), PNET, Monte Carlo Simulation (MCS), etc. Repetitive Scheduling Methods (RSM) Line of Balance (LOB) Flowline Method Slide 6 of 18
  • 7. Schedule Development Inputs Planners develop the project schedule by using: Available templates; Available quantities, resources and productivity rates; Available work/scope statements; Available construction logic; and Other assumptions/documents e.g. calendars, PMP, etc. Slide 7 of 18 All these add uncertainties to schedule and reduce the confidence level. What about risks and opportunities in the schedule?
  • 8. Schedule Development Outputs The outputs of Schedule Development process are: (Deterministic) Project Schedule; (Deterministic) Schedule Model Data (Deterministic) Schedule Baseline (Deterministic) Resource Requirements Slide 8 of 18 With all those uncertainties in the inputs and the possible risks and opportunities in the schedule, the question is, how confident we are in this schedule?
  • 9. Schedule Development Major Challenges Uncertainties due to assumptions; Logic, constraints, resources, calendars and activity durations are not always clear and agreed; What-If Scenarios; and Risks and Opportunities Slide 9 of 18 To have a realistic schedule, Schedule Development process should be improved by using Schedule Risk Analysis. In other words Project Time Management and Project Risk Management need to be integrated!
  • 10. Schedule DevelopmentRisks & Opportunities Every schedule has uncertainties/assumptions. Every schedule has risks and opportunities. Slide 10 of 18 Effect on project (positive or negative) Time Scope So, Risks and Opportunities should be managed effectively to minimize the surprises!! Cost Quality
  • 11. Project Risk Management Process Slide 11 of 18 Establish Context MONITOR AND REVIEW COMMUNICATE AND CONSULT Identify Risks Analyse Risks RISK ASSESSMENT Evaluate Risks Treat Risks AS/NZS ISO 31000:2009
  • 12. Project Risk ManagementRisk Assessment Risk Assessment include Risk Identification (both Uncertainties and Events) Risk Analysis Qualitative Quantitative (Schedule Risk Analysis or SRA) Risk Evaluation Slide 12 of 18 The goal is to have a better understanding of risks / opportunities and their overall impact on project completion date. This will bridges the gap between traditional CPM schedule and the REAL project.
  • 13. Project Risk ManagementRisk Analysis Risk Analysis is the process to comprehend the nature of risks (or opportunities) and to determine the level of risks (or opportunities) in the schedule Risk analysis provides the basis for risk evaluation and decisions about risk treatment; and Risk Analysis includes risk estimation. Slide 13 of 18 By Schedule Risk Analysis (SRA), we model the risks and opportunities (uncertainties and events) within the complexity of the interrelationships between the various tasks of the schedule.
  • 14. Schedule Risk Analysis(SRA) SRA is a probabilistic analysis to quantify the impacts to a project, program or portfolio as a result of carrying uncertainties and/or risks and opportunities or to simulate the possible what-if scenarios. Slide 14 of 18 Relying on a accurate most likely schedule as a base, SRA takes the project time management to the next level of accuracy and confidence.
  • 15. Schedule Risk AnalysisOverview Available data gathering Schedule Review Technical Research Risks & Opportunities Register Both Uncertainties and Events Schedule Risk Model Simulation Results and Discussions Slide 15 of 18
  • 16. Schedule Risk Analysis Data Gathering Required information for a SRA Well-developed project scope; Quality estimate excluding contingency and escalation; Schedule reflecting the estimate; Risk management policy/processes in your organisation; Risk checklist presenting typical risks and opportunities; Risk & Opportunities Template; Schedule Risk Templates/Models; and Sample report of the process and recommendations. Slide 16 of 18
  • 17. Schedule Risk Analysis Schedule Review How to review the deterministic schedule? Validation of all quantities (most likely); Validation of all productivity rates (most likely); Validation of all durations (most likely); Minimum number of constraints; Complete logic network; Reasonable duration for tasks; and Reasonable Critical Path. Slide 17 of 18
  • 18. SRA – Schedule ReviewSample Report Slide 18 of 20 Confidential
  • 19. Schedule Risk Analysis Technical Research When the team is confident that the project deterministic schedule reflects the most likely case, the technical research can begin. Historical data research Interviews Internet searches, etc. Slide 19 of 18 Issues may include items such as site access, Environmental Approvals, inclement weather, construction productivity concerns, construction modifications, equipment and material deliver, etc.
  • 20. Schedule Risk Analysis Risk Register The Technical Research will enable the schedule risk analyst to complete the Risk Register file: The identified risks & opportunities Likelihood of the identified risks and opportunities Impacted activities Schedule and/or Cost Impact/s Schedule and/or Cost Variations Correlation of risks and opportunities to one another Notes, etc. Slide 20 of 18
  • 21. Schedule Risk Analysis Risk Register (Sample) Slide 21 of 18 Confidential
  • 22. SRA – Risk Register (Sample)Rain details Slide 22 of 18
  • 23. SRA – Risk RegisterQuality Check Major risks and opportunities been identified; The likelihood and impacts been assessed; Risk Matrix aligned with the company’s risk management policy; Impacts checked against the allocated calendars; Correlations between risks been identified; Stage the opportunities if required; and Duplications are minimised and addressed. Slide 23 of 18
  • 24. SRA – Schedule Risk ModelUncertainties & Events Developing the Schedule Risk Model involves modelling the potential impacts and the likelihood of the risks and opportunities on the project and then applying those to the schedule. Two aspects of the risks and opportunities should be modelled within the schedule: Estimate Uncertainties (Optimistic, Most Likely and Pessimistic) Events including probabilistic branching (probability and the impacts) Slide 24 of 18
  • 25. SRA – Schedule Risk ModelProbability Distributions Probability Distribution is a way to indicate the likelihood of values between the optimistic and pessimistic values. Probability Distribution can be: Uniform (flat), Normal (bell shaped), Beta (skinny bell shaped), Triangle (pyramid shaped), or Customised (user defined). Slide 25 of 18
  • 26. SRA – Schedule Risk ModelProbability Distributions Slide 26 of 18
  • 27. SRA – Schedule Risk ModelSpecial Conditions Special conditions which needs extra attention: Probabilistic Branching – which considers the situation where the outcome of an event can cause in two or multiple possible courses of activities. Correlation between risks Positive Correlation: occurs when one risk goes higher, so must the other. Negative or Adverse Correlation: occurs when one risk increases, the other must decrease. Inclement Weather or other external influences Slide 27 of 18
  • 28. SRA – Schedule Risk ModelInclement Weather Inclement Weather can be a significant factor in a project schedule. Very often there is good data available but understanding the impact on the schedule is challenging. A proper modelling will allow the team to define risk assessment criteria for inclement weather conditions in the schedule, and include these uncertain weather conditions in the risk analysis. Slide 28 of 18
  • 29. SRA – Schedule Risk ModelInclement Weather There are two distinct ways of defining inclement weather events: Event with results in an uncertain number of non working days scattered throughout a period, e.g. rain or snow. Event with results in a single block of non working time with a probability of occurrence, e.g. chance of a hurricane in a period. Slide 29 of 18
  • 30. Schedule Risk Analysis Simulation Methods The SRA performs multiple simulations of the project using random samplings of the relevant risks and opportunities considering their probability and impact. Two popular methods: Monte Carlo Simulation (MCS) – faster method but has a larger possibility of sampling error Latin Hypercube Sampling (LHS) – slower method but less sampling errors Slide 30 of 18
  • 31. Schedule Risk Analysis Simulation Process Analysis does the simulation through multiple samplings or iterations. Each iteration is picking one sample point from each activity and calculating the project outcome. User defines the number of iteration (e.g. 1000, 5000, etc) depending on the complexity of the project and its risk model. Slide 31 of 18
  • 32. Schedule Risk Analysis Simulation Tools Main tools been widely used for simulation are: Primavera Risk Analysis (previously known as Pertmaster) @Risk for Project Crystal Ball Slide 32 of 18 The next slides are presenting results from simulations by using Primavera Risk Analysis.
  • 33. Schedule Risk Analysis Sample Programme Slide 33 of 18 Confidential Confidential
  • 34. Schedule Risk Analysis Finish Date Histogram Slide 34 of 18 Confidential
  • 35. Schedule Risk Analysis Histogram & Statistics Slide 35 of 18 Confidential
  • 36. Schedule Risk Analysis Criticality Index Tornado Slide 36 of 18 Confidential The Criticality Index of an activity is the proportion of the iterations in which the activity was critical. Usually more attention will be given to the activities with Criticality Index of more than 50%.
  • 37. Schedule Risk Analysis Criticality Path Report Slide 37 of 18 The Criticality Path Report highlights the path through the project containing the tasks with the highest Criticality Index values. Percent Criticality is the probability that an activity will be on the critical path; this indicates the relative importance of the activity to other activities in the programme. Confidential
  • 38. Schedule Risk Analysis Criticality Distribution Profile Slide 38 of 18 Criticality Distribution Profile plots the spread of Criticality Index in a project which gives an indication of the number and threat of near to critical path. A high percentage (more than 40%) indicates a relatively tight programme. Confidential
  • 39. Schedule Risk Analysis Action Plan The accuracy of the SRA outcomes should be improved through a number of iterations of this process. Based on the initial results, the team should: Review the risk register and make modifications where require; Make changes to the risk model accordingly; Run the simulation again and repeat the process to achieve the most cost-effective risk mitigation plan; Finalise the Risk Action Plan as well as the Contingency Plan; and Communicate this schedule with the team and then monitor it. Slide 39 of 18
  • 40. About the Author Pedram Daneshmand, Associate Director Blue Visions Management Pedram is a civil engineer with over 15 years experience in the construction industry. He is highly skilled and technically proficient in many aspects of construction including Programming, Programme Performance Measurement, Quantitative Risk Analysis, Contract Management, Schedule Risk Analysis (SRA), Cost Risk Analysis (CRA), Project Monitoring & Controls (PMC) Systems, Earned Value Performance Measurement technique (EVPM) and POW (Program of Work) Planning & Controls. As an industry innovation award winner for his programming and risk analysis skills, Pedram is currently an Associate Director with Blue Visions Management leading a team of planning and controls professionals within the infrastructure sector. With more than 15 articles in the professional conferences/journals, he is been regularly invited to the technical presentations as one of the industry leaders in his field. Slide 40 of 18