SlideShare une entreprise Scribd logo
1  sur  8
Télécharger pour lire hors ligne
COLLABORATE 12    Page 1 
Scheduling: Minimizing the input while maximizing the output
Chris Ackerman, PMI-SP
SSOE Group
Rick Fox, PMP
SSOE Group
Have you ever spent an abundance of time and energy developing the perfect detailed schedule for a client, only to
find out you have missed the mark? Perhaps you spelled out a specific project plan in great detail, incorporated
valuable input from all project stakeholders, laid it out beautifully atop an 11x17 colored PDF and illustrated it with
a Gantt chart showing relationship lines and a stair stepped critical path… only to receive a blank glare that says
“what am I supposed to do with this?”
At SSOE Group, an international engineering, architectural and consulting firm headquartered in Toledo Ohio, our
opportunities to create, update and maintain project schedules range from the initial needs analysis through the
detailed start up/commissioning phases. The schedules are often complex and require several iterations including
high level milestone schedules used for initial planning and conclude with a detailed logic and resource driven
project schedule. Often the required input comes from various places, both internally and externally, with resources
that have widely varying degrees of knowledge about the time, effort and information it takes to create a logic
driven schedule. Our presentation will show you some tips and tricks that we have found that help us both save time
and effort utilizing P6 and allow for a schedule deliverable that is user friendly, less cumbersome to update, and
capable of producing customizable reports to meet the client’s needs . We’ll showcase how SSOE, and subsequently
our clients, have benefitted from software components such as user defined fields, activity steps, high level
resources with custom resource curves, and level of effort/WBS summary activities. Let us help you turn those blank
stares and thoughts of “what am I supposed to do with this” to a friendly smile and a “Perfect!”
Objectives:
Problem: The time consuming task of statusing a complex multi-phase schedule makes it difficult to provide
complete project updates in a timely manner.
Solution: Dividing large project schedules into smaller and more manageable related schedules allows for flexibility
in updating. Furthermore, using activity steps can lessen the overall size and complexity of the schedule and
dramatically lesson the effort required to advance the data date.
Problem: Quickly and effectively resource loading a detailed schedule can be a time consuming and daunting task.
Solution: Assigning resources to WBS Summary and Level of Effort activity types allows for greater flexibility.
Concurrently, using high level resources and custom resource curves can increase one’s ability to quickly and
effectively develop a resource plan.
Problem: Using Primavera P6 standard reporting outputs on large schedules can produce lengthy reports that may
contain more information than is required.
Solution: Illustrate how using custom filters & user define fields can enhance reporting functionality and condense
reporting output.
Manageable Interlinked Schedules
On projects with a large amount of scope to manage, maintaining a single project schedule can be daunting.
Interlinking multiple schedules allows for assigning separate responsible parties for schedule updates, limiting the
overall information that needs to be reviewed by each responsible party and eases the baselining process.
COLLABORATE 12    Page 2 
On multi-discipline/contractor projects, input is often required from multiple responsible parties to complete a
schedule update. Breaking the project plan into individual schedules where scope is divided by responsible party
allows for flexibility in updating schedule progress. (See Example 1 below)
Example 1
Simultaneous updates can be made and schedules can be updated at separate times if information about specific
areas in unknown or in question. This also assists in the risk analysis or what-if scenario breakdown.
Another advantage of having interlinked schedules is baselining. As changes occur on the project, maintaining the
plan can be a difficult task for schedules that incorporate a large amount of scope. The update baseline function has
many options to sift through and not fully understanding all of the changes that are being made can result in lost data
(See Example 2.1 and 2.2 below). The log, although useful, can contain more information than needed and
information can be difficult to locate.
COLLABORATE 12    Page 3 
Example 2.1
Example 2.2
With schedules broken down by responsible party, new baselines can be assigned (See Example 3 below) as
approved changes are made or the update baseline function can be used. Both are much easier on smaller schedules
as there is less information to manage by a single responsible party.
COLLABORATE 12    Page 4 
Example 3
Activity Steps
The use of activity steps within a project schedule is a useful method that allows you to keep all of the necessary
details while minimizing the effort to understand and update the schedule. This method is best used when you have
a number of activities that are of short duration, directly linked to each other, and all part of a larger task. For
example, when scheduling the construction of foundations there are many activities that lead up to the pouring of
concrete. If you included all of those activities as steps, and only one activity for foundations, the amount of
maintenance needed to keep the schedule current is significantly reduced. This method produces a Gantt chart that
is easily understood and can be used as a communication tool at all levels of a project (see Example 4 below).
Example 4
COLLABORATE 12    Page 5 
Steps can also be used to expedite the creation of project schedules. Once a list of standard steps has been created, it
can be stored as a template for future use. This gives you the ability to quickly create first pass project schedules
with plenty of detail which can then be customized for project-specific needs (see Examples 5.1 through 5.3 below).
Example 5.1 Example 5.2
Example 5.3
The use of activity steps also allows for schedules to be updated very efficiently. You have the option to hold
traditional schedule update meetings or you can produce straightforward checklist reports that can be sent out to
project stakeholders for comments (see Example 6 below). The comments can then be sent to project schedulers for
input into the schedule. Also, these reports can be filtered to include only relevant activities for a given individual
or group. This reduces time spent in meetings listening to information that may not apply and allows the responsible
party the ability to update their activities without searching through a detailed project schedule to find them.
Example 6
COLLABORATE 12    Page 6 
Activity Types and High-Level Resources and Curves
WBS and Level of Effort (LOE) activity types are an efficient way to increase the ease of project creation, updating
and reporting. This is enhanced when using high level resources with customized resource curves.
By assigning resources to WBS and LOE activities, tracking of resource financials (budgets, actuals and forecasts)
can be managed at a higher level and the information that may be required is still available for progressing and
reporting (i.e. EV, CPI & SPI). As the schedule changes when resources are assigned at the task level the resource
data need to be adjusted at that level. This requires that each of those revised activity’s resource financials needs to
be updated and then reviewed for accuracy. WBS and LOE activities only need revised as activities are moved,
added or deleted from the WBS or from the chain of activities the LOE is assigned to.
In addition to assigning resources to WBS and LOE activity types, using high level resources such as job
classification (i.e. Project Manager, Project Controller) or discipline level (i.e. Architect, Structural Engineer) versus
named resources allows for easier schedule creation and updating. This is especially beneficial on large projects
where resources are grouped by job classification or departments and an overall average rate and work calendar can
be agreed upon.
Using resources that are classified by job classification or discipline level can further be enhanced by using custom
resource curves that are assigned at the project level. Resource curves, which are customizable, allow for historical
information to be incorporated into plans so that a more accurate baseline schedule can be created and reported
against.
P6 Reporting
Primavera standard reports tend to produce lengthy outputs with information that may be more than truly required.
The standard reports can be used as starting points to help users generate ideas, or through the use of simple methods
within the software, users can create project specific reports that can also be used as templates throughout an
organization.
All of the information needed for project reporting is already being generated through regular updating of the project
schedule. The trick is creating a report that extracts required information into an understandable format for the end
user. The quickest method for creating a new report is through the use of layouts. By creating a layout, with just the
required information, through the use of filters and other user defined data, a report can quickly be generated
through the use of the Report Wizard tool (see Examples 7.1 through 7.3 below).
COLLABORATE 12    Page 7 
Example 7.1
Example 7.2 Example 7.3
   
Once a report with the raw data has been created, the Modify report function can be used to depict the information in
a customizable format. This function can be used to show information in a user friendly spreadsheet format; colors
can be added to depict status or thresholds, custom graphics can be inserted to personalize reports, along with many
other options that can enhance reporting output (see Examples 8.1 through 8.2 below).
Example 8.1 
COLLABORATE 12    Page 8 
Example 8.2
These methods produce reports that give users a quick visual indication of status as well as the ability to review
detailed information that may be required for a specific task.
Conclusion
It easily becomes overwhelming when you stop and consider the amount of time and effort it would take to create
and manage detailed project schedules if programs like Primavera P6 weren’t available to assist you in that process.
Tasks such as baseline variance analysis, resource planning, and project reporting, that take minutes or hours to
complete in the software, would potentially take days to complete manually and the accuracy would be questionable
at best. The methods mentioned above are just a few of the options available within the software that can be used to
make planners, schedulers and project managers more efficient. In today’s culture of faster and cheaper, gaining
efficiency is a great way to remain competitive in the marketplace which helps to achieve everyone’s goal of long-
term success.

Contenu connexe

Tendances

The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkitsIT-Toolkits.org
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual Abbas Tahir
 
IBM Rational Team Concert at Landmap
IBM Rational Team Concert at LandmapIBM Rational Team Concert at Landmap
IBM Rational Team Concert at LandmapBharti Gupta
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010B Sai Prasad
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectMeryem Yıldız
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsInSync Conference
 
Schedule reader, viewer for xer, xml, xls project schedules
Schedule reader, viewer for xer, xml, xls project schedulesSchedule reader, viewer for xer, xml, xls project schedules
Schedule reader, viewer for xer, xml, xls project schedulesScheduleReader
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
Navigating Project 2010 (OMT II)
Navigating Project 2010 (OMT II)Navigating Project 2010 (OMT II)
Navigating Project 2010 (OMT II)Usman Zafar
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20developmentharwoodr
 
NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2Future Managers
 
A guide to create a quality project schedule
A guide to create a quality project scheduleA guide to create a quality project schedule
A guide to create a quality project scheduleNirtiSingla
 

Tendances (20)

The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkits
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
HM 418 2e hcpm05 (1)
HM 418 2e hcpm05 (1)HM 418 2e hcpm05 (1)
HM 418 2e hcpm05 (1)
 
IBM Rational Team Concert at Landmap
IBM Rational Team Concert at LandmapIBM Rational Team Concert at Landmap
IBM Rational Team Concert at Landmap
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and Traps
 
Schedule reader, viewer for xer, xml, xls project schedules
Schedule reader, viewer for xer, xml, xls project schedulesSchedule reader, viewer for xer, xml, xls project schedules
Schedule reader, viewer for xer, xml, xls project schedules
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Navigating Project 2010 (OMT II)
Navigating Project 2010 (OMT II)Navigating Project 2010 (OMT II)
Navigating Project 2010 (OMT II)
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Project time management
Project time managementProject time management
Project time management
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development
 
NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2
 
A guide to create a quality project schedule
A guide to create a quality project scheduleA guide to create a quality project schedule
A guide to create a quality project schedule
 

Similaire à Scheduling minimizing the input while maximizing the output white paper

Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
 
Control techniques
Control techniquesControl techniques
Control techniquesAdnan Shakir
 
Presentation4 5.1.pptx
Presentation4 5.1.pptxPresentation4 5.1.pptx
Presentation4 5.1.pptxDrRRajalakshmi
 
Primavara
PrimavaraPrimavara
Primavaradanabl
 
Training pm jan 11 part b
Training pm jan 11 part bTraining pm jan 11 part b
Training pm jan 11 part bSiep Littooij
 
Project Management Plan TemplateThis Project Management Plan.docx
Project Management Plan TemplateThis Project Management Plan.docxProject Management Plan TemplateThis Project Management Plan.docx
Project Management Plan TemplateThis Project Management Plan.docxwoodruffeloisa
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management ProjectMary Stevenson
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project ReportRISHABHSIINGH
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Managementtkrikau
 
Diploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity SequencesDiploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity Sequencesdanieljohn810
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptxTecnicoItca
 

Similaire à Scheduling minimizing the input while maximizing the output white paper (20)

Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Control techniques
Control techniquesControl techniques
Control techniques
 
Presentation4 5.1.pptx
Presentation4 5.1.pptxPresentation4 5.1.pptx
Presentation4 5.1.pptx
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Primavara
PrimavaraPrimavara
Primavara
 
Communication 1
Communication 1Communication 1
Communication 1
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
Training pm jan 11 part b
Training pm jan 11 part bTraining pm jan 11 part b
Training pm jan 11 part b
 
Project Management Plan TemplateThis Project Management Plan.docx
Project Management Plan TemplateThis Project Management Plan.docxProject Management Plan TemplateThis Project Management Plan.docx
Project Management Plan TemplateThis Project Management Plan.docx
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Ch05
Ch05Ch05
Ch05
 
Unit 5.pdf
Unit 5.pdfUnit 5.pdf
Unit 5.pdf
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project Report
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
Diploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity SequencesDiploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity Sequences
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
Version comparisondesktop
Version comparisondesktopVersion comparisondesktop
Version comparisondesktop
 

Plus de p6academy

Oracle OpenWorld 2015
Oracle OpenWorld 2015Oracle OpenWorld 2015
Oracle OpenWorld 2015p6academy
 
Plan and Execute the Right Projects— Easily and Affordably
Plan and Execute the Right Projects—  Easily and AffordablyPlan and Execute the Right Projects—  Easily and Affordably
Plan and Execute the Right Projects— Easily and Affordablyp6academy
 
What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1p6academy
 
Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2p6academy
 
Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2p6academy
 
What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1p6academy
 
What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1p6academy
 
What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1p6academy
 
What's New in Unifier 16.1
What's New in Unifier 16.1What's New in Unifier 16.1
What's New in Unifier 16.1p6academy
 
20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktopp6academy
 
Oracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 AnnouncedOracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 Announcedp6academy
 
Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1p6academy
 
P6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations OverviewP6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations Overviewp6academy
 
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM  (Web) Release 8 and laterAdministering Users, Access and Views in P6 EPPM  (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and laterp6academy
 
P6 Release 8 Installation Orientation
P6 Release 8 Installation OrientationP6 Release 8 Installation Orientation
P6 Release 8 Installation Orientationp6academy
 
Oracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value PropositionOracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value Propositionp6academy
 
Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition p6academy
 
Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)p6academy
 
Oracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study GuideOracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study Guidep6academy
 
Oracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study GuideOracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study Guidep6academy
 

Plus de p6academy (20)

Oracle OpenWorld 2015
Oracle OpenWorld 2015Oracle OpenWorld 2015
Oracle OpenWorld 2015
 
Plan and Execute the Right Projects— Easily and Affordably
Plan and Execute the Right Projects—  Easily and AffordablyPlan and Execute the Right Projects—  Easily and Affordably
Plan and Execute the Right Projects— Easily and Affordably
 
What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1
 
Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2
 
Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2
 
What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1
 
What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1
 
What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1
 
What's New in Unifier 16.1
What's New in Unifier 16.1What's New in Unifier 16.1
What's New in Unifier 16.1
 
20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop
 
Oracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 AnnouncedOracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 Announced
 
Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1
 
P6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations OverviewP6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations Overview
 
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM  (Web) Release 8 and laterAdministering Users, Access and Views in P6 EPPM  (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
 
P6 Release 8 Installation Orientation
P6 Release 8 Installation OrientationP6 Release 8 Installation Orientation
P6 Release 8 Installation Orientation
 
Oracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value PropositionOracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value Proposition
 
Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition
 
Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)
 
Oracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study GuideOracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study Guide
 
Oracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study GuideOracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study Guide
 

Dernier

KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 

Dernier (20)

KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 

Scheduling minimizing the input while maximizing the output white paper

  • 1. COLLABORATE 12    Page 1  Scheduling: Minimizing the input while maximizing the output Chris Ackerman, PMI-SP SSOE Group Rick Fox, PMP SSOE Group Have you ever spent an abundance of time and energy developing the perfect detailed schedule for a client, only to find out you have missed the mark? Perhaps you spelled out a specific project plan in great detail, incorporated valuable input from all project stakeholders, laid it out beautifully atop an 11x17 colored PDF and illustrated it with a Gantt chart showing relationship lines and a stair stepped critical path… only to receive a blank glare that says “what am I supposed to do with this?” At SSOE Group, an international engineering, architectural and consulting firm headquartered in Toledo Ohio, our opportunities to create, update and maintain project schedules range from the initial needs analysis through the detailed start up/commissioning phases. The schedules are often complex and require several iterations including high level milestone schedules used for initial planning and conclude with a detailed logic and resource driven project schedule. Often the required input comes from various places, both internally and externally, with resources that have widely varying degrees of knowledge about the time, effort and information it takes to create a logic driven schedule. Our presentation will show you some tips and tricks that we have found that help us both save time and effort utilizing P6 and allow for a schedule deliverable that is user friendly, less cumbersome to update, and capable of producing customizable reports to meet the client’s needs . We’ll showcase how SSOE, and subsequently our clients, have benefitted from software components such as user defined fields, activity steps, high level resources with custom resource curves, and level of effort/WBS summary activities. Let us help you turn those blank stares and thoughts of “what am I supposed to do with this” to a friendly smile and a “Perfect!” Objectives: Problem: The time consuming task of statusing a complex multi-phase schedule makes it difficult to provide complete project updates in a timely manner. Solution: Dividing large project schedules into smaller and more manageable related schedules allows for flexibility in updating. Furthermore, using activity steps can lessen the overall size and complexity of the schedule and dramatically lesson the effort required to advance the data date. Problem: Quickly and effectively resource loading a detailed schedule can be a time consuming and daunting task. Solution: Assigning resources to WBS Summary and Level of Effort activity types allows for greater flexibility. Concurrently, using high level resources and custom resource curves can increase one’s ability to quickly and effectively develop a resource plan. Problem: Using Primavera P6 standard reporting outputs on large schedules can produce lengthy reports that may contain more information than is required. Solution: Illustrate how using custom filters & user define fields can enhance reporting functionality and condense reporting output. Manageable Interlinked Schedules On projects with a large amount of scope to manage, maintaining a single project schedule can be daunting. Interlinking multiple schedules allows for assigning separate responsible parties for schedule updates, limiting the overall information that needs to be reviewed by each responsible party and eases the baselining process.
  • 2. COLLABORATE 12    Page 2  On multi-discipline/contractor projects, input is often required from multiple responsible parties to complete a schedule update. Breaking the project plan into individual schedules where scope is divided by responsible party allows for flexibility in updating schedule progress. (See Example 1 below) Example 1 Simultaneous updates can be made and schedules can be updated at separate times if information about specific areas in unknown or in question. This also assists in the risk analysis or what-if scenario breakdown. Another advantage of having interlinked schedules is baselining. As changes occur on the project, maintaining the plan can be a difficult task for schedules that incorporate a large amount of scope. The update baseline function has many options to sift through and not fully understanding all of the changes that are being made can result in lost data (See Example 2.1 and 2.2 below). The log, although useful, can contain more information than needed and information can be difficult to locate.
  • 3. COLLABORATE 12    Page 3  Example 2.1 Example 2.2 With schedules broken down by responsible party, new baselines can be assigned (See Example 3 below) as approved changes are made or the update baseline function can be used. Both are much easier on smaller schedules as there is less information to manage by a single responsible party.
  • 4. COLLABORATE 12    Page 4  Example 3 Activity Steps The use of activity steps within a project schedule is a useful method that allows you to keep all of the necessary details while minimizing the effort to understand and update the schedule. This method is best used when you have a number of activities that are of short duration, directly linked to each other, and all part of a larger task. For example, when scheduling the construction of foundations there are many activities that lead up to the pouring of concrete. If you included all of those activities as steps, and only one activity for foundations, the amount of maintenance needed to keep the schedule current is significantly reduced. This method produces a Gantt chart that is easily understood and can be used as a communication tool at all levels of a project (see Example 4 below). Example 4
  • 5. COLLABORATE 12    Page 5  Steps can also be used to expedite the creation of project schedules. Once a list of standard steps has been created, it can be stored as a template for future use. This gives you the ability to quickly create first pass project schedules with plenty of detail which can then be customized for project-specific needs (see Examples 5.1 through 5.3 below). Example 5.1 Example 5.2 Example 5.3 The use of activity steps also allows for schedules to be updated very efficiently. You have the option to hold traditional schedule update meetings or you can produce straightforward checklist reports that can be sent out to project stakeholders for comments (see Example 6 below). The comments can then be sent to project schedulers for input into the schedule. Also, these reports can be filtered to include only relevant activities for a given individual or group. This reduces time spent in meetings listening to information that may not apply and allows the responsible party the ability to update their activities without searching through a detailed project schedule to find them. Example 6
  • 6. COLLABORATE 12    Page 6  Activity Types and High-Level Resources and Curves WBS and Level of Effort (LOE) activity types are an efficient way to increase the ease of project creation, updating and reporting. This is enhanced when using high level resources with customized resource curves. By assigning resources to WBS and LOE activities, tracking of resource financials (budgets, actuals and forecasts) can be managed at a higher level and the information that may be required is still available for progressing and reporting (i.e. EV, CPI & SPI). As the schedule changes when resources are assigned at the task level the resource data need to be adjusted at that level. This requires that each of those revised activity’s resource financials needs to be updated and then reviewed for accuracy. WBS and LOE activities only need revised as activities are moved, added or deleted from the WBS or from the chain of activities the LOE is assigned to. In addition to assigning resources to WBS and LOE activity types, using high level resources such as job classification (i.e. Project Manager, Project Controller) or discipline level (i.e. Architect, Structural Engineer) versus named resources allows for easier schedule creation and updating. This is especially beneficial on large projects where resources are grouped by job classification or departments and an overall average rate and work calendar can be agreed upon. Using resources that are classified by job classification or discipline level can further be enhanced by using custom resource curves that are assigned at the project level. Resource curves, which are customizable, allow for historical information to be incorporated into plans so that a more accurate baseline schedule can be created and reported against. P6 Reporting Primavera standard reports tend to produce lengthy outputs with information that may be more than truly required. The standard reports can be used as starting points to help users generate ideas, or through the use of simple methods within the software, users can create project specific reports that can also be used as templates throughout an organization. All of the information needed for project reporting is already being generated through regular updating of the project schedule. The trick is creating a report that extracts required information into an understandable format for the end user. The quickest method for creating a new report is through the use of layouts. By creating a layout, with just the required information, through the use of filters and other user defined data, a report can quickly be generated through the use of the Report Wizard tool (see Examples 7.1 through 7.3 below).
  • 7. COLLABORATE 12    Page 7  Example 7.1 Example 7.2 Example 7.3     Once a report with the raw data has been created, the Modify report function can be used to depict the information in a customizable format. This function can be used to show information in a user friendly spreadsheet format; colors can be added to depict status or thresholds, custom graphics can be inserted to personalize reports, along with many other options that can enhance reporting output (see Examples 8.1 through 8.2 below). Example 8.1 
  • 8. COLLABORATE 12    Page 8  Example 8.2 These methods produce reports that give users a quick visual indication of status as well as the ability to review detailed information that may be required for a specific task. Conclusion It easily becomes overwhelming when you stop and consider the amount of time and effort it would take to create and manage detailed project schedules if programs like Primavera P6 weren’t available to assist you in that process. Tasks such as baseline variance analysis, resource planning, and project reporting, that take minutes or hours to complete in the software, would potentially take days to complete manually and the accuracy would be questionable at best. The methods mentioned above are just a few of the options available within the software that can be used to make planners, schedulers and project managers more efficient. In today’s culture of faster and cheaper, gaining efficiency is a great way to remain competitive in the marketplace which helps to achieve everyone’s goal of long- term success.