SlideShare une entreprise Scribd logo
1  sur  49
Télécharger pour lire hors ligne
IRR Program, Inventory
 and Funding Formula
       Update
     TRIBAL TRANSPORTATION AT A
  CROSSROAD: TRIBAL LEADERS FORUM
   ON THE CURRENT STATE OF TRIBAL
            TRANSPORTATION
   National Congress of American Indians
              Palm Springs, CA
                  10/11/09


                                           1
Presenters
• Mr. LeRoy Gishi
  Chief – BIA Division of Transportation
  Washington, DC
  202-513-7711
  leroy.gishi@bia.gov

• Mr. Robert Sparrow
  FHWA - IRR Program Manager
  Washington, DC
  202-366-9483
  robert.sparrow@dot.gov
IRR Program Update
Reauthorization
• Both SAFETEA-LU and the DOT Appropriations
  expired September 30
  – Currently operating under 31 day Extension and
    Continuing Resolution (CR)

• What does this mean?
  – Continues FY09 funding levels
  – 8.5% of funds being made available
  – Additional extensions and continuing resolutions
    could result in negative impacts to the FY10
    program delivery.

• Administration is developing a Reauthorization
  proposal.
How are Federal Highway
     Programs funded?
     Authority                Limitation
Highway Authorizations   DOT Appropriations Bills
    Multiple Year             Single Year
     Extensions          Continuing Resolutions




  31 day Extension             31 day CR
     $35 million               $35 million
IRR Program Funding
• In FY09
  – $45 million in August Redistribution
    • Will be returned to those Tribes that submitted it
      back to BIA and FHWA
• SAFETEA-LU
  – $1.88 billion made available
  – Obligation of over 97%
IRR Bridge Program
• FY09
  – 13 BIA Bridges       $9.6 million
  – 11 non-BIA Bridges   $3.5 million
• Total since FY98
  – 134 BIA Bridges     $74.6 million
  – 142 non-BIA Bridges $77.7 million


• 100% of the funds were obligated
ARRA
• $310 million made available
  – 186 tribal ARRA IRRTIPS approved for more than
    $200 million (67%)
  – Full obligation by September 30, 2010 or they expire.
• These funds are not subject to the extension or
  CR.
• Funding being provided to Tribes via BIA, OSG,
  and FHWA.
• Reporting requirements and process is still very
  fluid.
• Risk Plan developed
Program Risks
• Fund Availability
   – Per formula, redistribution in 2010
   – Strict control, required documentation
• Fund Transparency
   – Collecting and reporting correct data
• Project/Activity Oversight
   – Training (all), Project Reviews & Site Visits
• Assuring Uniform Interpretation
   – By BIA and FHWA
• Fund Obligation
   – Contracting and monitoring
ARRA Redistribution
• DOT Secretary given authority in ARRA to
  redistribute any unobligated funds within
  the program after 1 year.
• Policy developed with input from IRRPCC.
  – Currently being reviewed by FHWA officials.
  – Will be published in Federal Register
• All tribes will be provided numerous
  written notices of the status of their ARRA
  funds.
ARRA Redistribution
• Expect a call for projects in December.
• Projects evaluated and ranked prior to
  Feb. 17, 2010.
• Initial awards in late February. Additional
  review and awards until mid-May 2010.
IRR National Inventory II
• Scope of work
  – To develop policy and standards for the inventory,
    and to address trust responsibilities, stewardship
    needs, and the processes used for the inventory.
     •   QA/QC of critical data fields
     •   Update of coding guide
     •   Benchmark to other inventories
     •   Cost tables
     •   Identification of input parameters for other modes. (no
         generation of funding).
• Full undertaking FY10-FY11
  – Recommendations implemented in FY10, 11, 12
    inventory calculations.
FHWA Leadership
• Administrator
  – Victor Mendez - AZ
• Deputy Administrator
  – Greg Nadeau - ME
• Executive Director
  – Jeff Paniatti
The IRR Inventory and the Funding
            Formula
• The most notable issue in the Indian
  Reservation Roads (IRR) Program over
  the past year has been the funding
  formula, how it is being implemented, and
  the resulting funding trend.
• This is an issue that impacts all tribes.




                                              15
IRR Program (Pre-2005)
• The IRR Program was a BIA Regional priority
  program
   – the only routes that generated funding were the BIA
     routes included in their respective Inventories.
   – ExceptionS for Oklahoma and Alaska
• Other routes (tribal, state, county, township, etc.)
  were included in the inventory but did not
  generate any funding.
• BIA Regions with numerous reservations and
  Indian lands had a majority of BIA Routes and
  therefore received a majority of the funding.
                                                           16
IRR Program Today
• In FY2005, new regulations (25 CFR 170) were
  implemented as a result of Negotiated
  Rulemaking.
  – The IRR Program became a Tribal Share Program
  – The basic formula concept remained the same.
     • 50% Cost to construct (CTC).
     • 30% Vehicle Miles Traveled (VMT).
     • 20% Population.
  – All eligible public routes, regardless of ownership,
    generated funding.
  – All Tribes now able to participate in the program.
                                                           17
Implementation of Formula
• Since FY2005, when the IRR Program
  regulations were finalized, portions of the
  regulations (formula) have not been fully
  implemented because the inventory data could
  not make a distinction as to which roads should
  generate at 100 %, and which should be
  factored at a lower percentage as intended in
  the regulations. This portion of the regulation is
  25 CFR 170, Appendix C to Subpart C, Q10.


                                                       18
Implementation of Formula (cont.)
•   10. Do All IRR Transportation Facilities in the IRR Inventory Count at
    100 Percent of Their CTC and VMT?

•   No. The CTC and VMT must be computed at the non-Federal share
    requirement for matching funds for any transportation facility that is added
    to the IRR inventory and is eligible for funding for construction or
    reconstruction with Federal funds, other than Federal Lands Highway
    Program funds. However, if a facility falls into one or more of the following
    categories, then the CTC and VMT factors must be computed at 100
    percent:
     – (1) The transportation facility was approved, included, and funded at 100 percent
       of CTC and VMT in the IRR Inventory for funding purposes prior to the issuance
       of these regulations.
     – (2) The facility is not eligible for funding for construction or reconstruction with
       Federal funds, other than Federal Lands Highway Program funds; or
     – (3) The facility is eligible for funding for construction or reconstruction with
       Federal funds, however, the public authority responsible for maintenance of the
       facility provides certification of maintenance responsibility and its inability to
       provide funding for the project.



                                                                                         19
Implementation of Formula (cont.)
• Summary
 – Not all roads may generate 100% of CTC and
   VMT, the exceptions are described in three
   parts in Question 10:
   1. Roads which are „grandfathered‟
      – These are roads that generated funding prior to the
        regulations being finalized – Pre 2005.
   2. Roads which are “not eligible” for Federal funds,
     other than Federal Lands Highways Program
     funds.
   3. Roads in which the owner certifies of its inability
     to provide funding for the project and that it has a
     maintenance responsibility for the facility.

                                                              20
Observing A Trend
• Results:
  – Inventory growth since FY2005 has been
    primarily in routes other than BIA or Tribal.
  – Because the existing database did not
    distinguish which roads met the specific
    exception under (2) of Q.10, all road
    ownerships and classes, with the exception of
    State roads, were computed at 100%.
  – Impacts are trending to favor roads owned by
    others and away from the BIA and tribal
    routes.                                       21
Observing A Trend
                                     Public Authority Responsible for Maintaining/Improving Roads
Fiscal                                                       County                               Other Non-          TOTAL IRR
Year BIA            Tribal         State        Urban        Township Other BIA Other Fed Fed                No Owner Miles



FY2008   30,367.0       14,984.0       17,680.0     1,882.0    48,978.0      144.0      4,300.0     1,756.0      0.0 120,092.0

FY2007   29,750.7        9,734.2       13,666.4     1,465.3    43,180.2      144.5      2,294.0     1,631.8    330.4 102,197.5

FY2006   28,706.2        4,276.7       13,198.7      897.8     34,295.8      138.8      2,302.8     1,445.5    127.5   85,481.5

FY2005   27,384.9        2,851.2        9,048.7      544.7     22,323.7      134.1       370.8       121.6      90.2   62,869.9




                                                                                                                       22
IRR Mileage
80000
70000
60000
50000                               BIA & Tribal
40000                               County & State
30000                               Other

20000
10000
   0
        2005   2006   2007   2008
% IRR Fund Distribution
            (CTC and VMT only)
70

60

50

40                                      BIA & Tribal
                                        County & State
30                                      Other
20

10

0
     2005   2006   2007   2008   2009
Recognizing a Problem and
         Seeking a Solution

• 25 CFR 170 established the IRR Program
  Coordinating Committee (IRRPCC).
  – Provides input and recommendations to the
    Secretaries of DOI and DOT regarding
    regulatory policy and implementation issues
    that are brought to its attention.



                                                  25
Role of IRRPCC
• The IRRPCC has reviewed and discussed this
  issue over the past years and has not able to
  come up with a recommendation
  – The Committee reviewed all of the eligible roads and
    their corresponding classification
  – Numerous data runs were requested and analyzed.
  – A matrix was developed to show where some
    agreement might be possible (see next slide)
  – But because of diverse interests, no consensus could
    be reached.


                                                       26
27
Summary
• Recognizing a Problem
  – Because of the significant increase in mileage
    being added to the inventory and the fact that
    Q10 cannot be implemented as written:
    • The majority of the IRR funding is now generated by
      non-BIA/tribal roads. Most of these roads did not
      generate funding prior to 2005.
    • BIA and tribal roads are not generating enough
      funding in the formula to adequately keep pace with
      the deteriorating infrastructure.
    • The responsible public authority of non-BIA/tribal
      roads has other sources of funding made available to
      it for road infrastructure. BIA and tribal roads do not.


                                                            28
Summary
• Seeking a solution.
  – A preliminary Federal recommendation has
    been developed that closely coincides to the
    IRRPCC views.
  – This has been presented at several regional
    and national tribal meetings in the near future.
  – BIA and FHWA will continue to work with
    Tribes and the IRRPCC to develop a final
    resolution to this issue.



                                                   29
Data Runs
       (Using FY 07‟ Inventory Data)
• Run 1 – Baseline
  – Current implementation
    • (similar to FY 05‟, 06‟, 07‟)
  – All ownership except Ownership 3 (State)
    calculated at 100% CTC and VMT
  – Ownership 3 calculated at Non-Federal Share




                                              30
Data Runs
       (Using FY 07‟ Inventory Data)
• Run 2
  – Ownership 1 & 2        100% CTC and VMT
  – Ownership 5, Class 4&5 100% CTC and VMT
  – All Other               Non-Federal Share

• Run 3
  – Ownership 1 & 2        100% CTC and VMT
  – Ownership 3-9, Class 4&5100% CTC and
    VMT
  – All Others              Non-Federal Share

                                            31
Requested Data Cont‟d
• Run 4
  – Ownership 1 & 2   100% CTC and VMT
  – Ownership 4 & 5   Non-Federal Share
  – All Others        0% CTC and VMT


• Run 5 (Preliminary Federal
 Recommendation)


                                          32
Comparison of DATA RUNS

REGION                BASELINE                    RUN 1                       RUN 3                     RUN 4                       RUN 5
                 Share (%) Amount ($)    Share (%) Amount ($)     Share (%)    Amount ($)     Share (%)   Amount ($)    Share (%)     Amount ($)
A - GR. PLAINS    6.50%     19,194,818    7.62%      22,521,838     7.22%        21,335,200     6.87%      20,293,677     7.51%        22,175,231

B - SO. PLAINS    2.78%      8,216,738    3.34%       9,856,266     3.25%         9,593,942     2.32%       6,851,329     3.26%         9,617,834

C - ROCKY MTN     7.44%     21,988,927    8.44%      24,930,599     8.43%        24,890,233     7.98%      23,577,517     8.50%        25,101,548

E - ALASKA        12.21%    36,070,741 10.48%        30,963,959    11.18%        33,033,325    14.01%      41,379,198    11.01%        32,512,012

F - MIDWEST       13.38%    39,517,651 12.79%        37,777,619    13.28%        39,245,932    11.13%      32,891,678    12.20%        36,045,541

G - EASTERN OK    12.97%    38,317,409 15.08%        44,563,392    15.28%        45,143,901     7.93%      23,419,236    13.65%        40,314,074

H - WESTERN       6.27%     18,520,881    7.26%      21,442,171     6.95%        20,517,687     9.30%      27,477,141     7.57%        22,355,598

J - PACIFIC       2.34%      6,908,118    1.86%       5,499,835     1.94%         5,730,855     1.73%       5,121,581     1.89%         5,585,951

M - SOUTHWEST     4.41%     13,020,857    5.09%      15,047,024     4.80%        14,192,373     6.59%      19,457,253     5.32%        15,724,623

N - NAVAJO        23.50%    69,410,946 20.51%        60,599,412    19.26%        56,901,894    23.54%      69,547,773    21.38%        63,159,334

P - NORTHWEST     6.38%     18,840,531    5.34%      15,768,681     6.29%        18,594,459     5.97%      17,630,938     5.49%        16,212,378

S - EASTERN       1.83%      5,416,744    2.18%       6,453,565     2.11%         6,244,559     2.63%       7,777,040     2.24%         6,620,238

Max for Region

Min for Region




                                                                                                                                                   33
Preliminary Federal
            Recommendation
• The percentage of CTC and VMT used in
  the RNDF calculation is as follows:
  – (a) For facilities identified in the IRR Inventory
    as Ownership 1 and 2, – 100 percent;
  – (b) For facilities identified in the IRR Inventory
    as Ownership 5, Class 4 & 5 – The
    percentage used will be that shown under the
    80% Federal, 20% State column in the
    “Sliding Scale Rates of Federal-aid
    Participation in Public Lands States for
    Projects not on the Interstate System”,
    pursuant to 23 U.S.C. 120(b)(2); and
                                                     34
Preliminary Federal
           Recommendation
• Con‟t
  – (c) For facilities not included in (a) or (b)
    above - The percentage used will be the
    difference between 100 and that shown under
    the 80% Federal, 20% State column in the
    “Sliding Scale Rates of Federal-aid
    Participation in Public Lands States for
    Projects not on the Interstate System”,
    pursuant to 23 U.S.C. 120(b)(2), except for
    Class 1 roads which shall have a percentage
    of zero.


                                                35
36
Preliminary Federal
               Recommendation
• In brief:
  – (a) Roads owned by BIA and Tribal
    Governments for all Classifications should be
    factored into the formula at 100%.




                                                37
Preliminary Federal
          Recommendation
– (b) For facilities identified in the IRR Inventory
  as Ownership 5 (County/Local), Class 4 & 5 –
  The percentage used will be the Federal
  Share (+ 80% - 95%);

– (c) For facilities not included in (a) or (b)
  above - The percentage used will be the Non-
  Federal Share (+ 5 - 20%);



                                                   38
Preliminary Federal
           Recommendation
– (d) Class 1 roads for all road ownership other
  than BIA or Tribal which are the responsibility
  of other public authorities will not generate
  funding in the formula (0%).
   • They are still eligible IRR as required by law, but
     will not generate formula output




                                                           39
Preliminary Federal
             Recommendation
• Results
  – Roads owned by BIA and Tribes – 100%;
  – Roads owned by others and which make up the
    majority of roads in and around Indian Reservations,
    communities, and villages (Ownership 5, Class 4 & 5
    Roads) are factored into the formula at a high share;
  – All remaining roads, except Class 1 are factored into
    the formula at a lower share; and
  – Non-BIA, Non-Tribal Class 1 roads are not factored
    into the formula.


                                                        40
41
Federal Share
• The Federal Share referred to here is the
  maximum percentage of a project‟s cost
  for which Federal funds can be used.
  – It is a uniformly published % and has been
    consistent since 1992. It is generally about
    80% to 95% and is shown on the following
    table:




                                                   42
43
Non-Federal Share
• The Non-Federal Share referred to here is
  the minimum percentage of a project‟s
  cost for which state and local funds must
  contribute in order for Federal funds to be
  utilized on a project.




                                            44
45
Comparison of DATA RUNS

REGION                BASELINE                    RUN 1                       RUN 3                     RUN 4                       RUN 5
                 Share (%) Amount ($)    Share (%) Amount ($)     Share (%)    Amount ($)     Share (%)   Amount ($)    Share (%)     Amount ($)
A - GR. PLAINS    6.50%     19,194,818    7.62%      22,521,838     7.22%        21,335,200     6.87%      20,293,677     7.51%        22,175,231

B - SO. PLAINS    2.78%      8,216,738    3.34%       9,856,266     3.25%         9,593,942     2.32%       6,851,329     3.26%         9,617,834

C - ROCKY MTN     7.44%     21,988,927    8.44%      24,930,599     8.43%        24,890,233     7.98%      23,577,517     8.50%        25,101,548

E - ALASKA        12.21%    36,070,741 10.48%        30,963,959    11.18%        33,033,325    14.01%      41,379,198    11.01%        32,512,012

F - MIDWEST       13.38%    39,517,651 12.79%        37,777,619    13.28%        39,245,932    11.13%      32,891,678    12.20%        36,045,541

G - EASTERN OK    12.97%    38,317,409 15.08%        44,563,392    15.28%        45,143,901     7.93%      23,419,236    13.65%        40,314,074

H - WESTERN       6.27%     18,520,881    7.26%      21,442,171     6.95%        20,517,687     9.30%      27,477,141     7.57%        22,355,598

J - PACIFIC       2.34%      6,908,118    1.86%       5,499,835     1.94%         5,730,855     1.73%       5,121,581     1.89%         5,585,951

M - SOUTHWEST     4.41%     13,020,857    5.09%      15,047,024     4.80%        14,192,373     6.59%      19,457,253     5.32%        15,724,623

N - NAVAJO        23.50%    69,410,946 20.51%        60,599,412    19.26%        56,901,894    23.54%      69,547,773    21.38%        63,159,334

P - NORTHWEST     6.38%     18,840,531    5.34%      15,768,681     6.29%        18,594,459     5.97%      17,630,938     5.49%        16,212,378

S - EASTERN       1.83%      5,416,744    2.18%       6,453,565     2.11%         6,244,559     2.63%       7,777,040     2.24%         6,620,238

Max for Region

Min for Region




                                                                                                                                                   46
Future Issues
• The IRRPCC is also working to address
  the following:
  – How to determine lengths of eligible routes
    when a Tribe does not have a recognized
    Boundary?
  – Definition and measurement of an access
    route?
  – How Proposed Routes should be considered?



                                              47
Contacts
• Mr. LeRoy Gishi
  Chief – BIA Division of Transportation
  Washington, DC
  202-513-7711
  leroy.gishi@bia.gov

• Mr. Robert Sparrow
  FHWA - IRR Program Manager
  Washington, DC
  202-366-9483
  robert.sparrow@dot.gov
Comments


           49

Contenu connexe

Tendances (12)

Zephyr brochure_ang
Zephyr brochure_angZephyr brochure_ang
Zephyr brochure_ang
 
September 15, 2020 BPAC Virtual Meeting
September 15, 2020 BPAC Virtual MeetingSeptember 15, 2020 BPAC Virtual Meeting
September 15, 2020 BPAC Virtual Meeting
 
Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
06 hasan ikhrata
06 hasan ikhrata06 hasan ikhrata
06 hasan ikhrata
 
June 10, 2020 LCB Public Hearing & Meeting Slide Deck
June 10, 2020 LCB Public Hearing & Meeting Slide DeckJune 10, 2020 LCB Public Hearing & Meeting Slide Deck
June 10, 2020 LCB Public Hearing & Meeting Slide Deck
 
Where Will the $$ Come From?
Where Will the $$ Come From?Where Will the $$ Come From?
Where Will the $$ Come From?
 
Broadband and Economic Development (Terry McDermott, Brian Smith)
Broadband and Economic Development (Terry McDermott, Brian Smith)Broadband and Economic Development (Terry McDermott, Brian Smith)
Broadband and Economic Development (Terry McDermott, Brian Smith)
 
IZ Workshop 2014: A1 groton inclusionary zoning
IZ Workshop 2014: A1 groton inclusionary zoningIZ Workshop 2014: A1 groton inclusionary zoning
IZ Workshop 2014: A1 groton inclusionary zoning
 
County Executive Presentation of the FY 2013 Advertised Budget Plan
County Executive Presentation of the FY 2013 Advertised Budget PlanCounty Executive Presentation of the FY 2013 Advertised Budget Plan
County Executive Presentation of the FY 2013 Advertised Budget Plan
 
IHA Congress 2011 - Global Workshop - Jasper Oduor
IHA Congress 2011 - Global Workshop - Jasper OduorIHA Congress 2011 - Global Workshop - Jasper Oduor
IHA Congress 2011 - Global Workshop - Jasper Oduor
 
Roscoe mapd 6.7.12
Roscoe  mapd 6.7.12Roscoe  mapd 6.7.12
Roscoe mapd 6.7.12
 
Local self governance in 2012
Local self governance in 2012Local self governance in 2012
Local self governance in 2012
 

En vedette

Social Media Marketing
Social Media MarketingSocial Media Marketing
Social Media MarketingiBloomsrl
 
Hinduism
HinduismHinduism
Hinduismksisler
 
Brookings Institution four leaf messaging_ may 2009
Brookings Institution four leaf messaging_ may 2009Brookings Institution four leaf messaging_ may 2009
Brookings Institution four leaf messaging_ may 2009Suzanne Henry
 
Navigating Social Media Maze Four Leaf November 2009
Navigating Social Media Maze Four Leaf November 2009Navigating Social Media Maze Four Leaf November 2009
Navigating Social Media Maze Four Leaf November 2009Suzanne Henry
 
Miyamoto Musashi
Miyamoto Musashi Miyamoto Musashi
Miyamoto Musashi ksisler
 
Positioning And Messaging May 2009
Positioning And Messaging May 2009Positioning And Messaging May 2009
Positioning And Messaging May 2009Suzanne Henry
 
Leadership Charlottesville Storytelling Presentation
Leadership Charlottesville Storytelling PresentationLeadership Charlottesville Storytelling Presentation
Leadership Charlottesville Storytelling PresentationSuzanne Henry
 
Social Media for the Equipment Finance Company
Social Media for the Equipment Finance CompanySocial Media for the Equipment Finance Company
Social Media for the Equipment Finance CompanySuzanne Henry
 
My Personal Odyssey
My Personal OdysseyMy Personal Odyssey
My Personal Odysseyksisler
 
Arbitrary SelfPortaits
Arbitrary SelfPortaitsArbitrary SelfPortaits
Arbitrary SelfPortaitsSondra Johnson
 
Ambiently Powerpoint
Ambiently PowerpointAmbiently Powerpoint
Ambiently Powerpointkmnorris
 
Social Networking For Success
Social Networking For SuccessSocial Networking For Success
Social Networking For SuccessSuzanne Henry
 
Examen final de estadística descriptiva
Examen final de estadística descriptivaExamen final de estadística descriptiva
Examen final de estadística descriptivajoseasmar
 
Examen final de cálculo integral
Examen final de cálculo integralExamen final de cálculo integral
Examen final de cálculo integraljoseasmar
 
Teenage Depression
Teenage DepressionTeenage Depression
Teenage Depressionksisler
 

En vedette (18)

Introduction To The 2010 Census
Introduction To The 2010 CensusIntroduction To The 2010 Census
Introduction To The 2010 Census
 
E Portfolio
E PortfolioE Portfolio
E Portfolio
 
Social Media Marketing
Social Media MarketingSocial Media Marketing
Social Media Marketing
 
Hinduism
HinduismHinduism
Hinduism
 
Brookings Institution four leaf messaging_ may 2009
Brookings Institution four leaf messaging_ may 2009Brookings Institution four leaf messaging_ may 2009
Brookings Institution four leaf messaging_ may 2009
 
Navigating Social Media Maze Four Leaf November 2009
Navigating Social Media Maze Four Leaf November 2009Navigating Social Media Maze Four Leaf November 2009
Navigating Social Media Maze Four Leaf November 2009
 
Miyamoto Musashi
Miyamoto Musashi Miyamoto Musashi
Miyamoto Musashi
 
What's Your Story?
What's Your Story?What's Your Story?
What's Your Story?
 
Positioning And Messaging May 2009
Positioning And Messaging May 2009Positioning And Messaging May 2009
Positioning And Messaging May 2009
 
Leadership Charlottesville Storytelling Presentation
Leadership Charlottesville Storytelling PresentationLeadership Charlottesville Storytelling Presentation
Leadership Charlottesville Storytelling Presentation
 
Social Media for the Equipment Finance Company
Social Media for the Equipment Finance CompanySocial Media for the Equipment Finance Company
Social Media for the Equipment Finance Company
 
My Personal Odyssey
My Personal OdysseyMy Personal Odyssey
My Personal Odyssey
 
Arbitrary SelfPortaits
Arbitrary SelfPortaitsArbitrary SelfPortaits
Arbitrary SelfPortaits
 
Ambiently Powerpoint
Ambiently PowerpointAmbiently Powerpoint
Ambiently Powerpoint
 
Social Networking For Success
Social Networking For SuccessSocial Networking For Success
Social Networking For Success
 
Examen final de estadística descriptiva
Examen final de estadística descriptivaExamen final de estadística descriptiva
Examen final de estadística descriptiva
 
Examen final de cálculo integral
Examen final de cálculo integralExamen final de cálculo integral
Examen final de cálculo integral
 
Teenage Depression
Teenage DepressionTeenage Depression
Teenage Depression
 

Similaire à BIADOT Transportation Presentation Oct11 09

Visualize 2045: Highlights from the Draft Plan
Visualize 2045: Highlights from the Draft PlanVisualize 2045: Highlights from the Draft Plan
Visualize 2045: Highlights from the Draft PlanFairfax County
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumFairfax County
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Fairfax County
 
December 2012 regional_transportation_summit
December 2012 regional_transportation_summitDecember 2012 regional_transportation_summit
December 2012 regional_transportation_summitgeorgeleventhal
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Fairfax County
 
Accessing BUILD Grants to Improve Infrastructure
Accessing BUILD Grants to Improve InfrastructureAccessing BUILD Grants to Improve Infrastructure
Accessing BUILD Grants to Improve InfrastructureParsons Behle & Latimer
 
MAP-21: What's in it for my business? presented by Jack Schenendorf
MAP-21: What's in it for my business? presented by Jack SchenendorfMAP-21: What's in it for my business? presented by Jack Schenendorf
MAP-21: What's in it for my business? presented by Jack Schenendorfnssga
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Fairfax County
 
Fixing America's Surface Transportation (FAST) Act
Fixing America's Surface Transportation (FAST) ActFixing America's Surface Transportation (FAST) Act
Fixing America's Surface Transportation (FAST) ActJill Reeves
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Fairfax County
 
Final 12 01 community mtg phase ii presentation
Final 12 01 community mtg  phase ii presentationFinal 12 01 community mtg  phase ii presentation
Final 12 01 community mtg phase ii presentationSCVTA
 
Georgia's Transportation Investment Act of 2010
Georgia's Transportation Investment Act of 2010Georgia's Transportation Investment Act of 2010
Georgia's Transportation Investment Act of 2010RPO America
 
Councilfor Resource Development43rd Annual Conference111209
Councilfor Resource Development43rd Annual Conference111209Councilfor Resource Development43rd Annual Conference111209
Councilfor Resource Development43rd Annual Conference111209Cheryl Dettrick
 
PLAN 2040 RTP Update Overview
PLAN 2040 RTP Update OverviewPLAN 2040 RTP Update Overview
PLAN 2040 RTP Update OverviewMelissaARC
 
Special Local Road Fund
Special Local Road FundSpecial Local Road Fund
Special Local Road FundAlvin Almo
 

Similaire à BIADOT Transportation Presentation Oct11 09 (20)

Visualize 2045: Highlights from the Draft Plan
Visualize 2045: Highlights from the Draft PlanVisualize 2045: Highlights from the Draft Plan
Visualize 2045: Highlights from the Draft Plan
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 
UDOT Presentation to 2019 Legislature
UDOT Presentation to 2019 LegislatureUDOT Presentation to 2019 Legislature
UDOT Presentation to 2019 Legislature
 
Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
December 2012 regional_transportation_summit
December 2012 regional_transportation_summitDecember 2012 regional_transportation_summit
December 2012 regional_transportation_summit
 
Funding Opportunities for Premium Transit Corridors Presenation
Funding Opportunities for Premium Transit Corridors PresenationFunding Opportunities for Premium Transit Corridors Presenation
Funding Opportunities for Premium Transit Corridors Presenation
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)
 
Accessing BUILD Grants to Improve Infrastructure
Accessing BUILD Grants to Improve InfrastructureAccessing BUILD Grants to Improve Infrastructure
Accessing BUILD Grants to Improve Infrastructure
 
Georgia Transportation Infrastructure Bank
Georgia Transportation Infrastructure BankGeorgia Transportation Infrastructure Bank
Georgia Transportation Infrastructure Bank
 
MAP-21: What's in it for my business? presented by Jack Schenendorf
MAP-21: What's in it for my business? presented by Jack SchenendorfMAP-21: What's in it for my business? presented by Jack Schenendorf
MAP-21: What's in it for my business? presented by Jack Schenendorf
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
 
Fixing America's Surface Transportation (FAST) Act
Fixing America's Surface Transportation (FAST) ActFixing America's Surface Transportation (FAST) Act
Fixing America's Surface Transportation (FAST) Act
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
 
Final 12 01 community mtg phase ii presentation
Final 12 01 community mtg  phase ii presentationFinal 12 01 community mtg  phase ii presentation
Final 12 01 community mtg phase ii presentation
 
Georgia's Transportation Investment Act of 2010
Georgia's Transportation Investment Act of 2010Georgia's Transportation Investment Act of 2010
Georgia's Transportation Investment Act of 2010
 
Councilfor Resource Development43rd Annual Conference111209
Councilfor Resource Development43rd Annual Conference111209Councilfor Resource Development43rd Annual Conference111209
Councilfor Resource Development43rd Annual Conference111209
 
Financing Smart Cities
Financing Smart CitiesFinancing Smart Cities
Financing Smart Cities
 
PLAN 2040 RTP Update Overview
PLAN 2040 RTP Update OverviewPLAN 2040 RTP Update Overview
PLAN 2040 RTP Update Overview
 
Special Local Road Fund
Special Local Road FundSpecial Local Road Fund
Special Local Road Fund
 

Dernier

ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Q4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxQ4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxnelietumpap1
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 

Dernier (20)

LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Q4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxQ4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptx
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 

BIADOT Transportation Presentation Oct11 09

  • 1. IRR Program, Inventory and Funding Formula Update TRIBAL TRANSPORTATION AT A CROSSROAD: TRIBAL LEADERS FORUM ON THE CURRENT STATE OF TRIBAL TRANSPORTATION National Congress of American Indians Palm Springs, CA 10/11/09 1
  • 2. Presenters • Mr. LeRoy Gishi Chief – BIA Division of Transportation Washington, DC 202-513-7711 leroy.gishi@bia.gov • Mr. Robert Sparrow FHWA - IRR Program Manager Washington, DC 202-366-9483 robert.sparrow@dot.gov
  • 4. Reauthorization • Both SAFETEA-LU and the DOT Appropriations expired September 30 – Currently operating under 31 day Extension and Continuing Resolution (CR) • What does this mean? – Continues FY09 funding levels – 8.5% of funds being made available – Additional extensions and continuing resolutions could result in negative impacts to the FY10 program delivery. • Administration is developing a Reauthorization proposal.
  • 5. How are Federal Highway Programs funded? Authority Limitation Highway Authorizations DOT Appropriations Bills Multiple Year Single Year Extensions Continuing Resolutions 31 day Extension 31 day CR $35 million $35 million
  • 6. IRR Program Funding • In FY09 – $45 million in August Redistribution • Will be returned to those Tribes that submitted it back to BIA and FHWA • SAFETEA-LU – $1.88 billion made available – Obligation of over 97%
  • 7. IRR Bridge Program • FY09 – 13 BIA Bridges $9.6 million – 11 non-BIA Bridges $3.5 million • Total since FY98 – 134 BIA Bridges $74.6 million – 142 non-BIA Bridges $77.7 million • 100% of the funds were obligated
  • 8. ARRA • $310 million made available – 186 tribal ARRA IRRTIPS approved for more than $200 million (67%) – Full obligation by September 30, 2010 or they expire. • These funds are not subject to the extension or CR. • Funding being provided to Tribes via BIA, OSG, and FHWA. • Reporting requirements and process is still very fluid. • Risk Plan developed
  • 9. Program Risks • Fund Availability – Per formula, redistribution in 2010 – Strict control, required documentation • Fund Transparency – Collecting and reporting correct data • Project/Activity Oversight – Training (all), Project Reviews & Site Visits • Assuring Uniform Interpretation – By BIA and FHWA • Fund Obligation – Contracting and monitoring
  • 10. ARRA Redistribution • DOT Secretary given authority in ARRA to redistribute any unobligated funds within the program after 1 year. • Policy developed with input from IRRPCC. – Currently being reviewed by FHWA officials. – Will be published in Federal Register • All tribes will be provided numerous written notices of the status of their ARRA funds.
  • 11. ARRA Redistribution • Expect a call for projects in December. • Projects evaluated and ranked prior to Feb. 17, 2010. • Initial awards in late February. Additional review and awards until mid-May 2010.
  • 12. IRR National Inventory II • Scope of work – To develop policy and standards for the inventory, and to address trust responsibilities, stewardship needs, and the processes used for the inventory. • QA/QC of critical data fields • Update of coding guide • Benchmark to other inventories • Cost tables • Identification of input parameters for other modes. (no generation of funding). • Full undertaking FY10-FY11 – Recommendations implemented in FY10, 11, 12 inventory calculations.
  • 13. FHWA Leadership • Administrator – Victor Mendez - AZ • Deputy Administrator – Greg Nadeau - ME • Executive Director – Jeff Paniatti
  • 14.
  • 15. The IRR Inventory and the Funding Formula • The most notable issue in the Indian Reservation Roads (IRR) Program over the past year has been the funding formula, how it is being implemented, and the resulting funding trend. • This is an issue that impacts all tribes. 15
  • 16. IRR Program (Pre-2005) • The IRR Program was a BIA Regional priority program – the only routes that generated funding were the BIA routes included in their respective Inventories. – ExceptionS for Oklahoma and Alaska • Other routes (tribal, state, county, township, etc.) were included in the inventory but did not generate any funding. • BIA Regions with numerous reservations and Indian lands had a majority of BIA Routes and therefore received a majority of the funding. 16
  • 17. IRR Program Today • In FY2005, new regulations (25 CFR 170) were implemented as a result of Negotiated Rulemaking. – The IRR Program became a Tribal Share Program – The basic formula concept remained the same. • 50% Cost to construct (CTC). • 30% Vehicle Miles Traveled (VMT). • 20% Population. – All eligible public routes, regardless of ownership, generated funding. – All Tribes now able to participate in the program. 17
  • 18. Implementation of Formula • Since FY2005, when the IRR Program regulations were finalized, portions of the regulations (formula) have not been fully implemented because the inventory data could not make a distinction as to which roads should generate at 100 %, and which should be factored at a lower percentage as intended in the regulations. This portion of the regulation is 25 CFR 170, Appendix C to Subpart C, Q10. 18
  • 19. Implementation of Formula (cont.) • 10. Do All IRR Transportation Facilities in the IRR Inventory Count at 100 Percent of Their CTC and VMT? • No. The CTC and VMT must be computed at the non-Federal share requirement for matching funds for any transportation facility that is added to the IRR inventory and is eligible for funding for construction or reconstruction with Federal funds, other than Federal Lands Highway Program funds. However, if a facility falls into one or more of the following categories, then the CTC and VMT factors must be computed at 100 percent: – (1) The transportation facility was approved, included, and funded at 100 percent of CTC and VMT in the IRR Inventory for funding purposes prior to the issuance of these regulations. – (2) The facility is not eligible for funding for construction or reconstruction with Federal funds, other than Federal Lands Highway Program funds; or – (3) The facility is eligible for funding for construction or reconstruction with Federal funds, however, the public authority responsible for maintenance of the facility provides certification of maintenance responsibility and its inability to provide funding for the project. 19
  • 20. Implementation of Formula (cont.) • Summary – Not all roads may generate 100% of CTC and VMT, the exceptions are described in three parts in Question 10: 1. Roads which are „grandfathered‟ – These are roads that generated funding prior to the regulations being finalized – Pre 2005. 2. Roads which are “not eligible” for Federal funds, other than Federal Lands Highways Program funds. 3. Roads in which the owner certifies of its inability to provide funding for the project and that it has a maintenance responsibility for the facility. 20
  • 21. Observing A Trend • Results: – Inventory growth since FY2005 has been primarily in routes other than BIA or Tribal. – Because the existing database did not distinguish which roads met the specific exception under (2) of Q.10, all road ownerships and classes, with the exception of State roads, were computed at 100%. – Impacts are trending to favor roads owned by others and away from the BIA and tribal routes. 21
  • 22. Observing A Trend Public Authority Responsible for Maintaining/Improving Roads Fiscal County Other Non- TOTAL IRR Year BIA Tribal State Urban Township Other BIA Other Fed Fed No Owner Miles FY2008 30,367.0 14,984.0 17,680.0 1,882.0 48,978.0 144.0 4,300.0 1,756.0 0.0 120,092.0 FY2007 29,750.7 9,734.2 13,666.4 1,465.3 43,180.2 144.5 2,294.0 1,631.8 330.4 102,197.5 FY2006 28,706.2 4,276.7 13,198.7 897.8 34,295.8 138.8 2,302.8 1,445.5 127.5 85,481.5 FY2005 27,384.9 2,851.2 9,048.7 544.7 22,323.7 134.1 370.8 121.6 90.2 62,869.9 22
  • 23. IRR Mileage 80000 70000 60000 50000 BIA & Tribal 40000 County & State 30000 Other 20000 10000 0 2005 2006 2007 2008
  • 24. % IRR Fund Distribution (CTC and VMT only) 70 60 50 40 BIA & Tribal County & State 30 Other 20 10 0 2005 2006 2007 2008 2009
  • 25. Recognizing a Problem and Seeking a Solution • 25 CFR 170 established the IRR Program Coordinating Committee (IRRPCC). – Provides input and recommendations to the Secretaries of DOI and DOT regarding regulatory policy and implementation issues that are brought to its attention. 25
  • 26. Role of IRRPCC • The IRRPCC has reviewed and discussed this issue over the past years and has not able to come up with a recommendation – The Committee reviewed all of the eligible roads and their corresponding classification – Numerous data runs were requested and analyzed. – A matrix was developed to show where some agreement might be possible (see next slide) – But because of diverse interests, no consensus could be reached. 26
  • 27. 27
  • 28. Summary • Recognizing a Problem – Because of the significant increase in mileage being added to the inventory and the fact that Q10 cannot be implemented as written: • The majority of the IRR funding is now generated by non-BIA/tribal roads. Most of these roads did not generate funding prior to 2005. • BIA and tribal roads are not generating enough funding in the formula to adequately keep pace with the deteriorating infrastructure. • The responsible public authority of non-BIA/tribal roads has other sources of funding made available to it for road infrastructure. BIA and tribal roads do not. 28
  • 29. Summary • Seeking a solution. – A preliminary Federal recommendation has been developed that closely coincides to the IRRPCC views. – This has been presented at several regional and national tribal meetings in the near future. – BIA and FHWA will continue to work with Tribes and the IRRPCC to develop a final resolution to this issue. 29
  • 30. Data Runs (Using FY 07‟ Inventory Data) • Run 1 – Baseline – Current implementation • (similar to FY 05‟, 06‟, 07‟) – All ownership except Ownership 3 (State) calculated at 100% CTC and VMT – Ownership 3 calculated at Non-Federal Share 30
  • 31. Data Runs (Using FY 07‟ Inventory Data) • Run 2 – Ownership 1 & 2 100% CTC and VMT – Ownership 5, Class 4&5 100% CTC and VMT – All Other Non-Federal Share • Run 3 – Ownership 1 & 2 100% CTC and VMT – Ownership 3-9, Class 4&5100% CTC and VMT – All Others Non-Federal Share 31
  • 32. Requested Data Cont‟d • Run 4 – Ownership 1 & 2 100% CTC and VMT – Ownership 4 & 5 Non-Federal Share – All Others 0% CTC and VMT • Run 5 (Preliminary Federal Recommendation) 32
  • 33. Comparison of DATA RUNS REGION BASELINE RUN 1 RUN 3 RUN 4 RUN 5 Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($) A - GR. PLAINS 6.50% 19,194,818 7.62% 22,521,838 7.22% 21,335,200 6.87% 20,293,677 7.51% 22,175,231 B - SO. PLAINS 2.78% 8,216,738 3.34% 9,856,266 3.25% 9,593,942 2.32% 6,851,329 3.26% 9,617,834 C - ROCKY MTN 7.44% 21,988,927 8.44% 24,930,599 8.43% 24,890,233 7.98% 23,577,517 8.50% 25,101,548 E - ALASKA 12.21% 36,070,741 10.48% 30,963,959 11.18% 33,033,325 14.01% 41,379,198 11.01% 32,512,012 F - MIDWEST 13.38% 39,517,651 12.79% 37,777,619 13.28% 39,245,932 11.13% 32,891,678 12.20% 36,045,541 G - EASTERN OK 12.97% 38,317,409 15.08% 44,563,392 15.28% 45,143,901 7.93% 23,419,236 13.65% 40,314,074 H - WESTERN 6.27% 18,520,881 7.26% 21,442,171 6.95% 20,517,687 9.30% 27,477,141 7.57% 22,355,598 J - PACIFIC 2.34% 6,908,118 1.86% 5,499,835 1.94% 5,730,855 1.73% 5,121,581 1.89% 5,585,951 M - SOUTHWEST 4.41% 13,020,857 5.09% 15,047,024 4.80% 14,192,373 6.59% 19,457,253 5.32% 15,724,623 N - NAVAJO 23.50% 69,410,946 20.51% 60,599,412 19.26% 56,901,894 23.54% 69,547,773 21.38% 63,159,334 P - NORTHWEST 6.38% 18,840,531 5.34% 15,768,681 6.29% 18,594,459 5.97% 17,630,938 5.49% 16,212,378 S - EASTERN 1.83% 5,416,744 2.18% 6,453,565 2.11% 6,244,559 2.63% 7,777,040 2.24% 6,620,238 Max for Region Min for Region 33
  • 34. Preliminary Federal Recommendation • The percentage of CTC and VMT used in the RNDF calculation is as follows: – (a) For facilities identified in the IRR Inventory as Ownership 1 and 2, – 100 percent; – (b) For facilities identified in the IRR Inventory as Ownership 5, Class 4 & 5 – The percentage used will be that shown under the 80% Federal, 20% State column in the “Sliding Scale Rates of Federal-aid Participation in Public Lands States for Projects not on the Interstate System”, pursuant to 23 U.S.C. 120(b)(2); and 34
  • 35. Preliminary Federal Recommendation • Con‟t – (c) For facilities not included in (a) or (b) above - The percentage used will be the difference between 100 and that shown under the 80% Federal, 20% State column in the “Sliding Scale Rates of Federal-aid Participation in Public Lands States for Projects not on the Interstate System”, pursuant to 23 U.S.C. 120(b)(2), except for Class 1 roads which shall have a percentage of zero. 35
  • 36. 36
  • 37. Preliminary Federal Recommendation • In brief: – (a) Roads owned by BIA and Tribal Governments for all Classifications should be factored into the formula at 100%. 37
  • 38. Preliminary Federal Recommendation – (b) For facilities identified in the IRR Inventory as Ownership 5 (County/Local), Class 4 & 5 – The percentage used will be the Federal Share (+ 80% - 95%); – (c) For facilities not included in (a) or (b) above - The percentage used will be the Non- Federal Share (+ 5 - 20%); 38
  • 39. Preliminary Federal Recommendation – (d) Class 1 roads for all road ownership other than BIA or Tribal which are the responsibility of other public authorities will not generate funding in the formula (0%). • They are still eligible IRR as required by law, but will not generate formula output 39
  • 40. Preliminary Federal Recommendation • Results – Roads owned by BIA and Tribes – 100%; – Roads owned by others and which make up the majority of roads in and around Indian Reservations, communities, and villages (Ownership 5, Class 4 & 5 Roads) are factored into the formula at a high share; – All remaining roads, except Class 1 are factored into the formula at a lower share; and – Non-BIA, Non-Tribal Class 1 roads are not factored into the formula. 40
  • 41. 41
  • 42. Federal Share • The Federal Share referred to here is the maximum percentage of a project‟s cost for which Federal funds can be used. – It is a uniformly published % and has been consistent since 1992. It is generally about 80% to 95% and is shown on the following table: 42
  • 43. 43
  • 44. Non-Federal Share • The Non-Federal Share referred to here is the minimum percentage of a project‟s cost for which state and local funds must contribute in order for Federal funds to be utilized on a project. 44
  • 45. 45
  • 46. Comparison of DATA RUNS REGION BASELINE RUN 1 RUN 3 RUN 4 RUN 5 Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($) A - GR. PLAINS 6.50% 19,194,818 7.62% 22,521,838 7.22% 21,335,200 6.87% 20,293,677 7.51% 22,175,231 B - SO. PLAINS 2.78% 8,216,738 3.34% 9,856,266 3.25% 9,593,942 2.32% 6,851,329 3.26% 9,617,834 C - ROCKY MTN 7.44% 21,988,927 8.44% 24,930,599 8.43% 24,890,233 7.98% 23,577,517 8.50% 25,101,548 E - ALASKA 12.21% 36,070,741 10.48% 30,963,959 11.18% 33,033,325 14.01% 41,379,198 11.01% 32,512,012 F - MIDWEST 13.38% 39,517,651 12.79% 37,777,619 13.28% 39,245,932 11.13% 32,891,678 12.20% 36,045,541 G - EASTERN OK 12.97% 38,317,409 15.08% 44,563,392 15.28% 45,143,901 7.93% 23,419,236 13.65% 40,314,074 H - WESTERN 6.27% 18,520,881 7.26% 21,442,171 6.95% 20,517,687 9.30% 27,477,141 7.57% 22,355,598 J - PACIFIC 2.34% 6,908,118 1.86% 5,499,835 1.94% 5,730,855 1.73% 5,121,581 1.89% 5,585,951 M - SOUTHWEST 4.41% 13,020,857 5.09% 15,047,024 4.80% 14,192,373 6.59% 19,457,253 5.32% 15,724,623 N - NAVAJO 23.50% 69,410,946 20.51% 60,599,412 19.26% 56,901,894 23.54% 69,547,773 21.38% 63,159,334 P - NORTHWEST 6.38% 18,840,531 5.34% 15,768,681 6.29% 18,594,459 5.97% 17,630,938 5.49% 16,212,378 S - EASTERN 1.83% 5,416,744 2.18% 6,453,565 2.11% 6,244,559 2.63% 7,777,040 2.24% 6,620,238 Max for Region Min for Region 46
  • 47. Future Issues • The IRRPCC is also working to address the following: – How to determine lengths of eligible routes when a Tribe does not have a recognized Boundary? – Definition and measurement of an access route? – How Proposed Routes should be considered? 47
  • 48. Contacts • Mr. LeRoy Gishi Chief – BIA Division of Transportation Washington, DC 202-513-7711 leroy.gishi@bia.gov • Mr. Robert Sparrow FHWA - IRR Program Manager Washington, DC 202-366-9483 robert.sparrow@dot.gov
  • 49. Comments 49