SlideShare une entreprise Scribd logo
1  sur  16
MINI PROJECT ON
AUTO-RECLOSING
PRESENTED BY
K.Sandeep (10RC1A0228)
Patan. Rafi(10RC1A0247)
B.Shiva (10RC1A0203)
M.Uday teja(10RC1A0232)
Under the esteemed guidance of
Mr.R.Laveen,M.Tech(Asst.Prof).
1
AUTO-RECLOSING
• it is placed on over head transmission line and nearer to the
CB .
• It is also one of the protective relay.
2
What is
Auto – Reclosing ?
3
Introduction to auto-reclosing scheme
4
Types Of Faults
• Transient Faults
• Semi Permanent faults
• Permanent Faults
Utility Substation Customers
5
6
STEPS TO BE FOLLOWED IN AUTORECLOSING
Visual Check
Check of the
Power Supply
Test of the
Auto-re-closure settings
Functional Testing
(involving operation of
Protective Relays
& Circuit Breaker(s)
INSTALLATION
OPERATION
Scheme Of Operation
• Live bus Dead Line Charging
• Other end closing under synchronism check relay
• Live bus Live line charging
7
Types of Auto Reclosing
1. Medium voltage auto-reclose
• Aim of continuity of supply
• the obvious advantages are continuous supply except for short
duration when tripping and re-closure operations are being performed.
• high speed protection decreases the amount of damage incurred and
thus increases the probability of auto reclosure.
2. High voltage auto-reclose
• main considerations are of stability and synchronizing.
• the fault levels associated are extremely high.
• High speed re-closure in high voltage circuits improves the stability
to a considerable extent on single-circuit ties.
FACTORS TO BE CONSIDERED FOR
AUTO RECLOSING SYSTEM
• Protection Characteristics
• De- Ionization of Fault Arc
• Circuit Breaker Characteristics
• Reclaim Time
• Number of Shots
9
SINGLE PHASE AUTO – RECLOSING
ADVANTAGES:-
•Maintenance of System Integrity
• Reduced switching overvoltage due to reclosing
• Reduced shock to generators.
• Sudden changes in mechanical output are less
• Longer De – ionization time
DISADVANTAGE:-
10
1. Densely interconnected systems.

Where the Loss of a single line is unlikely to
cause loss of synchronism between two ends
2. Dead Time is allowed to be long enough for any
power swings due to fault and tripping allowed
to decay before reclosing

a) Less shock to system than with high speed
A/R
b) Problems of arc de – ionization times, and
circuit breaker operating characterstics are
eliminated.
Delayed Auto-Reclose Application
11
Operating feature of Auto reclosing schemes
• Dead Timer
• Anti Pumping Devices
• Reclaim timer
• CB Lockout
• Manual Closing
• Multi Shot Scheme
12
Auto - Reclose Blocking
• Receipt of transfer Trip
• Manual Trip
• Breaker failure
• Three phase Fault
• Faults On Buses
• Under frequency/ Under voltage load shedding trips
13
Benefits Of Auto - Reclosing
• Minimizing the interruption of supply.
• Maintenance of system stability and Synchronism.
• Minimum Outage and least expenditure of manpower.
• Ability to run substation unattended.
14
CONCLUSION
• Fast clearing of EHV faults is essential to
maintain power quality in an area, because
events on the EHV system affect the
underlying transmission and distribution
systems. Benefits of successful high speed
reclosing on EHV overhead transmission lines
are: improved system stability, reducing the
duration of fault arc, respectively disturbance
time, and economics in system design.
15
Thank you
16

Contenu connexe

Tendances

Protective relay
Protective relay Protective relay
Protective relay Uday Wankar
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & MaintenanceHimansu Pradhan
 
Introduction to power system analysis
Introduction to power system analysisIntroduction to power system analysis
Introduction to power system analysisRevathi Subramaniam
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devicesRahul Aman
 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptxMuhd Hafizi Idris
 
Basics of overcurrent protection
Basics of overcurrent protectionBasics of overcurrent protection
Basics of overcurrent protectionSalim Palayi
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONPower System Operation
 
Power system protection
Power system protectionPower system protection
Power system protectionAnu Priya
 
Power System Protection course - Part I
Power System Protection course - Part IPower System Protection course - Part I
Power System Protection course - Part ISlides Hub
 
Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basicsRajan Singh Tanwar
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power systemsneh pratap singh
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Deviceskhemraj298
 
Circuit Breaker : Types
Circuit Breaker : TypesCircuit Breaker : Types
Circuit Breaker : TypesRidwanul Hoque
 
Micro computer control of dc drive
Micro computer control of dc driveMicro computer control of dc drive
Micro computer control of dc driveraviarmugam
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1anuphowlader1
 
Relays and its types - complete guide
Relays and its types - complete guideRelays and its types - complete guide
Relays and its types - complete guideSlides Hub
 

Tendances (20)

Load flow study
Load flow studyLoad flow study
Load flow study
 
Protective relay
Protective relay Protective relay
Protective relay
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Introduction to power system analysis
Introduction to power system analysisIntroduction to power system analysis
Introduction to power system analysis
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devices
 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
 
Types of relay
Types of relayTypes of relay
Types of relay
 
Basics of overcurrent protection
Basics of overcurrent protectionBasics of overcurrent protection
Basics of overcurrent protection
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTION
 
Distribution transformer
Distribution transformerDistribution transformer
Distribution transformer
 
Power system protection
Power system protectionPower system protection
Power system protection
 
Power System Protection course - Part I
Power System Protection course - Part IPower System Protection course - Part I
Power System Protection course - Part I
 
Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basics
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power system
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Devices
 
Circuit Breaker : Types
Circuit Breaker : TypesCircuit Breaker : Types
Circuit Breaker : Types
 
Micro computer control of dc drive
Micro computer control of dc driveMicro computer control of dc drive
Micro computer control of dc drive
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
 
Relays and its types - complete guide
Relays and its types - complete guideRelays and its types - complete guide
Relays and its types - complete guide
 
EXCITATION SYSTEMS
EXCITATION SYSTEMSEXCITATION SYSTEMS
EXCITATION SYSTEMS
 

Similaire à auto-reclosure

Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"michaeljmack
 
Power_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfPower_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfYogeshGairola2
 
Auto Reclose Testing
Auto Reclose TestingAuto Reclose Testing
Auto Reclose Testingriam
 
Auto Reclose Function of Distance Relays
Auto Reclose Function of Distance RelaysAuto Reclose Function of Distance Relays
Auto Reclose Function of Distance RelaysToshaliMohapatra
 
Fundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based RelaysFundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based Relaysmichaeljmack
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2Himmelstern
 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodinationmichaeljmack
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordinationmichaeljmack
 
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptx
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptxOhiri-Principles-and-Philosophy-of-Protective-Relaying.pptx
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptxGodwin308555
 
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisShort-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisPower System Operation
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalNihal Shiroya
 
Testing of Circuit Breakers.pptx
Testing of Circuit Breakers.pptxTesting of Circuit Breakers.pptx
Testing of Circuit Breakers.pptxTafhim Bin Nasir
 
OneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterOneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterPaul Plavicheanu
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakersKabilesh K
 
Ieee transfer schemes for M-T-M distribution systems
Ieee transfer schemes for M-T-M distribution systemsIeee transfer schemes for M-T-M distribution systems
Ieee transfer schemes for M-T-M distribution systemsVincent Wedelich, PE MBA
 

Similaire à auto-reclosure (20)

Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"
 
Power_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfPower_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdf
 
Auto Reclose Testing
Auto Reclose TestingAuto Reclose Testing
Auto Reclose Testing
 
Auto Reclose Function of Distance Relays
Auto Reclose Function of Distance RelaysAuto Reclose Function of Distance Relays
Auto Reclose Function of Distance Relays
 
Fundamentals of Microprocessor-based Relaying
Fundamentals of Microprocessor-based RelayingFundamentals of Microprocessor-based Relaying
Fundamentals of Microprocessor-based Relaying
 
Fundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based RelaysFundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based Relays
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2
 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodination
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordination
 
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptx
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptxOhiri-Principles-and-Philosophy-of-Protective-Relaying.pptx
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptx
 
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisShort-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash Analysis
 
HV CB testing.pdf
HV CB testing.pdfHV CB testing.pdf
HV CB testing.pdf
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
Testing of Circuit Breakers.pptx
Testing of Circuit Breakers.pptxTesting of Circuit Breakers.pptx
Testing of Circuit Breakers.pptx
 
OneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterOneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft Starter
 
Auto reclosers
Auto reclosersAuto reclosers
Auto reclosers
 
Vcb ppt.
Vcb ppt.Vcb ppt.
Vcb ppt.
 
IEEE Blue Book
IEEE Blue BookIEEE Blue Book
IEEE Blue Book
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 
Ieee transfer schemes for M-T-M distribution systems
Ieee transfer schemes for M-T-M distribution systemsIeee transfer schemes for M-T-M distribution systems
Ieee transfer schemes for M-T-M distribution systems
 

Dernier

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 

Dernier (20)

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 

auto-reclosure

  • 1. MINI PROJECT ON AUTO-RECLOSING PRESENTED BY K.Sandeep (10RC1A0228) Patan. Rafi(10RC1A0247) B.Shiva (10RC1A0203) M.Uday teja(10RC1A0232) Under the esteemed guidance of Mr.R.Laveen,M.Tech(Asst.Prof). 1
  • 2. AUTO-RECLOSING • it is placed on over head transmission line and nearer to the CB . • It is also one of the protective relay. 2
  • 3. What is Auto – Reclosing ? 3
  • 5. Types Of Faults • Transient Faults • Semi Permanent faults • Permanent Faults Utility Substation Customers 5
  • 6. 6 STEPS TO BE FOLLOWED IN AUTORECLOSING Visual Check Check of the Power Supply Test of the Auto-re-closure settings Functional Testing (involving operation of Protective Relays & Circuit Breaker(s) INSTALLATION OPERATION
  • 7. Scheme Of Operation • Live bus Dead Line Charging • Other end closing under synchronism check relay • Live bus Live line charging 7
  • 8. Types of Auto Reclosing 1. Medium voltage auto-reclose • Aim of continuity of supply • the obvious advantages are continuous supply except for short duration when tripping and re-closure operations are being performed. • high speed protection decreases the amount of damage incurred and thus increases the probability of auto reclosure. 2. High voltage auto-reclose • main considerations are of stability and synchronizing. • the fault levels associated are extremely high. • High speed re-closure in high voltage circuits improves the stability to a considerable extent on single-circuit ties.
  • 9. FACTORS TO BE CONSIDERED FOR AUTO RECLOSING SYSTEM • Protection Characteristics • De- Ionization of Fault Arc • Circuit Breaker Characteristics • Reclaim Time • Number of Shots 9
  • 10. SINGLE PHASE AUTO – RECLOSING ADVANTAGES:- •Maintenance of System Integrity • Reduced switching overvoltage due to reclosing • Reduced shock to generators. • Sudden changes in mechanical output are less • Longer De – ionization time DISADVANTAGE:- 10
  • 11. 1. Densely interconnected systems.  Where the Loss of a single line is unlikely to cause loss of synchronism between two ends 2. Dead Time is allowed to be long enough for any power swings due to fault and tripping allowed to decay before reclosing  a) Less shock to system than with high speed A/R b) Problems of arc de – ionization times, and circuit breaker operating characterstics are eliminated. Delayed Auto-Reclose Application 11
  • 12. Operating feature of Auto reclosing schemes • Dead Timer • Anti Pumping Devices • Reclaim timer • CB Lockout • Manual Closing • Multi Shot Scheme 12
  • 13. Auto - Reclose Blocking • Receipt of transfer Trip • Manual Trip • Breaker failure • Three phase Fault • Faults On Buses • Under frequency/ Under voltage load shedding trips 13
  • 14. Benefits Of Auto - Reclosing • Minimizing the interruption of supply. • Maintenance of system stability and Synchronism. • Minimum Outage and least expenditure of manpower. • Ability to run substation unattended. 14
  • 15. CONCLUSION • Fast clearing of EHV faults is essential to maintain power quality in an area, because events on the EHV system affect the underlying transmission and distribution systems. Benefits of successful high speed reclosing on EHV overhead transmission lines are: improved system stability, reducing the duration of fault arc, respectively disturbance time, and economics in system design. 15