SlideShare une entreprise Scribd logo
1  sur  17
UNDERSTANDING
ACUMEN FUSE
SCORE
Rufran C. Frago, P. Eng., PMP®, CCEC, PMI-RMP®
Revision 1: July 22, 2013
2
The Project Controls Governance is looking to
finalize the Acumen Fuse score weightings and
calculation going forward.
The projects would like to fully understand how the
scores are to be calculated.
The manual metric calculation uses a simple
calculation of 1-point per metric on a standard
metric set consisting of 21 metrics. See Figure 1
3
Given Situation
Figure 1
We were expecting a straight forward calculation
that if we have 15 greens out of 21, we'll have a
result of (15/21)*100% or 71%. Green means pass,
Red means fail. Nothing in between.
Our passing score is set to 70% and up. We cannot
set this same weighting in Acumen Fuse.
This manual setting is not possible in Acumen Fuse.
4
Given Situation
During the last Gate Review, we found another thing
that caught our attention. We found that regardless
of how much improvement was done to improve the
quality of the schedule; the score did not change
much.
Let say we improved the number of green metric
from 15 to 19. The score remained below 70%, say
66% or 63%.
When certain metrics were removed from the 21 and
make the whole set consist of only 15, the score
more or less remained the same.
5
Given Situation … (continuation)
1) Activity-Based scoring requires that a task passes
all metrics in order to receive credit in the score.
The scoring method counts the number of tasks
that pass all metrics, divided by the number of total
tasks, times one-hundred percent.
2) By using Metric-Based scoring, an activity can
receive “partial credit.”
These are the only two type of scoring options
available in Acumen Fuse. Selecting either activity
based or metric based scoring has a critical influence
on the scoring outcome.
6
Metric-Based Score or Activity-Based
Score? Which one is better? 1)
By default in Acumen Fuse, activity-based scoring is
used.
7
Activity-Based Scoring
Activity-based scoring computes the final score by
requiring an activity to pass all metrics visible in the
ribbon view in order to count positively toward the
overall score.
In other words, activity-based scoring uses a pass/fail
method which calculates the number of activities
passing each metric and the number of activities failing
each metric to determine the overall score.
Only those tasks that pass all criteria will have a
positive influence on the overall score when activity
based scoring is used. By correcting the issues
associated with the activity, the individual activity
score is improved as well as the overall project score.
8
Activity-Based Scoring 3)
A task must be improved in all red areas and score
should be 100% in order to influence the overall score
positively. See Figure-2
In activity-based scoring, any degree of ‘Bad’ will
prevent the activity from having a positive impact on
the overall score.
Conversely, when a metric is rated as ‘Good’ and a
certain task fails to meet the criteria for the metric, it
will not count toward the score.
9
Activity-Based Scoring 3) … (continuation)
10
Activity-Based Scoring… (continuation)
Figure 2
Metric-based scoring allows tasks to receive ‘partial
credit’ toward the overall score. 3)
 Score is a lot higher than Activity-Based scoring. 3)
11
Metric-Based Scoring… (continuation)
Figure 3
Tasks receive credit based on how many of the
metrics they have passed and the weighting values
assigned to each of those metrics.
Figure 3 shows an example using metric-based scoring
rather than activity based.
Under the metric-based scoring system the project
receives a score of 94%, significantly higher than the
55% score the project received using activity based
scoring.
This higher score is because in metric-based scoring,
each task’s individual score counts toward the total.
The score values from individual tasks are averaged to
create the overall score rather than just the pass/fail
status of each activity. Effectively, each task now
receives partial credit toward the goal of 100%.
12
Metric-Based Scoring 3) … (continuation)
13
PROPOSED WEIGHTINGS
Tom Polen of Acumen Fuse has created a video and
written a guide that reviews the scoring process in
more detail.
Watch the video (follow hyperlink below):
Guide to Acumen Fuse Scoring Video
Read the written guide (follow hyperlink below):
Written Guide on Scores - Download
14
Video Guide-Acumen Fuse Scores 1)
1. If for example, there are two metrics out of the 21
metrics identified are still unavailable and I de-
activate the two metrics from the S2//Diagnostic
Window, will they still be counted to contribute to the
Overall score?
2. If so, what should I do to remove their contribution to
the score without removing them from the set of
metrics altogether?
Answer to Question 1 and 2.
If the metrics are de-activated from the Ribbon View in
the S2//Diagnostics window, they will not contribute to
the score. We can leave them in the metrics folder in the
Metrics tab without adjusting their weighting pointer.
15
Questions
16
1) 2013, Guide to Acumen Fuse Scores by Tom Polen of Acumen Fuse.
2) 2013, Written Guide on Scores - Download , Acumen Fuse Web Site
3) October 2012, Project Scoring in Acumen Fuse by Acumen
References & Additional Materials
17

Contenu connexe

Tendances

San diego city schools
San diego city schoolsSan diego city schools
San diego city schoolsRohit Kumar
 
Defining the Project Y
Defining the Project YDefining the Project Y
Defining the Project YMatt Hansen
 
The DMAIC Roadmap (Levels 1 & 2) with Matt Hansen at StatStuff
The DMAIC Roadmap (Levels 1 & 2) with Matt Hansen at StatStuffThe DMAIC Roadmap (Levels 1 & 2) with Matt Hansen at StatStuff
The DMAIC Roadmap (Levels 1 & 2) with Matt Hansen at StatStuffMatt Hansen
 
Case study of San Diego city schools
Case study of San Diego city schoolsCase study of San Diego city schools
Case study of San Diego city schoolsMayank Mittal
 
Using data to inform design decisions in a UX immature organization - Big Des...
Using data to inform design decisions in a UX immature organization - Big Des...Using data to inform design decisions in a UX immature organization - Big Des...
Using data to inform design decisions in a UX immature organization - Big Des...Mike Parker
 
Project Pre-Assessment Using a Min/Max Analysis with Matt Hansen at StatStuff
Project Pre-Assessment Using a Min/Max Analysis with Matt Hansen at StatStuffProject Pre-Assessment Using a Min/Max Analysis with Matt Hansen at StatStuff
Project Pre-Assessment Using a Min/Max Analysis with Matt Hansen at StatStuffMatt Hansen
 
Control Phase Roadmap (Level 3)
Control Phase Roadmap (Level 3)Control Phase Roadmap (Level 3)
Control Phase Roadmap (Level 3)Matt Hansen
 
Test Environment Management- An Emerging Truth Of DevOps
Test Environment Management- An Emerging Truth Of DevOpsTest Environment Management- An Emerging Truth Of DevOps
Test Environment Management- An Emerging Truth Of DevOpsEnov8
 
Defining Performance Objectives
Defining Performance ObjectivesDefining Performance Objectives
Defining Performance ObjectivesMatt Hansen
 
Building a Project Storyboard with Matt Hansen at StatStuff
Building a Project Storyboard with Matt Hansen at StatStuffBuilding a Project Storyboard with Matt Hansen at StatStuff
Building a Project Storyboard with Matt Hansen at StatStuffMatt Hansen
 
Maintenance Technical Debt
Maintenance Technical DebtMaintenance Technical Debt
Maintenance Technical DebtGlobant
 
Documenting a New Process with SOPs
Documenting a New Process with SOPsDocumenting a New Process with SOPs
Documenting a New Process with SOPsMatt Hansen
 
Ml0018 project management in retail
Ml0018  project management in retailMl0018  project management in retail
Ml0018 project management in retailsmumbahelp
 
Piloting Solutions: The Process
Piloting Solutions: The ProcessPiloting Solutions: The Process
Piloting Solutions: The ProcessMatt Hansen
 
Identify Root Causes – C&E Diagram
Identify Root Causes – C&E DiagramIdentify Root Causes – C&E Diagram
Identify Root Causes – C&E DiagramMatt Hansen
 
Building a Control Plan
Building a Control PlanBuilding a Control Plan
Building a Control PlanMatt Hansen
 
Comparing Distributions and Using the Graphical Summary
Comparing Distributions and Using the Graphical SummaryComparing Distributions and Using the Graphical Summary
Comparing Distributions and Using the Graphical SummaryMatt Hansen
 

Tendances (20)

San diego city schools
San diego city schoolsSan diego city schools
San diego city schools
 
Defining the Project Y
Defining the Project YDefining the Project Y
Defining the Project Y
 
The DMAIC Roadmap (Levels 1 & 2) with Matt Hansen at StatStuff
The DMAIC Roadmap (Levels 1 & 2) with Matt Hansen at StatStuffThe DMAIC Roadmap (Levels 1 & 2) with Matt Hansen at StatStuff
The DMAIC Roadmap (Levels 1 & 2) with Matt Hansen at StatStuff
 
Case study of San Diego city schools
Case study of San Diego city schoolsCase study of San Diego city schools
Case study of San Diego city schools
 
The san diego city schools case study
The san diego city schools case studyThe san diego city schools case study
The san diego city schools case study
 
Using data to inform design decisions in a UX immature organization - Big Des...
Using data to inform design decisions in a UX immature organization - Big Des...Using data to inform design decisions in a UX immature organization - Big Des...
Using data to inform design decisions in a UX immature organization - Big Des...
 
Project Pre-Assessment Using a Min/Max Analysis with Matt Hansen at StatStuff
Project Pre-Assessment Using a Min/Max Analysis with Matt Hansen at StatStuffProject Pre-Assessment Using a Min/Max Analysis with Matt Hansen at StatStuff
Project Pre-Assessment Using a Min/Max Analysis with Matt Hansen at StatStuff
 
Control Phase Roadmap (Level 3)
Control Phase Roadmap (Level 3)Control Phase Roadmap (Level 3)
Control Phase Roadmap (Level 3)
 
Test Environment Management- An Emerging Truth Of DevOps
Test Environment Management- An Emerging Truth Of DevOpsTest Environment Management- An Emerging Truth Of DevOps
Test Environment Management- An Emerging Truth Of DevOps
 
Defining Performance Objectives
Defining Performance ObjectivesDefining Performance Objectives
Defining Performance Objectives
 
Building a Project Storyboard with Matt Hansen at StatStuff
Building a Project Storyboard with Matt Hansen at StatStuffBuilding a Project Storyboard with Matt Hansen at StatStuff
Building a Project Storyboard with Matt Hansen at StatStuff
 
6 Sigma - Chapter6
6 Sigma - Chapter66 Sigma - Chapter6
6 Sigma - Chapter6
 
Value added testing (VAT)
Value added testing (VAT)Value added testing (VAT)
Value added testing (VAT)
 
Maintenance Technical Debt
Maintenance Technical DebtMaintenance Technical Debt
Maintenance Technical Debt
 
Documenting a New Process with SOPs
Documenting a New Process with SOPsDocumenting a New Process with SOPs
Documenting a New Process with SOPs
 
Ml0018 project management in retail
Ml0018  project management in retailMl0018  project management in retail
Ml0018 project management in retail
 
Piloting Solutions: The Process
Piloting Solutions: The ProcessPiloting Solutions: The Process
Piloting Solutions: The Process
 
Identify Root Causes – C&E Diagram
Identify Root Causes – C&E DiagramIdentify Root Causes – C&E Diagram
Identify Root Causes – C&E Diagram
 
Building a Control Plan
Building a Control PlanBuilding a Control Plan
Building a Control Plan
 
Comparing Distributions and Using the Graphical Summary
Comparing Distributions and Using the Graphical SummaryComparing Distributions and Using the Graphical Summary
Comparing Distributions and Using the Graphical Summary
 

Similaire à 072213 Understanding Acumen Fuse Scoring Methods

Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIGlen Alleman
 
LSSGB_Project_SimpliLearn.ppt
LSSGB_Project_SimpliLearn.pptLSSGB_Project_SimpliLearn.ppt
LSSGB_Project_SimpliLearn.pptMash92
 
Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPIGlen Alleman
 
Overall Result Analysis ~ digging deeper into mock-set-plus result analysis
Overall Result Analysis ~ digging deeper into mock-set-plus result analysisOverall Result Analysis ~ digging deeper into mock-set-plus result analysis
Overall Result Analysis ~ digging deeper into mock-set-plus result analysisquestionbang
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Earning Value from Earned Value
Earning Value from Earned ValueEarning Value from Earned Value
Earning Value from Earned ValueGlen Alleman
 
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docxSheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docxmaoanderton
 
QM-021-PDCA
QM-021-PDCAQM-021-PDCA
QM-021-PDCAhandbook
 
Mejoramiento Acelerado de la Inspección
Mejoramiento Acelerado de la InspecciónMejoramiento Acelerado de la Inspección
Mejoramiento Acelerado de la InspecciónBlackberry&Cross
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement BaselineGlen Alleman
 
Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Glen Alleman
 
Performance evaluation tool
Performance evaluation toolPerformance evaluation tool
Performance evaluation toolcarlocudicinis21
 
Project management
Project managementProject management
Project managementAhmed Said
 
Principles of Management MG6851 (Karthikeyan.I, AP, Mech, SRIT)
Principles of Management MG6851 (Karthikeyan.I, AP, Mech, SRIT)Principles of Management MG6851 (Karthikeyan.I, AP, Mech, SRIT)
Principles of Management MG6851 (Karthikeyan.I, AP, Mech, SRIT)Karthikeyan I
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineGlen Alleman
 

Similaire à 072213 Understanding Acumen Fuse Scoring Methods (20)

Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
 
ISS_1
ISS_1ISS_1
ISS_1
 
LSSGB_Project_SimpliLearn.ppt
LSSGB_Project_SimpliLearn.pptLSSGB_Project_SimpliLearn.ppt
LSSGB_Project_SimpliLearn.ppt
 
Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPI
 
Overall Result Analysis ~ digging deeper into mock-set-plus result analysis
Overall Result Analysis ~ digging deeper into mock-set-plus result analysisOverall Result Analysis ~ digging deeper into mock-set-plus result analysis
Overall Result Analysis ~ digging deeper into mock-set-plus result analysis
 
C O N T R O L L P R E S E N T A T I O N
C O N T R O L L  P R E S E N T A T I O NC O N T R O L L  P R E S E N T A T I O N
C O N T R O L L P R E S E N T A T I O N
 
formation.docx
formation.docxformation.docx
formation.docx
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Earning Value from Earned Value
Earning Value from Earned ValueEarning Value from Earned Value
Earning Value from Earned Value
 
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docxSheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
 
QM-021-PDCA
QM-021-PDCAQM-021-PDCA
QM-021-PDCA
 
PDCA
PDCAPDCA
PDCA
 
Mejoramiento Acelerado de la Inspección
Mejoramiento Acelerado de la InspecciónMejoramiento Acelerado de la Inspección
Mejoramiento Acelerado de la Inspección
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)
 
Performance evaluation tool
Performance evaluation toolPerformance evaluation tool
Performance evaluation tool
 
Project management
Project managementProject management
Project management
 
Principles of Management MG6851 (Karthikeyan.I, AP, Mech, SRIT)
Principles of Management MG6851 (Karthikeyan.I, AP, Mech, SRIT)Principles of Management MG6851 (Karthikeyan.I, AP, Mech, SRIT)
Principles of Management MG6851 (Karthikeyan.I, AP, Mech, SRIT)
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 

Plus de PM SOLUTION PRO| Risk-based Management and Services Inc.

Plus de PM SOLUTION PRO| Risk-based Management and Services Inc. (20)

121717 Kindle Issue 2 : Figures become so small than desired
121717 Kindle Issue 2 : Figures become so small than desired121717 Kindle Issue 2 : Figures become so small than desired
121717 Kindle Issue 2 : Figures become so small than desired
 
121717 Kindle Issue : Table lines were showing in kindle
121717 Kindle Issue : Table lines were showing in kindle121717 Kindle Issue : Table lines were showing in kindle
121717 Kindle Issue : Table lines were showing in kindle
 
101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)
 
063016 Man is the Center of the Risk Universe
063016 Man is the Center of the Risk Universe063016 Man is the Center of the Risk Universe
063016 Man is the Center of the Risk Universe
 
043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)
043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)
043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)
 
032815 DBM Schedule Development Workshop
032815 DBM Schedule Development Workshop032815 DBM Schedule Development Workshop
032815 DBM Schedule Development Workshop
 
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
 
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique 102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
 
091814 Failure Mode Effect and Analysis (FMEA)
091814 Failure Mode Effect and Analysis (FMEA)091814 Failure Mode Effect and Analysis (FMEA)
091814 Failure Mode Effect and Analysis (FMEA)
 
091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)
091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)
091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)
 
082314 Road to Operational Excellence
082314 Road to Operational Excellence082314 Road to Operational Excellence
082314 Road to Operational Excellence
 
072414 Resource Distribution Copy-Paste Problem
072414 Resource Distribution Copy-Paste Problem072414 Resource Distribution Copy-Paste Problem
072414 Resource Distribution Copy-Paste Problem
 
080714-Rufran's Primavera Scheduling Tips Tricks 02-14
080714-Rufran's Primavera Scheduling Tips  Tricks 02-14080714-Rufran's Primavera Scheduling Tips  Tricks 02-14
080714-Rufran's Primavera Scheduling Tips Tricks 02-14
 
011614 Scaffolding, what is it? Direct or Indirect?
011614 Scaffolding, what is it? Direct or Indirect?011614 Scaffolding, what is it? Direct or Indirect?
011614 Scaffolding, what is it? Direct or Indirect?
 
121013 Blackberry Business Audit (BMC 205 @ UofC)
121013 Blackberry Business Audit (BMC 205 @ UofC)121013 Blackberry Business Audit (BMC 205 @ UofC)
121013 Blackberry Business Audit (BMC 205 @ UofC)
 
103013 Case Study, Potash Corporation (BMC205, UofC)
103013 Case Study, Potash Corporation (BMC205, UofC)103013 Case Study, Potash Corporation (BMC205, UofC)
103013 Case Study, Potash Corporation (BMC205, UofC)
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)
072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)
072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)
 
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
 
071513 How to Prepare for Schedule Quantitative Risk Analysis
071513 How to Prepare for Schedule Quantitative Risk Analysis071513 How to Prepare for Schedule Quantitative Risk Analysis
071513 How to Prepare for Schedule Quantitative Risk Analysis
 

Dernier

Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 

Dernier (20)

Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 

072213 Understanding Acumen Fuse Scoring Methods

  • 1. UNDERSTANDING ACUMEN FUSE SCORE Rufran C. Frago, P. Eng., PMP®, CCEC, PMI-RMP® Revision 1: July 22, 2013
  • 2. 2
  • 3. The Project Controls Governance is looking to finalize the Acumen Fuse score weightings and calculation going forward. The projects would like to fully understand how the scores are to be calculated. The manual metric calculation uses a simple calculation of 1-point per metric on a standard metric set consisting of 21 metrics. See Figure 1 3 Given Situation Figure 1
  • 4. We were expecting a straight forward calculation that if we have 15 greens out of 21, we'll have a result of (15/21)*100% or 71%. Green means pass, Red means fail. Nothing in between. Our passing score is set to 70% and up. We cannot set this same weighting in Acumen Fuse. This manual setting is not possible in Acumen Fuse. 4 Given Situation
  • 5. During the last Gate Review, we found another thing that caught our attention. We found that regardless of how much improvement was done to improve the quality of the schedule; the score did not change much. Let say we improved the number of green metric from 15 to 19. The score remained below 70%, say 66% or 63%. When certain metrics were removed from the 21 and make the whole set consist of only 15, the score more or less remained the same. 5 Given Situation … (continuation)
  • 6. 1) Activity-Based scoring requires that a task passes all metrics in order to receive credit in the score. The scoring method counts the number of tasks that pass all metrics, divided by the number of total tasks, times one-hundred percent. 2) By using Metric-Based scoring, an activity can receive “partial credit.” These are the only two type of scoring options available in Acumen Fuse. Selecting either activity based or metric based scoring has a critical influence on the scoring outcome. 6 Metric-Based Score or Activity-Based Score? Which one is better? 1)
  • 7. By default in Acumen Fuse, activity-based scoring is used. 7 Activity-Based Scoring
  • 8. Activity-based scoring computes the final score by requiring an activity to pass all metrics visible in the ribbon view in order to count positively toward the overall score. In other words, activity-based scoring uses a pass/fail method which calculates the number of activities passing each metric and the number of activities failing each metric to determine the overall score. Only those tasks that pass all criteria will have a positive influence on the overall score when activity based scoring is used. By correcting the issues associated with the activity, the individual activity score is improved as well as the overall project score. 8 Activity-Based Scoring 3)
  • 9. A task must be improved in all red areas and score should be 100% in order to influence the overall score positively. See Figure-2 In activity-based scoring, any degree of ‘Bad’ will prevent the activity from having a positive impact on the overall score. Conversely, when a metric is rated as ‘Good’ and a certain task fails to meet the criteria for the metric, it will not count toward the score. 9 Activity-Based Scoring 3) … (continuation)
  • 11. Metric-based scoring allows tasks to receive ‘partial credit’ toward the overall score. 3)  Score is a lot higher than Activity-Based scoring. 3) 11 Metric-Based Scoring… (continuation) Figure 3
  • 12. Tasks receive credit based on how many of the metrics they have passed and the weighting values assigned to each of those metrics. Figure 3 shows an example using metric-based scoring rather than activity based. Under the metric-based scoring system the project receives a score of 94%, significantly higher than the 55% score the project received using activity based scoring. This higher score is because in metric-based scoring, each task’s individual score counts toward the total. The score values from individual tasks are averaged to create the overall score rather than just the pass/fail status of each activity. Effectively, each task now receives partial credit toward the goal of 100%. 12 Metric-Based Scoring 3) … (continuation)
  • 14. Tom Polen of Acumen Fuse has created a video and written a guide that reviews the scoring process in more detail. Watch the video (follow hyperlink below): Guide to Acumen Fuse Scoring Video Read the written guide (follow hyperlink below): Written Guide on Scores - Download 14 Video Guide-Acumen Fuse Scores 1)
  • 15. 1. If for example, there are two metrics out of the 21 metrics identified are still unavailable and I de- activate the two metrics from the S2//Diagnostic Window, will they still be counted to contribute to the Overall score? 2. If so, what should I do to remove their contribution to the score without removing them from the set of metrics altogether? Answer to Question 1 and 2. If the metrics are de-activated from the Ribbon View in the S2//Diagnostics window, they will not contribute to the score. We can leave them in the metrics folder in the Metrics tab without adjusting their weighting pointer. 15 Questions
  • 16. 16 1) 2013, Guide to Acumen Fuse Scores by Tom Polen of Acumen Fuse. 2) 2013, Written Guide on Scores - Download , Acumen Fuse Web Site 3) October 2012, Project Scoring in Acumen Fuse by Acumen References & Additional Materials
  • 17. 17