Peoria/Riverside Transit Study
            An Alternatives Analysis




Steering Committee Meeting #1
         June 15, 2012
Agenda

1) Regional Transit System Plan Review
         Adopted October 2011
2) What is Alternatives Analysis?
3) Role of Steering Committee
4) Bus Rapid Transit (BRT) Introduction
5) Service Scenarios and Segments
6) Next Steps
7) Questions and Discussion

10/29/2012                            2
How we got here

       Streets & Freeways
                           Trails & Bikeways
                                                       Transit




    1961 Tulsa Expressway Plan


                     1999 Regional Trail Master Plan
                                          2011 Regional Transit System Plan


10/29/2012                                                                    3
Adopted Regional Transit
                             System Plan
   Peoria/Riverside
       Corridor

        20.2 Miles
    Residents: 69,000

      Jobs: 37,000

    5,700 TOTAL daily
      trips to/from
        downtown




10/29/2012                                     4
Implementation Strategies
                               Near Term (1 – 5 Years)


                   • Conduct Alternatives Analysis for
                     Peoria/Riverside Corridor

                   • Define & Implement Transit
                     Governance Structure

                   • Establish Financial Plan

                   • Construct Transit Facilities
NEAR TERM

       1-5 years      RTSP IMPLEMENTATION

  10/29/2012                                             5
Fast Forward
             Funding Strategy




10/29/2012                      6
FTA Project Development
                                        Fast Forward Regional
              System Planning           Transit System Plan
                                        Adopted October 2011



             Alternatives Analysis            WE ARE HERE



                Selection of Locally
                Preferred Alternative


               FTA Rating & Decision




             Project Development



                  Implementation



10/29/2012                                                      7
Why Peoria?

             + Peoria creates a spine of
               rapid transit service
               connecting to other routes
             + 105 Peoria is Tulsa Transit’s
               busiest route
             + Peoria-Riverside is not traffic
               congested
             + Buses run in mixed traffic
             + Many Anchors & Activity
               Centers
             = Best chance for success


10/29/2012                                 8
Project Mission
                    Purpose & Objectives




• Improve mobility
• Increase travel choices
• Support economic
  development
• Best bang-for-your-buck
                                   Picture of Bus
  transit investment               Enhancement




10/29/2012                                          9
Work Program

    1) Identify Issues and Opportunities




                                                       Stakeholder Involvement
             What is the need? Who will benefit?
    2) Identify Potential Solutions
    3) Compare costs/benefits
    4) Determine feasible and cost-effective
       options
    5) Identify “Locally Preferred
       Alternative” (LPA)
    6) Develop Implementation Plan

    Key input from Steering Committee & Stakeholders
10/29/2012                                             10
Project Schedule

 Summer      Identify Problems & Potential Solutions
   ‘12                  Public Meeting #1


                  Evaluate Potential Solutions
  Fall ‘12
                       Public Meeting #2


  Winter       Select Locally Preferred Alternative
  ‘12/13                Public Meeting #3



Spring ‘13        Develop Implementation Plan



10/29/2012                                        11
Steering Committee

• Roles and Responsibilities
  –   Review and feedback
  –   Recommending committee
                                 Peoria/Riverside Steering
  –   Big picture view                  Committee
  –   Champions and advocates
• Meetings Schedule               INCOG Transportation
                                    Policy Committee
  –   June 15, 2012
  –   September 2012 (TBD)
                                       INCOG Board
  –   January 2013 (TBD)
  –   Other meetings as needed

 10/29/2012                                           12
Public Involvement

•Explore
   •Explain
      •Engage
         •Excite
Steering Committee
Peoria Transit Advisors (PTA)
3 Sets of Public Meetings (2 ea.)
Website & Social Media
Mailings




 10/29/2012                                       13
Federal Transit Administration
                      (FTA) Funding Framework
   New Starts            Small Starts    Very Small Starts


                        Medium-sized      Small projects
 Large projects
                          projects
35,000 riders/day                        3,000 riders/day
                        4,000 -10,000         min.
                          riders/day
   $250M-$7B
                                         Less than $50M
                       Less than $250M




10/29/2012                                             14
The Challenge

               5% of MTTA Operating Budget ($645k)




                    Very Small Starts
                     Project Proposal



                  At least 3,000 benefiting riders
             10 min. headways during peak/15 off peak




10/29/2012                                              15
Major Activity Centers


Downtown                        Tulsa Tech

                                                      St. John & Hillcrest




                                                                    Utica
                                                                   Square




 Blair Property Park


                                             Cherry Street




 Mabee Center/ORU                                      Brookside




10/29/2012                                                           16
Existing Rider Survey

All trips for nine corridor routes surveyed from
April 24-26, 2012 to determine number of
existing riders that would benefit from a project
FULL CORRIDOR ROUTES
• Serve majority of corridor (105)
• 1,620 benefitting riders

SOUTH PEORIA ROUTES
• Serve portions of South Peoria corridor
  (112, 222, 471)
• 541 benefitting riders

DOWNTOWN ROUTES
• Serve portions of 1st St / 2nd St corridor
  (100, 112, 203, 210, 221, 251)
• 1,910 benefitting riders



10/29/2012                                             17
Existing Corridor Riders




•   To qualify for FTA Very Small Starts funding, project must benefit at least
    3,000 weekday riders
•   Full Corridor (North Peoria + Downtown + South Peoria) benefits over
    4,000 weekday riders
•   South Peoria + Downtown also meets VSS criteria (3,700 weekday riders)


10/29/2012                                                                 18
Bus Rapid Transit




Branded Buses                 Off-Board Fare Collection




Enhanced Boarding Platforms   Passenger Information
  10/29/2012                                              19
BRT System Elements


                 Vehicles


                 Running Ways


                 Stations & Terminals


                 Passenger Information Systems


                 Service Plan
10/29/2012                                20
What is BRT?

             Varieties of BRT :
             On-Street in Mixed Traffic
             Reno, NV




             On-Street in Dedicated Lanes
             Eugene, OR




             Off-Street in Exclusive Lanes or
             Reserved Lanes on Freeways
             Pittsburg, PA



10/29/2012                                      21
BRT Examples




Oakland : San Pablo Rapid   Eugene, OR: EmX Green Line       Albuquerque: Rapid Ride




                                         Washington, D.C.:
  Fort Worth: Spur Route                  Metro Circulator   Baltimore: Charm City Circulator




10/29/2012                                                                             22
Potential Funding Sources

• Federal Grants
    – Very Small Starts
    – TIGER
    – Livable Communities
• Local funds
    – Capital (50:50 up to $25 million)
    – Operating (100%)
• Potential regional transit authority
  with dedicated source of funding
10/29/2012                                23
Operating Characteristics for
              Peoria/Riverside Corridor
                Service and Amenities
                • Less Time between buses:
                    – 10 minutes in peak periods
                    – 15 minutes in off-peak
                •   6am to 8pm Service Hours
                •   Low Floor, CNG Fueled Buses
                •   Signal Priority for Buses
                •   Branded Stops and Vehicles
                •   Stops Spaced 3 Blocks to ½-mile
                •   Passenger Shelters and Benches
                •   Next Bus Arrival Signs
                •   Pedestrian and Bicycle Amenities
                •   Transit Centers and Park-n-Rides


10/29/2012                                         24
Peoria/Riverside Corridor
                                          Fast Facts
Length: 24.8 mi. (56th N to 121st S)

People per sq. mi. 2,697

Jobs per sq. mi. 3,029

Daily transit riders: 4,050

Zero car households: 2,543

Miles of congested roadway: 5.6

Activity Centers per mile: 1.2

Downtown trips: 5,750

Vacant parcels per mile: 111




   10/29/2012                                              25
Scenarios for
                                       Peoria/Riverside Corridor
Length: 24.8 mi. (56th N to 121st S)




                                       Scenario
People per sq. mi. 2,697




                                          A
Jobs per sq. mi. 3,029

Existing transit riders: 4,050

One-way trip time: 75.7 – 81.4 min.

Est. Capital cost range:
$23.2M - $35.8M

Est. Annual Operating
cost range: $2.4M - $3.9M

Pct. Of MTTA Operating Budget (Fast
Forward projected): 13.2% - 21.6%



     10/29/2012                                                26
Scenarios for
                                     Peoria/Riverside Corridor
Length: 21.8 mi. (Pine to 121st S)

People per sq. mi. 2,741




                                     Scenario
Jobs per sq. mi. 3,394

Existing transit riders: 3,950




                                        B
One-way trip time:
65.4 – 71.1 min.

Est. Capital cost range:
$20.7M - $31.7M

Est. Annual Operating
cost range: $2.2M - $3.4M

Pct. Of MTTA Operating Budget (Fast
Forward projected): 12.3% - 19.1%


    10/29/2012                                               27
Scenarios for
                                    Peoria/Riverside Corridor
Length: 12.7 mi. (Pine to 81st S)

People per sq. mi. 3,494

Jobs per sq. mi. 5,833

Existing transit riders: 3,940

One-way trip time:
47.3 - 51.2 min.                    Scenario
Est. Capital cost range:
                                       C
$16.3M - $25.0M

Est. Annual Operating
cost range: $1.6M - $2.5M

Pct. Of MTTA Operating Budget (Fast
Forward projected): 8.7% - 13.8%


    10/29/2012                                              28
Scenarios for
                                 Peoria/Riverside Corridor
Length: 11.5 mi. (Downtown to 81st S)

People per sq. mi. 3,771

Jobs per sq. mi. 6,719

Existing transit riders: 3,690

One-way trip time:
30.0 – 37.5 min.

Est. Capital cost range:
$14.0M - $22.2M
                                   Scenario



Est. Annual Operating
cost range: $0.9M - $1.8M
                                      D




Pct. Of MTTA Operating Budget
(Fast Forward projected):
5.1% - 9.9%

    10/29/2012                                           29
Scenario Comparison
                        Scenario         Scenario        Scenario       Scenario
                           A                B               C              D
Length                   24.8 mi.        21.8 mi.        12.7 mi.        11.5 mi.
Pop. per sq. mi.          2,697            2,741          3,494            3,771
Emp. per sq. mi.          3,029            3,394          5,833            6,719
Existing transit
                          4,050            3,950          3,940            3,690
riders
One-way trip time       75 – 81 min     65 -71 min      47 – 51 min     30 – 38 min
Capital Cost Range     $23M - $35M      $21M - $32M    $16M - $25M     $14M - $22M
Operating Cost
                       $2.4M - $3.9M   $2.2M - $3.4M   $1.6M - $2.5M   $0.9M – $1.8M
Range
% of MTTA Budget
(Fast Forward proj.)
                        13% - 22%       12% – 19%       9% - 14%         5% - 10%
% of MTTA Budget
(Current)
                        19% - 31%       17% – 27%       12% - 20%        7% - 14%



 Corridor
 Extent


   10/29/2012                                                                      30
Next steps for
                        Peoria Transit Study …

•    Meetings with FTA & Sharing initial findings
•    Public and Stakeholder Input
•    Prepare Initiation Package with Purpose & Need
•    Refining Financial Estimates
•    Defining a Draft LPA
•    Public/Stakeholder Comment Period
•    Seeking Approval of Locally Preferred Alternative
     (LPA)




    10/29/2012                                           31
Future Considerations

Policy Leaders
• Develop Local Funding Requirements & Proposal
• Address Institutional and Financial Considerations
  for the region

Project Sponsor
• Work with FTA to develop a project proposal
• Preliminary Engineering and Final Design
• Project Construction Grant Agreement with FTA
• Construction
• Begin Service

10/29/2012                                        32
Public Meeting Schedule


Peoria North                  Peoria South
Tulsa Tech Peoria Campus      Southbrooke Church of Christ
3850 N. Peoria Ave.           38th & Peoria just behind Sonic
                              1132 E. 38th Street



Monday, July 16               Tuesday, July 17
Doors open at 5:30pm          Doors open at 5:30pm
Presentation at 6:00pm        Presentation at 6:00pm


Bus Route 105                 Bus Route 105 or 222




 10/29/2012                                               33
Questions & Discussion




      James Wagner, AICP                 Mike McAnelly, FAICP
Transportation Projects Coordinator        Project Manager
              INCOG                             Jacobs
         (918) 579-9447                     (214) 850-9046
       jwagner@incog.org              Mike.McAnelly@jacobs.com


10/29/2012                                                       34
What is BRT?

             BRT System Elements

             •Simple route layout
             •Frequent service
             •Less frequent stops
             •Level boarding and alighting
             •Branded vehicles and stations
             •Amenities at stops
             •Signal prioritization
             •Larger vehicles
             •Multiple-door on and off
             •Fare prepayment
             •Feeder network
             •Coordinated land use planning




10/29/2012                                    35
Benefits of BRT


 Implemented quickly       Express & Local
  and incrementally          service on a single
                             facility
 Flexible
                            Less costly than rail
 Operates on arterial
  streets                   Integrated into
                             surrounding
 Enhanced travel times      environment
  and passenger
  experience
10/29/2012                                           36
TECHNOLOGY COSTS PER MILE
           Bus Rapid Transit




            Modern Streetcar




Commuter Rail
                               Light Rail




  10/29/2012                                   37
Benefits of BRT

 “BRT is a flexible, rubber-tired rapid-transit mode
 that combines stations, vehicles, services, running ways, and
 Intelligent Transportation System (ITS) elements into an
 integrated system with a strong positive identity that evokes a
 unique image.”

  Features of BRT include:
  • Dedicated or mixed running ways
  • Attractive stations and bus stops
  • Distinctive easy-to-board vehicles
  • Off-vehicle fare collection
  • Use of ITS technologies (Passenger info, traffic signal equipment)
  • Frequent all-day service




10/29/2012                                                         38

Contenu connexe

En vedette

2.29.2012 Obesity Integration Steering Committee Presentation
2.29.2012 Obesity Integration Steering Committee Presentation2.29.2012 Obesity Integration Steering Committee Presentation
2.29.2012 Obesity Integration Steering Committee Presentationhoaglina
 
SME DEVELOPMENT STRATEGY IN LIBYA PROJECT STEERING COMMITTEE
SME DEVELOPMENT STRATEGY IN LIBYA PROJECT STEERING COMMITTEESME DEVELOPMENT STRATEGY IN LIBYA PROJECT STEERING COMMITTEE
SME DEVELOPMENT STRATEGY IN LIBYA PROJECT STEERING COMMITTEEOECDglobal
 
establish an effective it steering committee
establish an effective it steering committeeestablish an effective it steering committee
establish an effective it steering committeeInfo-Tech Research Group
 
Steering committee meeting june 25
Steering committee meeting june 25Steering committee meeting june 25
Steering committee meeting june 25Geneva2020
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance StructureSaurabh Sardesai
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedSlideShare
 

En vedette (7)

2.29.2012 Obesity Integration Steering Committee Presentation
2.29.2012 Obesity Integration Steering Committee Presentation2.29.2012 Obesity Integration Steering Committee Presentation
2.29.2012 Obesity Integration Steering Committee Presentation
 
Overview of PPI
Overview of PPIOverview of PPI
Overview of PPI
 
SME DEVELOPMENT STRATEGY IN LIBYA PROJECT STEERING COMMITTEE
SME DEVELOPMENT STRATEGY IN LIBYA PROJECT STEERING COMMITTEESME DEVELOPMENT STRATEGY IN LIBYA PROJECT STEERING COMMITTEE
SME DEVELOPMENT STRATEGY IN LIBYA PROJECT STEERING COMMITTEE
 
establish an effective it steering committee
establish an effective it steering committeeestablish an effective it steering committee
establish an effective it steering committee
 
Steering committee meeting june 25
Steering committee meeting june 25Steering committee meeting june 25
Steering committee meeting june 25
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance Structure
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
 

Similaire à Peoria AA Steering Committee June 2012

Tulsa Transit Board 10-30-2012
Tulsa Transit Board 10-30-2012Tulsa Transit Board 10-30-2012
Tulsa Transit Board 10-30-2012rtspincog
 
Transportation Advisory Board 12/4/2012
Transportation Advisory Board 12/4/2012Transportation Advisory Board 12/4/2012
Transportation Advisory Board 12/4/2012rtspincog
 
Peoria AA Steering Committee
Peoria AA Steering CommitteePeoria AA Steering Committee
Peoria AA Steering Committeertspincog
 
Bicycle Master Plan - Bicycle Boulevard Project - City of Austin
Bicycle Master Plan - Bicycle Boulevard Project - City of AustinBicycle Master Plan - Bicycle Boulevard Project - City of Austin
Bicycle Master Plan - Bicycle Boulevard Project - City of AustinBang the Table
 
TRANSIT ORIENTED DEVELOPMENT
TRANSIT ORIENTED DEVELOPMENTTRANSIT ORIENTED DEVELOPMENT
TRANSIT ORIENTED DEVELOPMENTRidam Shah
 
ULI Seattle’s Bus Rapid Transit and Land Use Initiative Developing the Next F...
ULI Seattle’s Bus Rapid Transit and Land Use Initiative Developing the Next F...ULI Seattle’s Bus Rapid Transit and Land Use Initiative Developing the Next F...
ULI Seattle’s Bus Rapid Transit and Land Use Initiative Developing the Next F...Virtual ULI
 
Project formulation slstl-iesl - 25th oct 2018 - to be published
Project formulation   slstl-iesl - 25th oct 2018 - to be publishedProject formulation   slstl-iesl - 25th oct 2018 - to be published
Project formulation slstl-iesl - 25th oct 2018 - to be publishedNamalie Siyambalapitiya
 
COTA NE AA Public Meeting Presentation
COTA NE AA Public Meeting PresentationCOTA NE AA Public Meeting Presentation
COTA NE AA Public Meeting PresentationCOTA BUS
 
A Complete Picture of Corridor Planning: The Fundamentals by Dwight Schock
A Complete Picture of Corridor Planning: The Fundamentals by Dwight Schock A Complete Picture of Corridor Planning: The Fundamentals by Dwight Schock
A Complete Picture of Corridor Planning: The Fundamentals by Dwight Schock Rail~Volution
 
June 28, 2012 Transportation Advisory Group Presentation
June 28, 2012 Transportation Advisory Group PresentationJune 28, 2012 Transportation Advisory Group Presentation
June 28, 2012 Transportation Advisory Group PresentationJing Zhang, AICP
 
LRPT Phase 2 Presentation
LRPT Phase 2 PresentationLRPT Phase 2 Presentation
LRPT Phase 2 PresentationCOTA BUS
 
Peoria Transit Study Public Meeting #3 Slides
Peoria Transit Study Public Meeting #3 SlidesPeoria Transit Study Public Meeting #3 Slides
Peoria Transit Study Public Meeting #3 Slidesrtspincog
 
Short-Range Transit Plan Public Comment Meeting
Short-Range Transit Plan Public Comment MeetingShort-Range Transit Plan Public Comment Meeting
Short-Range Transit Plan Public Comment MeetingCOTA BUS
 
Dan Ross NextGen ppt FINAL
Dan Ross NextGen ppt FINALDan Ross NextGen ppt FINAL
Dan Ross NextGen ppt FINALDan Ross
 
San Leandro Bus Rapid Transit (BRT) Public Meeting Presentation
San Leandro Bus Rapid Transit (BRT) Public Meeting PresentationSan Leandro Bus Rapid Transit (BRT) Public Meeting Presentation
San Leandro Bus Rapid Transit (BRT) Public Meeting PresentationAC Transit
 
Transit Panel (Steven Brown) - ULI fall meeting - 102711
Transit Panel (Steven Brown) - ULI fall meeting - 102711Transit Panel (Steven Brown) - ULI fall meeting - 102711
Transit Panel (Steven Brown) - ULI fall meeting - 102711Virtual ULI
 
RV 2014: People Don't Build Great Communities, Partnerships Do by Lynda Kompe...
RV 2014: People Don't Build Great Communities, Partnerships Do by Lynda Kompe...RV 2014: People Don't Build Great Communities, Partnerships Do by Lynda Kompe...
RV 2014: People Don't Build Great Communities, Partnerships Do by Lynda Kompe...Rail~Volution
 

Similaire à Peoria AA Steering Committee June 2012 (20)

Tulsa Transit Board 10-30-2012
Tulsa Transit Board 10-30-2012Tulsa Transit Board 10-30-2012
Tulsa Transit Board 10-30-2012
 
Transportation Advisory Board 12/4/2012
Transportation Advisory Board 12/4/2012Transportation Advisory Board 12/4/2012
Transportation Advisory Board 12/4/2012
 
Peoria AA Steering Committee
Peoria AA Steering CommitteePeoria AA Steering Committee
Peoria AA Steering Committee
 
Bicycle Master Plan - Bicycle Boulevard Project - City of Austin
Bicycle Master Plan - Bicycle Boulevard Project - City of AustinBicycle Master Plan - Bicycle Boulevard Project - City of Austin
Bicycle Master Plan - Bicycle Boulevard Project - City of Austin
 
Public Workshop #1
Public Workshop #1Public Workshop #1
Public Workshop #1
 
TRANSIT ORIENTED DEVELOPMENT
TRANSIT ORIENTED DEVELOPMENTTRANSIT ORIENTED DEVELOPMENT
TRANSIT ORIENTED DEVELOPMENT
 
ULI Seattle’s Bus Rapid Transit and Land Use Initiative Developing the Next F...
ULI Seattle’s Bus Rapid Transit and Land Use Initiative Developing the Next F...ULI Seattle’s Bus Rapid Transit and Land Use Initiative Developing the Next F...
ULI Seattle’s Bus Rapid Transit and Land Use Initiative Developing the Next F...
 
Project formulation slstl-iesl - 25th oct 2018 - to be published
Project formulation   slstl-iesl - 25th oct 2018 - to be publishedProject formulation   slstl-iesl - 25th oct 2018 - to be published
Project formulation slstl-iesl - 25th oct 2018 - to be published
 
SMART Plan Corridors' PD&Es Update
SMART Plan Corridors' PD&Es UpdateSMART Plan Corridors' PD&Es Update
SMART Plan Corridors' PD&Es Update
 
COTA NE AA Public Meeting Presentation
COTA NE AA Public Meeting PresentationCOTA NE AA Public Meeting Presentation
COTA NE AA Public Meeting Presentation
 
A Complete Picture of Corridor Planning: The Fundamentals by Dwight Schock
A Complete Picture of Corridor Planning: The Fundamentals by Dwight Schock A Complete Picture of Corridor Planning: The Fundamentals by Dwight Schock
A Complete Picture of Corridor Planning: The Fundamentals by Dwight Schock
 
June 28, 2012 Transportation Advisory Group Presentation
June 28, 2012 Transportation Advisory Group PresentationJune 28, 2012 Transportation Advisory Group Presentation
June 28, 2012 Transportation Advisory Group Presentation
 
LRPT Phase 2 Presentation
LRPT Phase 2 PresentationLRPT Phase 2 Presentation
LRPT Phase 2 Presentation
 
Peoria Transit Study Public Meeting #3 Slides
Peoria Transit Study Public Meeting #3 SlidesPeoria Transit Study Public Meeting #3 Slides
Peoria Transit Study Public Meeting #3 Slides
 
Short-Range Transit Plan Public Comment Meeting
Short-Range Transit Plan Public Comment MeetingShort-Range Transit Plan Public Comment Meeting
Short-Range Transit Plan Public Comment Meeting
 
Dan Ross NextGen ppt FINAL
Dan Ross NextGen ppt FINALDan Ross NextGen ppt FINAL
Dan Ross NextGen ppt FINAL
 
San Leandro Bus Rapid Transit (BRT) Public Meeting Presentation
San Leandro Bus Rapid Transit (BRT) Public Meeting PresentationSan Leandro Bus Rapid Transit (BRT) Public Meeting Presentation
San Leandro Bus Rapid Transit (BRT) Public Meeting Presentation
 
Not Your Grandfather's DOT: The FDOT District 5 and PennDOT Experiences--Bold...
Not Your Grandfather's DOT: The FDOT District 5 and PennDOT Experiences--Bold...Not Your Grandfather's DOT: The FDOT District 5 and PennDOT Experiences--Bold...
Not Your Grandfather's DOT: The FDOT District 5 and PennDOT Experiences--Bold...
 
Transit Panel (Steven Brown) - ULI fall meeting - 102711
Transit Panel (Steven Brown) - ULI fall meeting - 102711Transit Panel (Steven Brown) - ULI fall meeting - 102711
Transit Panel (Steven Brown) - ULI fall meeting - 102711
 
RV 2014: People Don't Build Great Communities, Partnerships Do by Lynda Kompe...
RV 2014: People Don't Build Great Communities, Partnerships Do by Lynda Kompe...RV 2014: People Don't Build Great Communities, Partnerships Do by Lynda Kompe...
RV 2014: People Don't Build Great Communities, Partnerships Do by Lynda Kompe...
 

Plus de rtspincog

City Council Public Works 12/3/2015
City Council Public Works 12/3/2015City Council Public Works 12/3/2015
City Council Public Works 12/3/2015rtspincog
 
Innovative MPO - Fast Forward Outreach 9-30-2015
Innovative MPO - Fast Forward Outreach 9-30-2015Innovative MPO - Fast Forward Outreach 9-30-2015
Innovative MPO - Fast Forward Outreach 9-30-2015rtspincog
 
GO Plan Final Public Forum - 9/17/15
GO Plan Final Public Forum - 9/17/15GO Plan Final Public Forum - 9/17/15
GO Plan Final Public Forum - 9/17/15rtspincog
 
Fast Forward Mobile Outreach
Fast Forward Mobile OutreachFast Forward Mobile Outreach
Fast Forward Mobile Outreachrtspincog
 
Peoria Bus Rapid Transit - Oct. 2013, Tulsa, OK
Peoria Bus Rapid Transit - Oct. 2013, Tulsa, OKPeoria Bus Rapid Transit - Oct. 2013, Tulsa, OK
Peoria Bus Rapid Transit - Oct. 2013, Tulsa, OKrtspincog
 
All Souls Church 10-21-2013
All Souls Church 10-21-2013All Souls Church 10-21-2013
All Souls Church 10-21-2013rtspincog
 
Sustainable Tulsa 8-1-2013
Sustainable Tulsa 8-1-2013Sustainable Tulsa 8-1-2013
Sustainable Tulsa 8-1-2013rtspincog
 
BRT Performance in Midwest & Southwest Cities
BRT Performance in Midwest & Southwest CitiesBRT Performance in Midwest & Southwest Cities
BRT Performance in Midwest & Southwest Citiesrtspincog
 
Steering Committee 2-15-2013
Steering Committee 2-15-2013Steering Committee 2-15-2013
Steering Committee 2-15-2013rtspincog
 

Plus de rtspincog (9)

City Council Public Works 12/3/2015
City Council Public Works 12/3/2015City Council Public Works 12/3/2015
City Council Public Works 12/3/2015
 
Innovative MPO - Fast Forward Outreach 9-30-2015
Innovative MPO - Fast Forward Outreach 9-30-2015Innovative MPO - Fast Forward Outreach 9-30-2015
Innovative MPO - Fast Forward Outreach 9-30-2015
 
GO Plan Final Public Forum - 9/17/15
GO Plan Final Public Forum - 9/17/15GO Plan Final Public Forum - 9/17/15
GO Plan Final Public Forum - 9/17/15
 
Fast Forward Mobile Outreach
Fast Forward Mobile OutreachFast Forward Mobile Outreach
Fast Forward Mobile Outreach
 
Peoria Bus Rapid Transit - Oct. 2013, Tulsa, OK
Peoria Bus Rapid Transit - Oct. 2013, Tulsa, OKPeoria Bus Rapid Transit - Oct. 2013, Tulsa, OK
Peoria Bus Rapid Transit - Oct. 2013, Tulsa, OK
 
All Souls Church 10-21-2013
All Souls Church 10-21-2013All Souls Church 10-21-2013
All Souls Church 10-21-2013
 
Sustainable Tulsa 8-1-2013
Sustainable Tulsa 8-1-2013Sustainable Tulsa 8-1-2013
Sustainable Tulsa 8-1-2013
 
BRT Performance in Midwest & Southwest Cities
BRT Performance in Midwest & Southwest CitiesBRT Performance in Midwest & Southwest Cities
BRT Performance in Midwest & Southwest Cities
 
Steering Committee 2-15-2013
Steering Committee 2-15-2013Steering Committee 2-15-2013
Steering Committee 2-15-2013
 

Dernier

57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeAbdulGhani778830
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest2
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendExperience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendFabwelt
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdfFIRST INDIA
 

Dernier (8)

57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendExperience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming Trend
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
 

Peoria AA Steering Committee June 2012

  • 1. Peoria/Riverside Transit Study An Alternatives Analysis Steering Committee Meeting #1 June 15, 2012
  • 2. Agenda 1) Regional Transit System Plan Review Adopted October 2011 2) What is Alternatives Analysis? 3) Role of Steering Committee 4) Bus Rapid Transit (BRT) Introduction 5) Service Scenarios and Segments 6) Next Steps 7) Questions and Discussion 10/29/2012 2
  • 3. How we got here Streets & Freeways Trails & Bikeways Transit 1961 Tulsa Expressway Plan 1999 Regional Trail Master Plan 2011 Regional Transit System Plan 10/29/2012 3
  • 4. Adopted Regional Transit System Plan Peoria/Riverside Corridor 20.2 Miles Residents: 69,000 Jobs: 37,000 5,700 TOTAL daily trips to/from downtown 10/29/2012 4
  • 5. Implementation Strategies Near Term (1 – 5 Years) • Conduct Alternatives Analysis for Peoria/Riverside Corridor • Define & Implement Transit Governance Structure • Establish Financial Plan • Construct Transit Facilities NEAR TERM 1-5 years RTSP IMPLEMENTATION 10/29/2012 5
  • 6. Fast Forward Funding Strategy 10/29/2012 6
  • 7. FTA Project Development Fast Forward Regional System Planning Transit System Plan Adopted October 2011 Alternatives Analysis WE ARE HERE Selection of Locally Preferred Alternative FTA Rating & Decision Project Development Implementation 10/29/2012 7
  • 8. Why Peoria? + Peoria creates a spine of rapid transit service connecting to other routes + 105 Peoria is Tulsa Transit’s busiest route + Peoria-Riverside is not traffic congested + Buses run in mixed traffic + Many Anchors & Activity Centers = Best chance for success 10/29/2012 8
  • 9. Project Mission Purpose & Objectives • Improve mobility • Increase travel choices • Support economic development • Best bang-for-your-buck Picture of Bus transit investment Enhancement 10/29/2012 9
  • 10. Work Program 1) Identify Issues and Opportunities Stakeholder Involvement What is the need? Who will benefit? 2) Identify Potential Solutions 3) Compare costs/benefits 4) Determine feasible and cost-effective options 5) Identify “Locally Preferred Alternative” (LPA) 6) Develop Implementation Plan Key input from Steering Committee & Stakeholders 10/29/2012 10
  • 11. Project Schedule Summer Identify Problems & Potential Solutions ‘12 Public Meeting #1 Evaluate Potential Solutions Fall ‘12 Public Meeting #2 Winter Select Locally Preferred Alternative ‘12/13 Public Meeting #3 Spring ‘13 Develop Implementation Plan 10/29/2012 11
  • 12. Steering Committee • Roles and Responsibilities – Review and feedback – Recommending committee Peoria/Riverside Steering – Big picture view Committee – Champions and advocates • Meetings Schedule INCOG Transportation Policy Committee – June 15, 2012 – September 2012 (TBD) INCOG Board – January 2013 (TBD) – Other meetings as needed 10/29/2012 12
  • 13. Public Involvement •Explore •Explain •Engage •Excite Steering Committee Peoria Transit Advisors (PTA) 3 Sets of Public Meetings (2 ea.) Website & Social Media Mailings 10/29/2012 13
  • 14. Federal Transit Administration (FTA) Funding Framework New Starts Small Starts Very Small Starts Medium-sized Small projects Large projects projects 35,000 riders/day 3,000 riders/day 4,000 -10,000 min. riders/day $250M-$7B Less than $50M Less than $250M 10/29/2012 14
  • 15. The Challenge 5% of MTTA Operating Budget ($645k) Very Small Starts Project Proposal At least 3,000 benefiting riders 10 min. headways during peak/15 off peak 10/29/2012 15
  • 16. Major Activity Centers Downtown Tulsa Tech St. John & Hillcrest Utica Square Blair Property Park Cherry Street Mabee Center/ORU Brookside 10/29/2012 16
  • 17. Existing Rider Survey All trips for nine corridor routes surveyed from April 24-26, 2012 to determine number of existing riders that would benefit from a project FULL CORRIDOR ROUTES • Serve majority of corridor (105) • 1,620 benefitting riders SOUTH PEORIA ROUTES • Serve portions of South Peoria corridor (112, 222, 471) • 541 benefitting riders DOWNTOWN ROUTES • Serve portions of 1st St / 2nd St corridor (100, 112, 203, 210, 221, 251) • 1,910 benefitting riders 10/29/2012 17
  • 18. Existing Corridor Riders • To qualify for FTA Very Small Starts funding, project must benefit at least 3,000 weekday riders • Full Corridor (North Peoria + Downtown + South Peoria) benefits over 4,000 weekday riders • South Peoria + Downtown also meets VSS criteria (3,700 weekday riders) 10/29/2012 18
  • 19. Bus Rapid Transit Branded Buses Off-Board Fare Collection Enhanced Boarding Platforms Passenger Information 10/29/2012 19
  • 20. BRT System Elements Vehicles Running Ways Stations & Terminals Passenger Information Systems Service Plan 10/29/2012 20
  • 21. What is BRT? Varieties of BRT : On-Street in Mixed Traffic Reno, NV On-Street in Dedicated Lanes Eugene, OR Off-Street in Exclusive Lanes or Reserved Lanes on Freeways Pittsburg, PA 10/29/2012 21
  • 22. BRT Examples Oakland : San Pablo Rapid Eugene, OR: EmX Green Line Albuquerque: Rapid Ride Washington, D.C.: Fort Worth: Spur Route Metro Circulator Baltimore: Charm City Circulator 10/29/2012 22
  • 23. Potential Funding Sources • Federal Grants – Very Small Starts – TIGER – Livable Communities • Local funds – Capital (50:50 up to $25 million) – Operating (100%) • Potential regional transit authority with dedicated source of funding 10/29/2012 23
  • 24. Operating Characteristics for Peoria/Riverside Corridor Service and Amenities • Less Time between buses: – 10 minutes in peak periods – 15 minutes in off-peak • 6am to 8pm Service Hours • Low Floor, CNG Fueled Buses • Signal Priority for Buses • Branded Stops and Vehicles • Stops Spaced 3 Blocks to ½-mile • Passenger Shelters and Benches • Next Bus Arrival Signs • Pedestrian and Bicycle Amenities • Transit Centers and Park-n-Rides 10/29/2012 24
  • 25. Peoria/Riverside Corridor Fast Facts Length: 24.8 mi. (56th N to 121st S) People per sq. mi. 2,697 Jobs per sq. mi. 3,029 Daily transit riders: 4,050 Zero car households: 2,543 Miles of congested roadway: 5.6 Activity Centers per mile: 1.2 Downtown trips: 5,750 Vacant parcels per mile: 111 10/29/2012 25
  • 26. Scenarios for Peoria/Riverside Corridor Length: 24.8 mi. (56th N to 121st S) Scenario People per sq. mi. 2,697 A Jobs per sq. mi. 3,029 Existing transit riders: 4,050 One-way trip time: 75.7 – 81.4 min. Est. Capital cost range: $23.2M - $35.8M Est. Annual Operating cost range: $2.4M - $3.9M Pct. Of MTTA Operating Budget (Fast Forward projected): 13.2% - 21.6% 10/29/2012 26
  • 27. Scenarios for Peoria/Riverside Corridor Length: 21.8 mi. (Pine to 121st S) People per sq. mi. 2,741 Scenario Jobs per sq. mi. 3,394 Existing transit riders: 3,950 B One-way trip time: 65.4 – 71.1 min. Est. Capital cost range: $20.7M - $31.7M Est. Annual Operating cost range: $2.2M - $3.4M Pct. Of MTTA Operating Budget (Fast Forward projected): 12.3% - 19.1% 10/29/2012 27
  • 28. Scenarios for Peoria/Riverside Corridor Length: 12.7 mi. (Pine to 81st S) People per sq. mi. 3,494 Jobs per sq. mi. 5,833 Existing transit riders: 3,940 One-way trip time: 47.3 - 51.2 min. Scenario Est. Capital cost range: C $16.3M - $25.0M Est. Annual Operating cost range: $1.6M - $2.5M Pct. Of MTTA Operating Budget (Fast Forward projected): 8.7% - 13.8% 10/29/2012 28
  • 29. Scenarios for Peoria/Riverside Corridor Length: 11.5 mi. (Downtown to 81st S) People per sq. mi. 3,771 Jobs per sq. mi. 6,719 Existing transit riders: 3,690 One-way trip time: 30.0 – 37.5 min. Est. Capital cost range: $14.0M - $22.2M Scenario Est. Annual Operating cost range: $0.9M - $1.8M D Pct. Of MTTA Operating Budget (Fast Forward projected): 5.1% - 9.9% 10/29/2012 29
  • 30. Scenario Comparison Scenario Scenario Scenario Scenario A B C D Length 24.8 mi. 21.8 mi. 12.7 mi. 11.5 mi. Pop. per sq. mi. 2,697 2,741 3,494 3,771 Emp. per sq. mi. 3,029 3,394 5,833 6,719 Existing transit 4,050 3,950 3,940 3,690 riders One-way trip time 75 – 81 min 65 -71 min 47 – 51 min 30 – 38 min Capital Cost Range $23M - $35M $21M - $32M $16M - $25M $14M - $22M Operating Cost $2.4M - $3.9M $2.2M - $3.4M $1.6M - $2.5M $0.9M – $1.8M Range % of MTTA Budget (Fast Forward proj.) 13% - 22% 12% – 19% 9% - 14% 5% - 10% % of MTTA Budget (Current) 19% - 31% 17% – 27% 12% - 20% 7% - 14% Corridor Extent 10/29/2012 30
  • 31. Next steps for Peoria Transit Study … • Meetings with FTA & Sharing initial findings • Public and Stakeholder Input • Prepare Initiation Package with Purpose & Need • Refining Financial Estimates • Defining a Draft LPA • Public/Stakeholder Comment Period • Seeking Approval of Locally Preferred Alternative (LPA) 10/29/2012 31
  • 32. Future Considerations Policy Leaders • Develop Local Funding Requirements & Proposal • Address Institutional and Financial Considerations for the region Project Sponsor • Work with FTA to develop a project proposal • Preliminary Engineering and Final Design • Project Construction Grant Agreement with FTA • Construction • Begin Service 10/29/2012 32
  • 33. Public Meeting Schedule Peoria North Peoria South Tulsa Tech Peoria Campus Southbrooke Church of Christ 3850 N. Peoria Ave. 38th & Peoria just behind Sonic 1132 E. 38th Street Monday, July 16 Tuesday, July 17 Doors open at 5:30pm Doors open at 5:30pm Presentation at 6:00pm Presentation at 6:00pm Bus Route 105 Bus Route 105 or 222 10/29/2012 33
  • 34. Questions & Discussion James Wagner, AICP Mike McAnelly, FAICP Transportation Projects Coordinator Project Manager INCOG Jacobs (918) 579-9447 (214) 850-9046 jwagner@incog.org Mike.McAnelly@jacobs.com 10/29/2012 34
  • 35. What is BRT? BRT System Elements •Simple route layout •Frequent service •Less frequent stops •Level boarding and alighting •Branded vehicles and stations •Amenities at stops •Signal prioritization •Larger vehicles •Multiple-door on and off •Fare prepayment •Feeder network •Coordinated land use planning 10/29/2012 35
  • 36. Benefits of BRT  Implemented quickly  Express & Local and incrementally service on a single facility  Flexible  Less costly than rail  Operates on arterial streets  Integrated into surrounding  Enhanced travel times environment and passenger experience 10/29/2012 36
  • 37. TECHNOLOGY COSTS PER MILE Bus Rapid Transit Modern Streetcar Commuter Rail Light Rail 10/29/2012 37
  • 38. Benefits of BRT “BRT is a flexible, rubber-tired rapid-transit mode that combines stations, vehicles, services, running ways, and Intelligent Transportation System (ITS) elements into an integrated system with a strong positive identity that evokes a unique image.” Features of BRT include: • Dedicated or mixed running ways • Attractive stations and bus stops • Distinctive easy-to-board vehicles • Off-vehicle fare collection • Use of ITS technologies (Passenger info, traffic signal equipment) • Frequent all-day service 10/29/2012 38

Notes de l'éditeur

  1. Introduce Mike. Worked on OKC Alternatives Analysis for streetcar.
  2. Project Mission Statement:The Peoria / Riverside Alternative Analysis will improve mobility, increase travel choice and support economic development through the use of low-cost, high-impact transit technology investments.
  3. Passengers “like” the service moreServes as a spine of transit service rather than one central transfer point downtownHelps promote economic developmentStations are perceived to be more important than conventional bus stopsRoutes currently serving the corridor may be re-routed due to the increased service with the new system
  4. Passengers “like” the service moreServes as a spine of transit service rather than one central transfer point downtownHelps promote economic developmentStations are perceived to be more important than conventional bus stopsRoutes currently serving the corridor may be re-routed due to the increased service with the new system