SlideShare une entreprise Scribd logo
1  sur  39
DMAIC Project Report


Please Select Belt Type:

                          DMAIC BB                       DMAIC GB



Project Title:                            Improve Technetium Pre-calibration
Project Number (1st, 2nd, 3rd…):          2nd
Instantis Project ID#:                    
Project Leader Name:                      Ramesh Rajan
Project Leader Job Title:               Process Engineer
                                   Imaging Solutions/Nuclear Pharmacy
Segment/GBU/Division/Plant/Region:
                                   Operations
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc



    Executive Summary
The Nuclear pharmacy network comprises 1/3 of the total Imaging division revenue.
Technetium-99 is a primary radioactive isotope which is used for various diagnostic
procedures at hospitals, imaging centers etc. This represents 80% of the pharmacy
product portfolio. The product has an extremely short shelf life; a 6 hour half-life and
hence is critical that it be used efficiently and in the most cost-effective manner. The pre-
calibration time of the product is time elapsed between when the product was dispensed
to the time it was used for the intended application.

Currently significant amount of Tc-99 was decaying at the customer site (>6hrs).
Historical data showed pre-calibration time for Tech products averaging at approx 8
hours. This represents significant product decay and lost revenue to the pharmacy
network. There was also a large degree of inconsistency in pharmacies adhering to
Pre-calibration policies with their customer base.

The goal of the project was to improve the pre-calibration time on Technetium base
products. Data collection was carried out by developing query language which helped in
presenting accurate data that gave high visibility to this project.

Through the use of the DMAIC methodology this project used tools such as VOC,
FMEA, Hypothesis test that focused primarily in improving the pre-calibration times for
Tech based products by implementation of the following:

- Revenue stream programming change to charge activity beyond the 6 hour pre-cal limit
-Customer letter from marketing addressing the goal to maximize the availability
of technetium 99m (Tc 99m) for patients, using as much as possible in procedures rather
than allowing it to decay on the shelf. These new policies would be designed to
encourage unit dose customers use a more “just in time” approach.

- Sales rep training on the Tc conservation program to help facilitate in changing
customer behavior; i.e. Move orders to later scheduled runs. To promote lower pre-
calibration times, Covidien will charge for pre-calibration activity beyond six hours,
new charges will be based on bulk Tc-99 pricing. Bulk Tc-99 will be calibrated for actual
delivery time, unless customer chooses to pay for additional activity

Annual impact estimated from this project is $3million/year. Results taken after program
launch in Oct 09 shows savings of $300K validate the projected revenue.

The final metrics for the project are as follows:

Name of Metric                      Baseline Goal                      Actual(A)-Oct09
Pre-calibration time                8.15     6.0                       7.15

.


                                                                                            2
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc

        Define
                Project Charter
                             Operational Excellence – Team Charter
   Program Name:          Improve Tech Pre-calibration       Total Savings Identified ($         $3 Million/yr
                                                             value)
   Team Leader:           Ramesh Rajan
   Team Champion:         Dave Becker                        Product or Service Impacted Nuclear Pharmacies
   Business Unit:         Imaging Solutions                              MBB:
   Start Date:            April 2009                         Target Completion Date:      October 2009
        Element                   Description                                      Team Charter
1. Process:              The process in which the           The pharmacy network holds significant improvement opportunities
                         opportunity exists.                in reducing length of pre-calibration time on technetium based unit
                                                            dose products and calibrating bulk doses at their delivery time.
2. Problem               Describe the problem that needs Currently significant amount of Technetium 99 is decaying at the
   Description:          to be solved, or the opportunity   customer site which results in product waste and lost revenue.
                         to be addressed.                   Global moly shortage severely impacts product availability.
3. Objective:            What improvement is targeted? Reduction in Tech pre-calibration time would yield significant cost
                                                            reduction to the pharmacy business. In addition it will improve
                                                            product availability and increase patient access to Tc99 products.
                                                            Saved Technetium could be sold at favorable price to a customer.
4. Metrics:              What are the measurements              Name of        Baseline      Goal       Entitlement* Units of
                         that quantify program progress          Metric                                                Measure
                         and success?                       Precalibration        8.15        6.0                        Hours
                         *W hat is the bes t the process is       time
                         expec ted to pro duc e?

5. Business Results:     What is the improvement in          Cost          Cost           WIP/        Cash        Labor     Inc.
                         business performance?             Reduction     Avoidance      Inventory     Flow       Savings   Sales
                         Please list any other                                          Reduction
                         improvements on a separate             X                                                            X
                         sheet as needed.
6. Program Scope:        Which parts of our business                   Included                            Excluded
                         processes will be considered?     The project will focus on all       All other products
                         Which customer segments,          Technetium based products
                         organizations, geographies, and   which represent 80% of a
                         timeframe?                        customer product portfolio.

7. Team Members:         Names and roles of team           Ramesh Rajan, Dave Becker ,Jeanne Landers, Terese Lafeber,
                         members                           Carolyn Samra, Andy Farrow, Brian Courtney, Pharmacy Regional
                                                           Managers.


8. Benefit to External   Who are the final customers,      Reduction in pre-calibration time will reduce cost, improve product
   Customers:            what are their most critical      availability to external customer and help mitigate the global moly
                         requirements/measurements,        shortage issue. In addition it will allow greater patient access to the
                         and what benefits do we expect    product.
                         to deliver to them?
8. Schedule:             Give the key milestones and                            Key Project Dates
                         dates.                            Project Start      April 2009
                                                           Define Complete    May 2009
                                                           Measure Complete July 2009
                                                           Analyze Complete August 2009
                                                           Improve Complete September 2009
                                                           Control Complete   October 2009
9. Budget:               What financial resources are      $5000 for TRON programming.
                         required for the team?


10. Support Required:    Do you anticipate the need for    IS programming, TRON user training, customer communications.
                         any special capabilities,
                         hardware, trials, etc.?




                                                                                                                                     3
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
             SIPOC Map
A SIPOC diagram was generated to provide a high level view of the Tech pre-calibration
process. This tool helped the team to understand important inputs and outputs to the
process.

      SUPPLIER                   INPUT                         PROCESS                     OUTPUT                      CUSTOMER
                                                       Pharmacy receives customer
   Customer(Hospital,       Standing, Demand             order for Tech dose with                                   Customer-Hospital,
                                                                                           Presciption
     Independent)             Orders,TRON                 requested delivery and                                     Independent user
                                                             calibration time

                                                        Dispense dose with activity
  Pharmacist ,Technician     Customer Order                                             Dispensed dose               Customer-Hospital
                                                         related to calibration time

                                                       Tech dose is ship confirmed
        Pharmacy           Bill of Lading, TRON                                        Shipconfirmed Dose                  Courier
                                                          and taken for delivery

                                                       Dose is delivered to customer
        Pharmacy           Driver , Bill of Lading                                       Delivered dose              Customer-Hospital
                                                        at requested delivery time

                                                       Pharmacy bills customer for
        Pharmacy              Dose charges                                              Customer Invoice                  Customer
                                                       dose includes freight charge.

   Customer(Hospital,                                    Pharmacy collects sales
                            Customer Invoice                                             Sales Revenue                    Pharmacy
     Independent)                                        revenue from dose sale




             Voice of the Customer/Business
The team also undertook a brainstorming exercise to come up with key customer
requirements. This “Voice of Customer” exercise showed the key outputs for the
project .These outputs influence the end customer (i.e. hospitals etc) in maintaining
reliable and quality supply. At the same time they also affect the pharmacies which are an
internal customer as it will help in reducing product decay and capture lost revenue due
to excessive pre-calibration.



                                                     Reduce Tc Pre-                     Limit Precalibratiion time compared to current practice to save Tech waste
                                                                                        Mimimize bulk dose waste by shrinking calibration limits
                                                       calibration                      Maintain accurate delivery time in TRON




                                                                                        Maintain ontime supply of Tech product to customer
 Voice of the                                        On Time Delivery                   Need more Technetium due to global "Moly" shortage

  Customer                                                                              Minimize product shortage




                                                                                        Develop efficient production schedule at pharmacy
                                                          Efficient                     Maintain efficient delivery routing for customer profile




                                                                                                                                           4
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc




Project Y’s (KPOV’s)
At the end of the Define Phase the team decided to focus on reducing the pre-calibration
time on Technetium products as the key Output (Big Y). This would be achieved while
still meeting product demand and delivery expectations.

Key Process Output Variable
   • Reduce Precalibration time on Technetium based products

Other Important Factors
   • Maintain product supply as per customer demand
   • Meet customer delivery schedules




                                                                                           5
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc

   Measure
         Process Map
A flowchart was developed to show the sequence and flow in the pre-calibration process.
Using this, the teams were able to breakdown and understand the intermediate steps and
determine inputs and outputs for each major step.
                            Process Flow Map for Tc 99 Precalibration


                                     Pharmacy receives Customer
       Calibration time,           Standing/Demand Order for Tech
        Delivery time                           dose
                                                                            Pharmacist
                                                                           enters order in
                                                                            TRON and
                                                                             generates
                                                                            prescription


                                  Dispense Dose with activity related                  Check
                                         to calibration time                           Order




                                      Is dose matching with BOL
                                                                              NO


                                     YES


                                   Tech dose is ship confirmed and
                                          taken for delivery



                                      Dose delivery to customer at
                                   requested delivery and calibration
                                                 time




                                      Pharmacy bills customer and
                                  collects sales revenue for dose sale
                                                                         Pharmacy
                                                                         Invoicing
                                                                            $$
                                    Pharmacy adds new customer ,
                                     negotiates existing customer
                                     contracts, communicates any
                                      change in policy or contract




                                                                                             6
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
             Cause and Effects Matrix
In order to prioritize the input variables affecting the output requiring improvement, the
team used a Cause and Effect (C&E) matrix. A Pareto was also done on the top raking
critical inputs from the C&E with a cut-off of 200. This tool helped to focus on the few
critical inputs which affect the output.
                                    Cause and Effect
                                        Matrix
                                      Rating of Importance to
                                                                               9                  10                                    8                                        9
                                             Customer
                                                                               1                      2                                 3                                        4




                                                                                        Requested Activity at calibration




                                                                                                                                                 Availability of Tech products
                                                                   On Time Deliveries




                                                                                                                            Drops per Delivery
                                                                                        time
                                                                                                                                                                                     Total
              Process Step                  Process Input
                                     Calibration,delivery time,
        Pharmacy receives
 1                                  calibration policy,Customer                9                      9                                 3                                        9      276
        customer order
                                    communication
        Pharmacy negotiates
                                    Calibration policy, Customer
 6      existing contracts,                                                    3                      9                                 9                                        9      270
                                    contract, Communication
        communicates changes
        Dose Dispensed with
                                    Customer Order,TRON,
 2      activity related to                                                    3                      9                                 3                                        9      222
                                    Calibration,Dely time
        calibration time
        Tech dose ship confirmed
 3                                  Dispensed dose, BOL                        9                      9                                 3                                        0      195
        and ready for delivery
        Dose delivered to customer
 4      at requested delivery and Dose, BOL, Driver                            9                      9                                 3                                        0      195
        calibration time
        Pharmacy bills customer
 5      and collects revenue from   Sales Invoice, Freight Bill                1                      9                                 9                                        1      180
        dose sale
                                                                                                                                                                                         0
                                                                                                                                                                                         0
                                                                         306

                                                                                                 540

                                                                                                                                  240


                                                                                                                                                                            252




Total
                                    Lower Spec
                                    Target
                                    Upper Spec



                                                                                                                                                                                              7
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc


                Pareto of C&E matrix

                                                                     C &E Pareto Analysis
                                                                                                             1400
                                                                                                                                                                                                          100
                                                                                                             1200
                                                                                                             1000
                                                                                                                                                                                                          80




                                                                                                                                                                                                                Percent
 Count




                                                                                                               800                                                                                        60
                                                                                                               600
                                                                                                                                                                                                          40
                                                                                                               400
                                                                                                               200                                                                                        20
                                                                                                                   0                                                                                      0
         Process Inputs
                                                                                                                               on               n              e          L            r           il l
                                                                                                                              i              io            tim          O           ve           tB
                                                                                                                            at            at                        ,B            ri           h
                                                                                                                         ic            ic            el
                                                                                                                                                        y
                                                                                                                                                                  se
                                                                                                                                                                               D            ig
                                                                                                                      un          un              ,D           do
                                                                                                                                                                            L,           re
                                                                                                                 m
                                                                                                                   m            m
                                                                                                                                             on              d           BO           ,F
                                                                                                              co            om r at i                     se         e,          ic
                                                                                                                                                                                    e
                                                                                                          er            ,C            b               en           os         vo
                                                                                                        m             ct          ali            i sp            D         In
                                                                                                     to           ra           ,C              D
                                                                                                  us            nt          N                                          les
                                                                                               ,C            co        R  O                                         Sa
                                                                                            cy           er        r ,T
                                                                                        oli            m
                                                                                                                de
                                                                                    n
                                                                                      p
                                                                                                 u sto         r
                                                                                                             O
                                                                               ti o          ,C            r
                                                                           ra            cy            me
                                                                       li b             li          to
                                                                   ca                po          us
                                                                e,            ion              C
                                                             tim           at
                                                           y           br
                                                       v er        ali
                                                   eli           C
                                               d
                                             n,
                                      ti o
                                   ra
                               lib
                          Ca




                FMEA
The FMEA focused on specific process failures that would affect the Tech pre-calibration
process and which would cause product decay and lost revenue. A RPN cut-off of 300
was established by the team for taking the critical inputs coming out of the FMEA into
the Analyze phase.




                                                                                                                                                                                                                          8
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
                                                       Improve Tech                                                                                                                                        Prepared by: Ramesh
                        Process or Product Name:
                                                       Precalibration                                                                                                                                      Rajan
                        Responsible:                   Ramesh Rajan                                                                                                                                        FMEA Date (Orig) _September 29th, 2009_______


                                                                                                                                   S                                                           O                                                D            R
                                                       Potential Failure                      Potential Failure
   Process Step                    Input                                                                                           E                       Potential Causes                    C                 Current Controls               E            P
                                                            Mode                                  Effects
                                                                                                                                   V                                                           C                                                T            N




                                                                                                                           How Severe is the




                                                                                                                                                                                                                                          How well can you
                                                                                                                               effect to the




                                                                                                                                                                                                                                           detect cause or
                                                                                                                                                                                          How often does
                                                                                                                                                                                            cause or FM
                                                                                                                                cusotmer?




                                                                                                                                                                                                 occur?




                                                                                                                                                                                                                                                     FM?
 Step of the process     Input under investigation?    In what ways does                 What is the impact                                     What causes the Key Input to go                            What are the existing
 under investigation                                   the Key Input go                  on the Key Output                                      wrong?                                                     controls and procedures
                                                       wrong?                            Variables (Customer                                                                                               (inspection and test) that
                                                                                         Requirements) or                                                                                                  prevent either the cause or
                                                                                         internal                                                                                                          the Failure Mode?
                                                                                         requirements?                                                                                                     Should include an SOP
                                                                                                                                                                                                           number.
Pharmacy receives                                          Excessive                         Product decay , Lost
                                  TRON                                                                                             8            Lack of limits on calibration time              7                      None                      8           448
customer order                                            precalibration                           revenue
 Dose dispensed with
                                                       Inaccurate delivery                                                                                                                                       Customer Delivery
  activity related to     Expected Delivery time                                                Product Decay                      7                       Customer Behaviour                   8                                                7           392
                                                              time                                                                                                                                                   schedule
   calibration time
Pharmacy negotiates
                                                       Miscommunicaiton                       Lost revenue due to
existing contracts,         Customer Contract,                                                                                                    Lack of attention to true need,                          Customer Communication
                                                            or lack of                          product decay,                     8                                                            8                                                6           384
communicates                 Calibration policy                                                                                                 overemphasis on safety insurance                                by Sales reps
                                                       standardized policy                     excess inventory
changes
Pharmacy receives                                          Excessive                                                                                Historical customer behaviour,
                              Calibration time                                                  Product Decay                      9                                                            8          Customer Communication                5           360
customer order                                            precalibration                                                                                  resistant to change
                                                                                             Lost revenue due to
                            Customer Contract,          No adherence to                                                                             Customer demand, variation in                          Customer Communication
                                                                                                product decay,                     8                                                            7                                                6           336
                             Calibration policy              policy                                                                                        Tech needs                                           by Sales reps
                                                                                              excess inventory
Pharmacy receives                                           Excessive                        Unfavourable product                                     Lack of standardized
                              Calibration time                                                                                     9                                                            7          Contract, Calibration policy          5           315
customer order                                             precalibration                           margin                                           policy/contract terms
                                                       Inaccurate delivery                                                                         Lack of foresight, Product                                  Delivery time loaded in
                          Expected Delivery time                                                Product Decay                      7                                                            8                                                4           224
                                                                time                                                                                          Insurance                                                 TRON
Pharmacy receives                                        Incorrect activity                  Product decay, loss                                No activity limits in TRON, wrong
                                  TRON                                                                                             6                                                            6                  TRON checks                   2           72
customer order                                               dispensed                           of revenue                                                  order entry


                                                                                                                                                                                                                                                             0
                                                                                                                                                                                                                                                             0

Pareto of FMEA


                                                                  Pareto of FMEA RPN
                                                              2500                                                                                                                                         100
                                                              2000                                                                                                                                         80




                                                                                                                                                                                                                  Percent
   Count




                                                              1500                                                                                                                                         60
                                                              1000                                                                                                                                         40
                                                               500                                                                                                                                         20
                                                                       0                                                                                                                                   0
           Potential Failure Mode                                                                n                     e                     ic y                        icy         er
                                                                                             t io                  t im                    ol                        l          th
                                                                                        ra                     y                       p                        po             O
                                                                                 a   lib                     er                   d                        to
                                                                            ec                            liv                 ize
                                                                                                     de                  rd                           ce
                                                                       pr                                              da                        en
                                                                iv
                                                                   e
                                                                                          a    te                    n                         er
                                                              ss                        ur                         ta                 h
                                                         ce                       c                              fs                ad
                                                       Ex                      ac                            o
                                                                                                                              No
                                                                            In                           k
                                                                                                     lac
                                                                                               or
                                                                                         n
                                                                                  it o
                                                                            n ic a
                                                                    u
                                                                   m
                                                                o m
                                                          isc
                                                         M
                                                       Count                             1123                        616                    384                   336             72
                                                      Percent                            44.4                       24.3                   15.2                  13.3            2.8
                                                      Cum %                              44.4                       68.7                   83.9                  97.2          100.0


The key inputs from the FMEA were Calibration time, Delivery time, Customer contracts
and TRON.


                                                                                                                                                                                                                            9
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
         Gage R&R
Data collection for the Measure phase was obtained from queries generated from the
TRON system A Gage R&R study was then conducted to test the precision of the
measurement system and this was done with the help of 2 operators on the critical metric;
Average pre-calibration time.

A Gage R&R review showed the variation due to repeatability and reproducibility to be
at 3% and part-to part variation at 99% which showed the measurement system was very
accurate.

Gage R&R for Over 6 hr precalibration time


Gage R&R Study - ANOVA Method

Two-Way ANOVA Table with Interaction

Source                DF        SS        MS         F       P
Sample                34   95.0457   2.79546   3007.40   0.000
Operator               1    0.0037   0.00370      3.98   0.054
Sample * Operator     34    0.0316   0.00093         *       *
Repeatability         70    0.0000   0.00000
Total                139   95.0810


Alpha to remove interaction term = 0.25


Gage R&R

                                  %Contribution
Source                  VarComp    (of VarComp)
Total Gage R&R         0.000504            0.07
  Repeatability        0.000000            0.00
  Reproducibility      0.000504            0.07
    Operator           0.000040            0.01
    Operator*Sample    0.000465            0.07
Part-To-Part           0.698633           99.93
Total Variation        0.699137          100.00


                                      Study Var   %Study Var
Source                 StdDev (SD)     (6 * SD)        (%SV)
Total Gage R&R            0.022457      0.13474         2.69
  Repeatability           0.000000      0.00000         0.00
  Reproducibility         0.022457      0.13474         2.69
    Operator              0.006288      0.03773         0.75
    Operator*Sample       0.021558      0.12935         2.58
Part-To-Part              0.835843      5.01506        99.96
Total Variation           0.836144      5.01687       100.00


Number of Distinct Categories = 52




                                                                                      10
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
 Gage R&R Study
                                                                                               Reported by :
 G age name:                                                                                   Tolerance:
 D ate of study :                                                                              M isc:


                                         Components of Variation                                                                      Over 6 hr precalibration time by Sample
                       100                                                          % Contribution      4.5
                                                                                    % Study Var
                                                                                                        3.0
      Percent




                                                                                                        1.5
                        50
                                                                                                                   a ta ll e m n o d us d a s n er it le rg l le n a s a es is mi rd o i a ok h d w co is ul t e o re
                                                                                                                 on n svi he st o ag la n b oo all yto nv tr o da u sv i st o n s in d e l ph i a f o nd ph r o rg la n na c s ou Pa e led ar
                                                                                                                                                                                                                             i
                                                                                                              t o tla l t le o i c e m w D Da De De er ri is b ick ou Ka a L ng em M M il r la de eb s buort agi a n t L St t P To sb
                                                                                                            A l A Be t h B Ch lev o lo es t               u d a H H om s A M                      O i la in it t P S F r S        S         e
                                                                                                                     Be          C C Cr                                                                                                i lk
                         0                                                                                                                              La H              L Lo                     Ph P P            n               W
                                                                                                                                                     Ft                                                           Sa
                              Gage R&R      Repeat       Reprod    Part-to-Part
                                                                                                                                                                                     Sample
                                           R Chart by Operator
                                                                                                                                    Over 6 hr precalibration time by Operator
                              Bernard                Ramesh
                       0.5                                                                              4.5
     Sample Range




                                                                                  _                     3.0
                       0.0                                                        LCL=0
                                                                                  UCL=0
                                                                                  R=0
                                                                                                        1.5

                       -0.5                                                                                                                   Bernard                                                                     Ramesh
                                                                                                                                                                                  Operator
                                         Xbar Chart by Operator
                              Bernard                Ramesh                                                                              Operator * Sample Interaction
                       4.5
                                                                                                                4.5
                                                                                                                                                                                                                                            Operator




                                                                                                      Average
         Sample Mean




                                                                                                                3.0                                                                                                                         Bernard
                       3.0                                                                                                                                                                                                                  Ramesh
                                                                                  _
                                                                                  _                             1.5
                                                                                  LCL=2.146
                                                                                  UCL=2.146
                                                                                  X=2.146
                                                                                                                                a ta l le m n o d us d a s n er it l e rg l l e n a s a es is m ir d o ia ok h d w co is u l te o re
                       1.5                                                                                                o n n svi he sto ag la n b ooally ton v t roda u svi to ns indel p hi a fo ndphr o rg la nna cis ouP a e leda r
                                                                                                                        to t l a t le o ic e mw D a e e r isb ck s a L g m M il la e b bur t gi n L t P o b
                                                                                                                                 l
                                                                                                                      Al A Be th B C hevo loes t D D D dea r i HiHo u K a AnM e MO rlad inei tts PoS a r a St S St Tk es
                                                                                                                             Be           Cl C Cr              u                ms                 i             F               il
                                                                                                                                                            La H             Lo L o             Ph P P        n               W
                                                                                                                                                        Ft                                                 Sa

                                                                                                                                                                          Sample




Data Normality
Data was collected on average pre- time calibration by pharmacy for June09 and it
showed it was normal.

                                                                       Normality Test for
                                                                                      Normal
                       99
                                                                                                                                                                                                                       Mean                  8.151
                                                                                                                                                                                                                       StDev                0.8384
                       95                                                                                                                                                                                              N                        35
                                                                                                                                                                                                                       AD                    0.180
                       90
                                                                                                                                                                                                                       P-Value               0.910
                       80
                       70
  Percent




                       60
                       50
                       40
                       30
                       20

                       10

                         5


                         1
                              6                      7               8             9                                                                                           10
                                                            Average precal time June


                                                                                                                                                                                                                                                       11
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc



         Process Capability
                                                  Process Capability Sixpack of Average precal time June
                                                                     I Chart                                                  Capability Histogram
                                                                                                                        LSL                     USL
                                                                                                         UCL=10.669
                                                                                                                                                                      S pecifications
          Individual Value


                                 10.0
                                                                                                         _                                                               LS L 0
                                                                                                         X=8.151                                                         USL 6
                                  7.5


                                                                                                         LCL=5.633
                                  5.0
                                          1   4   7    10     13     16   19   22   25   28   31   34                   0.0   1.5   3.0   4.5   6.0    7.5   9.0

                                                            Moving Range Chart                                                            Normal Prob Plot
                                                                                                         UCL=3.093
                                                                                                                                          A D : 0.180, P : 0.910
                                  3.0
                  Moving Range




                                  1.5
                                                                                                         __
                                                                                                         MR=0.947

                                  0.0                                                                    LCL=0
                                          1   4   7    10     13     16   19   22   25   28   31   34                   5.0                      7.5                      10.0

                                                        Last 25 Observations                                                              Capability Plot
                                                                                                                             Within               Within                O v erall
                                      9
                                                                                                                      S tD ev 0.839367                             S tDev 0.838408
                             Values




                                      8
                                                                                                                      Cp       1.19                                Pp      1.19
                                                                                                                                                 O v erall
                                                                                                                      C pk     -0.85                               P pk    -0.86
                                      7                                                                                                                            C pm    *
                                                                                                                                                  S pecs
                                                  15           20            25          30         35
                                                                    Observation


For the process capability calculations, the lower Specification limit was chosen as 0
hours and the upper limit was taken at 6 hours. The Cpk value of - 0.85 shows that the
process capability is less than favorable and there is vast scope for improvement.




                                                                                                                                                                    12
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc




         Data Collection
Data collection for the Measure phase was collected from TRON queries that measured
the average pre-calibration time across the pharmacy network for June09. This was taken
as the baseline.

For this project the Average pre-calibration time is taken as the (Y). The pre-calibration
time is defined as the time elapsed between the expected delivery time of the product and
its calibration time.




                                                                                        13
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc




                                                                   14
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc

                    Baseline Metrics
           From the data collected in June09 the report showed the following baselines

Baseline Measurements
                   Jun-09


Pharmacy                    Average Time over Delivery time( Bulks)         Average Precalibration time June


Ft Lauderdale                                 5.12                                        7.87
Crestwood                                     5.00                                        9.60
Kansas                                        2.00                                        7.95
Chicago                                       3.00                                        7.87
St Louis                                      6.25                                        6.98
Orlando                                       3.00                                        8.98
St Pete                                       3.00                                        7.87
Miami                                         4.00                                        9.04
Memphis                                       0.00                                       10.00
Atlanta                                       5.00                                        8.81
Boston                                        3.00                                        6.62
Wilkesbarre                                   3.00                                        7.12
Milford                                       3.00                                        7.41
Pinebrook                                     3.00                                        7.21
Hicksville                                    3.00                                        8.11
Hariisburg                                    4.00                                        7.80
Bethlehem                                     4.00                                        7.43
Altoona                                       4.25                                        7.38
Philadephia                                   3.00                                        8.10
Dallas                                        4.00                                        9.20
Los Angeles                                   3.00                                        7.52
Loma Linda                                    2.00                                        8.24
San Francisco                                 3.00                                        7.68
St Paul                                       3.00                                        9.50
Portland                                      4.00                                        8.34
Denver                                        3.00                                        8.12
Houston                                       3.00                                        8.46
Saginaw                                       2.15                                        7.62
Toledo                                        3.00                                        8.85
Colombus                                      3.00                                        6.65
Dayton                                        2.00                                        8.56
Detroit                                       3.00                                        8.66
Beltsville                                    3.00                                        8.67
Cleveland                                     3.00                                        9.25
Pittsburgh                                    3.00                                        7.81


Average                                       3.25                                        8.15



                                                                                                 15
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc


      Savings Summary
Tc-99 Conservation Plan
Annual Summary Impact

                          Bulk         Precal
Beltsville                 201,617       24,697
Cleveland                  182,709       21,821
Hicksville                 136,829       47,663
Pinebrook                  165,864        6,599
Dallas                     141,738       39,835
Los Angeles                142,937        4,037
St Pete                    148,092        9,581
Denver                     124,645        4,459
Orlando                    107,840       13,175
Pittsburgh                  81,113       52,328
Crestwood                  107,076       34,832
St Paul                     95,212       12,132
Boston                     113,921        4,489
Harriburg                   80,833        5,568
Detroit                     73,360        3,802
Chicago                     66,786        5,666
Milford                     63,819          776
Dayton                      38,784        6,496
Altoona                     71,915       15,905
Wilkes Barre                60,352        3,273
St Louis                    53,632        8,019
Bethlehem                   63,835        4,635
Houston                     25,771        2,203
Ft Lauderdale               54,235        5,967
Colombus                    33,115       14,977
Philadelphia                45,994        5,390
Atlanta                     40,616        5,900
Portland                    21,396        3,756
San Francisco               27,539        4,327
toledo                      22,373        5,967
Kansas City                 20,967        6,968
Saginaw                     23,145        1,298
Miami                       29,064        7,046
Loma Linda                  10,599       11,210
Cinci                        9,582        1,516
Memphis                         -         5,151
                         $2,687,299    $411,461

Bulk = All doses sold as Bulk calibrated at expected delivery time

Precal = All unit doses which exceed a 6 hour window between expected delivery and calibration time




                                                                                           16
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc



   Analyze

            Basic Statistics
Basic statistics were gathered on the key output to determine stability and shape.
Normality test was also done on the key output which showed data as a normal curve.

                        Summary for Average precal time June
                                                                               A nderson-D arling N ormality Test
                                                                                   A -S quared         0.18
                                                                                   P -V alue          0.910

                                                                                   M ean              8.1511
                                                                                   S tDev             0.8384
                                                                                   V ariance          0.7029
                                                                                   S kew ness       0.223511
                                                                                   Kurtosis        -0.483646
                                                                                   N                      35

                                                                                   M inimum          6.6209
                                                                                   1st Q uartile     7.5226
                                                                                   M edian           8.0986
                                                                                   3rd Q uartile     8.8137
                  7                  8               9           10                M aximum         10.0000
                                                                              95% C onfidence Interv al for M ean
                                                                                   7.8631            8.4391
                                                                              95% C onfidence Interv al for M edian
                                                                                   7.8038            8.5280
                                                                              95% C onfidence Interv al for S tDev
                            9 5 % C onfidence Inter vals
                                                                                   0.6782            1.0985
   Mean


  Median

           7.8        8.0                8.2               8.4         8.6




The Mean of the data was 8.15 hours while the median is 8.09 which indicate both are
very close to each other.

Descriptive Statistics: Average precal time June

Variable                             N    N*     Mean      SE Mean    StDev   Minimum           Q1       Median
Average precal time June            35     0    8.151        0.142    0.838     6.621        7.523        8.099

Variable                               Q3      Maximum
Average precal time June            8.814       10.000




                                                                                                                    17
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc


                                 Graphical Analysis
                                 Box plot of Pre-calibration time by pharmacy showed there exists a difference
                                 between means of data between pharmacies of different size. The pre-
                                 calibration time variation among pharmacies showed there was a lack of
                                 standardized policy related to pre-calibration time. The frequency graph shows
                                 historically there have been excessive pre-calibration times practiced at
                                 multiple sites with times extending as far as midnight which accounts for
                                 substantial product decay and lost revenue.

                                            Boxplot of Average Precalibration time

                              10.0

                               9.5
Average Precalibration time




                               9.0

                               8.5

                               8.0

                               7.5

                               7.0

                               6.5
                                           Large                 Medium                   Small
                                                              Pharmacy Size




                                                                                                             18
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
                              Graph of Calibration time V/s Frequency
             90

             80

             70

             60
 Frequency




             50

             40

             30

             20

             10

             0
                  10:30:00 12:30:00 13:00:00 13:15:00 13:30:00 13:45:00   14:45:00 16:00:00 23:59:00
                                                 Calibration time




                   Hypothesis Testing
                   Regression
                   A Regression analysis was performed with the Key input variables and the Key
                   output variable. The Calibration time and Expected delivery time are the critical
                   Project Input Variable (KPIV) with the highest correlation to Average Pre-
                   calibration time and is the root cause for pharmacies having excessive pre-
                   calibration time. In addition some of the other critical inputs such as TRON and
                   customer contracts were also taken into consideration for the Improve phase. A
                   another regression equation was also tested to see correlation between Value of
                   Tech waste due to excessive pre-calibration time and the Pre-calibration time
                   and there exists a high degree of correlation between them.

Regression Analysis: Average over 6 h versus Activity, ASP,

The regression equation is
Average over 6 hour Precal = - 4.99 - 0.00775 Activity - 0.31 ASP
                             + 20.6 Calibration time - 19.3 Delivery time


Predictor                             Coef        SE Coef            T           P
Constant                           -4.9892         0.4866       -10.25       0.000
Activity                         -0.007749       0.006703        -1.16       0.257
ASP                                 -0.314          1.081        -0.29       0.774
Calibration time                    20.556          1.088        18.88       0.000
Delivery time                      -19.292          1.504       -12.83       0.000


S = 0.219942                 R-Sq = 95.2%          R-Sq(adj) = 94.5%




                                                                                                       19
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
Analysis of Variance

Source           DF        SS         MS        F        P
Regression        4   28.5317     7.1329   147.45    0.000
Residual Error   30    1.4512     0.0484
Total            34   29.9829


Source             DF    Seq SS
Activity            1    0.1078
ASP                 1    0.0673
Calibration time    1   20.3951
Delivery time       1    7.9615




Regression Analysis: Tech value o versus Average over, Activity, ASP

The regression equation is
Tech value over 6 hour precal = - 864 + 296 Average over 6 hour Precal
                                + 79.8 Activity - 2450 ASP


Predictor                        Coef   SE Coef         T        P
Constant                         -864      1772     -0.49    0.629
Average over 6 hour Precal      296.3     143.4      2.07    0.048
Activity                        79.83     25.16      3.17    0.004
ASP                             -2450      5589     -0.44    0.664


S = 780.531    R-Sq = 32.4%       R-Sq(adj) = 25.4%


Analysis of Variance

Source           DF         SS          MS      F        P
Regression        3    8465699     2821900   4.63    0.009
Residual Error   29   17667618      609228
Total            32   26133318


T-Test- A 2 sample T test was also conducted to test the difference between Average
Pre-calibration time in June before the project was implemented and the time in October
after implementation. The analysis showed that the pre-calibration time dropped by an
average 1 hour with the project implementation.

Two-Sample T-Test and CI: Average precal time June, Average Precal time Oct

Two-sample T for Average precal time June vs Average Precal time Oct

                              N     Mean   StDev    SE Mean


                                                                                      20
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
Average precal time June      35   8.151   0.838      0.14
Average Precal time Oct       35   7.151   0.838      0.14


Difference = mu (Average precal time June) - mu (Average Precal time Oct)
Estimate for difference: 1.000
95% CI for difference: (0.600, 1.400)
T-Test of difference = 0 (vs not =): T-Value = 4.99 P-Value = 0.000 DF = 68
Both use Pooled StDev = 0.8384


          Results
Since the p-value is less than 0.05 we reject the null hypothesis which was taken as there
was no difference between the 2 populations and conclude that there is a positive
difference between the pre-calibration time measured before the project was implemented
to the time measured after which means the time has decreased since project
implementation and this is a favorable impact resulting from the project.




                 Project X’s
Key input variables coming out of the Analyze were

Calibration time – This is the time at which the requested dose is used for its intended
application. The pharmacist calculates activity that needs to be filled based on customer
requested calibration time.
Delivery time – This is the time when the customer requests delivery of the product at
it’s location.
Customer Contract – Contract is a binding document between Covidien and the
customer which contains information related to pricing, dose limits, calibration times and
freight policy. All negotiated contracts define the long-term commitment between
Covidien and its customers.
TRON – The system used by the pharmacy network to carry out all operations from
order processing to delivery of finished product. Since it’s a central processing system for
the network, it has a significant impact on operations related to Technetium products.




                                                                                           21
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc




.




             Improve
         Solutions Identified

Critical inputs from the Analyze phase was taken into consideration for improvement in
this phase and the “Tc Conservation program” which was launched across the network
captures all the improvements which were implemented in the field to achieve the desired
objective of reducing pre-calibration time and capturing lost revenue due to excessive
pre-calibration time.

Current issues identified with Tc-99m utilization

Significant amount of Tc-99 decaying at the customer site (~6hrs)
        - 50% of all doses dispensed with greater than 6 hours time
        - much bulk-tech is ordered with pre-cal for 12:00 am
        - In past, customers believed “Tc-99 is cheap”, the agent is expensive
        - customers like security of receiving daily doses early
        - past delivery issues may drive behavior for this “insurance” time
        - lack of standardized calibration policy and no pre-calibration limits in TRON

Tech Conservation - Opportunity

Valuing the saved material at current ASP -> Huge $$$’s
• Allows greater patient access to Tc-99m or charge for overage
• With generator shortages now and in FY10, we need fast action


                                                                                          22
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
• Excellent time to begin changing market behavior
• Next Steps
       - Meeting held with IS requesting TRON changes (80 hrs)
       - Roll out with Sales management on 8/10/09
       - Rep and pharmacy web-training (8/28 & 8/31)
       - Customer letter from marketing distributed on 9/1.
       - Reps have customer discussions in September
       - Target Go Live targeted for 9/26/09 (first day of FY10)




Customer Letter – Summary of Program:

Customer letter will be sent on 9/01/09, which will explain….

• Ongoing concern over global Moly supply
• Significant investment required to improve availability
• Our goal to increase patient access to Tc-99m based products
• Covidien committed to servicing maximum number of patients
• New conservation programs beginning on Sept. 26th, 2009(est.)
• To promote lower pre-calibration times, Covidien will charge for pre-calibration
activity beyond six hours
• New charges will be based on bulk Tc-99 pricing
• Bulk Tc-99 will be calibrated for actual delivery time, unless customer chooses to pay
for additional activity

Example #1 - Limit pre-calibration to 6 hours (expected delivery to cal time)

Example: Customer orders 30 mCi of Sestamibi calibrated for
1300, but wants it delivered with an expected delivery time of
0600. This would trigger a charge up, using the R005A0 code and
decay factor to charge them the customer’s bulk Tc-99m charge
(say $0.31/mci). We would charge the customer for the hours
beyond the 6 hr limit. In this case, it is one hour, so we would

                                                                                      23
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
              charge the customer $0.31 x (30mCi/.891)-30 mCi = $1.14 using a
              new item code R005PC – TC-99M PRE-CAL OVER TIME
              LIMIT which will be attached to the dose for reimbursement

              Bulk tech will no longer be calibrated past delivery times.




   Customer Impact Analysis - example
  This is a calculation of the new cost to each customer if they do not change.
  Example from the month of June:
Customer Name                                    Tech Value over recommended qty    Tech value over 6 hrs pre-cal at ASP
ALBERT EINSTEIN MED CTR Total                                               $0.00                               $1,826.52
ATLANTIC MEDICAL IMAGING,GALLOWAY,NJ Total                                  $0.00                                   $31.39
BOOTH RADIOLOGY Total                                                       $0.00                                   $98.36
CAPE MAY COURT HOUSE AMI Total                                              $0.00                                   $23.97
CARDIAC DIAGNOSTIC CENTER,LEWES,DE Total                                    $0.00                                    $0.96
CARDIAC DIAGNOSTIC CENTER,MIDDLETOWN,DE Total                               $0.00                                   $32.96
CARDIAC DIAGNOSTIC CENTER,WILMINGTON,DE Total                               $0.00                                    $2.04
CARDIOLOGY MEDICAL ASSOC,PHILADELPHIA,PA Total                              $0.00                                   $45.27
CARDIOVASCULAR SOLUTIONS,PHILADELPHIA,PA Total                              $0.00                                  $116.50
CHERRY HILL CARDIAC DIAGNOSTIC Total                                        $0.00                                  $111.73
COMM MED CTR Total                                                        $134.85                                  $473.56
DOVER CDC,DOVER,DE Total                                                    $1.55                                    $1.15
EINSTEIN CTR ONE RADIOLOGY Total                                            $1.55                                   $84.30
KIMBALL MEDICAL CENTER,LAKEWOOD,NJ Total                                    $0.00                               $1,690.34
LINWOOD AMI Total                                                           $0.00                                   $46.51
METHODIST HOSPITAL,PHILADELPHIA,PA Total                                    $0.00                                  $313.70
MOSS REHAB/EINSTEIN AT ELKINS PARK Total                                    $0.00                                  $371.03
NORTH WILMINGTON CDC Total                                                  $0.00                                    $2.04
PAMI Total                                                                  $0.00                                   $59.12
RADIOLOGY ASSOCIATES,WILMINGTON,DE Total                                    $0.00                                   $11.92
SOUTH JERSEY HEART GROUP,SEWELL,NJ Total                                    $0.00                                    $1.97
THOMAS JEFFERSON U HOSP Total                                               $0.00                                  $185.50
UNION HOSP OF CECIL CNTY Total                                              $0.00                               $1,343.71
WACHSPRESS & SHATKN CARDIO, VINELAND, NJ Total                              $0.00                                   $27.97
                                                                                                             24
Grand Total                                                               $139.50                               $7,013.32
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc




                                                                   25
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc

    Sales Rep Actions & Timeline:
• Study the customer letter and understand the key points
• Review the customer impact analysis with Regional manager
• Work with pharmacy manager
• Develop preliminary plan using customer knowledge to minimize customer
impact
• Shift doses to later deliveries, while minimizing impact on delivery costs
• Visit with customers
• Provide the customer a choice to remain with the status quo or shift schedule
• Finalize a plan for each customer with your pharmacy
• Understand changes to invoices

• Corporate will add pricing for bulk tech at rep guideline for customers
not having this item code currently on their contract

8/28 or 8/31      Wk of 8/31         Wk of 9/7           Wk of 9/14              Wk of 9/21           Sat. 9/26


                                                         - Meet with customers
 Attend                          - Meet with customers                           Finalize plan with    -Target Go Live
 Web-       Meet with Reg. Mgr                                                   pharmacy
 training   Meet with pharmacy
             team
            Review customers
            Develop plan




                                                                                                                         26
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc

  Sales Rep talk track:
• Reference the customer letter
• Explain that Tc-99m shortage will continue far into 2010
• Our focus is on increasing patient access to Tc-99m products
• Asked your customers to use Tc-99m more efficiently
• Explain how doses can be delivered on later runs
 If they purchase bulk tech, explain new pre-calibration policy
 Give them their options for:
            1       Unit doses with excess (> 6 hours) of calibration
                    a.) Move doses to later scheduled runs
                    b.) Pay for extra activity
            2       Bulk Tc-99m orders
                    a.) Move orders to later scheduled runs
                    b.) Reduce sizes of bulk Tc-99m orders
                    c.) Pay for extra activity
                    d.) Eliminate bulk Tc-99m orders and utilize STAT unit dose
                    orders where needed.
 • It’s the customers choice
• Use your Tools -> Moly calendar, delivery schedules, customer impact
                  analysis, Moly shortage update letter




Pharmacy Managers Actions:
• Study the customer letter and understand the key points
• Review the customer impact analysis with your sales team
• Develop a preliminary plan to minimize customer impact
• Ensure you are capturing accurate expected delivery times in TRON for
all customer orders.
• Consider shifts in delivery schedules without increasing costs
• Utilize existing scheduled runs and routes
• If freight costs exceed Tc-99m savings, exceptions approved by VP Ops, VP
of Sales, and Marketing through email.
• Make certain to capture freight revenue for these exception accounts
• Understand changes to TRON and invoices
• Finalize a plan for each customer
• On Go Live date, begin calibrating all bulk tech at delivery time

• Note that corporate will add pricing for bulk tech at rep guideline for
customers not having this item code currently on their contract




                                                                                  27
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc

  TRON Invoice change?

Invoices will show the added Tc-99 charges similar to I-131 caps.

Invoices will reflect any necessary surcharges on the line following the applicable dose,
assigned to the same prescription number for reporting ease.

The following product codes and descriptions will appear to indicate the surcharge type(s):

R005PC - TC-99M SODIUM PERTECHNETATE ACTIVITY OVER PRE-CALIBRATION
TIME LIMIT (PER MCI)




                                                                                            28
improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc
 Control
         The updated process flow shows the changes made to the TRON pharmacy
         system to generate invoices capturing the surcharge for products exceeding the
         6 hour pre-calibration limit.
         Updated Process Map

                    Updated Process Flow Map for Tc 99 Precalibration



                               Pharmacy receives Customer Standing /
Calibration time,                  Demand Order for Tech dose
 Delivery time                                                                Pharmacist
                                                                             enters order in
                                                                               TRON and
                                                                               generates
                                                                              prescription



                                Dispense Dose with activity related to                    Check
                                          calibration time                                Order




                                      Is dose matching with BOL
                                                                                 NO


                                  YES


                                     Tech dose is ship confirmed




                                      Is unit dose over 6 hour pre -          YES
                                  calibration?Bulk dose over delivery
                                                  time?
                                                                                      Excess
                                                                                     surcharge
                                                                                      billed to
                                                    NO
                                                                                     customer
                                                                                      invoice
                               Dose delivery to customer at requested
                                   delivery and calibration time

                                                                            Pharmacy
                                                                            Invoicing
                                                                               $$
                              Pharmacy bills customer and collects sales
                                       revenue for dose sale


                                                                             Exception sent to
                                                                                 Pricing for
                                                                              adjustment and
                                                                                 surcharge
                              Pharmacy adds new customer , negotiates         adjusted to $0
                             existing customer contracts , communicates
                                   any change in policy or contract
                                                                             Exception raised if
                                                                              freight revenue
                                                                               exceeds Tech
                                Customer changes delivery schedule ,              savings
                              adjusts calibration times to adhere to Tech
                                        Conservation program




                                                                                                   29
Improve Tech Pre Calibration Project Book
Improve Tech Pre Calibration Project Book
Improve Tech Pre Calibration Project Book
Improve Tech Pre Calibration Project Book
Improve Tech Pre Calibration Project Book
Improve Tech Pre Calibration Project Book
Improve Tech Pre Calibration Project Book
Improve Tech Pre Calibration Project Book
Improve Tech Pre Calibration Project Book
Improve Tech Pre Calibration Project Book

Contenu connexe

Tendances

PPM STUDIO for CMMI
PPM STUDIO for CMMIPPM STUDIO for CMMI
PPM STUDIO for CMMIPPM Studio
 
Stephen K. Allott - People Challenges for Test Teams - SoftTest Ireland
Stephen K. Allott - People Challenges for Test Teams - SoftTest IrelandStephen K. Allott - People Challenges for Test Teams - SoftTest Ireland
Stephen K. Allott - People Challenges for Test Teams - SoftTest IrelandDavid O'Dowd
 
Using HP Quality Center 10.0 Premier to introduce processes and control into ...
Using HP Quality Center 10.0 Premier to introduce processes and control into ...Using HP Quality Center 10.0 Premier to introduce processes and control into ...
Using HP Quality Center 10.0 Premier to introduce processes and control into ...Michael Deady
 
The New Distribution Strategy And How IT Enables It
The New Distribution Strategy And How IT Enables ItThe New Distribution Strategy And How IT Enables It
The New Distribution Strategy And How IT Enables ItSubhan Novianda
 
Vericenter Summary
Vericenter SummaryVericenter Summary
Vericenter Summarydeyoepw
 
Pbi Marcus Evans Sept2011presentation
Pbi Marcus Evans Sept2011presentationPbi Marcus Evans Sept2011presentation
Pbi Marcus Evans Sept2011presentationMichaelMcNamara
 
IBM Rational Software Conference 2009 Day 1 Keynote: Jamie Thomas
IBM Rational Software Conference 2009 Day 1 Keynote: Jamie ThomasIBM Rational Software Conference 2009 Day 1 Keynote: Jamie Thomas
IBM Rational Software Conference 2009 Day 1 Keynote: Jamie ThomasKathy (Kat) Mandelstein
 
Overview of CMMI and Software Process Improvement
Overview of CMMI and Software Process ImprovementOverview of CMMI and Software Process Improvement
Overview of CMMI and Software Process ImprovementNelson Piedra
 
Integrated methodology for testing and quality management.
Integrated methodology for testing and quality management.Integrated methodology for testing and quality management.
Integrated methodology for testing and quality management.Mindtree Ltd.
 
IIE Call For Paper
IIE Call For PaperIIE Call For Paper
IIE Call For Papermdmilward
 
Delivering ERP Excellence Through Testing Excellence - T-mobile USA and SAP S...
Delivering ERP Excellence Through Testing Excellence - T-mobile USA and SAP S...Delivering ERP Excellence Through Testing Excellence - T-mobile USA and SAP S...
Delivering ERP Excellence Through Testing Excellence - T-mobile USA and SAP S...SAP Solution Extensions
 
Upgrades and enhancement_packs_explained_mar_2008
Upgrades and enhancement_packs_explained_mar_2008Upgrades and enhancement_packs_explained_mar_2008
Upgrades and enhancement_packs_explained_mar_2008sissie1234
 
Predictable testing for faster time to market.
Predictable testing for faster time to market.Predictable testing for faster time to market.
Predictable testing for faster time to market.Mindtree Ltd.
 
Requirements Management Booklet Pages
Requirements Management Booklet PagesRequirements Management Booklet Pages
Requirements Management Booklet PagesTonda MacLeod
 
NG BB 53 Process Control [Compatibility Mode]
NG BB 53 Process Control [Compatibility Mode]NG BB 53 Process Control [Compatibility Mode]
NG BB 53 Process Control [Compatibility Mode]Leanleaders.org
 

Tendances (18)

PPM STUDIO for CMMI
PPM STUDIO for CMMIPPM STUDIO for CMMI
PPM STUDIO for CMMI
 
Stephen K. Allott - People Challenges for Test Teams - SoftTest Ireland
Stephen K. Allott - People Challenges for Test Teams - SoftTest IrelandStephen K. Allott - People Challenges for Test Teams - SoftTest Ireland
Stephen K. Allott - People Challenges for Test Teams - SoftTest Ireland
 
Using HP Quality Center 10.0 Premier to introduce processes and control into ...
Using HP Quality Center 10.0 Premier to introduce processes and control into ...Using HP Quality Center 10.0 Premier to introduce processes and control into ...
Using HP Quality Center 10.0 Premier to introduce processes and control into ...
 
Krishnan_Resume
Krishnan_ResumeKrishnan_Resume
Krishnan_Resume
 
The New Distribution Strategy And How IT Enables It
The New Distribution Strategy And How IT Enables ItThe New Distribution Strategy And How IT Enables It
The New Distribution Strategy And How IT Enables It
 
Vericenter Summary
Vericenter SummaryVericenter Summary
Vericenter Summary
 
Buvan kumar resume
Buvan kumar resumeBuvan kumar resume
Buvan kumar resume
 
Pbi Marcus Evans Sept2011presentation
Pbi Marcus Evans Sept2011presentationPbi Marcus Evans Sept2011presentation
Pbi Marcus Evans Sept2011presentation
 
IBM Rational Software Conference 2009 Day 1 Keynote: Jamie Thomas
IBM Rational Software Conference 2009 Day 1 Keynote: Jamie ThomasIBM Rational Software Conference 2009 Day 1 Keynote: Jamie Thomas
IBM Rational Software Conference 2009 Day 1 Keynote: Jamie Thomas
 
Overview of CMMI and Software Process Improvement
Overview of CMMI and Software Process ImprovementOverview of CMMI and Software Process Improvement
Overview of CMMI and Software Process Improvement
 
Integrated methodology for testing and quality management.
Integrated methodology for testing and quality management.Integrated methodology for testing and quality management.
Integrated methodology for testing and quality management.
 
IIE Call For Paper
IIE Call For PaperIIE Call For Paper
IIE Call For Paper
 
Delivering ERP Excellence Through Testing Excellence - T-mobile USA and SAP S...
Delivering ERP Excellence Through Testing Excellence - T-mobile USA and SAP S...Delivering ERP Excellence Through Testing Excellence - T-mobile USA and SAP S...
Delivering ERP Excellence Through Testing Excellence - T-mobile USA and SAP S...
 
Heizer 02
Heizer 02Heizer 02
Heizer 02
 
Upgrades and enhancement_packs_explained_mar_2008
Upgrades and enhancement_packs_explained_mar_2008Upgrades and enhancement_packs_explained_mar_2008
Upgrades and enhancement_packs_explained_mar_2008
 
Predictable testing for faster time to market.
Predictable testing for faster time to market.Predictable testing for faster time to market.
Predictable testing for faster time to market.
 
Requirements Management Booklet Pages
Requirements Management Booklet PagesRequirements Management Booklet Pages
Requirements Management Booklet Pages
 
NG BB 53 Process Control [Compatibility Mode]
NG BB 53 Process Control [Compatibility Mode]NG BB 53 Process Control [Compatibility Mode]
NG BB 53 Process Control [Compatibility Mode]
 

Similaire à Improve Tech Pre Calibration Project Book

A Radical Challenge in Reliability Dynamic Life Test.pdf; Burn-In program Con...
A Radical Challenge in Reliability Dynamic Life Test.pdf; Burn-In program Con...A Radical Challenge in Reliability Dynamic Life Test.pdf; Burn-In program Con...
A Radical Challenge in Reliability Dynamic Life Test.pdf; Burn-In program Con...Phillip Chan
 
Infodream Articles about Continuous Improvement, Aerospace, Quality Control a...
Infodream Articles about Continuous Improvement, Aerospace, Quality Control a...Infodream Articles about Continuous Improvement, Aerospace, Quality Control a...
Infodream Articles about Continuous Improvement, Aerospace, Quality Control a...Infodream
 
Sonu balasubramanian agile_qtp_selenium
Sonu balasubramanian  agile_qtp_seleniumSonu balasubramanian  agile_qtp_selenium
Sonu balasubramanian agile_qtp_seleniumSonu Balasubramanian
 
Bba501 & production and operations management
Bba501 & production and operations managementBba501 & production and operations management
Bba501 & production and operations managementsmumbahelp
 
Om0015 maintenance management
Om0015   maintenance managementOm0015   maintenance management
Om0015 maintenance managementStudy Stuff
 
RCA Presentation V0 1
RCA Presentation V0 1RCA Presentation V0 1
RCA Presentation V0 1Ian McDonald
 
Om0015 maintenance management
Om0015   maintenance managementOm0015   maintenance management
Om0015 maintenance managementsmumbahelp
 
Om0015 maintenance management
Om0015   maintenance managementOm0015   maintenance management
Om0015 maintenance managementsmumbahelp
 
Deepika_Sr. Tester(QA)
Deepika_Sr. Tester(QA)Deepika_Sr. Tester(QA)
Deepika_Sr. Tester(QA)DEEPIKA MANTOO
 
Odoo Implementation Methodology
Odoo Implementation MethodologyOdoo Implementation Methodology
Odoo Implementation MethodologyQuang Ngoc
 
Odoo implementation
Odoo implementationOdoo implementation
Odoo implementationOdoo Thaidev
 
KingGregory_ExpandedResume 20160808
KingGregory_ExpandedResume 20160808KingGregory_ExpandedResume 20160808
KingGregory_ExpandedResume 20160808Gregory King II
 
Rapid Deployment of BMC Remedy Solutions 2006
Rapid Deployment of BMC Remedy Solutions 2006Rapid Deployment of BMC Remedy Solutions 2006
Rapid Deployment of BMC Remedy Solutions 2006Antonio Rolle
 

Similaire à Improve Tech Pre Calibration Project Book (20)

A Radical Challenge in Reliability Dynamic Life Test.pdf; Burn-In program Con...
A Radical Challenge in Reliability Dynamic Life Test.pdf; Burn-In program Con...A Radical Challenge in Reliability Dynamic Life Test.pdf; Burn-In program Con...
A Radical Challenge in Reliability Dynamic Life Test.pdf; Burn-In program Con...
 
Infodream Articles about Continuous Improvement, Aerospace, Quality Control a...
Infodream Articles about Continuous Improvement, Aerospace, Quality Control a...Infodream Articles about Continuous Improvement, Aerospace, Quality Control a...
Infodream Articles about Continuous Improvement, Aerospace, Quality Control a...
 
Pravin_CV_4+years
Pravin_CV_4+yearsPravin_CV_4+years
Pravin_CV_4+years
 
Sonu balasubramanian agile_qtp_selenium
Sonu balasubramanian  agile_qtp_seleniumSonu balasubramanian  agile_qtp_selenium
Sonu balasubramanian agile_qtp_selenium
 
Incognito factors in web applications
Incognito factors in web applicationsIncognito factors in web applications
Incognito factors in web applications
 
Prasanth Namama_Resume
Prasanth Namama_ResumePrasanth Namama_Resume
Prasanth Namama_Resume
 
Vandana B
Vandana BVandana B
Vandana B
 
S3 p2 lee_kong_hui
S3 p2 lee_kong_huiS3 p2 lee_kong_hui
S3 p2 lee_kong_hui
 
Bba501 & production and operations management
Bba501 & production and operations managementBba501 & production and operations management
Bba501 & production and operations management
 
Om0015 maintenance management
Om0015   maintenance managementOm0015   maintenance management
Om0015 maintenance management
 
RCA Presentation V0 1
RCA Presentation V0 1RCA Presentation V0 1
RCA Presentation V0 1
 
Om0015 maintenance management
Om0015   maintenance managementOm0015   maintenance management
Om0015 maintenance management
 
Gears agile
Gears agileGears agile
Gears agile
 
Om0015 maintenance management
Om0015   maintenance managementOm0015   maintenance management
Om0015 maintenance management
 
Deepika_Sr. Tester(QA)
Deepika_Sr. Tester(QA)Deepika_Sr. Tester(QA)
Deepika_Sr. Tester(QA)
 
Odoo Implementation Methodology
Odoo Implementation MethodologyOdoo Implementation Methodology
Odoo Implementation Methodology
 
Odoo implementation
Odoo implementationOdoo implementation
Odoo implementation
 
KingGregory_ExpandedResume 20160808
KingGregory_ExpandedResume 20160808KingGregory_ExpandedResume 20160808
KingGregory_ExpandedResume 20160808
 
Rapid Deployment of BMC Remedy Solutions 2006
Rapid Deployment of BMC Remedy Solutions 2006Rapid Deployment of BMC Remedy Solutions 2006
Rapid Deployment of BMC Remedy Solutions 2006
 
Feasible
FeasibleFeasible
Feasible
 

Improve Tech Pre Calibration Project Book

  • 1. DMAIC Project Report Please Select Belt Type: DMAIC BB DMAIC GB Project Title:      Improve Technetium Pre-calibration Project Number (1st, 2nd, 3rd…):      2nd Instantis Project ID#:       Project Leader Name:      Ramesh Rajan Project Leader Job Title:      Process Engineer Imaging Solutions/Nuclear Pharmacy Segment/GBU/Division/Plant/Region: Operations
  • 2. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Executive Summary The Nuclear pharmacy network comprises 1/3 of the total Imaging division revenue. Technetium-99 is a primary radioactive isotope which is used for various diagnostic procedures at hospitals, imaging centers etc. This represents 80% of the pharmacy product portfolio. The product has an extremely short shelf life; a 6 hour half-life and hence is critical that it be used efficiently and in the most cost-effective manner. The pre- calibration time of the product is time elapsed between when the product was dispensed to the time it was used for the intended application. Currently significant amount of Tc-99 was decaying at the customer site (>6hrs). Historical data showed pre-calibration time for Tech products averaging at approx 8 hours. This represents significant product decay and lost revenue to the pharmacy network. There was also a large degree of inconsistency in pharmacies adhering to Pre-calibration policies with their customer base. The goal of the project was to improve the pre-calibration time on Technetium base products. Data collection was carried out by developing query language which helped in presenting accurate data that gave high visibility to this project. Through the use of the DMAIC methodology this project used tools such as VOC, FMEA, Hypothesis test that focused primarily in improving the pre-calibration times for Tech based products by implementation of the following: - Revenue stream programming change to charge activity beyond the 6 hour pre-cal limit -Customer letter from marketing addressing the goal to maximize the availability of technetium 99m (Tc 99m) for patients, using as much as possible in procedures rather than allowing it to decay on the shelf. These new policies would be designed to encourage unit dose customers use a more “just in time” approach. - Sales rep training on the Tc conservation program to help facilitate in changing customer behavior; i.e. Move orders to later scheduled runs. To promote lower pre- calibration times, Covidien will charge for pre-calibration activity beyond six hours, new charges will be based on bulk Tc-99 pricing. Bulk Tc-99 will be calibrated for actual delivery time, unless customer chooses to pay for additional activity Annual impact estimated from this project is $3million/year. Results taken after program launch in Oct 09 shows savings of $300K validate the projected revenue. The final metrics for the project are as follows: Name of Metric Baseline Goal Actual(A)-Oct09 Pre-calibration time 8.15 6.0 7.15 . 2
  • 3. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Define Project Charter Operational Excellence – Team Charter Program Name: Improve Tech Pre-calibration Total Savings Identified ($ $3 Million/yr value) Team Leader: Ramesh Rajan Team Champion: Dave Becker Product or Service Impacted Nuclear Pharmacies Business Unit: Imaging Solutions MBB: Start Date: April 2009 Target Completion Date: October 2009 Element Description Team Charter 1. Process: The process in which the The pharmacy network holds significant improvement opportunities opportunity exists. in reducing length of pre-calibration time on technetium based unit dose products and calibrating bulk doses at their delivery time. 2. Problem Describe the problem that needs Currently significant amount of Technetium 99 is decaying at the Description: to be solved, or the opportunity customer site which results in product waste and lost revenue. to be addressed. Global moly shortage severely impacts product availability. 3. Objective: What improvement is targeted? Reduction in Tech pre-calibration time would yield significant cost reduction to the pharmacy business. In addition it will improve product availability and increase patient access to Tc99 products. Saved Technetium could be sold at favorable price to a customer. 4. Metrics: What are the measurements Name of Baseline Goal Entitlement* Units of that quantify program progress Metric Measure and success? Precalibration 8.15 6.0 Hours *W hat is the bes t the process is time expec ted to pro duc e? 5. Business Results: What is the improvement in Cost Cost WIP/ Cash Labor Inc. business performance? Reduction Avoidance Inventory Flow Savings Sales Please list any other Reduction improvements on a separate X X sheet as needed. 6. Program Scope: Which parts of our business Included Excluded processes will be considered? The project will focus on all All other products Which customer segments, Technetium based products organizations, geographies, and which represent 80% of a timeframe? customer product portfolio. 7. Team Members: Names and roles of team Ramesh Rajan, Dave Becker ,Jeanne Landers, Terese Lafeber, members Carolyn Samra, Andy Farrow, Brian Courtney, Pharmacy Regional Managers. 8. Benefit to External Who are the final customers, Reduction in pre-calibration time will reduce cost, improve product Customers: what are their most critical availability to external customer and help mitigate the global moly requirements/measurements, shortage issue. In addition it will allow greater patient access to the and what benefits do we expect product. to deliver to them? 8. Schedule: Give the key milestones and Key Project Dates dates. Project Start April 2009 Define Complete May 2009 Measure Complete July 2009 Analyze Complete August 2009 Improve Complete September 2009 Control Complete October 2009 9. Budget: What financial resources are $5000 for TRON programming. required for the team? 10. Support Required: Do you anticipate the need for IS programming, TRON user training, customer communications. any special capabilities, hardware, trials, etc.? 3
  • 4. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc SIPOC Map A SIPOC diagram was generated to provide a high level view of the Tech pre-calibration process. This tool helped the team to understand important inputs and outputs to the process. SUPPLIER INPUT PROCESS OUTPUT CUSTOMER Pharmacy receives customer Customer(Hospital, Standing, Demand order for Tech dose with Customer-Hospital, Presciption Independent) Orders,TRON requested delivery and Independent user calibration time Dispense dose with activity Pharmacist ,Technician Customer Order Dispensed dose Customer-Hospital related to calibration time Tech dose is ship confirmed Pharmacy Bill of Lading, TRON Shipconfirmed Dose Courier and taken for delivery Dose is delivered to customer Pharmacy Driver , Bill of Lading Delivered dose Customer-Hospital at requested delivery time Pharmacy bills customer for Pharmacy Dose charges Customer Invoice Customer dose includes freight charge. Customer(Hospital, Pharmacy collects sales Customer Invoice Sales Revenue Pharmacy Independent) revenue from dose sale Voice of the Customer/Business The team also undertook a brainstorming exercise to come up with key customer requirements. This “Voice of Customer” exercise showed the key outputs for the project .These outputs influence the end customer (i.e. hospitals etc) in maintaining reliable and quality supply. At the same time they also affect the pharmacies which are an internal customer as it will help in reducing product decay and capture lost revenue due to excessive pre-calibration. Reduce Tc Pre- Limit Precalibratiion time compared to current practice to save Tech waste Mimimize bulk dose waste by shrinking calibration limits calibration Maintain accurate delivery time in TRON Maintain ontime supply of Tech product to customer Voice of the On Time Delivery Need more Technetium due to global "Moly" shortage Customer Minimize product shortage Develop efficient production schedule at pharmacy Efficient Maintain efficient delivery routing for customer profile 4
  • 5. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Project Y’s (KPOV’s) At the end of the Define Phase the team decided to focus on reducing the pre-calibration time on Technetium products as the key Output (Big Y). This would be achieved while still meeting product demand and delivery expectations. Key Process Output Variable • Reduce Precalibration time on Technetium based products Other Important Factors • Maintain product supply as per customer demand • Meet customer delivery schedules 5
  • 6. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Measure Process Map A flowchart was developed to show the sequence and flow in the pre-calibration process. Using this, the teams were able to breakdown and understand the intermediate steps and determine inputs and outputs for each major step. Process Flow Map for Tc 99 Precalibration Pharmacy receives Customer Calibration time, Standing/Demand Order for Tech Delivery time dose Pharmacist enters order in TRON and generates prescription Dispense Dose with activity related Check to calibration time Order Is dose matching with BOL NO YES Tech dose is ship confirmed and taken for delivery Dose delivery to customer at requested delivery and calibration time Pharmacy bills customer and collects sales revenue for dose sale Pharmacy Invoicing $$ Pharmacy adds new customer , negotiates existing customer contracts, communicates any change in policy or contract 6
  • 7. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Cause and Effects Matrix In order to prioritize the input variables affecting the output requiring improvement, the team used a Cause and Effect (C&E) matrix. A Pareto was also done on the top raking critical inputs from the C&E with a cut-off of 200. This tool helped to focus on the few critical inputs which affect the output. Cause and Effect Matrix Rating of Importance to 9 10 8 9 Customer 1 2 3 4 Requested Activity at calibration Availability of Tech products On Time Deliveries Drops per Delivery time Total Process Step Process Input Calibration,delivery time, Pharmacy receives 1 calibration policy,Customer 9 9 3 9 276 customer order communication Pharmacy negotiates Calibration policy, Customer 6 existing contracts, 3 9 9 9 270 contract, Communication communicates changes Dose Dispensed with Customer Order,TRON, 2 activity related to 3 9 3 9 222 Calibration,Dely time calibration time Tech dose ship confirmed 3 Dispensed dose, BOL 9 9 3 0 195 and ready for delivery Dose delivered to customer 4 at requested delivery and Dose, BOL, Driver 9 9 3 0 195 calibration time Pharmacy bills customer 5 and collects revenue from Sales Invoice, Freight Bill 1 9 9 1 180 dose sale 0 0 306 540 240 252 Total Lower Spec Target Upper Spec 7
  • 8. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Pareto of C&E matrix C &E Pareto Analysis 1400 100 1200 1000 80 Percent Count 800 60 600 40 400 200 20 0 0 Process Inputs on n e L r il l i io tim O ve tB at at ,B ri h ic ic el y se D ig un un ,D do L, re m m m on d BO ,F co om r at i se e, ic e er ,C b en os vo m ct ali i sp D In to ra ,C D us nt N les ,C co R O Sa cy er r ,T oli m de n p u sto r O ti o ,C r ra cy me li b li to ca po us e, ion C tim at y br v er ali eli C d n, ti o ra lib Ca FMEA The FMEA focused on specific process failures that would affect the Tech pre-calibration process and which would cause product decay and lost revenue. A RPN cut-off of 300 was established by the team for taking the critical inputs coming out of the FMEA into the Analyze phase. 8
  • 9. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Improve Tech Prepared by: Ramesh Process or Product Name: Precalibration Rajan Responsible: Ramesh Rajan FMEA Date (Orig) _September 29th, 2009_______ S O D R Potential Failure Potential Failure Process Step Input E Potential Causes C Current Controls E P Mode Effects V C T N How Severe is the How well can you effect to the detect cause or How often does cause or FM cusotmer? occur? FM? Step of the process Input under investigation? In what ways does What is the impact What causes the Key Input to go What are the existing under investigation the Key Input go on the Key Output wrong? controls and procedures wrong? Variables (Customer (inspection and test) that Requirements) or prevent either the cause or internal the Failure Mode? requirements? Should include an SOP number. Pharmacy receives Excessive Product decay , Lost TRON 8 Lack of limits on calibration time 7 None 8 448 customer order precalibration revenue Dose dispensed with Inaccurate delivery Customer Delivery activity related to Expected Delivery time Product Decay 7 Customer Behaviour 8 7 392 time schedule calibration time Pharmacy negotiates Miscommunicaiton Lost revenue due to existing contracts, Customer Contract, Lack of attention to true need, Customer Communication or lack of product decay, 8 8 6 384 communicates Calibration policy overemphasis on safety insurance by Sales reps standardized policy excess inventory changes Pharmacy receives Excessive Historical customer behaviour, Calibration time Product Decay 9 8 Customer Communication 5 360 customer order precalibration resistant to change Lost revenue due to Customer Contract, No adherence to Customer demand, variation in Customer Communication product decay, 8 7 6 336 Calibration policy policy Tech needs by Sales reps excess inventory Pharmacy receives Excessive Unfavourable product Lack of standardized Calibration time 9 7 Contract, Calibration policy 5 315 customer order precalibration margin policy/contract terms Inaccurate delivery Lack of foresight, Product Delivery time loaded in Expected Delivery time Product Decay 7 8 4 224 time Insurance TRON Pharmacy receives Incorrect activity Product decay, loss No activity limits in TRON, wrong TRON 6 6 TRON checks 2 72 customer order dispensed of revenue order entry 0 0 Pareto of FMEA Pareto of FMEA RPN 2500 100 2000 80 Percent Count 1500 60 1000 40 500 20 0 0 Potential Failure Mode n e ic y icy er t io t im ol l th ra y p po O a lib er d to ec liv ize de rd ce pr da en iv e a te n er ss ur ta h ce c fs ad Ex ac o No In k lac or n it o n ic a u m o m isc M Count 1123 616 384 336 72 Percent 44.4 24.3 15.2 13.3 2.8 Cum % 44.4 68.7 83.9 97.2 100.0 The key inputs from the FMEA were Calibration time, Delivery time, Customer contracts and TRON. 9
  • 10. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Gage R&R Data collection for the Measure phase was obtained from queries generated from the TRON system A Gage R&R study was then conducted to test the precision of the measurement system and this was done with the help of 2 operators on the critical metric; Average pre-calibration time. A Gage R&R review showed the variation due to repeatability and reproducibility to be at 3% and part-to part variation at 99% which showed the measurement system was very accurate. Gage R&R for Over 6 hr precalibration time Gage R&R Study - ANOVA Method Two-Way ANOVA Table with Interaction Source DF SS MS F P Sample 34 95.0457 2.79546 3007.40 0.000 Operator 1 0.0037 0.00370 3.98 0.054 Sample * Operator 34 0.0316 0.00093 * * Repeatability 70 0.0000 0.00000 Total 139 95.0810 Alpha to remove interaction term = 0.25 Gage R&R %Contribution Source VarComp (of VarComp) Total Gage R&R 0.000504 0.07 Repeatability 0.000000 0.00 Reproducibility 0.000504 0.07 Operator 0.000040 0.01 Operator*Sample 0.000465 0.07 Part-To-Part 0.698633 99.93 Total Variation 0.699137 100.00 Study Var %Study Var Source StdDev (SD) (6 * SD) (%SV) Total Gage R&R 0.022457 0.13474 2.69 Repeatability 0.000000 0.00000 0.00 Reproducibility 0.022457 0.13474 2.69 Operator 0.006288 0.03773 0.75 Operator*Sample 0.021558 0.12935 2.58 Part-To-Part 0.835843 5.01506 99.96 Total Variation 0.836144 5.01687 100.00 Number of Distinct Categories = 52 10
  • 11. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Gage R&R Study Reported by : G age name: Tolerance: D ate of study : M isc: Components of Variation Over 6 hr precalibration time by Sample 100 % Contribution 4.5 % Study Var 3.0 Percent 1.5 50 a ta ll e m n o d us d a s n er it le rg l le n a s a es is mi rd o i a ok h d w co is ul t e o re on n svi he st o ag la n b oo all yto nv tr o da u sv i st o n s in d e l ph i a f o nd ph r o rg la n na c s ou Pa e led ar i t o tla l t le o i c e m w D Da De De er ri is b ick ou Ka a L ng em M M il r la de eb s buort agi a n t L St t P To sb A l A Be t h B Ch lev o lo es t u d a H H om s A M O i la in it t P S F r S S e Be C C Cr i lk 0 La H L Lo Ph P P n W Ft Sa Gage R&R Repeat Reprod Part-to-Part Sample R Chart by Operator Over 6 hr precalibration time by Operator Bernard Ramesh 0.5 4.5 Sample Range _ 3.0 0.0 LCL=0 UCL=0 R=0 1.5 -0.5 Bernard Ramesh Operator Xbar Chart by Operator Bernard Ramesh Operator * Sample Interaction 4.5 4.5 Operator Average Sample Mean 3.0 Bernard 3.0 Ramesh _ _ 1.5 LCL=2.146 UCL=2.146 X=2.146 a ta l le m n o d us d a s n er it l e rg l l e n a s a es is m ir d o ia ok h d w co is u l te o re 1.5 o n n svi he sto ag la n b ooally ton v t roda u svi to ns indel p hi a fo ndphr o rg la nna cis ouP a e leda r to t l a t le o ic e mw D a e e r isb ck s a L g m M il la e b bur t gi n L t P o b l Al A Be th B C hevo loes t D D D dea r i HiHo u K a AnM e MO rlad inei tts PoS a r a St S St Tk es Be Cl C Cr u ms i F il La H Lo L o Ph P P n W Ft Sa Sample Data Normality Data was collected on average pre- time calibration by pharmacy for June09 and it showed it was normal. Normality Test for Normal 99 Mean 8.151 StDev 0.8384 95 N 35 AD 0.180 90 P-Value 0.910 80 70 Percent 60 50 40 30 20 10 5 1 6 7 8 9 10 Average precal time June 11
  • 12. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Process Capability Process Capability Sixpack of Average precal time June I Chart Capability Histogram LSL USL UCL=10.669 S pecifications Individual Value 10.0 _ LS L 0 X=8.151 USL 6 7.5 LCL=5.633 5.0 1 4 7 10 13 16 19 22 25 28 31 34 0.0 1.5 3.0 4.5 6.0 7.5 9.0 Moving Range Chart Normal Prob Plot UCL=3.093 A D : 0.180, P : 0.910 3.0 Moving Range 1.5 __ MR=0.947 0.0 LCL=0 1 4 7 10 13 16 19 22 25 28 31 34 5.0 7.5 10.0 Last 25 Observations Capability Plot Within Within O v erall 9 S tD ev 0.839367 S tDev 0.838408 Values 8 Cp 1.19 Pp 1.19 O v erall C pk -0.85 P pk -0.86 7 C pm * S pecs 15 20 25 30 35 Observation For the process capability calculations, the lower Specification limit was chosen as 0 hours and the upper limit was taken at 6 hours. The Cpk value of - 0.85 shows that the process capability is less than favorable and there is vast scope for improvement. 12
  • 13. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Data Collection Data collection for the Measure phase was collected from TRON queries that measured the average pre-calibration time across the pharmacy network for June09. This was taken as the baseline. For this project the Average pre-calibration time is taken as the (Y). The pre-calibration time is defined as the time elapsed between the expected delivery time of the product and its calibration time. 13
  • 15. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Baseline Metrics From the data collected in June09 the report showed the following baselines Baseline Measurements Jun-09 Pharmacy Average Time over Delivery time( Bulks) Average Precalibration time June Ft Lauderdale 5.12 7.87 Crestwood 5.00 9.60 Kansas 2.00 7.95 Chicago 3.00 7.87 St Louis 6.25 6.98 Orlando 3.00 8.98 St Pete 3.00 7.87 Miami 4.00 9.04 Memphis 0.00 10.00 Atlanta 5.00 8.81 Boston 3.00 6.62 Wilkesbarre 3.00 7.12 Milford 3.00 7.41 Pinebrook 3.00 7.21 Hicksville 3.00 8.11 Hariisburg 4.00 7.80 Bethlehem 4.00 7.43 Altoona 4.25 7.38 Philadephia 3.00 8.10 Dallas 4.00 9.20 Los Angeles 3.00 7.52 Loma Linda 2.00 8.24 San Francisco 3.00 7.68 St Paul 3.00 9.50 Portland 4.00 8.34 Denver 3.00 8.12 Houston 3.00 8.46 Saginaw 2.15 7.62 Toledo 3.00 8.85 Colombus 3.00 6.65 Dayton 2.00 8.56 Detroit 3.00 8.66 Beltsville 3.00 8.67 Cleveland 3.00 9.25 Pittsburgh 3.00 7.81 Average 3.25 8.15 15
  • 16. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Savings Summary Tc-99 Conservation Plan Annual Summary Impact Bulk Precal Beltsville 201,617 24,697 Cleveland 182,709 21,821 Hicksville 136,829 47,663 Pinebrook 165,864 6,599 Dallas 141,738 39,835 Los Angeles 142,937 4,037 St Pete 148,092 9,581 Denver 124,645 4,459 Orlando 107,840 13,175 Pittsburgh 81,113 52,328 Crestwood 107,076 34,832 St Paul 95,212 12,132 Boston 113,921 4,489 Harriburg 80,833 5,568 Detroit 73,360 3,802 Chicago 66,786 5,666 Milford 63,819 776 Dayton 38,784 6,496 Altoona 71,915 15,905 Wilkes Barre 60,352 3,273 St Louis 53,632 8,019 Bethlehem 63,835 4,635 Houston 25,771 2,203 Ft Lauderdale 54,235 5,967 Colombus 33,115 14,977 Philadelphia 45,994 5,390 Atlanta 40,616 5,900 Portland 21,396 3,756 San Francisco 27,539 4,327 toledo 22,373 5,967 Kansas City 20,967 6,968 Saginaw 23,145 1,298 Miami 29,064 7,046 Loma Linda 10,599 11,210 Cinci 9,582 1,516 Memphis - 5,151 $2,687,299 $411,461 Bulk = All doses sold as Bulk calibrated at expected delivery time Precal = All unit doses which exceed a 6 hour window between expected delivery and calibration time 16
  • 17. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Analyze Basic Statistics Basic statistics were gathered on the key output to determine stability and shape. Normality test was also done on the key output which showed data as a normal curve. Summary for Average precal time June A nderson-D arling N ormality Test A -S quared 0.18 P -V alue 0.910 M ean 8.1511 S tDev 0.8384 V ariance 0.7029 S kew ness 0.223511 Kurtosis -0.483646 N 35 M inimum 6.6209 1st Q uartile 7.5226 M edian 8.0986 3rd Q uartile 8.8137 7 8 9 10 M aximum 10.0000 95% C onfidence Interv al for M ean 7.8631 8.4391 95% C onfidence Interv al for M edian 7.8038 8.5280 95% C onfidence Interv al for S tDev 9 5 % C onfidence Inter vals 0.6782 1.0985 Mean Median 7.8 8.0 8.2 8.4 8.6 The Mean of the data was 8.15 hours while the median is 8.09 which indicate both are very close to each other. Descriptive Statistics: Average precal time June Variable N N* Mean SE Mean StDev Minimum Q1 Median Average precal time June 35 0 8.151 0.142 0.838 6.621 7.523 8.099 Variable Q3 Maximum Average precal time June 8.814 10.000 17
  • 18. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Graphical Analysis Box plot of Pre-calibration time by pharmacy showed there exists a difference between means of data between pharmacies of different size. The pre- calibration time variation among pharmacies showed there was a lack of standardized policy related to pre-calibration time. The frequency graph shows historically there have been excessive pre-calibration times practiced at multiple sites with times extending as far as midnight which accounts for substantial product decay and lost revenue. Boxplot of Average Precalibration time 10.0 9.5 Average Precalibration time 9.0 8.5 8.0 7.5 7.0 6.5 Large Medium Small Pharmacy Size 18
  • 19. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Graph of Calibration time V/s Frequency 90 80 70 60 Frequency 50 40 30 20 10 0 10:30:00 12:30:00 13:00:00 13:15:00 13:30:00 13:45:00 14:45:00 16:00:00 23:59:00 Calibration time Hypothesis Testing Regression A Regression analysis was performed with the Key input variables and the Key output variable. The Calibration time and Expected delivery time are the critical Project Input Variable (KPIV) with the highest correlation to Average Pre- calibration time and is the root cause for pharmacies having excessive pre- calibration time. In addition some of the other critical inputs such as TRON and customer contracts were also taken into consideration for the Improve phase. A another regression equation was also tested to see correlation between Value of Tech waste due to excessive pre-calibration time and the Pre-calibration time and there exists a high degree of correlation between them. Regression Analysis: Average over 6 h versus Activity, ASP, The regression equation is Average over 6 hour Precal = - 4.99 - 0.00775 Activity - 0.31 ASP + 20.6 Calibration time - 19.3 Delivery time Predictor Coef SE Coef T P Constant -4.9892 0.4866 -10.25 0.000 Activity -0.007749 0.006703 -1.16 0.257 ASP -0.314 1.081 -0.29 0.774 Calibration time 20.556 1.088 18.88 0.000 Delivery time -19.292 1.504 -12.83 0.000 S = 0.219942 R-Sq = 95.2% R-Sq(adj) = 94.5% 19
  • 20. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Analysis of Variance Source DF SS MS F P Regression 4 28.5317 7.1329 147.45 0.000 Residual Error 30 1.4512 0.0484 Total 34 29.9829 Source DF Seq SS Activity 1 0.1078 ASP 1 0.0673 Calibration time 1 20.3951 Delivery time 1 7.9615 Regression Analysis: Tech value o versus Average over, Activity, ASP The regression equation is Tech value over 6 hour precal = - 864 + 296 Average over 6 hour Precal + 79.8 Activity - 2450 ASP Predictor Coef SE Coef T P Constant -864 1772 -0.49 0.629 Average over 6 hour Precal 296.3 143.4 2.07 0.048 Activity 79.83 25.16 3.17 0.004 ASP -2450 5589 -0.44 0.664 S = 780.531 R-Sq = 32.4% R-Sq(adj) = 25.4% Analysis of Variance Source DF SS MS F P Regression 3 8465699 2821900 4.63 0.009 Residual Error 29 17667618 609228 Total 32 26133318 T-Test- A 2 sample T test was also conducted to test the difference between Average Pre-calibration time in June before the project was implemented and the time in October after implementation. The analysis showed that the pre-calibration time dropped by an average 1 hour with the project implementation. Two-Sample T-Test and CI: Average precal time June, Average Precal time Oct Two-sample T for Average precal time June vs Average Precal time Oct N Mean StDev SE Mean 20
  • 21. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Average precal time June 35 8.151 0.838 0.14 Average Precal time Oct 35 7.151 0.838 0.14 Difference = mu (Average precal time June) - mu (Average Precal time Oct) Estimate for difference: 1.000 95% CI for difference: (0.600, 1.400) T-Test of difference = 0 (vs not =): T-Value = 4.99 P-Value = 0.000 DF = 68 Both use Pooled StDev = 0.8384 Results Since the p-value is less than 0.05 we reject the null hypothesis which was taken as there was no difference between the 2 populations and conclude that there is a positive difference between the pre-calibration time measured before the project was implemented to the time measured after which means the time has decreased since project implementation and this is a favorable impact resulting from the project. Project X’s Key input variables coming out of the Analyze were Calibration time – This is the time at which the requested dose is used for its intended application. The pharmacist calculates activity that needs to be filled based on customer requested calibration time. Delivery time – This is the time when the customer requests delivery of the product at it’s location. Customer Contract – Contract is a binding document between Covidien and the customer which contains information related to pricing, dose limits, calibration times and freight policy. All negotiated contracts define the long-term commitment between Covidien and its customers. TRON – The system used by the pharmacy network to carry out all operations from order processing to delivery of finished product. Since it’s a central processing system for the network, it has a significant impact on operations related to Technetium products. 21
  • 22. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc . Improve Solutions Identified Critical inputs from the Analyze phase was taken into consideration for improvement in this phase and the “Tc Conservation program” which was launched across the network captures all the improvements which were implemented in the field to achieve the desired objective of reducing pre-calibration time and capturing lost revenue due to excessive pre-calibration time. Current issues identified with Tc-99m utilization Significant amount of Tc-99 decaying at the customer site (~6hrs) - 50% of all doses dispensed with greater than 6 hours time - much bulk-tech is ordered with pre-cal for 12:00 am - In past, customers believed “Tc-99 is cheap”, the agent is expensive - customers like security of receiving daily doses early - past delivery issues may drive behavior for this “insurance” time - lack of standardized calibration policy and no pre-calibration limits in TRON Tech Conservation - Opportunity Valuing the saved material at current ASP -> Huge $$$’s • Allows greater patient access to Tc-99m or charge for overage • With generator shortages now and in FY10, we need fast action 22
  • 23. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc • Excellent time to begin changing market behavior • Next Steps - Meeting held with IS requesting TRON changes (80 hrs) - Roll out with Sales management on 8/10/09 - Rep and pharmacy web-training (8/28 & 8/31) - Customer letter from marketing distributed on 9/1. - Reps have customer discussions in September - Target Go Live targeted for 9/26/09 (first day of FY10) Customer Letter – Summary of Program: Customer letter will be sent on 9/01/09, which will explain…. • Ongoing concern over global Moly supply • Significant investment required to improve availability • Our goal to increase patient access to Tc-99m based products • Covidien committed to servicing maximum number of patients • New conservation programs beginning on Sept. 26th, 2009(est.) • To promote lower pre-calibration times, Covidien will charge for pre-calibration activity beyond six hours • New charges will be based on bulk Tc-99 pricing • Bulk Tc-99 will be calibrated for actual delivery time, unless customer chooses to pay for additional activity Example #1 - Limit pre-calibration to 6 hours (expected delivery to cal time) Example: Customer orders 30 mCi of Sestamibi calibrated for 1300, but wants it delivered with an expected delivery time of 0600. This would trigger a charge up, using the R005A0 code and decay factor to charge them the customer’s bulk Tc-99m charge (say $0.31/mci). We would charge the customer for the hours beyond the 6 hr limit. In this case, it is one hour, so we would 23
  • 24. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc charge the customer $0.31 x (30mCi/.891)-30 mCi = $1.14 using a new item code R005PC – TC-99M PRE-CAL OVER TIME LIMIT which will be attached to the dose for reimbursement Bulk tech will no longer be calibrated past delivery times. Customer Impact Analysis - example This is a calculation of the new cost to each customer if they do not change. Example from the month of June: Customer Name Tech Value over recommended qty Tech value over 6 hrs pre-cal at ASP ALBERT EINSTEIN MED CTR Total $0.00 $1,826.52 ATLANTIC MEDICAL IMAGING,GALLOWAY,NJ Total $0.00 $31.39 BOOTH RADIOLOGY Total $0.00 $98.36 CAPE MAY COURT HOUSE AMI Total $0.00 $23.97 CARDIAC DIAGNOSTIC CENTER,LEWES,DE Total $0.00 $0.96 CARDIAC DIAGNOSTIC CENTER,MIDDLETOWN,DE Total $0.00 $32.96 CARDIAC DIAGNOSTIC CENTER,WILMINGTON,DE Total $0.00 $2.04 CARDIOLOGY MEDICAL ASSOC,PHILADELPHIA,PA Total $0.00 $45.27 CARDIOVASCULAR SOLUTIONS,PHILADELPHIA,PA Total $0.00 $116.50 CHERRY HILL CARDIAC DIAGNOSTIC Total $0.00 $111.73 COMM MED CTR Total $134.85 $473.56 DOVER CDC,DOVER,DE Total $1.55 $1.15 EINSTEIN CTR ONE RADIOLOGY Total $1.55 $84.30 KIMBALL MEDICAL CENTER,LAKEWOOD,NJ Total $0.00 $1,690.34 LINWOOD AMI Total $0.00 $46.51 METHODIST HOSPITAL,PHILADELPHIA,PA Total $0.00 $313.70 MOSS REHAB/EINSTEIN AT ELKINS PARK Total $0.00 $371.03 NORTH WILMINGTON CDC Total $0.00 $2.04 PAMI Total $0.00 $59.12 RADIOLOGY ASSOCIATES,WILMINGTON,DE Total $0.00 $11.92 SOUTH JERSEY HEART GROUP,SEWELL,NJ Total $0.00 $1.97 THOMAS JEFFERSON U HOSP Total $0.00 $185.50 UNION HOSP OF CECIL CNTY Total $0.00 $1,343.71 WACHSPRESS & SHATKN CARDIO, VINELAND, NJ Total $0.00 $27.97 24 Grand Total $139.50 $7,013.32
  • 26. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Sales Rep Actions & Timeline: • Study the customer letter and understand the key points • Review the customer impact analysis with Regional manager • Work with pharmacy manager • Develop preliminary plan using customer knowledge to minimize customer impact • Shift doses to later deliveries, while minimizing impact on delivery costs • Visit with customers • Provide the customer a choice to remain with the status quo or shift schedule • Finalize a plan for each customer with your pharmacy • Understand changes to invoices • Corporate will add pricing for bulk tech at rep guideline for customers not having this item code currently on their contract 8/28 or 8/31 Wk of 8/31 Wk of 9/7 Wk of 9/14 Wk of 9/21 Sat. 9/26 - Meet with customers Attend - Meet with customers Finalize plan with -Target Go Live Web- Meet with Reg. Mgr pharmacy training Meet with pharmacy team Review customers Develop plan 26
  • 27. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Sales Rep talk track: • Reference the customer letter • Explain that Tc-99m shortage will continue far into 2010 • Our focus is on increasing patient access to Tc-99m products • Asked your customers to use Tc-99m more efficiently • Explain how doses can be delivered on later runs If they purchase bulk tech, explain new pre-calibration policy Give them their options for: 1 Unit doses with excess (> 6 hours) of calibration a.) Move doses to later scheduled runs b.) Pay for extra activity 2 Bulk Tc-99m orders a.) Move orders to later scheduled runs b.) Reduce sizes of bulk Tc-99m orders c.) Pay for extra activity d.) Eliminate bulk Tc-99m orders and utilize STAT unit dose orders where needed. • It’s the customers choice • Use your Tools -> Moly calendar, delivery schedules, customer impact analysis, Moly shortage update letter Pharmacy Managers Actions: • Study the customer letter and understand the key points • Review the customer impact analysis with your sales team • Develop a preliminary plan to minimize customer impact • Ensure you are capturing accurate expected delivery times in TRON for all customer orders. • Consider shifts in delivery schedules without increasing costs • Utilize existing scheduled runs and routes • If freight costs exceed Tc-99m savings, exceptions approved by VP Ops, VP of Sales, and Marketing through email. • Make certain to capture freight revenue for these exception accounts • Understand changes to TRON and invoices • Finalize a plan for each customer • On Go Live date, begin calibrating all bulk tech at delivery time • Note that corporate will add pricing for bulk tech at rep guideline for customers not having this item code currently on their contract 27
  • 28. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc TRON Invoice change? Invoices will show the added Tc-99 charges similar to I-131 caps. Invoices will reflect any necessary surcharges on the line following the applicable dose, assigned to the same prescription number for reporting ease. The following product codes and descriptions will appear to indicate the surcharge type(s): R005PC - TC-99M SODIUM PERTECHNETATE ACTIVITY OVER PRE-CALIBRATION TIME LIMIT (PER MCI) 28
  • 29. improvetechprecalibrationprojectbook-12584117210388-phpapp01.doc Control The updated process flow shows the changes made to the TRON pharmacy system to generate invoices capturing the surcharge for products exceeding the 6 hour pre-calibration limit. Updated Process Map Updated Process Flow Map for Tc 99 Precalibration Pharmacy receives Customer Standing / Calibration time, Demand Order for Tech dose Delivery time Pharmacist enters order in TRON and generates prescription Dispense Dose with activity related to Check calibration time Order Is dose matching with BOL NO YES Tech dose is ship confirmed Is unit dose over 6 hour pre - YES calibration?Bulk dose over delivery time? Excess surcharge billed to NO customer invoice Dose delivery to customer at requested delivery and calibration time Pharmacy Invoicing $$ Pharmacy bills customer and collects sales revenue for dose sale Exception sent to Pricing for adjustment and surcharge Pharmacy adds new customer , negotiates adjusted to $0 existing customer contracts , communicates any change in policy or contract Exception raised if freight revenue exceeds Tech Customer changes delivery schedule , savings adjusts calibration times to adhere to Tech Conservation program 29