// Baseline Compliance Analysis
          A True Measure of How Well a Project is Performing




         Dr. Dan Patterson, PMP
          CEO & President, Acumen

                June 2011




                        +1 512 291 6261 // info@projectacumen.com

                                 www.projectacumen.com
Table of Contents
  	
  
  Introduction ................................................................................................................. 3	
  
  Traditional Project Performance Techniques ................................................................ 3	
  
  Percent Complete ......................................................................................................... 3	
  
  Earned Value & Earned Schedule ................................................................................. 3	
  
  Introducing Baseline Compliance Analysis .................................................................. 4	
  
         Figure 1 – Early, On-Time, Late Scenarios ........................................................... 5	
  
  How Is Baseline Compliance Measured? ...................................................................... 5	
  
         Figure 2 – Example Schedule ............................................................................... 6	
  
         Figure 3 – Metrics Applied to the Baseline Schedule ........................................... 6	
  
         Figure 4 – Baseline Metrics Applied to the Schedule ........................................... 7	
  
         Figure 5 – Updated, Statused Schedule Showing Baseline Comparison .............. 7	
  
         Figure 6 – Metrics Applied to the Actual Schedule ............................................... 8	
  
         Figure 7 – Compliance Calculations .................................................................... 9	
  
         Figure 8 – Compliance Trending ........................................................................ 10	
  
  Conclusion ................................................................................................................. 10	
  




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                       2	
  
                                                                                                                                     	
  
                                                                                                                                     	
  
Introduction
This paper describes a technique for determining how well a project is performing
relative to an agreed upon plan (often known as a baseline). Overcoming some of the
limitations of traditional performance tracking, this new approach puts an emphasis on
identifying how much variance from the plan occurs over time. Further enhancing this
valuable insight, is the ability to apply this analysis technique to different groupings or
sections of a project and determine which of these best complies with the project plan.
In summary: this approach allows for a quick determination of whether your project is
being executed as planned, and if not, where the areas and time periods of non-
compliance are.

The technique is applicable to both project execution as well as post-execution for
keeping the project on track and determining lessons learned. It is also a powerful
means of understanding root cause of project delays during a project forensics
exercise.


Traditional Project Performance Techniques
There are numerous techniques for tracking the performance of a project: that is “how
well is the project being executed relative to a given plan of work?” This can be relative
to project expenditure or project schedule or even quality of the project deliverable.

Percent Complete
The most simplistic measure of performance or status is to track projects using what is
known as percent complete. While there are many variations around the calculation of
percent complete, the basic premise is to track performance by determining how much
work, progress or time relative to a given quantity has been achieved.

While a common technique, it is widely seen as falling short with regards to true
performance tracking as it does not give any indication as to the context of the
progress. For example, if an activity is 90% complete, it cannot be determined from this
metric alone whether performance is good or bad – the activity may be very close to
completion but months later than expected.

Earned Value & Earned Schedule
Earned value is a cost-based measure that compares three bases (planned, earned and
actual) within a project so as to determine relative performance indicators. By
comparing how much work or progress has been achieved (earned) with how much
should have been achieved (planned), and additionally with how much it took to achieve


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       3	
  
                                                                                              	
  
                                                                                              	
  
this status (actual) we are able to determine performance factors and ratios that give
insight as to whether performance is better or worse than planned.

Unfortunately, earned value is a cost-based measure only and the effort required to
capture the data for the three bases can be seen as a drawback to this method.

For those projects that are wanting to track schedule performance using an earned
value-type approach, there is the option known as Earned-Schedule. Similar to Earned
Value, earned schedule looks at how much progress has been achieved (earned)
relative to how much was planned, with regards to the schedule.

While earned schedule provides schedule-based performance insight it suffers from a
shared issue also found with earned value. Neither Earned Value nor Earned Schedule
actually enable us to determine how close to the (baseline) plan did the execution of the
project actually fall. Instead these two techniques focus on execution efficiency. Net
efficiency on a project may calculate at 100% but what if the sequence of work was
executed completely out of sync from the plan, for example?

So you may be wondering “so what if the sequence of execution was not to plan or so
what if half the activities were delayed and the other half were early – the net result was
a successful project right?” Wrong… The whole purpose of project management is to
set a realistic plan and then use this plan to accurately track execution through to
completion. If compliance to the plan is not upheld then the likes of delays, disputes
regarding payment milestones, potential litigation surrounding cause and effect of
change all become too commonplace in a project. These “To-be-avoided pitfalls” are
the reason behind using baseline compliance analysis.


Introducing Baseline Compliance Analysis
Baseline Compliance Analysis compares (on a per-period basis) what was originally
planned and what is actual reality in the current schedule. By examining variance
surrounding activity starts and finishes relative to a given basis (baseline), this approach
provides insight as to whether the project is being executed to plan or alternatively
suffering from delayed starts and/or delayed completions.

A fundamental aspect to the analysis is that the comparison is not simply a “is the
current activity date later than it’s corresponding baseline date?” Instead, phases or
periods of time are used as thresholds to capture whether an activity is early, late or on-
time. For example, if running an analysis based on months on an activity that was
scheduled to start on March 5th and didn’t start until March 31st, this activity would still
be classified as “starting on time” within the context of the monthly reporting cycle.


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       4	
  
                                                                                               	
  
                                                                                               	
  
Figure 1 shows the 5 different outcomes from a baseline compliance analysis for a
single activity. These are all measured using start and finish variance.




                          Figure 1 – Early, On-Time, Late Scenarios

The results of the baseline compliance analysis are then summarized using compliance
metrics:

    •   Start compliance is a measure of how many activities start on time relative to a
        given baseline (within the confines of a given phase such as months). This gives
        insight into the knock-on effect of previous period delays. If start compliance is
        low, then few activities are able to start on time due to their predecessors
        causing delay.
    •   Finish compliance is a measure of how many activities finish on time relative to
        a given baseline (within the confines of a given phase such as months). This is a
        strong indicator of execution performance.

How Is Baseline Compliance Measured?
Consider a baseline schedule as shown in Figure 2. The schedule contains ten
activities. There are two paths through the network.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       5	
  
                                                                                             	
  
                                                                                             	
  
Figure 2 – Example Schedule

Firstly, metrics pertaining to the baseline are calculated so as to create a basis:
    1. Scheduled to Start: # of activities scheduled to start in a given period
    2. Scheduled to Finish: # of activities scheduled to finish in a given period

Figure 3 shows these two metrics applied to each monthly period.




                    Figure 3 – Metrics Applied to the Baseline Schedule

Figure 4 shows how the two scheduled to start/finish metrics vary per month.
Interestingly, while several activities span the month of April (Figure 3), none are
planned to either actually start or finish in this month (Figure 4).




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       6	
  
                                                                                       	
  
                                                                                       	
  
5	
  
                 4	
                                         4	
      4	
                                              4	
  
         4	
  
                                                                              Scheduled	
  to	
  Start	
  
                                                                              Scheduled	
  to	
  Finish	
  
         3	
  
                           2	
                                                                                2	
  
         2	
  
                                    1	
      1	
  
         1	
  
                                                                                0	
      0	
  
         0	
  
                  Jan-­‐11	
        Feb-­‐11	
               Mar-­‐11	
         Apr-­‐11	
                    May-­‐11	
  

                         Figure 4 – Baseline Metrics Applied to the Schedule

Now consider an updated version of the schedule created during execution. Changes
have occurred with regards to the sequence, duration and dates of the activities in the
schedule. This results in a schedule very different to the baseline (see figure 5).




         Figure 5 – Updated, Statused Schedule Showing Baseline Comparison

When the equivalent metrics for number of starts and number of finishes are applied to
the updated schedule so as to calculate early, on-time and late starts and finishes, the
result is very different (Figure 6).




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                7	
  
                                                                                                                               	
  
                                                                                                                               	
  
Figure 6 – Metrics Applied to the Actual Schedule

Once the metric analysis has been completed, Baseline Start and Finish Compliance
can quickly be calculated as a percentage of activities that uphold the baseline (i.e.
those activities that don’t trigger a start or finish variance). Figure 7 shows a summary
of these results.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       8	
  
                                                                                            	
  
                                                                                            	
  
Feb-   Mar-   Apr-   May-   TOTA
Group          Metric                       Jan-11          11    11     11     11       L
Baseline       Scheduled/Baselined to
               Start                                  4      1     4      0       1      10
               Scheduled/Baselined to
               Finish                                 2      1     4      0       3      10
Updated        Start/ed                               2      4     1      2       1      10
Schedule       Finish/ed                              1      3     1      3       2      10
Statistics     Start/ed on Time                       2      0     0      0       1       3
               Start/ed Early                         0      0     2      0       0       2
               Start/ed Late                          2      1     2      0       0       5
               Finish/ed on Time                      1      1     1      0       2       5
               Finish/ed Early                        0      0     1      0       1       2
               Finish/ed Late                         1      0     2      0       0       3
               Start/ed on Time,
               Finish/ed Late                         0      0     1      0       0       0
Compliance     Start Variance                         2      1     4      0       0       7
               Cum Start Variance                     2      3     7      7       7
               Start Compliance                     50%    0%     0%    N/A    100%    30%
               Finish Variance                        1      0     3      0       1       5
               Cum Finish Variance                    1      1     4      4       5
               Finish Compliance                    50%   100%   25%    N/A    67%     50%

                             Figure 7 – Compliance Calculations

Multiple conclusions can be drawn from Figure 7:
           • Start compliance started off at 50% in January and continued to slip
               through to the last month of the project.
           • Finish compliance actually improved to perfection in February (100%)
               before massively falling behind in March (25%)
           • Overall start compliance was only 30% compared to overall finish
               compliance of 50%. This shows that while start compliance was low, the
               project actually finished more activities ‘on-time’
           • April was forecasted as a month with no starts and no finishes and yet it
               actually experienced 2 unplanned starts and 3 unplanned finishes.

When start and finish variance is plotted on a cumulative timescale (Figure 8), it can be
seen that the start variance is getting worse at a faster rate than finish variance. Hence,
the project is showing signs of being able to complete closer to on-time despite an
increasing number of start delays.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       9	
  
                                                                                              	
  
                                                                                              	
  
9	
  
 8	
  
 7	
  
 6	
  
                                                                                           Start	
  Variance	
  
 5	
  
                                                                                           Finish	
  Variance	
  
 4	
  
                                                                                           Linear	
  (Start	
  Variance)	
  
 3	
  
                                                                                           Linear	
  (Finish	
  Variance)	
  
 2	
  
 1	
  
 0	
  
         Jan-­‐11	
     Feb-­‐11	
       Mar-­‐11	
          Apr-­‐11	
     May-­‐11	
  

                                       Figure 8 – Compliance Trending


Conclusion
Baseline compliance is an effective means of determining how well a project is able to
perform relative to a given baseline. By determining the number of activities that either
start or finish within a given forecasted range, we are able to get a better understanding
as to where and when compliance is falling short. Once this insight is gained, we then
have a much better chance of proactively focusing on those activities that require
remediation and acceleration. Looking at baseline compliance over time and by WBS
groupings gives even further insight into schedule hotspots and performance
bottlenecks.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                   10	
  
                                                                                                                       	
  
                                                                                                                       	
  

Contenu connexe

Tendances

Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokaya
Discover JKUAT
 

Tendances (20)

Faster, Yet Less Risky Projects through Goal-Based Schedule Acceleration
Faster, Yet Less Risky Projects through Goal-Based Schedule AccelerationFaster, Yet Less Risky Projects through Goal-Based Schedule Acceleration
Faster, Yet Less Risky Projects through Goal-Based Schedule Acceleration
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact Analysis
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Primavera P6
Primavera P6Primavera P6
Primavera P6
 
A guide to create a quality project schedule
A guide to create a quality project scheduleA guide to create a quality project schedule
A guide to create a quality project schedule
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
SanDiegoPresentation
SanDiegoPresentationSanDiegoPresentation
SanDiegoPresentation
 
PERT MBO GANTT CHART
PERT MBO GANTT CHARTPERT MBO GANTT CHART
PERT MBO GANTT CHART
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
PERT
PERTPERT
PERT
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)
 
Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokaya
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Analyzing data, performance and impacts in construction
Analyzing data, performance and impacts in constructionAnalyzing data, performance and impacts in construction
Analyzing data, performance and impacts in construction
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 

Similaire à Baseline Compliance Analysis

By now you certainly appreciate how very challenging defining
By now you certainly appreciate how very challenging defining By now you certainly appreciate how very challenging defining
By now you certainly appreciate how very challenging defining
TawnaDelatorrejs
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
sslovepk
 
Cole ready aim fire impact!- status impact analysis - nasa
Cole   ready aim fire impact!- status impact analysis - nasaCole   ready aim fire impact!- status impact analysis - nasa
Cole ready aim fire impact!- status impact analysis - nasa
NASAPMC
 

Similaire à Baseline Compliance Analysis (20)

Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchart
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.
 
By now you certainly appreciate how very challenging defining
By now you certainly appreciate how very challenging defining By now you certainly appreciate how very challenging defining
By now you certainly appreciate how very challenging defining
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project Schedules
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
PMBOK7-201-300.pdf
PMBOK7-201-300.pdfPMBOK7-201-300.pdf
PMBOK7-201-300.pdf
 
Cole ready aim fire impact!- status impact analysis - nasa
Cole   ready aim fire impact!- status impact analysis - nasaCole   ready aim fire impact!- status impact analysis - nasa
Cole ready aim fire impact!- status impact analysis - nasa
 
Unit II.pptx
Unit II.pptxUnit II.pptx
Unit II.pptx
 
Communication 1
Communication 1Communication 1
Communication 1
 
Project time
Project timeProject time
Project time
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 

Plus de Acumen

Plus de Acumen (20)

How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent Acceleration
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project Performance
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case Study
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule Integration
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
 

Dernier

Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Anamikakaur10
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 

Dernier (20)

RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 

Baseline Compliance Analysis

  • 1. // Baseline Compliance Analysis A True Measure of How Well a Project is Performing Dr. Dan Patterson, PMP CEO & President, Acumen June 2011 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com
  • 2. Table of Contents   Introduction ................................................................................................................. 3   Traditional Project Performance Techniques ................................................................ 3   Percent Complete ......................................................................................................... 3   Earned Value & Earned Schedule ................................................................................. 3   Introducing Baseline Compliance Analysis .................................................................. 4   Figure 1 – Early, On-Time, Late Scenarios ........................................................... 5   How Is Baseline Compliance Measured? ...................................................................... 5   Figure 2 – Example Schedule ............................................................................... 6   Figure 3 – Metrics Applied to the Baseline Schedule ........................................... 6   Figure 4 – Baseline Metrics Applied to the Schedule ........................................... 7   Figure 5 – Updated, Statused Schedule Showing Baseline Comparison .............. 7   Figure 6 – Metrics Applied to the Actual Schedule ............................................... 8   Figure 7 – Compliance Calculations .................................................................... 9   Figure 8 – Compliance Trending ........................................................................ 10   Conclusion ................................................................................................................. 10   +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 2      
  • 3. Introduction This paper describes a technique for determining how well a project is performing relative to an agreed upon plan (often known as a baseline). Overcoming some of the limitations of traditional performance tracking, this new approach puts an emphasis on identifying how much variance from the plan occurs over time. Further enhancing this valuable insight, is the ability to apply this analysis technique to different groupings or sections of a project and determine which of these best complies with the project plan. In summary: this approach allows for a quick determination of whether your project is being executed as planned, and if not, where the areas and time periods of non- compliance are. The technique is applicable to both project execution as well as post-execution for keeping the project on track and determining lessons learned. It is also a powerful means of understanding root cause of project delays during a project forensics exercise. Traditional Project Performance Techniques There are numerous techniques for tracking the performance of a project: that is “how well is the project being executed relative to a given plan of work?” This can be relative to project expenditure or project schedule or even quality of the project deliverable. Percent Complete The most simplistic measure of performance or status is to track projects using what is known as percent complete. While there are many variations around the calculation of percent complete, the basic premise is to track performance by determining how much work, progress or time relative to a given quantity has been achieved. While a common technique, it is widely seen as falling short with regards to true performance tracking as it does not give any indication as to the context of the progress. For example, if an activity is 90% complete, it cannot be determined from this metric alone whether performance is good or bad – the activity may be very close to completion but months later than expected. Earned Value & Earned Schedule Earned value is a cost-based measure that compares three bases (planned, earned and actual) within a project so as to determine relative performance indicators. By comparing how much work or progress has been achieved (earned) with how much should have been achieved (planned), and additionally with how much it took to achieve +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 3      
  • 4. this status (actual) we are able to determine performance factors and ratios that give insight as to whether performance is better or worse than planned. Unfortunately, earned value is a cost-based measure only and the effort required to capture the data for the three bases can be seen as a drawback to this method. For those projects that are wanting to track schedule performance using an earned value-type approach, there is the option known as Earned-Schedule. Similar to Earned Value, earned schedule looks at how much progress has been achieved (earned) relative to how much was planned, with regards to the schedule. While earned schedule provides schedule-based performance insight it suffers from a shared issue also found with earned value. Neither Earned Value nor Earned Schedule actually enable us to determine how close to the (baseline) plan did the execution of the project actually fall. Instead these two techniques focus on execution efficiency. Net efficiency on a project may calculate at 100% but what if the sequence of work was executed completely out of sync from the plan, for example? So you may be wondering “so what if the sequence of execution was not to plan or so what if half the activities were delayed and the other half were early – the net result was a successful project right?” Wrong… The whole purpose of project management is to set a realistic plan and then use this plan to accurately track execution through to completion. If compliance to the plan is not upheld then the likes of delays, disputes regarding payment milestones, potential litigation surrounding cause and effect of change all become too commonplace in a project. These “To-be-avoided pitfalls” are the reason behind using baseline compliance analysis. Introducing Baseline Compliance Analysis Baseline Compliance Analysis compares (on a per-period basis) what was originally planned and what is actual reality in the current schedule. By examining variance surrounding activity starts and finishes relative to a given basis (baseline), this approach provides insight as to whether the project is being executed to plan or alternatively suffering from delayed starts and/or delayed completions. A fundamental aspect to the analysis is that the comparison is not simply a “is the current activity date later than it’s corresponding baseline date?” Instead, phases or periods of time are used as thresholds to capture whether an activity is early, late or on- time. For example, if running an analysis based on months on an activity that was scheduled to start on March 5th and didn’t start until March 31st, this activity would still be classified as “starting on time” within the context of the monthly reporting cycle. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 4      
  • 5. Figure 1 shows the 5 different outcomes from a baseline compliance analysis for a single activity. These are all measured using start and finish variance. Figure 1 – Early, On-Time, Late Scenarios The results of the baseline compliance analysis are then summarized using compliance metrics: • Start compliance is a measure of how many activities start on time relative to a given baseline (within the confines of a given phase such as months). This gives insight into the knock-on effect of previous period delays. If start compliance is low, then few activities are able to start on time due to their predecessors causing delay. • Finish compliance is a measure of how many activities finish on time relative to a given baseline (within the confines of a given phase such as months). This is a strong indicator of execution performance. How Is Baseline Compliance Measured? Consider a baseline schedule as shown in Figure 2. The schedule contains ten activities. There are two paths through the network. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 5      
  • 6. Figure 2 – Example Schedule Firstly, metrics pertaining to the baseline are calculated so as to create a basis: 1. Scheduled to Start: # of activities scheduled to start in a given period 2. Scheduled to Finish: # of activities scheduled to finish in a given period Figure 3 shows these two metrics applied to each monthly period. Figure 3 – Metrics Applied to the Baseline Schedule Figure 4 shows how the two scheduled to start/finish metrics vary per month. Interestingly, while several activities span the month of April (Figure 3), none are planned to either actually start or finish in this month (Figure 4). +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 6      
  • 7. 5   4   4   4   4   4   Scheduled  to  Start   Scheduled  to  Finish   3   2   2   2   1   1   1   0   0   0   Jan-­‐11   Feb-­‐11   Mar-­‐11   Apr-­‐11   May-­‐11   Figure 4 – Baseline Metrics Applied to the Schedule Now consider an updated version of the schedule created during execution. Changes have occurred with regards to the sequence, duration and dates of the activities in the schedule. This results in a schedule very different to the baseline (see figure 5). Figure 5 – Updated, Statused Schedule Showing Baseline Comparison When the equivalent metrics for number of starts and number of finishes are applied to the updated schedule so as to calculate early, on-time and late starts and finishes, the result is very different (Figure 6). +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 7      
  • 8. Figure 6 – Metrics Applied to the Actual Schedule Once the metric analysis has been completed, Baseline Start and Finish Compliance can quickly be calculated as a percentage of activities that uphold the baseline (i.e. those activities that don’t trigger a start or finish variance). Figure 7 shows a summary of these results. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 8      
  • 9. Feb- Mar- Apr- May- TOTA Group Metric Jan-11 11 11 11 11 L Baseline Scheduled/Baselined to Start 4 1 4 0 1 10 Scheduled/Baselined to Finish 2 1 4 0 3 10 Updated Start/ed 2 4 1 2 1 10 Schedule Finish/ed 1 3 1 3 2 10 Statistics Start/ed on Time 2 0 0 0 1 3 Start/ed Early 0 0 2 0 0 2 Start/ed Late 2 1 2 0 0 5 Finish/ed on Time 1 1 1 0 2 5 Finish/ed Early 0 0 1 0 1 2 Finish/ed Late 1 0 2 0 0 3 Start/ed on Time, Finish/ed Late 0 0 1 0 0 0 Compliance Start Variance 2 1 4 0 0 7 Cum Start Variance 2 3 7 7 7 Start Compliance 50% 0% 0% N/A 100% 30% Finish Variance 1 0 3 0 1 5 Cum Finish Variance 1 1 4 4 5 Finish Compliance 50% 100% 25% N/A 67% 50% Figure 7 – Compliance Calculations Multiple conclusions can be drawn from Figure 7: • Start compliance started off at 50% in January and continued to slip through to the last month of the project. • Finish compliance actually improved to perfection in February (100%) before massively falling behind in March (25%) • Overall start compliance was only 30% compared to overall finish compliance of 50%. This shows that while start compliance was low, the project actually finished more activities ‘on-time’ • April was forecasted as a month with no starts and no finishes and yet it actually experienced 2 unplanned starts and 3 unplanned finishes. When start and finish variance is plotted on a cumulative timescale (Figure 8), it can be seen that the start variance is getting worse at a faster rate than finish variance. Hence, the project is showing signs of being able to complete closer to on-time despite an increasing number of start delays. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 9      
  • 10. 9   8   7   6   Start  Variance   5   Finish  Variance   4   Linear  (Start  Variance)   3   Linear  (Finish  Variance)   2   1   0   Jan-­‐11   Feb-­‐11   Mar-­‐11   Apr-­‐11   May-­‐11   Figure 8 – Compliance Trending Conclusion Baseline compliance is an effective means of determining how well a project is able to perform relative to a given baseline. By determining the number of activities that either start or finish within a given forecasted range, we are able to get a better understanding as to where and when compliance is falling short. Once this insight is gained, we then have a much better chance of proactively focusing on those activities that require remediation and acceleration. Looking at baseline compliance over time and by WBS groupings gives even further insight into schedule hotspots and performance bottlenecks. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 10