This document outlines plans for an Innovative Technology Educational Center. The center aims to improve education quality by utilizing technology. Its objectives are to provide infrastructure for virtual servers, maintain servers and migrate existing ones, provide 24/7 support, and offer training. Deliverables include assessing virtual servers and designing server setup processes. Roles include a project sponsor, manager, team members in IT fields, and advisors. The schedule runs from January 2011 to August 2011, with needs assessment, facilities planning, ordering, building, installation and training phases. The estimated budget is $24,200, with $6,000 for initial capital and $16,200 for manpower.
3. MISSION
To establish a center that will improve and advance
the quality of education by utilizing technological
means.
To provide ongoing technology support and training
in the area of educational technology.
To provide students with the knowledge to fix and
repair basic technology problems. .
4. OBJECTIVES
The integration of innovated information
technology in the higher education sector is a very
important step in meeting the challenges presented
by new styles of learning, especially with the
increased global communication and availability of
information. It is vital that the students become
familiar with the concept and use of innovative
information technology in order equip them for
future job market. Likewise, the faculty will also
achieve better quality in their teaching approach.
5. OBJECTIVES
Provide infrastructure and development to support
“live and virtual” services for Windows
Maintain and create servers and migrate some
existing servers to the new virtual environments
Provide standard platform definitions for quick
server setup (golden images)
Maintain 24 x 7 Support, quick response time
Provide first round of training for support
organizations
Provide redundancy, backup and recovery along
with data security
Offer support of Windows, Linux, and Mac OS file
systems
6. DELIVERABLES
Objective 1 – Assess the concept of virtual servers
and possible hardware and software suppliers.
Objective 2 – Design a clear process to set up new
virtual servers and computers. Migrate existing
servers and computers to the virtual environment.
7. ROLES AND RESPONSIBILITIES
Project Sponsor: Provides support to the project manager and
the project team. Creates high level contacts and creates
exposure to the public. Is in charge of overall performance of the
project.
Project Manager: Involved in all major planning and ensure the
project is completed on time, within budget and within the scope.
Project Team Members:
Server Expert
Storage Manager
IT Services Expert
Windows Application Specialist
Educational Technology Specialist
Curriculum development specialist
Advisors: Ensures compliance with educational accreditation
and provides direction in implementation into current teaching
methods.
Library Services Supervisor: Creates seamless implementation
with current library resources and staff.
8. WORK BREAKDOWN STRUCTURE
ITEC Structure Design and Development: A proper
location and equipment needs to be designed and
purchased. Once completed equipment needs to be
installed in proper locations.
Campus-wide Research and Development: Analyze
existing methods of utilizing technology in the
classroom. Use findings to direct ITEC development and
structure.
Faculty Development: Create training program for
faculty to use new technology methods in the
classroom.
Student Development: Create training program for
students to develop themselves effect technology
education methods. Provide them the tools and
resources to assist faculty in solving technology related
problems.
9. RISKS
Non-acceptance of the idea
Environment does not perform satisfactorily
Budget is not approved, outside money is not
obtained
Deployment is to complex or difficult to manage
10. SCHEDULE
Project Start- January 2011
Needs Assessment 14 days
Facilities Planning 15 days
Component order and delivery 90 days
Facilities Building 60 days
Installation 15 days
Training 15 days
System launch 1 days
Project Complete August 1st 2011
11. BUDGET
Total Investment Cost: $24,200
Initial Working Capital $6,000
Manpower
15 persons x 90 man hours (avg. 12/hr) = $16,200
ROI= est. 36 months
12. ACTION STEPS
Project charter needs approval by January 2nd 2010
Leadership Committees finalized
Questions and Discussion