BPP 3213 PROJECT ESTIMATION AND
                  SCHEDULING

Lecture 2   Network Scheduling and Precedence Diagram
                    Method (PDM)
                           Oct, 2012

                       Faculty of Technology
                     Universiti Malaysia Pahang


                      Jane Doe & Jane Doe
RECAP
Organization
  Structure

                            Challenges


                Project
               life cycle
Purpose of this lecture

To better understand:

• brief history of scheduling techniques

• network scheduling and logic diagrams

• the importance of Critical Path Method (CPM)

• the fundamental elements of precedence diagram
method (PDM)
Scheduling is for everyone
     it is a discipline that is
performed by every person,
every day.

 Scheduling is an application of special
    knowledge or judgment of the
 mathematical , physical, or engineering
     sciences to the conception or
   implementation of creative work.
The History
Brief History
      Gantt Charts / Bar Charts
History                     Advantage                 Drawback
Until 1958, the only tool   Simple to construct and   difficult to determine the
for project scheduling      read                      impact of slip on one task
was a bar chart                                       on the rest of the project

Henry Gantt had
developed a complete
notational system
showing progress with
bar chart, thus they
called Gantt charts
Brief History (cont’d)
Arrow Diagrams
History                  Advantage            Drawback
Late 1950s and early     An arrow diagram     Tend to be too
1960s, two methods       help the team        complicated for
of scheduling were       understand the       some teams
developed to             interdependencies of
capture the              the tasks
sequential and
parallel relationships
among project
activities
Brief History (cont’d)
          Critical Path Method (CPM)
History                      Advantages                   Drawbacks
Developed by Du Pont in      Graphical view of the        CPM can be complicated,
1957                         project                      and complexity increases for
                                                          larger projects
 Initially to address the    Predicts the time required
challenge of shutting down   for the project              Does not handling the
chemical plants for                                       scheduling of personnel and
maintenance and restarting   Shows which activities are   resource allocation
it again once maintenance    critical to maintain the
completed                    schedule and which are not   Not always clear and need
                                                          to be calculated carefully
Utilizes the planner’s
knowledge, experience, and                                Estimating activity
instincts in a logical way                                completion times can be
                                                          difficult
Brief History (cont’d)
    Program Evaluation and Review Technique
    (PERT)
History                   Advantages               Drawbacks
Developed by US Navy      It allows for            Complicated chart
and Booze, Allen and      randomness in activity
Hamilton at late 1950’s   completion times         Prediction inaccuracies

                          Has potential of
                          reducing both time and
                          cost required to
                          complete the project
Brief History (cont’d)
Purpose of a
Schedule
Purpose of Schedule

 • Schedules are tool to :




Communicate time         Assess time plan
     plan
Purpose of Schedule (cont’d)

 Benefits:
- Identify the timeframe
- Identify the resource requirement
- identify the key milestones
- Identify the key stakeholder engagement
points
- Assess impact of resource constraints
- Determine your commitment and obstacles
Schedule Development Process
Network-logic




Estimates - times

                                        Project
                           Scheduling   Schedule
Resource capability




Resource capacity
Example Gantt Chart
Logic Diagram &
Networks
Your New Tool
•Defacto standard for scheduling software in
construction industry has been Primavera Project
Planner aka P3

•In 2000, P3 has improved for the use by
manufacturing and IT industries
Your New Tool (cont’d)
•Major differences that distinguish one software
system from another are

   •Ease of input

   •Ease and variety of means of reporting output

   •Features that permit the user to get around some
   of the limitation of the math upon which CPM is
   founded to more perfectly model the real world
Logic Diagrams and Networks

• Effective project plan – address equally the
parameters and activity logic

• Illustrate the inductive and deductive reasoning to
achieve objectives within time given

• Constructed similarly to bar charts – supposing
nothing will go wrong

• Normally accompanied by detailed
questions/checklist
The Logic of the Logic Diagrams
• backbone of traditional implementation of CPM is
graphical model of a project

•Basic component is the arrow

•Each arrow represents one activity in a project

                  activity
        start                finish
The Critical Path
The Critical Path
• The longest path throughout a project
network

• Has no slack (or float) therefore all activities
on the critical path must be completed as
scheduled

• End date will begin to slip – one day for each
day a critical activity is delayed
The Critical Path (cont’d)
• Originally, the critical path considered only
logical dependencies between terminal
elements

•Since then, it has been expanded to allow for
the inclusion of resources related to each
activity , through processes called activity-based
resource assignments and resource leveling
What is CPM really?
The Critical Path (cont’d)

• Also known as Critical Path Analysis (CPA) – is a
mathematically base algorithm for scheduling a set of
project activities

• An important tool for effective project management

• Commonly used with all forms of projects including
construction, software development, research
projects, product development, engineering, and plant
maintenance among others
The Critical Path (cont’d)

• Essentially, to construct a model for a project,
we need:




   WBS            Time (duration)    Dependencies
Terms you have to get used to...
• Event: equivalent to a milestone – indicate the start
and finish dates

• Activity: element of work that must be accomplished

• Duration: total time required

• Effort: amount of work actually performed within the
duration
Calender Scheduling
• Calendar  unit:
- Time measurement for project schedule
- The smallest unit of time
- In hours, days, or weeks, years, months, shifts, even
in minutes

• Take into account for issues such as:
- For non-working time (weekend, holidays)
- Resource constraint
- Change risk
- Cash flow
- Logistics
Precedence Diagram Method (PDM)

• Visual representation technique
• Depicts the activities involved in a project
• Also known as Project Network Diagrams

• PDM helps:
- Communicate
- Identify missing activities
- Identify critical activities
- Create project schedule
Precedence Diagram Method (PDM) (cont’d)

   •Types of Dependencies:

   - Finish to Start (FS) : the predecessor must be
   completed before the successor can start



           Predecessor       FS      Successor
           10 days                   5 days

           Start Day: 1              Start Day: 10
           Finish Day: 10            Finish Day: Start Day + 5
Precedence Diagram Method (PDM) (cont’d)

  •Types of Dependencies:

  - Start to Start (SS) : the successor can start at the
  earliest after the start of its immediate predecessor

         Predecessor
         10 days
   SS
         Successor
         5 days

         Start Day: 1     Start Day: 1
         Finish Day: 10   Finish Day: 5 days after start day
Precedence Diagram Method (PDM) (cont’d)

  •Types of Dependencies:

  -Finish-Finish (FF): the successor will finish at the latest
  after its predecessor finished

                                Predecessor
                                10 days

                                                          FF
                                Successor
                                5 days

           Start Day: 1        Finish Day: 10
           Finish Day: 10      Start Day: 5 days before finish day
Precedence Diagram Method (PDM) (cont’d)

  •Types of Dependencies:

  -Start-Finish (SF) : the successor can finish only after
  the predecessor has started
          Predecessor
          10 days

                        SF



                        Successor
                        5 days
Precedence Diagram Method (PDM) (cont’d)
   Multiple PDM Relationships:
   • Two PDM dependencies/relationships can be used
   together – combination
   • Having both SS and FF relationships in one activity
             SS =5


    15                   15           • B must be finished not later than 10
    Activity A           Activity B   days after A is finished and starts
                                      after 5 days A started i.e. starts at day
                                      10
                     FF=10
Precedence Diagram Method (PDM) (cont’d)
   Lag Time:

   • It’s a technique
   • Occurs when you add time to the start or finish of
   predecessor task
   • Causes a gap in timing
   • E.g.: FS dependency with 5 days lag = the successor
   cannot start until 5 days the predecessor has finished
Precedence Diagram Method (PDM) (cont’d)
   Lead Time:

   • It’s also a technique
   • Created when you subtract time from the start or
   finish of predecessor task
   • Causes overlap between two tasks
   • Allow acceleration of the successor activity
   • E.g.: FS dependency with 5 days lead= the successor
   can start 5 days before the predecessor has finished
Level of Detail
• Should never have too little nor too much detail

• Logical structure with appropriate level of detail is
the key to tracking throughout the project

• Contents information required to manage the project
– only that information

• Rule of thumb:
- 80 hour rule
- if it make sense
Conventional Assumptions

• Activity duration – scheduling done based on
expected or most likely time duration for each activity

• Contingency allowance for activity duration

• Availability of resources

• Schedules to have low cost or ideally lowest cost
Summary


•Network scheduling and PDM are techniques
to assist PM in scheduling – translating project
brief into time schedule
Questions??? 
   He who ask is a fool for five minutes, but he who
                       does not ask is a fool forever.

Contenu connexe

Tendances

Project mangement chp 1 12
Project mangement chp 1 12Project mangement chp 1 12
Project mangement chp 1 12Dreams Design
 
The Project Management Professional (PMP) - Is it For You?
The Project Management Professional (PMP) - Is it For You?The Project Management Professional (PMP) - Is it For You?
The Project Management Professional (PMP) - Is it For You?Carla Fair-Wright
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Bryan.moser
Bryan.moserBryan.moser
Bryan.moserNASAPMC
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidyNASAPMC
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software EngineeringFáber D. Giraldo
 
PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0PhuocNT (Fresher.VN)
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jimNASAPMC
 
Lean planning with Oracle Primavera Cloud
Lean planning  with Oracle Primavera CloudLean planning  with Oracle Primavera Cloud
Lean planning with Oracle Primavera CloudPRMYAZILIM
 
Hyatt.mark
Hyatt.markHyatt.mark
Hyatt.markNASAPMC
 
A Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementA Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementWorkfront
 

Tendances (20)

Pmp an introduction
Pmp an introductionPmp an introduction
Pmp an introduction
 
Spm lecture-3
Spm lecture-3Spm lecture-3
Spm lecture-3
 
Project mangement chp 1 12
Project mangement chp 1 12Project mangement chp 1 12
Project mangement chp 1 12
 
Spm lecture-2
Spm lecture-2Spm lecture-2
Spm lecture-2
 
The Project Management Professional (PMP) - Is it For You?
The Project Management Professional (PMP) - Is it For You?The Project Management Professional (PMP) - Is it For You?
The Project Management Professional (PMP) - Is it For You?
 
Basic Software Engineering v1.0
Basic Software Engineering v1.0Basic Software Engineering v1.0
Basic Software Engineering v1.0
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Bryan.moser
Bryan.moserBryan.moser
Bryan.moser
 
4 Scheduling Monitoring
4 Scheduling Monitoring4 Scheduling Monitoring
4 Scheduling Monitoring
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 
Project managemen concept
Project managemen conceptProject managemen concept
Project managemen concept
 
Rita's Process Chart
Rita's Process ChartRita's Process Chart
Rita's Process Chart
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software Engineering
 
3. project time management
3. project time management3. project time management
3. project time management
 
PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
 
Lean planning with Oracle Primavera Cloud
Lean planning  with Oracle Primavera CloudLean planning  with Oracle Primavera Cloud
Lean planning with Oracle Primavera Cloud
 
Hyatt.mark
Hyatt.markHyatt.mark
Hyatt.mark
 
Software project managment
Software project managmentSoftware project managment
Software project managment
 
A Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementA Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project Management
 

En vedette

Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDMShaiful Amri Mansur
 
Critical Path Analysis Notes
Critical Path Analysis NotesCritical Path Analysis Notes
Critical Path Analysis Notesmattbentley34
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
Constructing a network diagram
Constructing a network diagramConstructing a network diagram
Constructing a network diagramnelramlawy
 
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacksglibson rojer
 
Precedence Diagram Method 2
Precedence Diagram Method 2Precedence Diagram Method 2
Precedence Diagram Method 2Nurul Angreliany
 
Lesson02_new
Lesson02_newLesson02_new
Lesson02_newshengvn
 
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...CA Technologies
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpasyamputra
 
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)Ron Gill
 
PDM - Precedence Diagram Method
PDM - Precedence Diagram MethodPDM - Precedence Diagram Method
PDM - Precedence Diagram Methodphantai24
 
Integrated Marketing Communications
Integrated Marketing CommunicationsIntegrated Marketing Communications
Integrated Marketing CommunicationsJeff Hilton
 
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgePMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgeSaket Bansal
 
Session 4 critical path method upload
Session 4   critical path method uploadSession 4   critical path method upload
Session 4 critical path method uploadArun
 
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisLesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisHoly Angel University
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysissimu_mihai
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path AnalysisDavid Zaki
 
Year 12 Maths A Textbook - Chapter 8
Year 12 Maths A Textbook - Chapter 8Year 12 Maths A Textbook - Chapter 8
Year 12 Maths A Textbook - Chapter 8westy67968
 

En vedette (20)

Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDM
 
Critical Path Analysis Notes
Critical Path Analysis NotesCritical Path Analysis Notes
Critical Path Analysis Notes
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Constructing a network diagram
Constructing a network diagramConstructing a network diagram
Constructing a network diagram
 
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacks
 
Precedence Diagram Method 2
Precedence Diagram Method 2Precedence Diagram Method 2
Precedence Diagram Method 2
 
Lesson02_new
Lesson02_newLesson02_new
Lesson02_new
 
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpa
 
Critical Path Analysis for a New Product Release
Critical Path Analysis for a New Product ReleaseCritical Path Analysis for a New Product Release
Critical Path Analysis for a New Product Release
 
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
 
PDM - Precedence Diagram Method
PDM - Precedence Diagram MethodPDM - Precedence Diagram Method
PDM - Precedence Diagram Method
 
Network Anaysis_ critical path methods
Network Anaysis_ critical path methodsNetwork Anaysis_ critical path methods
Network Anaysis_ critical path methods
 
Integrated Marketing Communications
Integrated Marketing CommunicationsIntegrated Marketing Communications
Integrated Marketing Communications
 
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgePMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
 
Session 4 critical path method upload
Session 4   critical path method uploadSession 4   critical path method upload
Session 4 critical path method upload
 
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisLesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Year 12 Maths A Textbook - Chapter 8
Year 12 Maths A Textbook - Chapter 8Year 12 Maths A Textbook - Chapter 8
Year 12 Maths A Textbook - Chapter 8
 

Similaire à Bpp 3213 lecture 2

Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.pptssusere57332
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path methodPrathima Girish
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptxPigPug1
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.pptMdHelalHossain6
 
AWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewAWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewDanielle Murphy
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling DiagramsSaqib Raza
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxMdSabujHossen2
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 

Similaire à Bpp 3213 lecture 2 (20)

Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path method
 
06 project time management
06  project time management06  project time management
06 project time management
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptx
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
08 ch06
08 ch0608 ch06
08 ch06
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Intro to PM.ppt
Intro to PM.pptIntro to PM.ppt
Intro to PM.ppt
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.ppt
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
AWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewAWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overview
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 

Plus de Saddan Juhari

Wk 4 technology life cycle
Wk 4   technology life cycleWk 4   technology life cycle
Wk 4 technology life cycleSaddan Juhari
 
Wk 3 critical factors in managing technology
Wk 3   critical factors in managing technologyWk 3   critical factors in managing technology
Wk 3 critical factors in managing technologySaddan Juhari
 
Wk 2 role of technology
Wk 2   role of technologyWk 2   role of technology
Wk 2 role of technologySaddan Juhari
 
Wk 1 technology mgmt.
Wk 1   technology mgmt.Wk 1   technology mgmt.
Wk 1 technology mgmt.Saddan Juhari
 
Chapter 4 balancing stakeholders
Chapter 4   balancing stakeholdersChapter 4   balancing stakeholders
Chapter 4 balancing stakeholdersSaddan Juhari
 
Chapter 2b project stakeholder management process
Chapter 2b   project stakeholder management processChapter 2b   project stakeholder management process
Chapter 2b project stakeholder management processSaddan Juhari
 
Chapter 2a project stakeholder management process
Chapter 2a   project stakeholder management processChapter 2a   project stakeholder management process
Chapter 2a project stakeholder management processSaddan Juhari
 
Chapter 1 -_intro_to_project_stakeholder_management[1]
Chapter 1 -_intro_to_project_stakeholder_management[1]Chapter 1 -_intro_to_project_stakeholder_management[1]
Chapter 1 -_intro_to_project_stakeholder_management[1]Saddan Juhari
 

Plus de Saddan Juhari (8)

Wk 4 technology life cycle
Wk 4   technology life cycleWk 4   technology life cycle
Wk 4 technology life cycle
 
Wk 3 critical factors in managing technology
Wk 3   critical factors in managing technologyWk 3   critical factors in managing technology
Wk 3 critical factors in managing technology
 
Wk 2 role of technology
Wk 2   role of technologyWk 2   role of technology
Wk 2 role of technology
 
Wk 1 technology mgmt.
Wk 1   technology mgmt.Wk 1   technology mgmt.
Wk 1 technology mgmt.
 
Chapter 4 balancing stakeholders
Chapter 4   balancing stakeholdersChapter 4   balancing stakeholders
Chapter 4 balancing stakeholders
 
Chapter 2b project stakeholder management process
Chapter 2b   project stakeholder management processChapter 2b   project stakeholder management process
Chapter 2b project stakeholder management process
 
Chapter 2a project stakeholder management process
Chapter 2a   project stakeholder management processChapter 2a   project stakeholder management process
Chapter 2a project stakeholder management process
 
Chapter 1 -_intro_to_project_stakeholder_management[1]
Chapter 1 -_intro_to_project_stakeholder_management[1]Chapter 1 -_intro_to_project_stakeholder_management[1]
Chapter 1 -_intro_to_project_stakeholder_management[1]
 

Bpp 3213 lecture 2

  • 1. BPP 3213 PROJECT ESTIMATION AND SCHEDULING Lecture 2 Network Scheduling and Precedence Diagram Method (PDM) Oct, 2012 Faculty of Technology Universiti Malaysia Pahang Jane Doe & Jane Doe
  • 2. RECAP Organization Structure Challenges Project life cycle
  • 3. Purpose of this lecture To better understand: • brief history of scheduling techniques • network scheduling and logic diagrams • the importance of Critical Path Method (CPM) • the fundamental elements of precedence diagram method (PDM)
  • 4. Scheduling is for everyone it is a discipline that is performed by every person, every day. Scheduling is an application of special knowledge or judgment of the mathematical , physical, or engineering sciences to the conception or implementation of creative work.
  • 6. Brief History Gantt Charts / Bar Charts History Advantage Drawback Until 1958, the only tool Simple to construct and difficult to determine the for project scheduling read impact of slip on one task was a bar chart on the rest of the project Henry Gantt had developed a complete notational system showing progress with bar chart, thus they called Gantt charts
  • 7. Brief History (cont’d) Arrow Diagrams History Advantage Drawback Late 1950s and early An arrow diagram Tend to be too 1960s, two methods help the team complicated for of scheduling were understand the some teams developed to interdependencies of capture the the tasks sequential and parallel relationships among project activities
  • 8. Brief History (cont’d) Critical Path Method (CPM) History Advantages Drawbacks Developed by Du Pont in Graphical view of the CPM can be complicated, 1957 project and complexity increases for larger projects Initially to address the Predicts the time required challenge of shutting down for the project Does not handling the chemical plants for scheduling of personnel and maintenance and restarting Shows which activities are resource allocation it again once maintenance critical to maintain the completed schedule and which are not Not always clear and need to be calculated carefully Utilizes the planner’s knowledge, experience, and Estimating activity instincts in a logical way completion times can be difficult
  • 9. Brief History (cont’d) Program Evaluation and Review Technique (PERT) History Advantages Drawbacks Developed by US Navy It allows for Complicated chart and Booze, Allen and randomness in activity Hamilton at late 1950’s completion times Prediction inaccuracies Has potential of reducing both time and cost required to complete the project
  • 12. Purpose of Schedule • Schedules are tool to : Communicate time Assess time plan plan
  • 13. Purpose of Schedule (cont’d) Benefits: - Identify the timeframe - Identify the resource requirement - identify the key milestones - Identify the key stakeholder engagement points - Assess impact of resource constraints - Determine your commitment and obstacles
  • 14. Schedule Development Process Network-logic Estimates - times Project Scheduling Schedule Resource capability Resource capacity
  • 17. Your New Tool •Defacto standard for scheduling software in construction industry has been Primavera Project Planner aka P3 •In 2000, P3 has improved for the use by manufacturing and IT industries
  • 18. Your New Tool (cont’d) •Major differences that distinguish one software system from another are •Ease of input •Ease and variety of means of reporting output •Features that permit the user to get around some of the limitation of the math upon which CPM is founded to more perfectly model the real world
  • 19. Logic Diagrams and Networks • Effective project plan – address equally the parameters and activity logic • Illustrate the inductive and deductive reasoning to achieve objectives within time given • Constructed similarly to bar charts – supposing nothing will go wrong • Normally accompanied by detailed questions/checklist
  • 20. The Logic of the Logic Diagrams • backbone of traditional implementation of CPM is graphical model of a project •Basic component is the arrow •Each arrow represents one activity in a project activity start finish
  • 22. The Critical Path • The longest path throughout a project network • Has no slack (or float) therefore all activities on the critical path must be completed as scheduled • End date will begin to slip – one day for each day a critical activity is delayed
  • 23. The Critical Path (cont’d) • Originally, the critical path considered only logical dependencies between terminal elements •Since then, it has been expanded to allow for the inclusion of resources related to each activity , through processes called activity-based resource assignments and resource leveling
  • 24. What is CPM really?
  • 25. The Critical Path (cont’d) • Also known as Critical Path Analysis (CPA) – is a mathematically base algorithm for scheduling a set of project activities • An important tool for effective project management • Commonly used with all forms of projects including construction, software development, research projects, product development, engineering, and plant maintenance among others
  • 26. The Critical Path (cont’d) • Essentially, to construct a model for a project, we need: WBS Time (duration) Dependencies
  • 27. Terms you have to get used to... • Event: equivalent to a milestone – indicate the start and finish dates • Activity: element of work that must be accomplished • Duration: total time required • Effort: amount of work actually performed within the duration
  • 28. Calender Scheduling • Calendar unit: - Time measurement for project schedule - The smallest unit of time - In hours, days, or weeks, years, months, shifts, even in minutes • Take into account for issues such as: - For non-working time (weekend, holidays) - Resource constraint - Change risk - Cash flow - Logistics
  • 29. Precedence Diagram Method (PDM) • Visual representation technique • Depicts the activities involved in a project • Also known as Project Network Diagrams • PDM helps: - Communicate - Identify missing activities - Identify critical activities - Create project schedule
  • 30. Precedence Diagram Method (PDM) (cont’d) •Types of Dependencies: - Finish to Start (FS) : the predecessor must be completed before the successor can start Predecessor FS Successor 10 days 5 days Start Day: 1 Start Day: 10 Finish Day: 10 Finish Day: Start Day + 5
  • 31. Precedence Diagram Method (PDM) (cont’d) •Types of Dependencies: - Start to Start (SS) : the successor can start at the earliest after the start of its immediate predecessor Predecessor 10 days SS Successor 5 days Start Day: 1 Start Day: 1 Finish Day: 10 Finish Day: 5 days after start day
  • 32. Precedence Diagram Method (PDM) (cont’d) •Types of Dependencies: -Finish-Finish (FF): the successor will finish at the latest after its predecessor finished Predecessor 10 days FF Successor 5 days Start Day: 1 Finish Day: 10 Finish Day: 10 Start Day: 5 days before finish day
  • 33. Precedence Diagram Method (PDM) (cont’d) •Types of Dependencies: -Start-Finish (SF) : the successor can finish only after the predecessor has started Predecessor 10 days SF Successor 5 days
  • 34. Precedence Diagram Method (PDM) (cont’d) Multiple PDM Relationships: • Two PDM dependencies/relationships can be used together – combination • Having both SS and FF relationships in one activity SS =5 15 15 • B must be finished not later than 10 Activity A Activity B days after A is finished and starts after 5 days A started i.e. starts at day 10 FF=10
  • 35. Precedence Diagram Method (PDM) (cont’d) Lag Time: • It’s a technique • Occurs when you add time to the start or finish of predecessor task • Causes a gap in timing • E.g.: FS dependency with 5 days lag = the successor cannot start until 5 days the predecessor has finished
  • 36. Precedence Diagram Method (PDM) (cont’d) Lead Time: • It’s also a technique • Created when you subtract time from the start or finish of predecessor task • Causes overlap between two tasks • Allow acceleration of the successor activity • E.g.: FS dependency with 5 days lead= the successor can start 5 days before the predecessor has finished
  • 37. Level of Detail • Should never have too little nor too much detail • Logical structure with appropriate level of detail is the key to tracking throughout the project • Contents information required to manage the project – only that information • Rule of thumb: - 80 hour rule - if it make sense
  • 38. Conventional Assumptions • Activity duration – scheduling done based on expected or most likely time duration for each activity • Contingency allowance for activity duration • Availability of resources • Schedules to have low cost or ideally lowest cost
  • 39. Summary •Network scheduling and PDM are techniques to assist PM in scheduling – translating project brief into time schedule
  • 40. Questions???  He who ask is a fool for five minutes, but he who does not ask is a fool forever.

Notes de l'éditeur

  1. Scheduling is a tool used to manage jobs and should not be considered as the primary one in project management. Project management is not just about schedulingGantt charts remain the best tool to use for communicating to team members about what they need to do within given time framesBar charts do not show the interdependencies of the work thus the serious drawback.PERT methods use probability techniques, whereas CPM does not. Meaning: PERT enable PM to calculate the probability that an activity will be completed by a certain time whereas CPM unable to do that.
  2. Communicating tool: putting project brief into schedules against timeAssess time plan: possibilities of delay e.g. client sign off, force majeure Resource constraint: availability of people (on leave??), availability of plants/machines (set priority if sharing plants and machines with other project)Determine your commitment: make sure we have enough time to resolve the issues in the schedule
  3. Communicating tool: putting project brief into schedules against timeAssess time plan: possibilities of delay e.g. client sign off, force majeure Resource constraint: availability of people (on leave??), availability of plants/machines (set priority if sharing plants and machines with other project)Determine your commitment: make sure we have enough time to resolve the issues in the schedule
  4. The network provides the logic for the order in which activities need to be carried outTime estimates show the time that the project requires for completionResource capability is the set of tasks that the resources available to the project manager can reasonably undertake. Often referred to as resource pool.Resource capacity depends on the volume of resources available and issues such as resource calendar. E.g. machine utilisation is not to be taken into the same consideration with human.
  5. Gantt chart becomes cluttered when the number of activities and logical relationship increase inductive reasoning takes events and make generalizationsdeductive reasoning arrives at specific conclusion based on generalization
  6. Gantt chart becomes cluttered when the number of activities and logical relationship increase inductive reasoning takes events and make generalizationsdeductive reasoning arrives at specific conclusion based on generalization
  7. Gantt chart becomes cluttered when the number of activities and logical relationship increase inductive reasoning takes events and make generalizationsdeductive reasoning arrives at specific conclusion based on generalization
  8. Gantt chart becomes cluttered when the number of activities and logical relationship increase inductive reasoning takes events and make generalizationsdeductive reasoning arrives at specific conclusion based on generalization
  9. Slack time: time differential between the scheduled completion date and the required date to meet critical pathSlack: the difference between the latest allowable date and the earliest expected date. Allowable deviation between when an activity must take place at the latest and when it can take place at the earliest LS-ES, LF-EF
  10. Finish-Start is the most commonly used dependencyDefault setting for MS Project
  11. Finish-Start is the most commonly used dependency
  12. The predecessor is the task that determines the scheduling for the successorUsed to determine the task prior to but dependent on another taske.g: new theatre building n selling ticket tasks