2. Group Members
Saba Afaq
Plan Quality Management
Saba Mehboob
Perform Quality Assurance
Reeha Noor
Perform Quality Control
3. Project Quality Management
Project Quality Management includes the
processes and activities of the performing
organization that determines quality
policies, objectives, and responsibilities so
that the project will satisfy the needs for
which it was undertaken
3
5. Plan Quality Management
5
Process of identifying quality requirements
and standards for the project and its
deliverables and documenting how the
project will demonstrate compliance with
quality requirements.
6. Plan Quality Management
INPUTS
1.Project management
plan
.2 Stakeholder register
.3 Risk register
.4 Requirements
documentation
.5 Enterprise
environmental
factors
.6 Organizational
process
TOOLS & TECHNIQUES
.1 Cost-benefit analysis
OUTPUTS
.2 Cost of quality
1 Quality management
plan
.3 Seven basic quality
tools
.2 Process improvement
.4 Benchmarking
plan
.5 Design of experiments
.3 Quality metrics
.6 Statistical sampling
.4 Quality checklists
.7 Additional quality
.5 Project documents
planning tools
updates
.8 Meetings
11. Cost of Quality (COQ)
11
Cost of
Conformance
Prevention Costs
(Build a quality
product)
• Training
• Document processes
• Equipment
Cost of nonConformance
Internal Failure Costs
(Failures found by the
project)
• Rework
• Scrap
• Time to do it right
Appraisal Costs
External Failure Costs
(Assess the quality)
(Failures found by the
customer)
• Testing
• Liabilities
• Destructive testing
loss
• Warranty work
• Lost business
20. Plan Quality Management: Tools and
Techniques
20
Benchmarking
Design of Experiments
Statistical Sampling
Additional Quality Planning Tools
Brainstorming
Force field analysis
Nominal group technique
Quality management and control tools
Meetings
22. Quality Management Plan : Outputs
22
Quality Management Plan
The quality management plan is a component of the project
management plan that describes how the organization’s quality
policies will be implemented.
Process Improvement Plan
Process boundaries.
Process configuration.
Process metrics..
Targets for improved performance.
23. Quality Management Plan :
Outputs
Quality Metrics
A quality metric specifically describes a project or
product attribute and how the control quality
process will measure it.
Quality Checklists
A checklist is a structured tool, usually componentspecific, used to verify that a set of required steps has
been performed
Project Documents Updates
Stakeholder register
Responsibility assignment matrix
WBS and WBS Dictionary.
25. Perform Quality Assurance
Quality Assurance (QA) is concerned with establishing,
evaluating , improving and maintaining the quality of the
processes. Once processes are consistent, QA "assure" that the
same level of quality will be incorporated into each product
produced by that process by use of different tools and
techniques.
OUTPUTS
INPUTS
1. Quality management
plan
2 Process improvement
plan
TOOLS & Techniques
.1 Change requests
1. Quality
management &
.2 Project management
plan
control tools
updates
3 Quality metrics
.2 Quality audits
.3 Project documents
updates
4 Quality control
measurements
.3 Process analysis
.4 Organizational process
assets
5 Project documents
updates
26. 1. Quality Management and Control Tools
1. Affinity Diagrams
2. Process decision program charts
(PDPC)
3. Interrelationship digraphs
4. Tree diagrams
5. Prioritization matrices
6. Activity network diagrams
7. Matrix diagrams
27. I. Steps to Create Affinity Diagrams
It is an orderly extension of a structured brainstorming session to generate
ideas
STEP 1
Write each idea
on a separate
index card
STEP 2
Randomly place
each index card on
flat surface. Wall
board or flipchart
STEP 3
In silence, team
members move the
cards into
meaningful groups
until the group
stops moving the
cards.
STEP 4
As a team,
discuss and then
label each
category with a
title
STEP 5
As a team, discuss
Each category,
Using cause-and
Effect diagrams, if
needed.
28. II. Steps to Create PDPC
systematically identifies what might go wrong in a plan under development.
By using PDPC, you can either revise the plan to avoid the problems or be
ready with the best response when a problem occurs.
1
• Develop a tree diagram of the proposed plan
2
• For each task on the third level, brainstorm what could go wrong
3
• Review all the potential problems and eliminate any that are insignificant
4
• For each potential problem, brainstorm possible countermeasures
5
• Decide how practical each countermeasure is. Use criteria such as cost,
time required, ease of implementation and effectiveness. Mark impractical
countermeasures with an X and practical ones with an O.
29. III. How to Construct an Interrelationship Digraph
Show cause-and-effect relationships, and help analyze the natural links
between different aspects of a complex situation
2. Brainstorm
Ideas
1. Create a
Problem
Statement
3. Determine
Relationships
Between
Ideas
4. Analyze
the Diagram
30. IV. Tree diagrams and Prioritization Matrices
It is used to figure out all the various tasks that must be undertaken to achieve a
given objective
Prioritization Matrix
1
Unavailability of
Construction
Material
Scarcity of raw
materials
Shortage of funds
Delay of Bridge
Construction
Unfavorable
weather
conditions
Equipment
Damage
Equipment
Problems
Unavailabity of
equipment
2
3
4
31. 1. Quality Management & Control Tools
VI. Activity network diagrams –used with
project scheduling methodologies
Activity on arrow
Activity on node
Can be used for review technique
(PERT), critical path method (CPM) &
precedence diagramming method
(PDM).
VII. Matrix diagrams –used to perform data
analysis within the organizational structure
show the strength of relationships between
factors, causes, and objectives that exist
between the rows and columns of matrix
32. Perform Quality Assurance: Tools &
Techniques
2.
Quality Audits
3.
Structured, independent process to determine if project
activities comply with organizational and project policies,
processes, and procedures.
can confirm the implementation of approved change requests
including updates, corrective actions, defect repairs, and
preventive actions.
Process Analysis
follows the steps outlined in the process improvement plan to
identify needed improvements.
examines problems experienced, constraints experienced, and
non-value-added activities identified during process operation.
33. Perform Quality Assurance: Outputs
Change Requests
used as input into the Perform Integrated Change Control process
used to take
corrective action,
preventive action,
to perform defect repair
Project Management Plan Updates
Quality management plan
Scope management plan
Schedule management plan
Cost management plan
Project Documents Updates
Quality audit reports,
Training plans
Process documentation.
Organizational Process Assets Updates
35. Control Quality
Control Quality is the process of monitoring and recording results
of executing the quality activities to assess performance and
recommend necessary changes
36. Perform Quality Control :Inputs
Project
management
plan
• The project management plan
contains the quality management
plan, which is used to control
quality
Quality Metrics
• A quality metric describes a project
or product attribute and how it will
be measured.
Quality Checklist
• Quality checklists are structured lists
that help to verify that the work of
the project and its deliverables fulfill
a set of requirements.
37. Perform Quality Control :Inputs
Work performance
data
• Work performance data is Planned vs.
actual technical performance, actual
schedule performance, and actual cost
performance.
Approved Change
Requests
• As part of the Perform Integrated
Change Control process, a change log
update indicates that some changes are
approved and some are not.
Deliverables
•A deliverable is any unique and verifiable
product, result, or capability that results in
a validated deliverable required by the
project.
38. Perform Quality Control :Inputs
Project
Documents
Organizational
Process Assets
• Project documents may include
Agreements, Quality audit reports and
change logs , Training plans and
assessments and Process
documentation .
• The organizational process assets
includes the organization’s quality
standards and policies, guidelines,
reporting procedures and
communication policies.
39. Perform Quality Control: T&T
Seven Basic Quality Tools
The seven basic quality tools are illustrated earlier.
Statistical Sampling
Samples are selected and tested as defined in
the quality management plan.
Inspection
An inspection is the examination of a work
product to determine if it conforms to
documented standards.
Approved Change Requests Review
All approved change requests should be reviewed
to verify that they were implemented as approved.
40. Perform Quality Control :Outputs
Quality Control Measurements
Quality control measurements are the documented results of
control quality activities.
Verified Deliverables
A goal of the Control Quality process is to determine the
correctness of deliverables.
Work Performance Information
Work performance information is the performance data
collected
Validated Changes
Any changed or repaired items are inspected and will be either
accepted or rejected before notification of the decision is
provided.
41. Perform Quality Control :Outputs
Change Requests
If the recommended corrective or preventive actions or a
defect repair requires a change to the project management
plan, a change request should be initiated.
Project Management Plan Updates
Elements of the project management plan that may be
updated include Quality management plan , and Process
improvement plan
Project Documents Updates
Project documents is being updated
Organizational Process Assets Updates
Elements of the organizational process assets that may be
updated include Completed checklists and Lessons learned
documentation
Quality management plan provides the scope and schedule for performing audit and inspection activities. Process Improvement Plan provides information about which processes needs to be improves and how they should be improved.Quality Metrics provide the baseline for measuring the processes that needs to be control, Here they will be helpful in audit and process analysis.QC Measurements are used to evaluate o/p against specified requirements. They can also be used to compare the process for creating the measurements and validating actual measurements to determine the level of accuracy.Project Documents for configuration management
A Tree Diagram is a chart that begins with one central item and then branches into more and keeps branching until the line of inquiry begun with the central item is exhausted.
When to Use PDPCBefore implementing a plan, especially when the plan is large and complex.When the plan must be completed on schedule.When the price of failure is high.
It is a chart that begins with one central item and then branches into more and keeps branching until the line of inquiry begun with the central item is exhaustedWhen to Use a Tree Diagram When an issue is known or being addressed in broad generalities and you must move to specific details, such as when developing logical steps to achieve an objective. When developing actions to carry out a solution or other plan. When analyzing processes in detail. When probing for the root cause of a problem. When evaluating implementation issues for several potential solutions. After an affinity diagram or relations diagram has uncovered key issues. As a communication tool, to explain details to others.