// The Value of a Standard
    Schedule Quality Index


 Dr. Dan Patterson, PMP
  CEO & President, Acumen

       March 2012




               +1 512 291 6261 // info@projectacumen.com

                        www.projectacumen.com
Table of Contents
  Introduction ................................................................................................................. 3
  What is the Schedule Index™? .................................................................................... 3
  How is it Calculated? ................................................................................................... 3
         Figure 1- Combining Individual metrics into Schedule Index™ ........................... 4
  Why the Need for Standardization? .............................................................................. 4
  What Score Should I Be Achieving? .............................................................................. 5
  Benchmarking: The Value of Cloud Computing ............................................................ 5
         Figure 2- Benchmark Analysis on a Schedule Index™ Score ............................... 6
  Conclusions ................................................................................................................. 6
  Appendix A – Schedule Index ....................................................................................... 7




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                       2
Introduction
This white paper describes the need for and value of adopting a single and
standardized index (score) to reflect the quality of a project schedule. This discussion is
based upon the recently launched Schedule Index™, which is now available in a
standard format to any project team wanting to determine how their schedule quality
ranks. In addition, the paper describes the value of using Cloud-based technology to
not only score your project, but also compare the results with other similar projects,
providing a means of benchmarking your project against others.


What is the Schedule Index™?
The Schedule Index™ is an overarching score that gives direct insight into the quality of
a schedule. Prior to this Index, objectively determining the quality of a schedule has
been somewhat of a art and science hybrid. While the project management industry as
a whole has made positive steps forward with regards to developing various checks
and balances (metrics) for project critique, there has lacked a single overarching
indicator of quality; that is, until now.

How is it Calculated?
The Schedule Index™ is a single score that is calculated from nine separate schedule
check metrics. These are described in Appendix A. The metrics span multiple key
attributes, or building blocks of a schedule that together form the underpinnings of a
structurally sound schedule:

    •   Logic: ensuring sufficient, yet not overly complicated logic
    •   Float: determining how much of the schedule is critical
    •   Duration: checking for consistent level of detail within the schedule
    •   Constraints: focusing on two-way, or hard, constraints
    •   Leads/Lags: reviewing the application of durations on activity relationships

These five core attributes are key to the successful development of a sound and
realistic schedule used as the plan of attack for any given project. The nine specific
metrics have been tried and tested on thousands of projects and over the past three
years have been criteria-adjusted and calibrated in order to provide the most accurate
and useful insight possible. For example, within the Index, specific criteria have been
applied to exclude milestone and summary activities to avoid skewing the results of an
analysis.

The metrics themselves are each weighted based on importance and its potential
impact on the overall quality of the schedule. Much calibration work has been

+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       3
conducted to ensure appropriate weighting for each of the metrics. The goal here has
been to establish an Index that gives a broad, yet representative range of results taking
into account the key drivers of schedule quality.

The Schedule Index™ itself provides a zero to 100 range with zero being the worst
possible and 100 being a ‘perfectly formed’ schedule.




      Figure 1- Combining Individual metrics into an overarching Schedule Index™


Why the Need for Standardization?
The need for standardization is compelling yet simple: projects, irrespective of type and
size, all benefit from a means of determining the quality of their schedules that is
consistent and repeatable. There is a reason why the likes of consumer credit scores or
college entrance exams use common and agreed upon scoring systems – scores are
only useful if we can consistently use them to compare against a benchmark or other
similar entity.

Example use cases of adopting the Schedule Index™ include but are not limited to:


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       4
•   Monthly comparisons of schedule updates by an owner organization
    •   Internal self-assessment of a contractor-developed schedule
    •   Agreed-upon target goals between owners and contractors


What Score Should I Be Achieving?
In addition to having a standardized Index, it is valuable to establish thresholds or goals
that a project should be achieving with regards to schedule quality. This is similar to
defining a given Confidence Level (e.g., P75) when conducting a risk analysis.

The standard pass/fail threshold established for the Schedule Index™ is 75 or higher. It
is not reasonable to expect large, complex projects to score 100. Conversely, there
needs to be a threshold against which a schedule is rejected or at least reviewed and
updated. Anything less than 75 should trigger a schedule review.

If your organization is looking to be truly best of breed or accelerate its schedule quality
maturity then consider pushing this threshold to 85.


Benchmarking: The Value of Cloud Computing
Closely tied to the value of scoring a project based on its schedule quality is being able
to see how this score compares to other projects. The results can be extremely
insightful. Prior to cloud computing, such comparisons were time consuming at best
and at worst, physically impossible.

Cloud computing became hugely popular with the introduction of social networking.
This has since spilled into the analytics world and is now a key component of the Fuse
Schedule Index™ solution.

By comparing the results of a Fuse Schedule Index™ to other projects whose results
are stored anonymously in Acumen Cloud™, you now, for the first time, have an instant
means of seeing how your project compares to others. Being able to understand how
you rank gives you much more insight than a non-contextual score.

Figure 2 shows an example of a project that scores 72 (below the 75 threshold) yet,
relative to other similar projects, it actually ranks in the 87th percentile.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       5
Figure 2- Benchmark Analysis on a Schedule Index™ Score


Conclusions
It is generally accepted that the higher the quality of a project schedule, the higher
chance the project will be executed smoothly and to agreed upon expectations.

Tied to this, standardizing schedule quality assessment scoring has obvious benefits.
Being able to consistently score projects while accounting for the core building blocks
of a schedule provides a repeatable and defendable means of objectively critiquing a
project plan. This is now possible with the Schedule Index™.

Adding to the mix the ability to rank a project and benchmark it against other projects
gives further insight into whether the obtained Schedule Index™ score is acceptable
based on the project’s type and size.

The Schedule Index™ is an indicator of quality and not in itself a magic solution to
fixing the schedule. The activities highlighted through the individual metrics within the
overarching Schedule Index™ should still be used as checklists for resolving the
shortcomings in the schedule itself.


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       6
Appendix A – Schedule Index
Missing Logic
In theory, all activities should have at least one predecessor and one successor
associated with them. Failure to do so will impact the quality of results derived from a
time analysis as well as a risk analysis. This number should not exceed more than 5%.

Logic Density™
This metric calculates the average number of logic links per activity. An average of less
than two indicates that there is logic missing within the schedule. An average greater
than four indicates overly complex logic, with a high likelihood of redundant links.
Therefore, Logic Density™ should be between two and four.

Critical
While a highly critical schedule is not necessarily a sign of poor scheduling, it can
indicate a highly risky schedule. Use this metric as a point of reference.

Hard Constraints
Hard, or two-way, constraints such as ‘Must Start On’ or ‘Must Finish On’ should be
avoided. Use of such constraints can lead to inaccurate finish dates and a lack of
insight into the impact of schedule changes, risk events, and earlier delays.

Negative Float
Negative float is a result of an artificially accelerated or constrained schedule, and is an
indication that a schedule is not possible based on the current completion dates.

Insufficient Detail™
Activities with a high duration relative to the life of the project are an indication of poor
schedule definition. Detail should be added to the schedule.

Number of Lags
A lag is a duration applied to a logic link often used to represent non-working time
between activities such as concrete curing. Lags tend to hide detail within the schedule
and cannot be statused like normal activities; therefore, lags should be converted to
actual activities with durations.

Number of Leads
A lead, also known as a negative lag, is often used to adjust the successor start or end
date relative to the logic link applied. This is a poor practice as it can result in the
successor starting before the start of the predecessor.


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       7
Merge Hotspot
A merge hotspot is an indication of how complex the start of an activity is. If the
number of links is greater than two, there is a high probability that the activity in
question will be delayed due to the cumulative effect of all links having to complete on-
time in order for the activity to start on time.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       8

Contenu connexe

Tendances

Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government ContractingGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Glen Alleman
 
MCS Technical Article
MCS Technical ArticleMCS Technical Article
MCS Technical ArticleMartin Gough
 
Capabilities based planning essay
Capabilities based planning essayCapabilities based planning essay
Capabilities based planning essayGlen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Glen Alleman
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleGlen Alleman
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned valueGlen Alleman
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleGlen Alleman
 
Project Management Control Systems
Project Management Control SystemsProject Management Control Systems
Project Management Control Systemsskillern
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceGlen Alleman
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as OpportunityGlen Alleman
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountGlen Alleman
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?Glen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project managementGlen Alleman
 

Tendances (20)

Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government Contracting
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
MCS Technical Article
MCS Technical ArticleMCS Technical Article
MCS Technical Article
 
Capabilities based planning essay
Capabilities based planning essayCapabilities based planning essay
Capabilities based planning essay
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned value
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Project Management Control Systems
Project Management Control SystemsProject Management Control Systems
Project Management Control Systems
 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performance
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 

Similaire à The Value of Standardized Schedule Quality Scoring

Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
Test Planning and Test Estimation Techniques
Test Planning and Test Estimation TechniquesTest Planning and Test Estimation Techniques
Test Planning and Test Estimation TechniquesMurageppa-QA
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsarah david
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleKate Pynn
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templatesHoa PN Thaycacac
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsarah david
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk toleranceGlen Alleman
 
Project control and process instrumentation
Project control and process instrumentationProject control and process instrumentation
Project control and process instrumentationKuppusamy P
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure CycleGlen Alleman
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsarah david
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsarah david
 
Maksym Vyshnivetskyi: PMO KPIs ( UA ).
Maksym  Vyshnivetskyi:  PMO KPIs ( UA ).Maksym  Vyshnivetskyi:  PMO KPIs ( UA ).
Maksym Vyshnivetskyi: PMO KPIs ( UA ).Lviv Startup Club
 
CORTAC PPC General
CORTAC PPC GeneralCORTAC PPC General
CORTAC PPC GeneralDerek Regan
 
Performance Methodology It Project Metrics Workbook
Performance Methodology It Project Metrics WorkbookPerformance Methodology It Project Metrics Workbook
Performance Methodology It Project Metrics WorkbookDavid Paschane, Ph.D.
 
EFFICACY OF PROJECT MANAGEMENT
EFFICACY OF PROJECT MANAGEMENTEFFICACY OF PROJECT MANAGEMENT
EFFICACY OF PROJECT MANAGEMENTAssignment Studio
 
Efficacy of Project Management,
Efficacy of Project Management, Efficacy of Project Management,
Efficacy of Project Management, Assignment Studio
 
Bridging the cost schedule divide - integrating primavera and cost systems wh...
Bridging the cost schedule divide - integrating primavera and cost systems wh...Bridging the cost schedule divide - integrating primavera and cost systems wh...
Bridging the cost schedule divide - integrating primavera and cost systems wh...p6academy
 
PMP Exam Flashcards common definitions 7th edition original v2.0
PMP Exam Flashcards common definitions 7th edition original v2.0PMP Exam Flashcards common definitions 7th edition original v2.0
PMP Exam Flashcards common definitions 7th edition original v2.0Vinod Kumar, PMP®
 
Chrysalis Cleariew Introductory V3
Chrysalis Cleariew Introductory V3Chrysalis Cleariew Introductory V3
Chrysalis Cleariew Introductory V3Robbie Hazlehurst
 

Similaire à The Value of Standardized Schedule Quality Scoring (20)

Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Test Planning and Test Estimation Techniques
Test Planning and Test Estimation TechniquesTest Planning and Test Estimation Techniques
Test Planning and Test Estimation Techniques
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdf
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training Example
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptx
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk tolerance
 
Project control and process instrumentation
Project control and process instrumentationProject control and process instrumentation
Project control and process instrumentation
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Estimation
EstimationEstimation
Estimation
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptx
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdf
 
Maksym Vyshnivetskyi: PMO KPIs ( UA ).
Maksym  Vyshnivetskyi:  PMO KPIs ( UA ).Maksym  Vyshnivetskyi:  PMO KPIs ( UA ).
Maksym Vyshnivetskyi: PMO KPIs ( UA ).
 
CORTAC PPC General
CORTAC PPC GeneralCORTAC PPC General
CORTAC PPC General
 
Performance Methodology It Project Metrics Workbook
Performance Methodology It Project Metrics WorkbookPerformance Methodology It Project Metrics Workbook
Performance Methodology It Project Metrics Workbook
 
EFFICACY OF PROJECT MANAGEMENT
EFFICACY OF PROJECT MANAGEMENTEFFICACY OF PROJECT MANAGEMENT
EFFICACY OF PROJECT MANAGEMENT
 
Efficacy of Project Management,
Efficacy of Project Management, Efficacy of Project Management,
Efficacy of Project Management,
 
Bridging the cost schedule divide - integrating primavera and cost systems wh...
Bridging the cost schedule divide - integrating primavera and cost systems wh...Bridging the cost schedule divide - integrating primavera and cost systems wh...
Bridging the cost schedule divide - integrating primavera and cost systems wh...
 
PMP Exam Flashcards common definitions 7th edition original v2.0
PMP Exam Flashcards common definitions 7th edition original v2.0PMP Exam Flashcards common definitions 7th edition original v2.0
PMP Exam Flashcards common definitions 7th edition original v2.0
 
Chrysalis Cleariew Introductory V3
Chrysalis Cleariew Introductory V3Chrysalis Cleariew Introductory V3
Chrysalis Cleariew Introductory V3
 

Plus de Acumen

Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskAcumen
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueAcumen
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyAcumen
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationAcumen
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Acumen
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentAcumen
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceAcumen
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit KeynoteAcumen
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessAcumen
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Acumen
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Acumen
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute ResolutionAcumen
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAcumen
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Acumen
 
Fuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCFuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCAcumen
 

Plus de Acumen (20)

Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent Acceleration
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project Performance
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case Study
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule Integration
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
 
Fuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCFuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPC
 

Dernier

NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerAggregage
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...Hector Del Castillo, CPM, CPMM
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxShruti Mittal
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryWhittensFineJewelry1
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSendBig4
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfDanny Diep To
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdfChris Skinner
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
BAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxBAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxran17april2001
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 

Dernier (20)

NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors Data
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon Harmer
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptx
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.com
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
BAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxBAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptx
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 

The Value of Standardized Schedule Quality Scoring

  • 1. // The Value of a Standard Schedule Quality Index Dr. Dan Patterson, PMP CEO & President, Acumen March 2012 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com
  • 2. Table of Contents Introduction ................................................................................................................. 3 What is the Schedule Index™? .................................................................................... 3 How is it Calculated? ................................................................................................... 3 Figure 1- Combining Individual metrics into Schedule Index™ ........................... 4 Why the Need for Standardization? .............................................................................. 4 What Score Should I Be Achieving? .............................................................................. 5 Benchmarking: The Value of Cloud Computing ............................................................ 5 Figure 2- Benchmark Analysis on a Schedule Index™ Score ............................... 6 Conclusions ................................................................................................................. 6 Appendix A – Schedule Index ....................................................................................... 7 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 2
  • 3. Introduction This white paper describes the need for and value of adopting a single and standardized index (score) to reflect the quality of a project schedule. This discussion is based upon the recently launched Schedule Index™, which is now available in a standard format to any project team wanting to determine how their schedule quality ranks. In addition, the paper describes the value of using Cloud-based technology to not only score your project, but also compare the results with other similar projects, providing a means of benchmarking your project against others. What is the Schedule Index™? The Schedule Index™ is an overarching score that gives direct insight into the quality of a schedule. Prior to this Index, objectively determining the quality of a schedule has been somewhat of a art and science hybrid. While the project management industry as a whole has made positive steps forward with regards to developing various checks and balances (metrics) for project critique, there has lacked a single overarching indicator of quality; that is, until now. How is it Calculated? The Schedule Index™ is a single score that is calculated from nine separate schedule check metrics. These are described in Appendix A. The metrics span multiple key attributes, or building blocks of a schedule that together form the underpinnings of a structurally sound schedule: • Logic: ensuring sufficient, yet not overly complicated logic • Float: determining how much of the schedule is critical • Duration: checking for consistent level of detail within the schedule • Constraints: focusing on two-way, or hard, constraints • Leads/Lags: reviewing the application of durations on activity relationships These five core attributes are key to the successful development of a sound and realistic schedule used as the plan of attack for any given project. The nine specific metrics have been tried and tested on thousands of projects and over the past three years have been criteria-adjusted and calibrated in order to provide the most accurate and useful insight possible. For example, within the Index, specific criteria have been applied to exclude milestone and summary activities to avoid skewing the results of an analysis. The metrics themselves are each weighted based on importance and its potential impact on the overall quality of the schedule. Much calibration work has been +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 3
  • 4. conducted to ensure appropriate weighting for each of the metrics. The goal here has been to establish an Index that gives a broad, yet representative range of results taking into account the key drivers of schedule quality. The Schedule Index™ itself provides a zero to 100 range with zero being the worst possible and 100 being a ‘perfectly formed’ schedule. Figure 1- Combining Individual metrics into an overarching Schedule Index™ Why the Need for Standardization? The need for standardization is compelling yet simple: projects, irrespective of type and size, all benefit from a means of determining the quality of their schedules that is consistent and repeatable. There is a reason why the likes of consumer credit scores or college entrance exams use common and agreed upon scoring systems – scores are only useful if we can consistently use them to compare against a benchmark or other similar entity. Example use cases of adopting the Schedule Index™ include but are not limited to: +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 4
  • 5. Monthly comparisons of schedule updates by an owner organization • Internal self-assessment of a contractor-developed schedule • Agreed-upon target goals between owners and contractors What Score Should I Be Achieving? In addition to having a standardized Index, it is valuable to establish thresholds or goals that a project should be achieving with regards to schedule quality. This is similar to defining a given Confidence Level (e.g., P75) when conducting a risk analysis. The standard pass/fail threshold established for the Schedule Index™ is 75 or higher. It is not reasonable to expect large, complex projects to score 100. Conversely, there needs to be a threshold against which a schedule is rejected or at least reviewed and updated. Anything less than 75 should trigger a schedule review. If your organization is looking to be truly best of breed or accelerate its schedule quality maturity then consider pushing this threshold to 85. Benchmarking: The Value of Cloud Computing Closely tied to the value of scoring a project based on its schedule quality is being able to see how this score compares to other projects. The results can be extremely insightful. Prior to cloud computing, such comparisons were time consuming at best and at worst, physically impossible. Cloud computing became hugely popular with the introduction of social networking. This has since spilled into the analytics world and is now a key component of the Fuse Schedule Index™ solution. By comparing the results of a Fuse Schedule Index™ to other projects whose results are stored anonymously in Acumen Cloud™, you now, for the first time, have an instant means of seeing how your project compares to others. Being able to understand how you rank gives you much more insight than a non-contextual score. Figure 2 shows an example of a project that scores 72 (below the 75 threshold) yet, relative to other similar projects, it actually ranks in the 87th percentile. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 5
  • 6. Figure 2- Benchmark Analysis on a Schedule Index™ Score Conclusions It is generally accepted that the higher the quality of a project schedule, the higher chance the project will be executed smoothly and to agreed upon expectations. Tied to this, standardizing schedule quality assessment scoring has obvious benefits. Being able to consistently score projects while accounting for the core building blocks of a schedule provides a repeatable and defendable means of objectively critiquing a project plan. This is now possible with the Schedule Index™. Adding to the mix the ability to rank a project and benchmark it against other projects gives further insight into whether the obtained Schedule Index™ score is acceptable based on the project’s type and size. The Schedule Index™ is an indicator of quality and not in itself a magic solution to fixing the schedule. The activities highlighted through the individual metrics within the overarching Schedule Index™ should still be used as checklists for resolving the shortcomings in the schedule itself. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 6
  • 7. Appendix A – Schedule Index Missing Logic In theory, all activities should have at least one predecessor and one successor associated with them. Failure to do so will impact the quality of results derived from a time analysis as well as a risk analysis. This number should not exceed more than 5%. Logic Density™ This metric calculates the average number of logic links per activity. An average of less than two indicates that there is logic missing within the schedule. An average greater than four indicates overly complex logic, with a high likelihood of redundant links. Therefore, Logic Density™ should be between two and four. Critical While a highly critical schedule is not necessarily a sign of poor scheduling, it can indicate a highly risky schedule. Use this metric as a point of reference. Hard Constraints Hard, or two-way, constraints such as ‘Must Start On’ or ‘Must Finish On’ should be avoided. Use of such constraints can lead to inaccurate finish dates and a lack of insight into the impact of schedule changes, risk events, and earlier delays. Negative Float Negative float is a result of an artificially accelerated or constrained schedule, and is an indication that a schedule is not possible based on the current completion dates. Insufficient Detail™ Activities with a high duration relative to the life of the project are an indication of poor schedule definition. Detail should be added to the schedule. Number of Lags A lag is a duration applied to a logic link often used to represent non-working time between activities such as concrete curing. Lags tend to hide detail within the schedule and cannot be statused like normal activities; therefore, lags should be converted to actual activities with durations. Number of Leads A lead, also known as a negative lag, is often used to adjust the successor start or end date relative to the logic link applied. This is a poor practice as it can result in the successor starting before the start of the predecessor. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 7
  • 8. Merge Hotspot A merge hotspot is an indication of how complex the start of an activity is. If the number of links is greater than two, there is a high probability that the activity in question will be delayed due to the cumulative effect of all links having to complete on- time in order for the activity to start on time. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 8