SlideShare une entreprise Scribd logo
1  sur  7
Télécharger pour lire hors ligne
TR0902: Report on matched-melt coordination as
      used for selecting windfarm fuses


                           By
                    Dan Gardner,
                    P.E., R&D Manager
           Hi-Tech, Thomas & Betts Corporation
TR0902: Report on matched-melt coordination as used for selecting windfarm fuses


WHAT IS MATCH-MELT COORDINATION?

Matched-melt coordination as defined in IEEE C37.48 is a variation of time-current curve
coordination that is used to ensure that the expulsion fuse melts open during any overload or
fault condition. As stated in IEEE C37.48,

The principal advantage of the matched-melt method is that the expulsion fuse will melt open
even if the current limiting fuse does the actual clearing. Because the expulsion fuse opens, the
current-limiting fuse is not likely to have the system’s voltage impressed across it after it has
operated.
The main advantage of this type of coordination is that in most three-phase applications, the
voltage rating of the backup current-limiting fuse need only be equal to the system’s line-to-
neutral voltage as long as the voltage rating of the expulsion fuse is equal to the system’s line-to-
line voltage.

WHAT DOES MATCHED-MELT COORDINATION HAVE TO DO WITH WINDFARM
TRANSFORMER PROTECTION?

Windfarm transformers are predominately 34.5kV and are delta-connected (or ungrounded).
IEEE C37.48 specifies that fuses used to protect ungrounded systems should have a maximum
voltage rating equal to or exceeding the maximum system L-L voltage. The only exception to
this rule allowed by the standard is when matched-melt coordination is used. As stated
previously, when matched-melt coordination requirements are met, L-N rated backup fuses can
often be used.
Until recently, no 38kV oil-submersible backup fuses were available. It was therefore not
possible to provide a L-L rated backup fuse for a 34.5kV delta-connected transformer. Matched-
melt coordination has therefore been used with the L-L rated 34.5kV ABB weak link expulsion
fuses to allow the use of 23kV backup fuses.

WHY IS IT CRITICAL THAT MATCHED-MELT COORDINATION REQUIREMENTS ARE
STRICTLY OBSERVED IN DELTA-CONNECTED WINDFARM APPLICATIONS IF L-N
RATED BACKUP FUSES ARE TO BE USED?

Due to the nature of a windfarm application, a number of conditions exist that are not explicitly
covered in IEEE C37.48 as it focuses on distribution transformer protection. Most importantly, in
a windfarm application, both sides of the transformer are “active”, meaning that a fault can be
fed from either side, the generator on the low voltage side and the collector system on the high
voltage side (this as opposed to a distribution transformer application where the load side of the
transformer is “passive”).
When a fault occurs causing the fusing on the 34.5kV side of the transformer to operate, a brief
period of de-synchronization can occur between the phase voltages on the generator side of the
transformer and the phase voltages on the collector side of the transformer. The phase voltages
can move out of sync until such a time as the generator protection opens, entirely isolating the
transformer. During this period of time, the voltage across the open fuses could be on the
magnitude of twice system L-L voltage.
The long oil gap that results in the open ABB 34.5kV weak link appears to be able to withstand
this voltage until the breaker on the low voltage side of the transformer operates, often sharing
that duty with the open backup fuse. There is not sufficient testing or experience to show that an
L-N rated backup fuse could withstand what could be on the order of three times its rated
voltage alone, even if it did initially interrupt.



                                                                                                        2
TR0902: Report on matched-melt coordination as used for selecting windfarm fuses



WHAT IS REQUIRED TO ACHIEVE MATCH-MELT COORDINATION WITH THE ABB 34.5KV
WEAK LINKS?

In addition to meeting all requirements needed for time-current curve crossover coordination as
specified in IEEE C37.48, there are two other requirements that must be met:

1. The first requirement is that one must ensure that the expulsion fuse melts open any time
   the two fuse combination clears an overload or fault. IEEE C37.48 states that

Coordination can be realized as long as the maximum melting I2t of the expulsion fuse does not
exceed approximately twice the minimum melting I2t of the current-limiting fuse.

While the minimum melting I2t for backup fuses is readily available in published literature, the
maximum melt I2t for expulsion fuses is not so readily available. IEEE C37.48 therefore
recommends a method for calculating this value from the minimum melting curves of the
expulsion fuses as stated below
One method of calculation involves first determining the current corresponding to the value of
time representing the fewest whole numbers of quarter-cycles. For many published curves this
might be the current corresponding to three (3) quarter cycles (0.0125 s). Once the current has
been determined from the expulsion fuse’s minimum melting curve, it should be increased by an
appropriate factor to take into account variations resulting from manufacturing tolerances. In
the case of expulsion fuses having silver elements, this factor is 10%. For fuses with elements
made from other materials, this factor is normally 20%. After the current has been corrected to
allow for manufacturing tolerances, the maximum melting I 2t of the expulsion fuse can be
calculated by first squaring this current and then multiplying that value by the time (expressed in
seconds) that was the basis for determining the current.

However, while this method works well for many types of expulsion fuses, it cannot be used to
calculate the maximum melt I2t of the ABB 34.5kV weak link fuses that are used in Windfarm
applications. This is because C37.48 assumes that published curves meet the requirements set
forth in IEEE C37.47 which states that

When publishing time current curves, the maximum melting current shall not exceed the
minimum melting current by more than 20% for any given melting time.

The ABB weak link curves were published well before the present IEEE standards and therefore
do not meet the above requirement as it did not exist. In some cases, the margins on the
published ABB curves are as large as 60%. They also publish an average clearing curve as
opposed to the total clearing curve required by the present standards. Their average clearing
curve must be shifted by 10% to the right in order to model the total clearing curve needed to
perform time-current curve crossover coordination per C37.48. Using the published ABB
minimum melting curves to calculate their maximum melting I2t will result in values that can be
off by a factor of almost two.
Maximum melting I2t values for the ABB weak links must therefore be obtained through other
means. An example of this for the ABB #9 weak link can be seen in Appendix I.

2. The second requirement is one that is specific to applications where match-melt
   coordination is used to coordinate fuses used in pad-mounted transformers due to the very



                                                                                                      3
TR0902: Report on matched-melt coordination as used for selecting windfarm fuses


   low maximum interrupting currents of the expulsion fuses in such applications. Specifically,
   matched-melt coordination as specified in IEEE C37.48 assumes that the current-limiting
   fuses being used will be melting in the first loop of fault current at the maximum interrupting
   current of the expulsion fuse.

When this is not the case, additional testing on the L-N rated backup fuses is needed to show
that they can interrupt L-L voltage at currents that cause melting in times longer than 1 loop
down to a current equal to the maximum interrupting current of the expulsion fuse.

It is well-known that two L-N rated current-limiting fuses (one from each phase) will melt
simultaneously and share the interruption duty to interrupt a L-L fault when operating in their
current-limiting mode (i.e. melting during the first loop of fault current); hence the assumption
made in the standard as described in the preceding paragraph. However, at longer melting
times, conditions can occur due to slight differences in fuse tolerances or starting temperatures
that will result in one fuse melting slightly ahead of the other.
When a fuse in one phase melts even slightly ahead of the fuse in another phase, the
resistance that it introduces into the circuit will cause the current to drop significantly, and the
second fuse may not melt in time to share in the interruption. It is therefore imperative that any
L-N rated backup fuse that might be matched-melt coordinated with the ABB weak links is
shown to be capable of interrupting L-L voltage by itself (as a single fuse) from 1200A (the
maximum interrupting current of the ABB 34.5kV expulsion fuses) up to a current that is high
enough to ensure that the fuses from each phase on a L-L fault will always melt together and
share the interruption duty, regardless of the slight variations described above.

WHAT BACKUP FUSES ARE AVAILABLE TODAY THAT MEET BOTH OF THE
REQUIREMENTS DISCUSSED ABOVE FOR THE ABB #8 AND #9 WEAK LINKS?

In addition to the windfarm specific testing described in the second requirement above, any
backup fuse that is to be used should have a published melt I2t that is greater than the values
listed in the table below in order to meet match-melt coordination requirements per IEEE
C37.48.




                                                                                                       4
TR0902: Report on matched-melt coordination as used for selecting windfarm fuses



T&B Hi-Tech has performed the testing as described in the second requirement above on fuse
ratings that meet match-melt coordination requirements for both the #8 and #9 weak links. The
Hi-Tech HTDS352100 fuse has been tested and match-melt coordinates with the ABB #8 weak
links. The 2xHTSS252100 fuses have been tested and match-melt coordinates with the ABB #9
weak links. Full test reports that show how the fuses were tested are available. A competitor is
now also claiming to have performed the extra testing required on some of their backup fuse
ratings to allow them to be used on windfarm applications. However, some of the fuses they
claim meet match-melt coordination requirements with the ABB #8 and #9 weak links do not
meet the key requirement needed to achieve match-melt coordination as specified by the IEEE
because the competitor used the published ABB curves to calculate the maximum melt I2t’s of
the ABB links. An example of the recommendation that is being made using the #9 ABB weak
link, and why that recommendation is not suitable and does not indeed meet IEEE specified
requirements for match-melt coordination, is shown in Appendix II. The size of the competitor’s
fuse that would be needed to meet match-melt coordination requirements with the #9 weak link
has not had any of the additional testing performed on it and has therefore not been shown to
be suitable for windfarm applications at this time.




                                                                                                   5
TR0902: Report on matched-melt coordination as used for selecting windfarm fuses




                                                                                   6
TR0902: Report on matched-melt coordination as used for selecting windfarm fuses




                                                                                   7

Contenu connexe

Tendances

Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformersLeonardo ENERGY
 
Tan delta test for power transformers
Tan delta test for power transformersTan delta test for power transformers
Tan delta test for power transformersjibinjoy1988
 
69726637-Ppt-on-Transformer
69726637-Ppt-on-Transformer69726637-Ppt-on-Transformer
69726637-Ppt-on-TransformerMurshedur Rahman
 
Grounding pad mounted transformers
Grounding   pad mounted transformersGrounding   pad mounted transformers
Grounding pad mounted transformersJimmy Chaparro
 
Sumpners Test of Transformers
Sumpners Test of TransformersSumpners Test of Transformers
Sumpners Test of TransformersGirin Chutia
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.Geetesh Verma
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer ProtectionAng Sovann
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in briefMuthar Hussain
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHShankar Singh
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta testDonald Stephen
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protectionBinit Das
 
Impulse test for power transformers
Impulse test for power transformersImpulse test for power transformers
Impulse test for power transformersjibinjoy1988
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersLiving Online
 
open circuit and short circuit test on transformer
open circuit and short circuit test on transformeropen circuit and short circuit test on transformer
open circuit and short circuit test on transformerMILAN MANAVAR
 
Power transformer
Power transformerPower transformer
Power transformerZunAib Ali
 

Tendances (20)

Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformers
 
Tan delta test for power transformers
Tan delta test for power transformersTan delta test for power transformers
Tan delta test for power transformers
 
Circuit breakers
Circuit breakersCircuit breakers
Circuit breakers
 
69726637-Ppt-on-Transformer
69726637-Ppt-on-Transformer69726637-Ppt-on-Transformer
69726637-Ppt-on-Transformer
 
Grounding pad mounted transformers
Grounding   pad mounted transformersGrounding   pad mounted transformers
Grounding pad mounted transformers
 
Sumpners Test of Transformers
Sumpners Test of TransformersSumpners Test of Transformers
Sumpners Test of Transformers
 
Auto transformer
Auto transformerAuto transformer
Auto transformer
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
 
TRANSFORMERS
TRANSFORMERSTRANSFORMERS
TRANSFORMERS
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta test
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protection
 
Low voltage switchgear ppt
Low voltage switchgear pptLow voltage switchgear ppt
Low voltage switchgear ppt
 
Impulse test for power transformers
Impulse test for power transformersImpulse test for power transformers
Impulse test for power transformers
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
AIR FLOW DETECTOR SYSTEM
AIR FLOW DETECTOR SYSTEMAIR FLOW DETECTOR SYSTEM
AIR FLOW DETECTOR SYSTEM
 
open circuit and short circuit test on transformer
open circuit and short circuit test on transformeropen circuit and short circuit test on transformer
open circuit and short circuit test on transformer
 
Power transformer
Power transformerPower transformer
Power transformer
 

En vedette

Unique Role Of Wtsu Transformers
Unique Role Of Wtsu TransformersUnique Role Of Wtsu Transformers
Unique Role Of Wtsu Transformerspacificcresttrans
 
Pct Solution For Emerging Energy Markets
Pct Solution For Emerging Energy MarketsPct Solution For Emerging Energy Markets
Pct Solution For Emerging Energy Marketspacificcresttrans
 
Datasheet Padmount Transformer
Datasheet Padmount TransformerDatasheet Padmount Transformer
Datasheet Padmount Transformerpacificcresttrans
 
Pacific Crest Transformers - On Going Green
Pacific Crest Transformers - On Going GreenPacific Crest Transformers - On Going Green
Pacific Crest Transformers - On Going Greenpacificcresttrans
 

En vedette (6)

Unique Role Of Wtsu Transformers
Unique Role Of Wtsu TransformersUnique Role Of Wtsu Transformers
Unique Role Of Wtsu Transformers
 
Unique Role Wind Turbine
Unique Role Wind TurbineUnique Role Wind Turbine
Unique Role Wind Turbine
 
Pct Solution For Emerging Energy Markets
Pct Solution For Emerging Energy MarketsPct Solution For Emerging Energy Markets
Pct Solution For Emerging Energy Markets
 
Transformer Smart Grid
Transformer Smart GridTransformer Smart Grid
Transformer Smart Grid
 
Datasheet Padmount Transformer
Datasheet Padmount TransformerDatasheet Padmount Transformer
Datasheet Padmount Transformer
 
Pacific Crest Transformers - On Going Green
Pacific Crest Transformers - On Going GreenPacific Crest Transformers - On Going Green
Pacific Crest Transformers - On Going Green
 

Similaire à Report on matched-melt coordination as used for selecting windfarm fuses

Application data explusion links
Application data explusion linksApplication data explusion links
Application data explusion linksing_eliali4748
 
Ansi mv tech_topics43_en
Ansi mv tech_topics43_enAnsi mv tech_topics43_en
Ansi mv tech_topics43_enANURAG GUPTA
 
transformerdesignandprotection-130408132534-phpapp02.ppt
transformerdesignandprotection-130408132534-phpapp02.ppttransformerdesignandprotection-130408132534-phpapp02.ppt
transformerdesignandprotection-130408132534-phpapp02.pptThien Phan Bản
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformerRitesh Verma
 
2003 09-08 joeck icefa fuse protection in transformer pole substation
2003 09-08 joeck icefa fuse protection in transformer pole substation2003 09-08 joeck icefa fuse protection in transformer pole substation
2003 09-08 joeck icefa fuse protection in transformer pole substationRemigiusz Joeck
 
Parametros diodos
Parametros diodosParametros diodos
Parametros diodosKarenCo12
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & MaintenanceHimansu Pradhan
 
Transformer Protection Fundamentals
Transformer Protection FundamentalsTransformer Protection Fundamentals
Transformer Protection FundamentalsHarjit Birdi
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardIJAPEJOURNAL
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculationsRonald Santos
 
Busbar protection LEC 2.pptx
Busbar protection LEC 2.pptxBusbar protection LEC 2.pptx
Busbar protection LEC 2.pptxRahaf Waheep
 
Relay operation principles
Relay operation principlesRelay operation principles
Relay operation principlesAmmar Al Hakeim
 
The sheath voltage_limiter
The sheath voltage_limiterThe sheath voltage_limiter
The sheath voltage_limiterGilberto Mejía
 
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...IRJET Journal
 
Multi-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital CircuitsMulti-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital CircuitsIRJET Journal
 

Similaire à Report on matched-melt coordination as used for selecting windfarm fuses (20)

Application data explusion links
Application data explusion linksApplication data explusion links
Application data explusion links
 
7PG2111 Solkor Relay
7PG2111 Solkor Relay7PG2111 Solkor Relay
7PG2111 Solkor Relay
 
How to build a Inverters
How to build a InvertersHow to build a Inverters
How to build a Inverters
 
Ansi mv tech_topics43_en
Ansi mv tech_topics43_enAnsi mv tech_topics43_en
Ansi mv tech_topics43_en
 
transformerdesignandprotection-130408132534-phpapp02.ppt
transformerdesignandprotection-130408132534-phpapp02.ppttransformerdesignandprotection-130408132534-phpapp02.ppt
transformerdesignandprotection-130408132534-phpapp02.ppt
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformer
 
2003 09-08 joeck icefa fuse protection in transformer pole substation
2003 09-08 joeck icefa fuse protection in transformer pole substation2003 09-08 joeck icefa fuse protection in transformer pole substation
2003 09-08 joeck icefa fuse protection in transformer pole substation
 
Thông số kĩ thuật siemens fuse 001
Thông số kĩ thuật siemens fuse 001Thông số kĩ thuật siemens fuse 001
Thông số kĩ thuật siemens fuse 001
 
Parametros diodos
Parametros diodosParametros diodos
Parametros diodos
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Transformer Protection Fundamentals
Transformer Protection FundamentalsTransformer Protection Fundamentals
Transformer Protection Fundamentals
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazard
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculations
 
Busbar protection LEC 2.pptx
Busbar protection LEC 2.pptxBusbar protection LEC 2.pptx
Busbar protection LEC 2.pptx
 
Relay operation principles
Relay operation principlesRelay operation principles
Relay operation principles
 
The sheath voltage_limiter
The sheath voltage_limiterThe sheath voltage_limiter
The sheath voltage_limiter
 
Get 8402
Get 8402Get 8402
Get 8402
 
Dp35648654
Dp35648654Dp35648654
Dp35648654
 
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...
 
Multi-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital CircuitsMulti-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital Circuits
 

Dernier

Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxBkGupta21
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESmohitsingh558521
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 

Dernier (20)

Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptx
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 

Report on matched-melt coordination as used for selecting windfarm fuses

  • 1. TR0902: Report on matched-melt coordination as used for selecting windfarm fuses By Dan Gardner, P.E., R&D Manager Hi-Tech, Thomas & Betts Corporation
  • 2. TR0902: Report on matched-melt coordination as used for selecting windfarm fuses WHAT IS MATCH-MELT COORDINATION? Matched-melt coordination as defined in IEEE C37.48 is a variation of time-current curve coordination that is used to ensure that the expulsion fuse melts open during any overload or fault condition. As stated in IEEE C37.48, The principal advantage of the matched-melt method is that the expulsion fuse will melt open even if the current limiting fuse does the actual clearing. Because the expulsion fuse opens, the current-limiting fuse is not likely to have the system’s voltage impressed across it after it has operated. The main advantage of this type of coordination is that in most three-phase applications, the voltage rating of the backup current-limiting fuse need only be equal to the system’s line-to- neutral voltage as long as the voltage rating of the expulsion fuse is equal to the system’s line-to- line voltage. WHAT DOES MATCHED-MELT COORDINATION HAVE TO DO WITH WINDFARM TRANSFORMER PROTECTION? Windfarm transformers are predominately 34.5kV and are delta-connected (or ungrounded). IEEE C37.48 specifies that fuses used to protect ungrounded systems should have a maximum voltage rating equal to or exceeding the maximum system L-L voltage. The only exception to this rule allowed by the standard is when matched-melt coordination is used. As stated previously, when matched-melt coordination requirements are met, L-N rated backup fuses can often be used. Until recently, no 38kV oil-submersible backup fuses were available. It was therefore not possible to provide a L-L rated backup fuse for a 34.5kV delta-connected transformer. Matched- melt coordination has therefore been used with the L-L rated 34.5kV ABB weak link expulsion fuses to allow the use of 23kV backup fuses. WHY IS IT CRITICAL THAT MATCHED-MELT COORDINATION REQUIREMENTS ARE STRICTLY OBSERVED IN DELTA-CONNECTED WINDFARM APPLICATIONS IF L-N RATED BACKUP FUSES ARE TO BE USED? Due to the nature of a windfarm application, a number of conditions exist that are not explicitly covered in IEEE C37.48 as it focuses on distribution transformer protection. Most importantly, in a windfarm application, both sides of the transformer are “active”, meaning that a fault can be fed from either side, the generator on the low voltage side and the collector system on the high voltage side (this as opposed to a distribution transformer application where the load side of the transformer is “passive”). When a fault occurs causing the fusing on the 34.5kV side of the transformer to operate, a brief period of de-synchronization can occur between the phase voltages on the generator side of the transformer and the phase voltages on the collector side of the transformer. The phase voltages can move out of sync until such a time as the generator protection opens, entirely isolating the transformer. During this period of time, the voltage across the open fuses could be on the magnitude of twice system L-L voltage. The long oil gap that results in the open ABB 34.5kV weak link appears to be able to withstand this voltage until the breaker on the low voltage side of the transformer operates, often sharing that duty with the open backup fuse. There is not sufficient testing or experience to show that an L-N rated backup fuse could withstand what could be on the order of three times its rated voltage alone, even if it did initially interrupt. 2
  • 3. TR0902: Report on matched-melt coordination as used for selecting windfarm fuses WHAT IS REQUIRED TO ACHIEVE MATCH-MELT COORDINATION WITH THE ABB 34.5KV WEAK LINKS? In addition to meeting all requirements needed for time-current curve crossover coordination as specified in IEEE C37.48, there are two other requirements that must be met: 1. The first requirement is that one must ensure that the expulsion fuse melts open any time the two fuse combination clears an overload or fault. IEEE C37.48 states that Coordination can be realized as long as the maximum melting I2t of the expulsion fuse does not exceed approximately twice the minimum melting I2t of the current-limiting fuse. While the minimum melting I2t for backup fuses is readily available in published literature, the maximum melt I2t for expulsion fuses is not so readily available. IEEE C37.48 therefore recommends a method for calculating this value from the minimum melting curves of the expulsion fuses as stated below One method of calculation involves first determining the current corresponding to the value of time representing the fewest whole numbers of quarter-cycles. For many published curves this might be the current corresponding to three (3) quarter cycles (0.0125 s). Once the current has been determined from the expulsion fuse’s minimum melting curve, it should be increased by an appropriate factor to take into account variations resulting from manufacturing tolerances. In the case of expulsion fuses having silver elements, this factor is 10%. For fuses with elements made from other materials, this factor is normally 20%. After the current has been corrected to allow for manufacturing tolerances, the maximum melting I 2t of the expulsion fuse can be calculated by first squaring this current and then multiplying that value by the time (expressed in seconds) that was the basis for determining the current. However, while this method works well for many types of expulsion fuses, it cannot be used to calculate the maximum melt I2t of the ABB 34.5kV weak link fuses that are used in Windfarm applications. This is because C37.48 assumes that published curves meet the requirements set forth in IEEE C37.47 which states that When publishing time current curves, the maximum melting current shall not exceed the minimum melting current by more than 20% for any given melting time. The ABB weak link curves were published well before the present IEEE standards and therefore do not meet the above requirement as it did not exist. In some cases, the margins on the published ABB curves are as large as 60%. They also publish an average clearing curve as opposed to the total clearing curve required by the present standards. Their average clearing curve must be shifted by 10% to the right in order to model the total clearing curve needed to perform time-current curve crossover coordination per C37.48. Using the published ABB minimum melting curves to calculate their maximum melting I2t will result in values that can be off by a factor of almost two. Maximum melting I2t values for the ABB weak links must therefore be obtained through other means. An example of this for the ABB #9 weak link can be seen in Appendix I. 2. The second requirement is one that is specific to applications where match-melt coordination is used to coordinate fuses used in pad-mounted transformers due to the very 3
  • 4. TR0902: Report on matched-melt coordination as used for selecting windfarm fuses low maximum interrupting currents of the expulsion fuses in such applications. Specifically, matched-melt coordination as specified in IEEE C37.48 assumes that the current-limiting fuses being used will be melting in the first loop of fault current at the maximum interrupting current of the expulsion fuse. When this is not the case, additional testing on the L-N rated backup fuses is needed to show that they can interrupt L-L voltage at currents that cause melting in times longer than 1 loop down to a current equal to the maximum interrupting current of the expulsion fuse. It is well-known that two L-N rated current-limiting fuses (one from each phase) will melt simultaneously and share the interruption duty to interrupt a L-L fault when operating in their current-limiting mode (i.e. melting during the first loop of fault current); hence the assumption made in the standard as described in the preceding paragraph. However, at longer melting times, conditions can occur due to slight differences in fuse tolerances or starting temperatures that will result in one fuse melting slightly ahead of the other. When a fuse in one phase melts even slightly ahead of the fuse in another phase, the resistance that it introduces into the circuit will cause the current to drop significantly, and the second fuse may not melt in time to share in the interruption. It is therefore imperative that any L-N rated backup fuse that might be matched-melt coordinated with the ABB weak links is shown to be capable of interrupting L-L voltage by itself (as a single fuse) from 1200A (the maximum interrupting current of the ABB 34.5kV expulsion fuses) up to a current that is high enough to ensure that the fuses from each phase on a L-L fault will always melt together and share the interruption duty, regardless of the slight variations described above. WHAT BACKUP FUSES ARE AVAILABLE TODAY THAT MEET BOTH OF THE REQUIREMENTS DISCUSSED ABOVE FOR THE ABB #8 AND #9 WEAK LINKS? In addition to the windfarm specific testing described in the second requirement above, any backup fuse that is to be used should have a published melt I2t that is greater than the values listed in the table below in order to meet match-melt coordination requirements per IEEE C37.48. 4
  • 5. TR0902: Report on matched-melt coordination as used for selecting windfarm fuses T&B Hi-Tech has performed the testing as described in the second requirement above on fuse ratings that meet match-melt coordination requirements for both the #8 and #9 weak links. The Hi-Tech HTDS352100 fuse has been tested and match-melt coordinates with the ABB #8 weak links. The 2xHTSS252100 fuses have been tested and match-melt coordinates with the ABB #9 weak links. Full test reports that show how the fuses were tested are available. A competitor is now also claiming to have performed the extra testing required on some of their backup fuse ratings to allow them to be used on windfarm applications. However, some of the fuses they claim meet match-melt coordination requirements with the ABB #8 and #9 weak links do not meet the key requirement needed to achieve match-melt coordination as specified by the IEEE because the competitor used the published ABB curves to calculate the maximum melt I2t’s of the ABB links. An example of the recommendation that is being made using the #9 ABB weak link, and why that recommendation is not suitable and does not indeed meet IEEE specified requirements for match-melt coordination, is shown in Appendix II. The size of the competitor’s fuse that would be needed to meet match-melt coordination requirements with the #9 weak link has not had any of the additional testing performed on it and has therefore not been shown to be suitable for windfarm applications at this time. 5
  • 6. TR0902: Report on matched-melt coordination as used for selecting windfarm fuses 6
  • 7. TR0902: Report on matched-melt coordination as used for selecting windfarm fuses 7