SlideShare une entreprise Scribd logo
1  sur  45
2
ENGINEERING TEAM
PROJECT MANAGER: Alice Madjani
TRANSPORTATION ENGINEER: Eric Hulme
STRUCTURAL ENGINEER: Matt Murray
ENVIRONMENTAL ENGINEER: Mike Broyles
STRUCTURAL ENGINEER: Ryan Laughlin
Introduction Facility Drainag Structura ConstructioLEEDAcces
Presentation Overview
 Baseball Facility
 Soccer Facility
 Site Layout
 Drainage
 Site Access
 Structural Aspects
 LEED Credentials
 Construction and Cost
3Introduction Facility Drainag Structura ConstructioLEEDAcces
Time for a New Facility
 Other Big Ten Facilities
 Current Purdue Facility
4Introduction Facility Drainag Structura ConstructioLEEDAcces
The Facility
5Introduction Facility Drainag Structura ConstructioLEEDAcces
 1,800 Permanent
Seats
 2 Green Spaces
 State of the art Press
Box
 High Definition
 Grass Berme Seating
 Home & Away
Lockers
 Indoor Batting Cages
 Unique Architecture
Soccer Facility
 Continue using the eastern
field for competition
 Option of using the west field
for a future men’s team
 Expanded Seating
 Support Facilities
 Concessions Stand
 Restrooms
 Locker Room
 H.D. Lighting
 Opportunities to share
facilities
6Introduction Facility Drainag Structura ConstructioLEEDAcces
Facility Location
7Introduction Facility Drainag Structura ConstructioLEEDAcces
Drainage and Grading
 Storm Water Management Overview
 Stream running through the center of the site
 Detention Basin on the west end of the site
 Drainage system for the baseball field
 Grading Summary
 Buildings are elevated 1-2 ft to prevent infiltration during
heavy storms.
 The stream is the low point of the site, allowing the site
to drain to it.
8Introduction Facility Drainag Structura ConstructioLEEDAcces
Stream Design
 Trapezoidal Channel
 Designed for 100-year, 12 hour duration rain event
 4:1 side slopes for stability
 Lined with cobbles to prevent erosion
 Side slopes lined with native grasses
 Prevent erosion
 Remove sediment (TSS) and nutrients from runoff
 3 connected sections
 Connector from east drainage basin to the site
 East Channel (about 1/2 of developed site drainage)
 West Channel (all of developed site drainage)
9Introduction Facility Drainag Structura ConstructioLEEDAcces
Stream Dimensions
 Connector from east drainage
basin
 Depth: 3 ft
 Bottom Width: 2 ft
 Top Width: 10 ft
 East Channel
 Depth: 4 ft
 Bottom Width: 1 ft
 Top Width: 33 ft
 West Channel
 Depth: 4 ft
 Bottom Width: 6 ft
 Top Width: 38 ft
10Introduction Facility Drainag Structura ConstructioLEEDAcces
Stream Layout
11Introduction Facility Drainag Structura ConstructioLEEDAcces
Steam Cross Section
12Introduction Facility Drainag Structura ConstructioLEEDAcces
Detention Basin Design
 Design storm: 100-year, 12 hr duration rain
event
 Required Storage Volume: 16.64 acre-ft
 Design Characteristics
 Overflow weir: 45 ft wide x 1 ft high
 4 outflow pipes
 2 – 12” diameter pipes at invert elevation of 670.1
ft
 2 – 15” diameter pipes at invert elevation of 672.2
ft
 Depth of 8 feet and bottom elevation of 667.4
ft
 Top elevation of 675.4 ft 13Introduction Facility Drainag Structura ConstructioLEEDAcces
Baseball Field Drainage
 Hydraway 2000 drainage system
 Geotextile drainage mat
 12” wide x 1” thick
 Strong, able to withstand heavy loading
 Placed every 20 feet
 Drain to a central drainage pipe
 Installation
 After field is graded appropriately
 Smaller trencher creates a 6” wide x 12” deep
 Backfill with granular fill to promote drainage
14Introduction Facility Drainag Structura ConstructioLEEDAcces
Baseball Field Drainage
Layout
• Blue Lines = Hydraway 2000
Mats
• Pink Line = Central Drainage
Collector
Source: Hydraway website
15Introduction Facility Drainag Structura ConstructioLEEDAcces
Pavement Systems
Surface Asphalt
Binder Asphalt
Type #53
Sub-base
1 ½ inch
4 ½ inch
8 inch
Surface Asphalt
Binder Asphalt
Type #53
Sub-base
1 ½ inch
3 inch
8 inch
Concrete
Type #53
Sub-base
6 inch
8 inch
Pervious
Concrete
Sand
Type #53
Sub-base
9 inch
2 inch
9 inch
Introduction Facility Drainag Structura ConstructioLEEDAcces 16
Pedestrian Access
17
Upper Pedestrian Corridor
Lower Pedestrian Corridor
Central Pathway
Eastern Pathway
Western Pathway
Bike Path
Extension
Site Access: Existing Traffic Volumes
LOS ANALYSIS
 McCormick & Cherry (AWSC)
 A.M. Peak Hour:
 LOS E
 41 sec Delay
 McCormick & Tennis Center
(TWSC)
 A.M. Peak Hour:
 LOS B
 15 sec Delay
 P.M. Peak Hour:
• LOS F
• 330 sec Delay
– P.M. Peak Hour:
• LOS C
• 18 sec Delay
Introduction Facility Drainag Structura ConstructioLEEDAcces 18
Site Access: 2010 Background
Volumes
LOS ANALYSIS
 McCormick & Cherry (AWSC)
 A.M. Peak Hour:
• LOS F
• 95 sec Delay
 McCormick & Tennis Center
(TWSC)
 A.M. Peak Hour:
• LOS C
• 16 sec Delay
 P.M. Peak Hour:
• LOS F
• 492 sec Delay
 P.M. Peak Hour:
• LOS C
• 20 sec Delay
Introduction Facility Drainag Structura ConstructioLEEDAcces 19
Site Access: 2010 Total Volumes
LOS ANALYSIS
 McCormick & Cherry (RDBT)
 A.M. Peak Hour:
• LOS C
• 18 sec Delay
 McCormick & Tennis Center (TWSC)
 A.M. Peak Hour:
• LOS C
• 17 sec Delay
 McCormick & Perimeter Pkwy (TWSC)
 A.M. Peak Hour:
• LOS A
• 0 sec Delay
 P.M. Peak Hour:
• LOS C
• 19 sec Delay
 P.M. Peak Hour:
• LOS C
• 21 sec Delay
 P.M. Peak Hour:
• LOS A
• 0 sec Delay
Introduction Facility Drainag Structura ConstructioLEEDAcces 20
Traffic Maintenance Plan
 Construction Access
 Baseball Stadium: Proposed AlignmentPerimeter Parkway
 Soccer Stadium: Existing gravel access north of Tennis
parking Lot
 McCormick Road Improvements
 Long-Term Stationary Work Zone
 Work Zone Type
 Intermittent Closure (off-peak hours only)
 Use of shoulder
 Construction Phasing
 Reconstruction by Halves (sides)
 Work Zone Speed limit: 40 mph
 As prescribed by INDOT Design Manual, Part VII - Work Zone Traffic Control
Introduction Facility Drainag Structura ConstructioLEEDAcces 21
 Live Load
 60.0 psf for stadium seating
 50.0 psf for rooms
 20.0 psf roof live load
 0.54 psf live load reduction factor
 Seismic Load
 60 kip base shear
 Lateral Loads
 First Story = 17.4 kip
 Second Story = 21.0 kip
 Third Story = 21.6 kip
 Dead Load
 63.0 psf roof load
 74.0 psf for other floors
 Wind Load
 10.7 psf lateral load
 13.4 psf uplift
 Environmental Load
 22.0 psf snow load
 11.9 psf ice load
Structural Design: Loads
22Introduction Facility Drainag Structura ConstructioLEEDAcces
 SAP2000 Analysis
 Placing columns & beams
 Model of main stadium
structure
 Application of loads
 Computer analysis
 Approximate Analysis
 Axial forces in columns of the
critical section
 Portal method for lateral load
Structural Design: Stadium Frame
Analysis
23Introduction Facility Drainag Structura ConstructioLEEDAcces
Structural Design:Sizing Stadium Component
First Floor Column
Sizes
First Floor Beam Sizes
24Introduction Facility Drainag Structura ConstructioLEEDAcces
Structural Design:Sizing Stadium
Components
 4” concrete
decking
 18K5 joists
spaced at 5’ for
third story
 12K3 joists
spaced at 5’ for
lower stories
Additional
Structural
Components
:
25Introduction Facility Drainag Structura ConstructioLEEDAcces
Structural Design: Concrete Stadium
Seating
 Seating
Structure:
 Reinforced
Concrete
 Beams, Girders,
Columns
 Masonry on
Backstop
26Introduction Facility Drainag Structura ConstructioLEEDAcces
Structural Design: Concrete Stadium
Seating
 Design: Isolate
Beams, Girders,
and Columns
 Assume no
moment Transfer
 Reduction to a
determinate
structure
 Load Path for
Structure
Beams
 24 ft span
 Simply supported
 2.5 ft wide
 PCI Design Handbook
Load
Path
27Introduction Facility Drainag Structura ConstructioLEEDAcces
 29.5 ft span
 Simply supported
 Apply distributed beam
loads
 Neglect compression
 Flexure controls
 PCI Design Handbook
Structural Design: Concrete Stadium
Seating
 Design: Isolate
beams, Girders,
and Columns
 Assume no
moment Transfer
 Reduction to a
determinate
structure
Girders
28Introduction Facility Drainag Structura ConstructioLEEDAcces
 No moments – No
interaction diagrams
 Tributary area of
girders for total loads
 Detail the section –
Check strength
 PCI Design Handbook
 Design: Isolate
beams, Girders,
and Columns
 Assume no
moment Transfer
 Reduction to a
determinate
structure
Columns
29Introduction Facility Drainag Structura ConstructioLEEDAcces
Structural Design: Concrete Stadium
Seating
 Complicated
Moment Resistant
Frame
 Truss  remove
indeterminacy
 Consider tributary
area
 Apply joint loads
 Joint analysis 
member forces
 Check Stresses
Reality
Model
30Introduction Facility Drainag Structura ConstructioLEEDAcces
Structural Design: Awning Support
Structure
Support Section
Foundation Design
 Soil Capacity
 Gross soil bearing capacity of
6,400 psf
 2,000 psf net allowable
bearing pressure used in
design
 Shallow Foundations
 Combined Footings
 3 columns per footing
 Eleven 5-ft x 35-ft reinforced
concrete footings
 Design Considerations
 Soil bearing capacity
 Immediate settlement
 Consolidation settlement
31Introduction Facility Drainag Structura ConstructioLEEDAcces
L.E.E.D.
 LEED Certification and Benefits
 CE 498 Ratings
32
LEED Rating Points
Certified 14-17
Silver 18-20
Gold 21-27
Platinum 28-37
Introduction Facility Drainag Structura ConstructioLEEDAcces
L.E.E.D
 LEED Reviews
 Reviewer 1: 12 points - not certified
 Reviewer 2: 17 points - LEED Certified
 LEED re-submittals
 Requesting Silver certification
 Submitted documents (22 points)
 Sustainable Site Credits: 10
 Water Efficiency Credits: 4
 Materials and Resources Credits: 6
 Innovation & Design Process Credits: 2
 Gold Certification Potential
33Introduction Facility Drainag Structura ConstructioLEEDAcces
Project Controls
 Project Organization/communication
 Design-Build firm advantages
 Site Management
 Lines of communication
34Introduction Facility Drainag Structura ConstructioLEEDAcces
Quality, Materials and Safety
 Quality
 ZEAL’s Quality Control and Quality Assurance Manual
 Monitoring of all products, materials, and work
 Inspections
 Material
 Building : Steel framing, reinforced concrete, masonry
 Parking lot: Pervious concrete
 Access road: Asphalt pavement
 Safety
 ZEAL’s Safety Manager
 Subcontractor’s safety requirements
35Introduction Facility Drainag Structura ConstructioLEEDAcces
Cost Estimate
 Price Proposal
 Schedule of values
 Request for payment due the 1st of every month and payment
received by the 15th of the next month
 5% retainage on all payments
36
PRICE PROPOSAL
Basic Facility Proposal Price $6,458,182
Optional Facilities Proposal Price $3,160,805
Parking and Transportation Facility Proposal price $3,545,865
Total Project Price Proposal $13,164,853
Introduction Facility Drainag Structura ConstructioLEEDAcces
Cost Estimate
 Basic Facility
37
CSI division Total Cost
Direct cost
Division 3 - Concrete $433,181
Division 4 - Masonry $180,063
Division 5 -Metals $483,996
Division 7 -Thermal & Moisture protection $62,603
Division 8 - Openings $28,930
Division 9 - Finishes $308,803
Division 10 - Specialties $41,392
Division 11 - Equipments $133,642
Division 31 - Earthwork $213,827
Division 32 - Exterior Improvement $828,657
Division 33 - Utilities $1,993,004
Total Direct Cost $4,708,098
Indirect Cost
Fees $1,155,338
Insurance $245,002
Allowance $1,131,676
Total indirect Cost $2,532,016
Total Facility cost (89.2% reduction factor) $6,458,182
Introduction Facility Drainag Structura ConstructioLEEDAcces
Cost Estimate
 Parking and Transportation Facility
38
CSI division Total Cost
Direct cost
Division 31 - Earthwork $144,271.58
Division 32 - Exterior Improvement $2,320,927.91
Division 33 - Utilities $275,384.21
Total Direct Cost $2,740,583.70
Indirect Cost
Fees $426,129
Insurance $143,881
Allowance $664,592
Total indirect Cost $1,234,602
Total Facility cost (89.2% reduction factor) $3,545,865
Introduction Facility Drainag Structura ConstructioLEEDAcces
Cost Estimate
 Optional Facility
39
Direct cost Total Cost
Soccer $664,047
Seat expansion $105,000
Other Roadways and parking facility $1,666,245
Total Direct cost $2,435,292
Indirect Cost
Fees $389,800
Insurance $127,853
Allowance $590,558
Total indirect Cost $1,108,211
Total Facility cost (89.2% reduction factor) $3,160,805
Introduction Facility Drainag Structura ConstructioLEEDAcces
Project Schedule
 Project duration: 462 days; ~ 20 months
 Design schedule
 Conceptual Design: Jan 13,09 –May 5, 09
 Final Design: May 1, 09 – Aug 12, 09
 Construction schedule
 Site preparation and mobilization: Aug 3, 09
 Construction starts: Aug 17, 09
 Scheduled completion date: Oct 20, 2010
 Latest construction completion date : Nov 30, 2010
40Introduction Facility Drainag Structura ConstructioLEEDAcces
Construction Scheduling
41Introduction Facility Drainag Structura ConstructioLEEDAcces
Summary
42
 Purdue’s need
 Baseball Facility
 Soccer Facility
 Drainage
 Site Access
 Structural Aspects
 LEED Credentials
 Construction and Cost
Questions!
43
References
 Ashley, Erin. "Using Pervious Concrete to achieve LEED credits." 2008.
Pervious Concrete Pavement. 02 February 2009
<http://www.perviouspavement.org/benefits_LEEDcredit.htm>.
 B4UBUILD. A Sample Residential Construction Schedule. 1998 - 2008. 19
February 2009 <http://www.b4ubuild.com/resources/schedule/6kproj.shtml>.
 CE 498 - CE Design Project. January 2009. 02 February 2009
<https://engineering.purdue.edu/Courses/CE498>.
 Corporation, The Schneider. "Storm Water Analysis." 2007.
 Google. Google Earth. West Lafayette, February 2009.
 Hydraway Drainage Systems. “Hydraway 2000.” 2007.
<http://www.hydraway.net/hydraway_2000.php>
 HNTB. Purdue University - Athletic Facilities Master Plan. Conceptual
master plan. Indianapolis: HNTB, 2007.
 J&M Equipment Specialist & Salvage Recovery. 2008. 2 February 2009
<jmequipmentspecialist.com/id7.html>.
 Michigan, University of. Michigan Go Blue. February 2009. February 2009
<http://www.mgoblue.com/facilities/article.aspx?id=28646#>.
44
References cont’d
 Microsoft. Live Search Maps. February 2009. February 2009
<http://maps.live.com/>.
 Office of the University Architect. "Consultant's Handbook." 2006. Office of
University Architect. 20 January 2009
<http://www.purdue.edu/architect/resources/handbook/index.html>.
 Qualite. Design Soccer. 2008. 12 February 2009
<http://www.qualite.com/DesignSoccer.html>.
 RS Means. Building Construction Cost Data. Kingston, MA: R.S. Means
Company, 2009.
 The Schneider Corporation. "Report of Geotechnical Engineering Study."
2008.
 The Schneider Corporation. "Storm Water Analysis." 2007.
 U.S. Fish and Wildlife Service. "Viewing Wetland with Google Earth (Plug-in
for Google Earth)." July 2008.
 U.S. Green Building Council. New Construction Version 2.2 Reference
Guide. Washington, DC: U.S. Green Building Council, 2006.
 US Green Building Council. 2009. 20 January 2009 <http://www.usgbc.org/>.
45

Contenu connexe

Tendances

Rotary System
Rotary SystemRotary System
Rotary SystemAFATous
 
Ground Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingGround Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingTim Leung
 
16176745 drilling-rig-operations-a-to-z-rotary-drilling-rig-components
16176745 drilling-rig-operations-a-to-z-rotary-drilling-rig-components16176745 drilling-rig-operations-a-to-z-rotary-drilling-rig-components
16176745 drilling-rig-operations-a-to-z-rotary-drilling-rig-componentsJohansson Engineering Ltd
 
Landing Gear Project Final Report
Landing Gear Project Final ReportLanding Gear Project Final Report
Landing Gear Project Final ReportKevin Osman
 
ASW-22DB (Eta Biter) Evolution
ASW-22DB (Eta Biter) EvolutionASW-22DB (Eta Biter) Evolution
ASW-22DB (Eta Biter) EvolutionGlider Pilot
 
Rig types and components
Rig types and componentsRig types and components
Rig types and componentsMarwan Elaraby
 
Manifold design, verification,_and_validation
Manifold design, verification,_and_validationManifold design, verification,_and_validation
Manifold design, verification,_and_validationjpegd
 
Drilling Rig Components ( Illustrated Glossary )
Drilling Rig Components ( Illustrated Glossary )Drilling Rig Components ( Illustrated Glossary )
Drilling Rig Components ( Illustrated Glossary )guest521158
 
رضا مصطفوی طباطبایی WELL SERVICE EQUIPMENT MECHANICAL TECHNICAL ENGINEERING 2015
رضا مصطفوی طباطبایی WELL SERVICE EQUIPMENT MECHANICAL TECHNICAL ENGINEERING 2015رضا مصطفوی طباطبایی WELL SERVICE EQUIPMENT MECHANICAL TECHNICAL ENGINEERING 2015
رضا مصطفوی طباطبایی WELL SERVICE EQUIPMENT MECHANICAL TECHNICAL ENGINEERING 2015Reza Mostafavi Tabatabaei
 
Q922+de2+l10 v1
Q922+de2+l10 v1Q922+de2+l10 v1
Q922+de2+l10 v1AFATous
 
Drilling rig operations a to z rotary drilling rig components
Drilling rig operations  a to z rotary drilling rig componentsDrilling rig operations  a to z rotary drilling rig components
Drilling rig operations a to z rotary drilling rig componentsamrhaggag
 
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasSubsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasAshwin Gadgil
 
InterMoor Installation of Subsea Pile and Manifold at AC24
InterMoor Installation of Subsea Pile and Manifold at AC24InterMoor Installation of Subsea Pile and Manifold at AC24
InterMoor Installation of Subsea Pile and Manifold at AC24jonathonmiller2008
 
Culvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsCulvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsPath Marketing Inc.
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Nandan Shandilya
 
Functions of drilling rig components Presentation
Functions of drilling rig components PresentationFunctions of drilling rig components Presentation
Functions of drilling rig components PresentationThanos Paraschos
 
(2) drilling rig operations &amp; a to z rotary drilling rig components
(2) drilling rig operations &amp; a to z rotary drilling rig components(2) drilling rig operations &amp; a to z rotary drilling rig components
(2) drilling rig operations &amp; a to z rotary drilling rig componentsmakrand tripathi
 

Tendances (19)

Rotary System
Rotary SystemRotary System
Rotary System
 
Ground Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingGround Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional Drilling
 
16176745 drilling-rig-operations-a-to-z-rotary-drilling-rig-components
16176745 drilling-rig-operations-a-to-z-rotary-drilling-rig-components16176745 drilling-rig-operations-a-to-z-rotary-drilling-rig-components
16176745 drilling-rig-operations-a-to-z-rotary-drilling-rig-components
 
Landing Gear Project Final Report
Landing Gear Project Final ReportLanding Gear Project Final Report
Landing Gear Project Final Report
 
ASW-22DB (Eta Biter) Evolution
ASW-22DB (Eta Biter) EvolutionASW-22DB (Eta Biter) Evolution
ASW-22DB (Eta Biter) Evolution
 
Rig types and components
Rig types and componentsRig types and components
Rig types and components
 
Manifold design, verification,_and_validation
Manifold design, verification,_and_validationManifold design, verification,_and_validation
Manifold design, verification,_and_validation
 
Drilling Rig Components ( Illustrated Glossary )
Drilling Rig Components ( Illustrated Glossary )Drilling Rig Components ( Illustrated Glossary )
Drilling Rig Components ( Illustrated Glossary )
 
رضا مصطفوی طباطبایی WELL SERVICE EQUIPMENT MECHANICAL TECHNICAL ENGINEERING 2015
رضا مصطفوی طباطبایی WELL SERVICE EQUIPMENT MECHANICAL TECHNICAL ENGINEERING 2015رضا مصطفوی طباطبایی WELL SERVICE EQUIPMENT MECHANICAL TECHNICAL ENGINEERING 2015
رضا مصطفوی طباطبایی WELL SERVICE EQUIPMENT MECHANICAL TECHNICAL ENGINEERING 2015
 
Introduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface FacilitiesIntroduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface Facilities
 
Q922+de2+l10 v1
Q922+de2+l10 v1Q922+de2+l10 v1
Q922+de2+l10 v1
 
Drilling rig operations a to z rotary drilling rig components
Drilling rig operations  a to z rotary drilling rig componentsDrilling rig operations  a to z rotary drilling rig components
Drilling rig operations a to z rotary drilling rig components
 
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasSubsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
 
InterMoor Installation of Subsea Pile and Manifold at AC24
InterMoor Installation of Subsea Pile and Manifold at AC24InterMoor Installation of Subsea Pile and Manifold at AC24
InterMoor Installation of Subsea Pile and Manifold at AC24
 
Culvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsCulvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & Applications
 
West leda
West ledaWest leda
West leda
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
 
Functions of drilling rig components Presentation
Functions of drilling rig components PresentationFunctions of drilling rig components Presentation
Functions of drilling rig components Presentation
 
(2) drilling rig operations &amp; a to z rotary drilling rig components
(2) drilling rig operations &amp; a to z rotary drilling rig components(2) drilling rig operations &amp; a to z rotary drilling rig components
(2) drilling rig operations &amp; a to z rotary drilling rig components
 

En vedette

2313 – al arabi stadium upgrade-structural presentation
2313 – al arabi stadium upgrade-structural presentation2313 – al arabi stadium upgrade-structural presentation
2313 – al arabi stadium upgrade-structural presentationShyam Sundar
 
2016 AEC Excellence Awards Showcase Book
2016 AEC Excellence Awards Showcase Book2016 AEC Excellence Awards Showcase Book
2016 AEC Excellence Awards Showcase BookAutodesk AEC
 
Bs procedure
Bs procedureBs procedure
Bs procedurehlksd
 
Anz Stadium Case Study - SeatShare Concept Test - CheckinLine
Anz Stadium Case Study - SeatShare Concept Test - CheckinLineAnz Stadium Case Study - SeatShare Concept Test - CheckinLine
Anz Stadium Case Study - SeatShare Concept Test - CheckinLineCheckinLine
 
Stadiums That Changed The Game - Structure Development Of Stadiums
Stadiums That Changed The Game - Structure Development Of StadiumsStadiums That Changed The Game - Structure Development Of Stadiums
Stadiums That Changed The Game - Structure Development Of Stadiumssoumya2492
 
Building construction-2 project-2
Building construction-2 project-2Building construction-2 project-2
Building construction-2 project-2kerneng
 
Stadium Design Project Details
Stadium Design Project DetailsStadium Design Project Details
Stadium Design Project Detailscelsesser
 
Building Construction 2 Project 2 Report
Building Construction 2 Project 2 ReportBuilding Construction 2 Project 2 Report
Building Construction 2 Project 2 ReportWilden How
 
Stadium Project
Stadium ProjectStadium Project
Stadium Projectlakvij
 
Civil structural engineering - Flat slab design
Civil structural engineering -  Flat slab designCivil structural engineering -  Flat slab design
Civil structural engineering - Flat slab designSatish Narayan
 
Beijing National Stadium
Beijing National StadiumBeijing National Stadium
Beijing National Stadiumluisaam
 
Stadium negara report history2
Stadium negara report history2Stadium negara report history2
Stadium negara report history2ForestedTiger
 

En vedette (13)

2313 – al arabi stadium upgrade-structural presentation
2313 – al arabi stadium upgrade-structural presentation2313 – al arabi stadium upgrade-structural presentation
2313 – al arabi stadium upgrade-structural presentation
 
2016 AEC Excellence Awards Showcase Book
2016 AEC Excellence Awards Showcase Book2016 AEC Excellence Awards Showcase Book
2016 AEC Excellence Awards Showcase Book
 
Bs procedure
Bs procedureBs procedure
Bs procedure
 
Anz Stadium Case Study - SeatShare Concept Test - CheckinLine
Anz Stadium Case Study - SeatShare Concept Test - CheckinLineAnz Stadium Case Study - SeatShare Concept Test - CheckinLine
Anz Stadium Case Study - SeatShare Concept Test - CheckinLine
 
Stadiums That Changed The Game - Structure Development Of Stadiums
Stadiums That Changed The Game - Structure Development Of StadiumsStadiums That Changed The Game - Structure Development Of Stadiums
Stadiums That Changed The Game - Structure Development Of Stadiums
 
Structural lightweight concrete
Structural lightweight concreteStructural lightweight concrete
Structural lightweight concrete
 
Building construction-2 project-2
Building construction-2 project-2Building construction-2 project-2
Building construction-2 project-2
 
Stadium Design Project Details
Stadium Design Project DetailsStadium Design Project Details
Stadium Design Project Details
 
Building Construction 2 Project 2 Report
Building Construction 2 Project 2 ReportBuilding Construction 2 Project 2 Report
Building Construction 2 Project 2 Report
 
Stadium Project
Stadium ProjectStadium Project
Stadium Project
 
Civil structural engineering - Flat slab design
Civil structural engineering -  Flat slab designCivil structural engineering -  Flat slab design
Civil structural engineering - Flat slab design
 
Beijing National Stadium
Beijing National StadiumBeijing National Stadium
Beijing National Stadium
 
Stadium negara report history2
Stadium negara report history2Stadium negara report history2
Stadium negara report history2
 

Similaire à Rfp09498 p2 pres_t05

Harlem Park Building Design Project
Harlem Park Building Design ProjectHarlem Park Building Design Project
Harlem Park Building Design ProjectEd Guerra, P.E.
 
Titan Rover CDR Presentation
Titan Rover CDR PresentationTitan Rover CDR Presentation
Titan Rover CDR PresentationKristopherKerames
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTMUHAMMAD NOMAN KHAN
 
Senior Design Capstone Presentation
Senior Design Capstone PresentationSenior Design Capstone Presentation
Senior Design Capstone Presentationfinkjosh
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183Miklos Peller, Sr.
 
Long Span Building Construction
Long Span Building ConstructionLong Span Building Construction
Long Span Building ConstructionAsz My
 
Success story fischer fze
Success story  fischer fzeSuccess story  fischer fze
Success story fischer fzefischer_ae
 
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)Franco Bontempi Org Didattica
 
hochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxhochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxZakaria156221
 
Présentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxPrésentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxZakaria156221
 
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsKeep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsCommunications Branding
 
King Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 PresentationKing Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 Presentationguest2d44ee
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design PresentationKeith Kong
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridgejupallipavan2911
 

Similaire à Rfp09498 p2 pres_t05 (20)

Harlem Park Building Design Project
Harlem Park Building Design ProjectHarlem Park Building Design Project
Harlem Park Building Design Project
 
Titan Rover CDR Presentation
Titan Rover CDR PresentationTitan Rover CDR Presentation
Titan Rover CDR Presentation
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
 
Company profile
Company profileCompany profile
Company profile
 
Senior Design Capstone Presentation
Senior Design Capstone PresentationSenior Design Capstone Presentation
Senior Design Capstone Presentation
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
 
Long Span Building Construction
Long Span Building ConstructionLong Span Building Construction
Long Span Building Construction
 
Success story fischer fze
Success story  fischer fzeSuccess story  fischer fze
Success story fischer fze
 
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)
 
hochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxhochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptx
 
Présentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxPrésentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptx
 
Defense thesis
Defense thesisDefense thesis
Defense thesis
 
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsKeep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
 
New Roadside Hardware Improvements
New Roadside Hardware ImprovementsNew Roadside Hardware Improvements
New Roadside Hardware Improvements
 
King Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 PresentationKing Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 Presentation
 
ES3_Simpson
ES3_SimpsonES3_Simpson
ES3_Simpson
 
Final Presentation - Group 2 (1)
Final Presentation - Group 2 (1)Final Presentation - Group 2 (1)
Final Presentation - Group 2 (1)
 
Concerto
ConcertoConcerto
Concerto
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
 

Rfp09498 p2 pres_t05

  • 1.
  • 2. 2 ENGINEERING TEAM PROJECT MANAGER: Alice Madjani TRANSPORTATION ENGINEER: Eric Hulme STRUCTURAL ENGINEER: Matt Murray ENVIRONMENTAL ENGINEER: Mike Broyles STRUCTURAL ENGINEER: Ryan Laughlin Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 3. Presentation Overview  Baseball Facility  Soccer Facility  Site Layout  Drainage  Site Access  Structural Aspects  LEED Credentials  Construction and Cost 3Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 4. Time for a New Facility  Other Big Ten Facilities  Current Purdue Facility 4Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 5. The Facility 5Introduction Facility Drainag Structura ConstructioLEEDAcces  1,800 Permanent Seats  2 Green Spaces  State of the art Press Box  High Definition  Grass Berme Seating  Home & Away Lockers  Indoor Batting Cages  Unique Architecture
  • 6. Soccer Facility  Continue using the eastern field for competition  Option of using the west field for a future men’s team  Expanded Seating  Support Facilities  Concessions Stand  Restrooms  Locker Room  H.D. Lighting  Opportunities to share facilities 6Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 7. Facility Location 7Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 8. Drainage and Grading  Storm Water Management Overview  Stream running through the center of the site  Detention Basin on the west end of the site  Drainage system for the baseball field  Grading Summary  Buildings are elevated 1-2 ft to prevent infiltration during heavy storms.  The stream is the low point of the site, allowing the site to drain to it. 8Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 9. Stream Design  Trapezoidal Channel  Designed for 100-year, 12 hour duration rain event  4:1 side slopes for stability  Lined with cobbles to prevent erosion  Side slopes lined with native grasses  Prevent erosion  Remove sediment (TSS) and nutrients from runoff  3 connected sections  Connector from east drainage basin to the site  East Channel (about 1/2 of developed site drainage)  West Channel (all of developed site drainage) 9Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 10. Stream Dimensions  Connector from east drainage basin  Depth: 3 ft  Bottom Width: 2 ft  Top Width: 10 ft  East Channel  Depth: 4 ft  Bottom Width: 1 ft  Top Width: 33 ft  West Channel  Depth: 4 ft  Bottom Width: 6 ft  Top Width: 38 ft 10Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 11. Stream Layout 11Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 12. Steam Cross Section 12Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 13. Detention Basin Design  Design storm: 100-year, 12 hr duration rain event  Required Storage Volume: 16.64 acre-ft  Design Characteristics  Overflow weir: 45 ft wide x 1 ft high  4 outflow pipes  2 – 12” diameter pipes at invert elevation of 670.1 ft  2 – 15” diameter pipes at invert elevation of 672.2 ft  Depth of 8 feet and bottom elevation of 667.4 ft  Top elevation of 675.4 ft 13Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 14. Baseball Field Drainage  Hydraway 2000 drainage system  Geotextile drainage mat  12” wide x 1” thick  Strong, able to withstand heavy loading  Placed every 20 feet  Drain to a central drainage pipe  Installation  After field is graded appropriately  Smaller trencher creates a 6” wide x 12” deep  Backfill with granular fill to promote drainage 14Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 15. Baseball Field Drainage Layout • Blue Lines = Hydraway 2000 Mats • Pink Line = Central Drainage Collector Source: Hydraway website 15Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 16. Pavement Systems Surface Asphalt Binder Asphalt Type #53 Sub-base 1 ½ inch 4 ½ inch 8 inch Surface Asphalt Binder Asphalt Type #53 Sub-base 1 ½ inch 3 inch 8 inch Concrete Type #53 Sub-base 6 inch 8 inch Pervious Concrete Sand Type #53 Sub-base 9 inch 2 inch 9 inch Introduction Facility Drainag Structura ConstructioLEEDAcces 16
  • 17. Pedestrian Access 17 Upper Pedestrian Corridor Lower Pedestrian Corridor Central Pathway Eastern Pathway Western Pathway Bike Path Extension
  • 18. Site Access: Existing Traffic Volumes LOS ANALYSIS  McCormick & Cherry (AWSC)  A.M. Peak Hour:  LOS E  41 sec Delay  McCormick & Tennis Center (TWSC)  A.M. Peak Hour:  LOS B  15 sec Delay  P.M. Peak Hour: • LOS F • 330 sec Delay – P.M. Peak Hour: • LOS C • 18 sec Delay Introduction Facility Drainag Structura ConstructioLEEDAcces 18
  • 19. Site Access: 2010 Background Volumes LOS ANALYSIS  McCormick & Cherry (AWSC)  A.M. Peak Hour: • LOS F • 95 sec Delay  McCormick & Tennis Center (TWSC)  A.M. Peak Hour: • LOS C • 16 sec Delay  P.M. Peak Hour: • LOS F • 492 sec Delay  P.M. Peak Hour: • LOS C • 20 sec Delay Introduction Facility Drainag Structura ConstructioLEEDAcces 19
  • 20. Site Access: 2010 Total Volumes LOS ANALYSIS  McCormick & Cherry (RDBT)  A.M. Peak Hour: • LOS C • 18 sec Delay  McCormick & Tennis Center (TWSC)  A.M. Peak Hour: • LOS C • 17 sec Delay  McCormick & Perimeter Pkwy (TWSC)  A.M. Peak Hour: • LOS A • 0 sec Delay  P.M. Peak Hour: • LOS C • 19 sec Delay  P.M. Peak Hour: • LOS C • 21 sec Delay  P.M. Peak Hour: • LOS A • 0 sec Delay Introduction Facility Drainag Structura ConstructioLEEDAcces 20
  • 21. Traffic Maintenance Plan  Construction Access  Baseball Stadium: Proposed AlignmentPerimeter Parkway  Soccer Stadium: Existing gravel access north of Tennis parking Lot  McCormick Road Improvements  Long-Term Stationary Work Zone  Work Zone Type  Intermittent Closure (off-peak hours only)  Use of shoulder  Construction Phasing  Reconstruction by Halves (sides)  Work Zone Speed limit: 40 mph  As prescribed by INDOT Design Manual, Part VII - Work Zone Traffic Control Introduction Facility Drainag Structura ConstructioLEEDAcces 21
  • 22.  Live Load  60.0 psf for stadium seating  50.0 psf for rooms  20.0 psf roof live load  0.54 psf live load reduction factor  Seismic Load  60 kip base shear  Lateral Loads  First Story = 17.4 kip  Second Story = 21.0 kip  Third Story = 21.6 kip  Dead Load  63.0 psf roof load  74.0 psf for other floors  Wind Load  10.7 psf lateral load  13.4 psf uplift  Environmental Load  22.0 psf snow load  11.9 psf ice load Structural Design: Loads 22Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 23.  SAP2000 Analysis  Placing columns & beams  Model of main stadium structure  Application of loads  Computer analysis  Approximate Analysis  Axial forces in columns of the critical section  Portal method for lateral load Structural Design: Stadium Frame Analysis 23Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 24. Structural Design:Sizing Stadium Component First Floor Column Sizes First Floor Beam Sizes 24Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 25. Structural Design:Sizing Stadium Components  4” concrete decking  18K5 joists spaced at 5’ for third story  12K3 joists spaced at 5’ for lower stories Additional Structural Components : 25Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 26. Structural Design: Concrete Stadium Seating  Seating Structure:  Reinforced Concrete  Beams, Girders, Columns  Masonry on Backstop 26Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 27. Structural Design: Concrete Stadium Seating  Design: Isolate Beams, Girders, and Columns  Assume no moment Transfer  Reduction to a determinate structure  Load Path for Structure Beams  24 ft span  Simply supported  2.5 ft wide  PCI Design Handbook Load Path 27Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 28.  29.5 ft span  Simply supported  Apply distributed beam loads  Neglect compression  Flexure controls  PCI Design Handbook Structural Design: Concrete Stadium Seating  Design: Isolate beams, Girders, and Columns  Assume no moment Transfer  Reduction to a determinate structure Girders 28Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 29.  No moments – No interaction diagrams  Tributary area of girders for total loads  Detail the section – Check strength  PCI Design Handbook  Design: Isolate beams, Girders, and Columns  Assume no moment Transfer  Reduction to a determinate structure Columns 29Introduction Facility Drainag Structura ConstructioLEEDAcces Structural Design: Concrete Stadium Seating
  • 30.  Complicated Moment Resistant Frame  Truss  remove indeterminacy  Consider tributary area  Apply joint loads  Joint analysis  member forces  Check Stresses Reality Model 30Introduction Facility Drainag Structura ConstructioLEEDAcces Structural Design: Awning Support Structure Support Section
  • 31. Foundation Design  Soil Capacity  Gross soil bearing capacity of 6,400 psf  2,000 psf net allowable bearing pressure used in design  Shallow Foundations  Combined Footings  3 columns per footing  Eleven 5-ft x 35-ft reinforced concrete footings  Design Considerations  Soil bearing capacity  Immediate settlement  Consolidation settlement 31Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 32. L.E.E.D.  LEED Certification and Benefits  CE 498 Ratings 32 LEED Rating Points Certified 14-17 Silver 18-20 Gold 21-27 Platinum 28-37 Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 33. L.E.E.D  LEED Reviews  Reviewer 1: 12 points - not certified  Reviewer 2: 17 points - LEED Certified  LEED re-submittals  Requesting Silver certification  Submitted documents (22 points)  Sustainable Site Credits: 10  Water Efficiency Credits: 4  Materials and Resources Credits: 6  Innovation & Design Process Credits: 2  Gold Certification Potential 33Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 34. Project Controls  Project Organization/communication  Design-Build firm advantages  Site Management  Lines of communication 34Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 35. Quality, Materials and Safety  Quality  ZEAL’s Quality Control and Quality Assurance Manual  Monitoring of all products, materials, and work  Inspections  Material  Building : Steel framing, reinforced concrete, masonry  Parking lot: Pervious concrete  Access road: Asphalt pavement  Safety  ZEAL’s Safety Manager  Subcontractor’s safety requirements 35Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 36. Cost Estimate  Price Proposal  Schedule of values  Request for payment due the 1st of every month and payment received by the 15th of the next month  5% retainage on all payments 36 PRICE PROPOSAL Basic Facility Proposal Price $6,458,182 Optional Facilities Proposal Price $3,160,805 Parking and Transportation Facility Proposal price $3,545,865 Total Project Price Proposal $13,164,853 Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 37. Cost Estimate  Basic Facility 37 CSI division Total Cost Direct cost Division 3 - Concrete $433,181 Division 4 - Masonry $180,063 Division 5 -Metals $483,996 Division 7 -Thermal & Moisture protection $62,603 Division 8 - Openings $28,930 Division 9 - Finishes $308,803 Division 10 - Specialties $41,392 Division 11 - Equipments $133,642 Division 31 - Earthwork $213,827 Division 32 - Exterior Improvement $828,657 Division 33 - Utilities $1,993,004 Total Direct Cost $4,708,098 Indirect Cost Fees $1,155,338 Insurance $245,002 Allowance $1,131,676 Total indirect Cost $2,532,016 Total Facility cost (89.2% reduction factor) $6,458,182 Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 38. Cost Estimate  Parking and Transportation Facility 38 CSI division Total Cost Direct cost Division 31 - Earthwork $144,271.58 Division 32 - Exterior Improvement $2,320,927.91 Division 33 - Utilities $275,384.21 Total Direct Cost $2,740,583.70 Indirect Cost Fees $426,129 Insurance $143,881 Allowance $664,592 Total indirect Cost $1,234,602 Total Facility cost (89.2% reduction factor) $3,545,865 Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 39. Cost Estimate  Optional Facility 39 Direct cost Total Cost Soccer $664,047 Seat expansion $105,000 Other Roadways and parking facility $1,666,245 Total Direct cost $2,435,292 Indirect Cost Fees $389,800 Insurance $127,853 Allowance $590,558 Total indirect Cost $1,108,211 Total Facility cost (89.2% reduction factor) $3,160,805 Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 40. Project Schedule  Project duration: 462 days; ~ 20 months  Design schedule  Conceptual Design: Jan 13,09 –May 5, 09  Final Design: May 1, 09 – Aug 12, 09  Construction schedule  Site preparation and mobilization: Aug 3, 09  Construction starts: Aug 17, 09  Scheduled completion date: Oct 20, 2010  Latest construction completion date : Nov 30, 2010 40Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 41. Construction Scheduling 41Introduction Facility Drainag Structura ConstructioLEEDAcces
  • 42. Summary 42  Purdue’s need  Baseball Facility  Soccer Facility  Drainage  Site Access  Structural Aspects  LEED Credentials  Construction and Cost
  • 44. References  Ashley, Erin. "Using Pervious Concrete to achieve LEED credits." 2008. Pervious Concrete Pavement. 02 February 2009 <http://www.perviouspavement.org/benefits_LEEDcredit.htm>.  B4UBUILD. A Sample Residential Construction Schedule. 1998 - 2008. 19 February 2009 <http://www.b4ubuild.com/resources/schedule/6kproj.shtml>.  CE 498 - CE Design Project. January 2009. 02 February 2009 <https://engineering.purdue.edu/Courses/CE498>.  Corporation, The Schneider. "Storm Water Analysis." 2007.  Google. Google Earth. West Lafayette, February 2009.  Hydraway Drainage Systems. “Hydraway 2000.” 2007. <http://www.hydraway.net/hydraway_2000.php>  HNTB. Purdue University - Athletic Facilities Master Plan. Conceptual master plan. Indianapolis: HNTB, 2007.  J&M Equipment Specialist & Salvage Recovery. 2008. 2 February 2009 <jmequipmentspecialist.com/id7.html>.  Michigan, University of. Michigan Go Blue. February 2009. February 2009 <http://www.mgoblue.com/facilities/article.aspx?id=28646#>. 44
  • 45. References cont’d  Microsoft. Live Search Maps. February 2009. February 2009 <http://maps.live.com/>.  Office of the University Architect. "Consultant's Handbook." 2006. Office of University Architect. 20 January 2009 <http://www.purdue.edu/architect/resources/handbook/index.html>.  Qualite. Design Soccer. 2008. 12 February 2009 <http://www.qualite.com/DesignSoccer.html>.  RS Means. Building Construction Cost Data. Kingston, MA: R.S. Means Company, 2009.  The Schneider Corporation. "Report of Geotechnical Engineering Study." 2008.  The Schneider Corporation. "Storm Water Analysis." 2007.  U.S. Fish and Wildlife Service. "Viewing Wetland with Google Earth (Plug-in for Google Earth)." July 2008.  U.S. Green Building Council. New Construction Version 2.2 Reference Guide. Washington, DC: U.S. Green Building Council, 2006.  US Green Building Council. 2009. 20 January 2009 <http://www.usgbc.org/>. 45

Notes de l'éditeur

  1. http://www.usgbc.org/DisplayPage.aspx?CMSPageID=1720
  2. http://www.concretedecor.net/images/Feature_Photos/CD506/Technology/cd506chusid02.jpg