SlideShare une entreprise Scribd logo
1  sur  19
Financial models & going &
seeing in construction
Jaskaran singh saini
Kartikeya Pandey
Manisha minu
MBA Infrastructure
Why This Study ?
• How to improve operations and plan reliability
in a large laboratory replacement project?
(In San Diego with the concept of going &
seeing concern)
How they researched
• Analyzing root causes the team realized the two
categories that reduced reliability were over-
committing and revising the plan.
• Tools employed to track the data included value
stream maps and employee feedback to inform
project planning.
• The counter measures employed improved
performance in these categories, which improved
reliability of meeting scheduled commitments.
• But the concrete walls pours increase.
• Thus making them use Going & seeing concern.
Results
• “Going and seeing” brought the team closer to
managing the project as a production line.
• data collected provided insight to the
contributing factors to production cycle times
including
– wait time,
– inventory, and
– rework
• Thus providing necessary balance to complement
the implementation of last planner on this
project.
• Limitations: data were collected from a single
project.
• Implications: Real time data collected directly
from field observations and feedback from
workers was used to make adjustments every
week.
• Value for practitioners: examples from a project
that used the principle of going and seeing to
continuously improve production and increase
the reliability of weekly work plans.
Introduction
• A general contractor team’s journey from
learning about the main production problems to
going and seeing in the field.
• How to improve operations and plan reliability on
a large laboratory replacement project in San
Diego, CA.
• The data collected from “going and seeing”
provided valuable insight to the contributing
factors to production cycle times including, wait
time, inventory, and rework.
• This helped the team to understand where did
they needed to improve
The Case
• The case refers to Ohno & Shingo with their team
who observed the productions .
• This process became famous by the name of
“Gemba walks” (gemba Actual Place) as
observing production gives more details and
insights.
• In doing so you look at the minimal details
scientifically & how they impact the production.
• Making TPS very sucessful
VSM
• The term going and seeing is recognized in the Lean
Production literature relates to the action of verifying
data at the source through personal observation.
• The glasses sign in the Value stream maps refers to the
Go & See the field by direct observation.
• VSMs are maps that show the sequence of tasks in a
value stream using symbols that have been
standardized and popularized by the Lean Enterprise
• Institute, based on the work developed at Toyota.
VSMs depict data related to each activity (value-
added, non-value added and supporting) while
simultaneously illustrating the flows of material and
information to deliver a product or service to the client
Plan-Do-Check-Act (PDCA)
• Going and seeing is one step
• PDCA cycle (Deming/Shewhart Cycle) provides a
structured way to improve production through a
series of structured observations, test, and
documentations.
• The Last Planner System of Production Control™
(LPS™) is an example of a system that uses the
basic tenets of the PDCA cycle and the going and
seeing principle to shield construction operations
against uncertainty
• Ideally last planners make ready process
during the lookahead plan preparation.
• in reality production pressures bring some
tension to the planning process.
• There are times when managers choose to
push tasks ,which have not been completely
screened through the make ready process.
• After the end of each planning cycle, the
completion of work packages is tracked and
causes for non-completion are recorded.
• actions to prevent recurrence of problems are
defined.
• The planning and control cycle continues as
the plan for the following week addresses the
shortcomings of the previous week and
defines new work packages.
• The planning and control cycle continues as the plan
for the following week addresses the shortcomings of
the previous week and defines new work packages.
• Work on it by cycle namely
– plan,
– try,
– reflect, and
– Standardize
• “standardize” means that uniform ground rules are set
based on the way operations are currently executed
• Standardization also allows small continuous
improvement activities (kaizen) to depart from
a common ground (standard) which is used as
a step to the next level
The project and the work methods
• The new $60 million facility will provide
oceanic research to assist in the management
and maintenance of the marine ecosystems in
the Pacific Ocean.
• The total constructed area will be 287,000
square feet, which includes
– new parking, offices and laboratory areas.
– an extensive aquaria area, necropsy lab, biology
labs, chemistry labs
– Class 100 clean room and a new 1-million-liter
seawater ocean technology development tank
• The project is funded by the American
Recovery and Reinvestment Act and is seeking
LEED Gold certification through numerous
sustainable features, including
– a 250KW rooftop photovoltaic system, vegetative
roofs for storm water management, recycled
andregionally sourced building materials, and
natural ventilation systems
• The contract structure is a firm-fixed price
based solely upon project solicitation
instructions, plans and specifications
Work Method – Going and seeing
• The use of LPS™ was employed from the start of
the project and was familiar to a good percentage
of the project team management staff.
• LPS™ was a new process to the self-performed
concrete personnel assigned to the project.
• two major factors were contributing to reducing
reliability
– over-committing and design changes
• the team employed two countermeasures to help
address the causes of these problems
– Preplanning meetings and constraint analysis
• To address the over-committing, early on the team
initiated a weekly concrete production pre-planning
meeting to discuss activities for the week related to
self performed concrete.
• The intent of this meeting was to thoroughly analyze
the plan for self-performed work and confirm the
commitments that would be shared in the weekly
subcontractor foremen planning meeting.
• This effort helped to increase reliability and affirm
realistic commitments for the week.
• Data told that this meeting helped to reduce the
incidence of over-committing as a problem that
contributed to unreliable plans
• Anticipation
– a contributing factor toreducing plan reliability would be
the impact of design and constructability issues
• Being a traditional design-bid-build project, there was
no cross-functional team during the development of
the design documents.
• a thorough constraint analysis effort was developed
and employed as a part of owner architect contract
• A constraint log was used to document the items that
needed attention and make them visible to all involved
• The constraint log was updated weekly and
summarized a variety of constraint types in a concise
one-page report
• The list was prioritized by importance and employed
visual categorization to improve communication. Since
this report was a “work plan” for the Design team and
Owner, reliability was measured to track performance.
Going & seeing in construction

Contenu connexe

Tendances

Project control wps office
Project control wps officeProject control wps office
Project control wps officekaransingh1064
 
EPA Project - Andy Smith
EPA Project - Andy SmithEPA Project - Andy Smith
EPA Project - Andy SmithAndy Smith
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & MonitoringJawad Ahmad
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaJoshua Render
 
SapSchedule
SapScheduleSapSchedule
SapSchedulecgentile
 
Case study 4 project cost management -- ppt slides
Case study 4   project cost management -- ppt slidesCase study 4   project cost management -- ppt slides
Case study 4 project cost management -- ppt slidesHarhar Caparida
 
Wrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control SystemWrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control Systemjunejalok
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
Gentile Consulting
Gentile ConsultingGentile Consulting
Gentile Consultingcgentile
 
The project plan
The project planThe project plan
The project planVatsalaPG
 
How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003bebocole
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Building Value Into The Nepa Process (Aka Why Is This Important)
Building Value Into The Nepa Process (Aka Why Is This Important)Building Value Into The Nepa Process (Aka Why Is This Important)
Building Value Into The Nepa Process (Aka Why Is This Important)pwhavens
 
EPA Presentation - Andy Smith
EPA Presentation - Andy SmithEPA Presentation - Andy Smith
EPA Presentation - Andy SmithAndy Smith
 

Tendances (20)

Project control wps office
Project control wps officeProject control wps office
Project control wps office
 
EPA Project - Andy Smith
EPA Project - Andy SmithEPA Project - Andy Smith
EPA Project - Andy Smith
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & Monitoring
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
Project Management
Project ManagementProject Management
Project Management
 
SapSchedule
SapScheduleSapSchedule
SapSchedule
 
Case study 4 project cost management -- ppt slides
Case study 4   project cost management -- ppt slidesCase study 4   project cost management -- ppt slides
Case study 4 project cost management -- ppt slides
 
Wrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control SystemWrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control System
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Project Control
Project ControlProject Control
Project Control
 
Gentile Consulting
Gentile ConsultingGentile Consulting
Gentile Consulting
 
The project plan
The project planThe project plan
The project plan
 
Chap09
Chap09Chap09
Chap09
 
CJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint PresentationCJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint Presentation
 
How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Building Value Into The Nepa Process (Aka Why Is This Important)
Building Value Into The Nepa Process (Aka Why Is This Important)Building Value Into The Nepa Process (Aka Why Is This Important)
Building Value Into The Nepa Process (Aka Why Is This Important)
 
Project cost management
Project cost managementProject cost management
Project cost management
 
EPA Presentation - Andy Smith
EPA Presentation - Andy SmithEPA Presentation - Andy Smith
EPA Presentation - Andy Smith
 

Similaire à Going & seeing in construction

Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...IRJET Journal
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
Lean Methods & Last Planning
Lean Methods & Last PlanningLean Methods & Last Planning
Lean Methods & Last PlanningThomas Almore
 
Project life cycle
Project life cycleProject life cycle
Project life cycleAbhishek Raj
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10Hari Krishna Shrestha
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheederKarin Rheeder
 
Applying both of waterfall and iterative development
Applying both of waterfall and iterative developmentApplying both of waterfall and iterative development
Applying both of waterfall and iterative developmentDeny Prasetia
 
10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptxJanak82
 
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdf
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdfGOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdf
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdfKarthikaSampathkumar2
 
component 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfcomponent 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfAnatole9
 
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02Durga Prasad Mishra
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.pptAlfredoArturoGranado
 
Project integration management
Project integration managementProject integration management
Project integration managementSaad Al Jabri
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
 

Similaire à Going & seeing in construction (20)

MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
Lean Methods & Last Planning
Lean Methods & Last PlanningLean Methods & Last Planning
Lean Methods & Last Planning
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Session 21 4th edition PMP
Session 21 4th edition PMPSession 21 4th edition PMP
Session 21 4th edition PMP
 
Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
Applying both of waterfall and iterative development
Applying both of waterfall and iterative developmentApplying both of waterfall and iterative development
Applying both of waterfall and iterative development
 
10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx
 
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdf
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdfGOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdf
GOLL+-+Practical+Project+Management+for+Clinical-Biomedical+Engineering.pdf
 
component 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfcomponent 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdf
 
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt
 
define phase.pptx
define phase.pptxdefine phase.pptx
define phase.pptx
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 

Plus de Kartikeya Pandey

Plus de Kartikeya Pandey (20)

Water and sanitation
Water and sanitationWater and sanitation
Water and sanitation
 
oil & gas drilling preliminaries
oil & gas drilling preliminariesoil & gas drilling preliminaries
oil & gas drilling preliminaries
 
Supplementary benefits
Supplementary benefitsSupplementary benefits
Supplementary benefits
 
Property tax
Property taxProperty tax
Property tax
 
Metros summary by Kartikeya Pandey
Metros summary by Kartikeya PandeyMetros summary by Kartikeya Pandey
Metros summary by Kartikeya Pandey
 
Marketing product placement strategies
Marketing product placement strategiesMarketing product placement strategies
Marketing product placement strategies
 
seven cs
seven csseven cs
seven cs
 
Indian ports (1)
Indian ports (1)Indian ports (1)
Indian ports (1)
 
Human resource planning ppt.
Human resource planning ppt.Human resource planning ppt.
Human resource planning ppt.
 
Gis
GisGis
Gis
 
Fire d project
Fire d projectFire d project
Fire d project
 
Alandur sewerage proj arun
Alandur sewerage proj   arunAlandur sewerage proj   arun
Alandur sewerage proj arun
 
24 x7 water in three states of karnataka
24 x7 water in three states of karnataka24 x7 water in three states of karnataka
24 x7 water in three states of karnataka
 
4
44
4
 
Land adjustment Land value capture
Land adjustment Land value captureLand adjustment Land value capture
Land adjustment Land value capture
 
Solid waste management practices in dehradun under jn nurm
Solid waste management practices in dehradun under jn nurmSolid waste management practices in dehradun under jn nurm
Solid waste management practices in dehradun under jn nurm
 
Infrastructure unbundling in south africa
Infrastructure unbundling in south africaInfrastructure unbundling in south africa
Infrastructure unbundling in south africa
 
Indian accounting standard (ind as) 27
Indian accounting standard (ind as) 27Indian accounting standard (ind as) 27
Indian accounting standard (ind as) 27
 
Hr presentation
Hr presentationHr presentation
Hr presentation
 
Concrete technology
Concrete technologyConcrete technology
Concrete technology
 

Dernier

IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 

Dernier (20)

IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 

Going & seeing in construction

  • 1. Financial models & going & seeing in construction Jaskaran singh saini Kartikeya Pandey Manisha minu MBA Infrastructure
  • 2. Why This Study ? • How to improve operations and plan reliability in a large laboratory replacement project? (In San Diego with the concept of going & seeing concern)
  • 3. How they researched • Analyzing root causes the team realized the two categories that reduced reliability were over- committing and revising the plan. • Tools employed to track the data included value stream maps and employee feedback to inform project planning. • The counter measures employed improved performance in these categories, which improved reliability of meeting scheduled commitments. • But the concrete walls pours increase. • Thus making them use Going & seeing concern.
  • 4. Results • “Going and seeing” brought the team closer to managing the project as a production line. • data collected provided insight to the contributing factors to production cycle times including – wait time, – inventory, and – rework • Thus providing necessary balance to complement the implementation of last planner on this project.
  • 5. • Limitations: data were collected from a single project. • Implications: Real time data collected directly from field observations and feedback from workers was used to make adjustments every week. • Value for practitioners: examples from a project that used the principle of going and seeing to continuously improve production and increase the reliability of weekly work plans.
  • 6. Introduction • A general contractor team’s journey from learning about the main production problems to going and seeing in the field. • How to improve operations and plan reliability on a large laboratory replacement project in San Diego, CA. • The data collected from “going and seeing” provided valuable insight to the contributing factors to production cycle times including, wait time, inventory, and rework. • This helped the team to understand where did they needed to improve
  • 7. The Case • The case refers to Ohno & Shingo with their team who observed the productions . • This process became famous by the name of “Gemba walks” (gemba Actual Place) as observing production gives more details and insights. • In doing so you look at the minimal details scientifically & how they impact the production. • Making TPS very sucessful
  • 8. VSM • The term going and seeing is recognized in the Lean Production literature relates to the action of verifying data at the source through personal observation. • The glasses sign in the Value stream maps refers to the Go & See the field by direct observation. • VSMs are maps that show the sequence of tasks in a value stream using symbols that have been standardized and popularized by the Lean Enterprise • Institute, based on the work developed at Toyota. VSMs depict data related to each activity (value- added, non-value added and supporting) while simultaneously illustrating the flows of material and information to deliver a product or service to the client
  • 9. Plan-Do-Check-Act (PDCA) • Going and seeing is one step • PDCA cycle (Deming/Shewhart Cycle) provides a structured way to improve production through a series of structured observations, test, and documentations. • The Last Planner System of Production Control™ (LPS™) is an example of a system that uses the basic tenets of the PDCA cycle and the going and seeing principle to shield construction operations against uncertainty
  • 10. • Ideally last planners make ready process during the lookahead plan preparation. • in reality production pressures bring some tension to the planning process. • There are times when managers choose to push tasks ,which have not been completely screened through the make ready process.
  • 11. • After the end of each planning cycle, the completion of work packages is tracked and causes for non-completion are recorded. • actions to prevent recurrence of problems are defined. • The planning and control cycle continues as the plan for the following week addresses the shortcomings of the previous week and defines new work packages.
  • 12. • The planning and control cycle continues as the plan for the following week addresses the shortcomings of the previous week and defines new work packages. • Work on it by cycle namely – plan, – try, – reflect, and – Standardize • “standardize” means that uniform ground rules are set based on the way operations are currently executed
  • 13. • Standardization also allows small continuous improvement activities (kaizen) to depart from a common ground (standard) which is used as a step to the next level
  • 14. The project and the work methods • The new $60 million facility will provide oceanic research to assist in the management and maintenance of the marine ecosystems in the Pacific Ocean. • The total constructed area will be 287,000 square feet, which includes – new parking, offices and laboratory areas. – an extensive aquaria area, necropsy lab, biology labs, chemistry labs – Class 100 clean room and a new 1-million-liter seawater ocean technology development tank
  • 15. • The project is funded by the American Recovery and Reinvestment Act and is seeking LEED Gold certification through numerous sustainable features, including – a 250KW rooftop photovoltaic system, vegetative roofs for storm water management, recycled andregionally sourced building materials, and natural ventilation systems • The contract structure is a firm-fixed price based solely upon project solicitation instructions, plans and specifications
  • 16. Work Method – Going and seeing • The use of LPS™ was employed from the start of the project and was familiar to a good percentage of the project team management staff. • LPS™ was a new process to the self-performed concrete personnel assigned to the project. • two major factors were contributing to reducing reliability – over-committing and design changes • the team employed two countermeasures to help address the causes of these problems – Preplanning meetings and constraint analysis
  • 17. • To address the over-committing, early on the team initiated a weekly concrete production pre-planning meeting to discuss activities for the week related to self performed concrete. • The intent of this meeting was to thoroughly analyze the plan for self-performed work and confirm the commitments that would be shared in the weekly subcontractor foremen planning meeting. • This effort helped to increase reliability and affirm realistic commitments for the week. • Data told that this meeting helped to reduce the incidence of over-committing as a problem that contributed to unreliable plans
  • 18. • Anticipation – a contributing factor toreducing plan reliability would be the impact of design and constructability issues • Being a traditional design-bid-build project, there was no cross-functional team during the development of the design documents. • a thorough constraint analysis effort was developed and employed as a part of owner architect contract • A constraint log was used to document the items that needed attention and make them visible to all involved • The constraint log was updated weekly and summarized a variety of constraint types in a concise one-page report • The list was prioritized by importance and employed visual categorization to improve communication. Since this report was a “work plan” for the Design team and Owner, reliability was measured to track performance.

Notes de l'éditeur

  1. In this concept they started observing the complete production line and making informed decisions
  2. The use of a standard allows results to be compared and deviations from plans to be quickly detected