SlideShare une entreprise Scribd logo
1  sur  5
Télécharger pour lire hors ligne
Checklist for a Design & Build Project
The 2011-2012 court decisions in Trebor Bassett v ADT Fire and Security1 analysed in detail how two
partners carried out pre-contract processes for the design and installation of equipment. The
judgments are full of tips for those involved in high risk or D&B projects. It should also act as a
warning as the claim for £110m arose out of a contract for the design and supply of equipment
costing a mere £9,000.
The tips, quotes and lessons have been collated into a series of recommendations for partners
entering into contracts for construction projects, particularly those involving hazardous processes.

Risk Analysis
You Should:



















Assess and appreciate the risk of each project separately: in this case, the buyer “never fully
appreciated the increased risk” that the project would bring. [55]2
Assess “the risks before the project workscope was defined.” [77]
Avoid preparing “a specification based on a 'minimum spend'” which decision could be
exacerbated by “a refusal to consider any recommendation which might add to the workscope,
even if they provided the only way of truly controlling the risk.” [77]
Never assume that a similar system is appropriate for a similar project. {21}
Ascertain or communicate any history of risk events occurring on similar projects, especially to
the designer of a system intended to protect or minimise the consequences of those risk events.
Your designer should appreciate all significant risks. [140] {21}
Carry out a proper technical appraisal of the risks, ideally in conjunction with the supplier of
relevant risk protection equipment. [75]
Identify precisely the risks and hazards on each project “and/or how those risks could be best
dealt with.”3 This should be done in detail. [61, 367]
Make sure one person within your organisation ‘owns the risk.’ Often this is the project manager
who is responsible for “recognising and then minimising all the risks created by that project.”62]
Check all assumptions made for significant risk factors (i.e. those with potentially catastrophic
consequences). “This erroneous assumption gave rise to the conclusion that there was no health
and safety issue; it follows that, if the [buyers] had bothered to check the as-built drawings, they
would have seen that the assumption was wrong, and that therefore there was a major health
and safety issue.”[88]4
Take advice from risk professionals, but make sure their advice is based on evidence and not
assumptions. [68-69]
Ensure all recommendations from risk managers are properly followed through: “one significant
recommendation made by the [buyer’s own risk managers]…was not followed” and that none
are ignored. [7, 36]
Where the best option to protect against a risk event is not adopted, ensure that the alternative
means of protecting against risk events are adopted. [72]
Keep records of meetings with Fire Officers. [121]
Not “decide what to do and then assess the risk” but the other way round. [77-78]

Page 1© 500 Word Contracts, 2014




Not determine the significance of risks on the “value of the proposed works”5 but on “the value
of the building and equipment at risk if those works were not properly specified and designed.”
[85]
Not assume that Certification by the Fire Brigade is sufficient to establish risks have been
managed and the process is not hazardous, such as “an industrial process involving naked
flames.” [44]

Specifying the Works
You Should:









Decide your objective – you cannot have both high quality, low price and tight timescales: “The
timing was very tight… it was imperative that the new lines were up and running by Christmas
2003, in order to meet the surge in demand for popcorn, particularly for the cinema trade, over
the Christmas period. This timetable could not be changed.” But the same project was costed “on
a requirement of minimum spend to introduce a safe system of work.” [54, 58]
Agree what design responsibility each partner will have: “the most important element of the
workscope was that done by the [sellers’] designers: the decision to use a particular piece of
equipment in a particular place, with the intention of achieving a particular effect.” [215]
Specify the works based on the needs of the project, not on existing experience. [92-96]
Ensure the partners work together on producing the design and specification: “the [buyers’]
haphazard approach at the outset was not picked by the [sellers], and was compounded by the
[sellers’] rather cavalier attitude to what they were being asked to do.” [113]
Avoid using standard form specifications for bespoke projects with significant risks. [107]

Specifying Standards of Quality
You should:
 Understand the general standards of quality. A contractor providing design services “will not
generally owe a higher obligation than the duty to use reasonable skill and care.” If you want a
higher standard, you will have to say so, clearly. [217]

 Be specific if you want quality guaranteed: “one would need to identify with much more
specificity precisely what it is that [the sellers were] alleged to have been impliedly asked to do
and, in consequence, what result it is that it is said to have undertaken to bring about.” {56}

 State the standards you require. If your contract states ‘good quality’, the court will not imply a


term what the goods will be of satisfactory quality.6 [218-220]
Ensure, in a contract for the sale of goods, where you want to rely on an implied obligation as to
fitness for purpose, that you:
o State your particular purpose “must have been made clear… At no stage did the [buyers]
ever indicate any particular purpose” for which the system was being acquired; [223224]7
o rely on the sellers’ advice or expertise; in the case, the buyers “did not rely on the
defendant's skill or judgment at all.” [226]

Page 2© 500 Word Contracts, 2014





Set out the standards on quality in the specification: “The specification, with its reference to
British Standard 5306 and other assumptions and requirements, formed the benchmark against
which the [sellers’] obligations were to be performed.” [264]
Understand what any relevant British Standard requires – often it is more a set of
recommendations, which is not sufficient for a guarantee or warranty. [243]
Set out any promise or guarantee in clear words: “[T]he fact that the system had been designed
‘to suit the specific requirements of the risks to be protected’ (to use the words of the
specification) does not mean that the system was guaranteed to eliminate those risks every time.
It was designed, manufactured and installed with those risks in mind, but the obligation as to
design was to take reasonable skill and care and there was nothing in these words to impose
upon the defendant a more onerous obligation. A design intended 'to suit the specific
requirements of the risks' may or may not be done with reasonable skill and care, but it was not a
promise that the design would eliminate all risks. A promise that a particular risk will be
eliminated must say so in clear terms. The specification did not do so.” [242]

Designing and Commissioning the Works
As a designer/D&B contractor, you should:












Use correct and detailed drawings in order to prepare your design. In this case, “the working
documents should have identified the relevant hazards.” [105,111]
Seek “as much information” as you can. Do not design “on assumptions [but]… find out the facts
for itself.” [509]
As your first step, “identify the risks which were to be protected and to design a system that
suited the specific requirements of the risks to be protected.” [510]
Ensure, as “a specialist was providing a design, and then manufacturing and installing the
product so designed…that there was proper communication between the designer and the
installer.” [511]
Ensure any checks of design assumptions by the installer or buyers are followed up: “if the
design engineer worked from drawings, he would need the installing engineer to check that his
design assumptions were well-founded.” [112-113, 138]
Ensure your design is based on detailed accurate information, reviewed and checked. [113]
Obtain good information and corroborate with your partners, to avoid: “the patently inadequate
information which the [sellers] had, and the difference of approach between its two designers
which was its probable result, demonstrates a fundamental flaw at the heart of the [sellers’]
work on this contract.” [140]
Do more than just check “the system had been installed in accordance with the drawings” where
the drawings are inadequate. [145]

Agreeing the Terms and Conditions
You Should:


Keep records to show that previous contracts have been agreed on the same basis, if you want
to establish a course of dealing, and that your T&C are incorporated as a result. [161]

Page 3© 500 Word Contracts, 2014





Ask for a copy of any T&C referred to on any contract document, especially where it states
“already supplied… Additional copies available on request”. You must also respond to any terms
with which you disagree. {27}
Understand the rules relating to incorporation of terms and conditions. 8 [172-173]
Ensure your terms and conditions are sensible and certain: a clause limiting liability to a multiple
of an annual service charge is not effective in a contract for the provision of goods and services.
Such a limit “was meaningless, because the limitation was calculable only by reference to the
value of a non-existent contract. That was too uncertain to be enforceable.” [197-198]

Training Staff
You Should:














Use risk identification processes to establish standard operating procedures. [367]
Create clear safety procedures and train operatives accordingly. [367]
Ensure all relevant staff are given a detailed demonstration of all relevant systems as part of the
commissioning or post-commissioning follow-up. Do not leave it to one person. [270-286]
Ensure all operatives are aware of any safety features or procedures on newly installed or
altered equipment: “very few of the operatives in the 'oil pop' popcorn production area were
aware that the CO2 suppression system protecting the elevator and the hopper could be
manually activated, and even fewer knew how that manual activation was to be triggered.”[8]
Ensure the procedures approved by managers are appropriate. [10]
Ensure there is a satisfactory and safe working environment for operatives, and a satisfactory
system to detect and respond to risk events such as fires. [264-266]
Follow up when risks events occur. [269]
Ensure checks required by a manual or users’ handbook are completed as required. [311]
Check whether training is reflected in changed behaviours. [333-335]
Write down all approved procedures for dealing with risk events. [338]
Act on knowledge that operatives are not aware of safety procedures. [346]
Undertake structured and systematic evaluations of processes to identify risk to personnel and
equipment, in a HAZOP format. [349]

The Author
Sarah Fox of Enjoy Legal Learning wrote this note. She is a speaker and trainer who cuts through the
complexities of construction law. She provides confidence to construction companies to read, use
and understand their contracts. She is also author of the 500 Word Contract™.
To find out how Sarah can help you love your terms and conditions, contact her on: 07767 342747 or
by email: sarah@enjoylegallearning.co.uk

Footnotes
1
2
3

The first was by Mr Justice Coulson in Trebor Bassett Holdings Ltd & Anor v ADT Fire and Security Plc
[2011] EWHC 1936 (TCC) and the second by the Court of Appeal [2012] EWCA Civ 1158.
References in square brackets are to the TCC judgment and in curly brackets are to the Court of
Appeal judgment.
TCC, 56.

Page 4© 500 Word Contracts, 2014
4
5

6
7

8

See also paragraphs 7 “A critical assumption about the existence of fire segregation turned out to be
entirely misplaced”, and 45-49.
See e.g. the comments at paragraph 91: the suggestion from the claimant that they “might be overspending, by installing a system costing a few thousand pounds, in order to protect building and
equipment now said to be worth £110 million, is unfathomable. It betrays an absence of
understanding of what the fire risks really were, and restates the false cost=significance proposition.”
This term is implied under s4 of the Supply of Goods and Services Act 1982.
In the Court of Appeal judgment, Tomlinson LJ said, at paragraph 57: “[The buyers] cannot, for the
purposes of s.4(4) of the 1982 Act, show that it made known to [the sellers] a particular purpose for
which the system was being acquired. {The buyers] did not sufficiently explain the process or its
hazardous nature…no such absolute but undefined obligation could be undertaken or guarantee
given.”
A quotation is an offer, and a purchase order with a different set of terms and conditions is a counteroffer. If this is the ‘last-shot’, then the buyers’ terms and conditions apply. The fact that the buyers’
terms and conditions were not enclosed with their purchase order does not prevent their
incorporation if (1) they were incorporated by notice (2) there was no requirement for specific or
particular notice as none of the terms and conditions were unduly onerous. [191-192]

Page 5© 500 Word Contracts, 2014

Contenu connexe

Plus de Sarah Fox

How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...Sarah Fox
 
Creating effective contracts
Creating effective contracts Creating effective contracts
Creating effective contracts Sarah Fox
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Sarah Fox
 
From Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah FoxFrom Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah FoxSarah Fox
 
Checklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR complianceChecklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR complianceSarah Fox
 
10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal Writing10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal WritingSarah Fox
 
8 Habits of Highly Defective Contracts
8 Habits of Highly Defective Contracts8 Habits of Highly Defective Contracts
8 Habits of Highly Defective ContractsSarah Fox
 
Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do? Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do? Sarah Fox
 
Guide to Tort in Construction
Guide to Tort in ConstructionGuide to Tort in Construction
Guide to Tort in ConstructionSarah Fox
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract AdministratorsSarah Fox
 
Excluding Liability for Latent Defects
Excluding Liability for Latent DefectsExcluding Liability for Latent Defects
Excluding Liability for Latent DefectsSarah Fox
 
What's So Great About Construction?
What's So Great About Construction?What's So Great About Construction?
What's So Great About Construction?Sarah Fox
 
How Courts Decide Whose Terms Apply
How Courts Decide Whose Terms ApplyHow Courts Decide Whose Terms Apply
How Courts Decide Whose Terms ApplySarah Fox
 
Checklist for Trainers & Facilitators
Checklist for Trainers & FacilitatorsChecklist for Trainers & Facilitators
Checklist for Trainers & FacilitatorsSarah Fox
 
Summary of Construction Acts 1996 & 2009
Summary of Construction Acts 1996 & 2009Summary of Construction Acts 1996 & 2009
Summary of Construction Acts 1996 & 2009Sarah Fox
 
When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?Sarah Fox
 
A Legal Checklist
A Legal Checklist A Legal Checklist
A Legal Checklist Sarah Fox
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesSarah Fox
 
Guide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementGuide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementSarah Fox
 
Briefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction ProjectsBriefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction ProjectsSarah Fox
 

Plus de Sarah Fox (20)

How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...
 
Creating effective contracts
Creating effective contracts Creating effective contracts
Creating effective contracts
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4
 
From Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah FoxFrom Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah Fox
 
Checklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR complianceChecklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR compliance
 
10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal Writing10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal Writing
 
8 Habits of Highly Defective Contracts
8 Habits of Highly Defective Contracts8 Habits of Highly Defective Contracts
8 Habits of Highly Defective Contracts
 
Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do? Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do?
 
Guide to Tort in Construction
Guide to Tort in ConstructionGuide to Tort in Construction
Guide to Tort in Construction
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract Administrators
 
Excluding Liability for Latent Defects
Excluding Liability for Latent DefectsExcluding Liability for Latent Defects
Excluding Liability for Latent Defects
 
What's So Great About Construction?
What's So Great About Construction?What's So Great About Construction?
What's So Great About Construction?
 
How Courts Decide Whose Terms Apply
How Courts Decide Whose Terms ApplyHow Courts Decide Whose Terms Apply
How Courts Decide Whose Terms Apply
 
Checklist for Trainers & Facilitators
Checklist for Trainers & FacilitatorsChecklist for Trainers & Facilitators
Checklist for Trainers & Facilitators
 
Summary of Construction Acts 1996 & 2009
Summary of Construction Acts 1996 & 2009Summary of Construction Acts 1996 & 2009
Summary of Construction Acts 1996 & 2009
 
When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?
 
A Legal Checklist
A Legal Checklist A Legal Checklist
A Legal Checklist
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement Strategies
 
Guide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementGuide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on Procurement
 
Briefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction ProjectsBriefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction Projects
 

Dernier

Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 

Dernier (20)

Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 

Checklist for Partners Working on High Risk D&B Projects

  • 1. Checklist for a Design & Build Project The 2011-2012 court decisions in Trebor Bassett v ADT Fire and Security1 analysed in detail how two partners carried out pre-contract processes for the design and installation of equipment. The judgments are full of tips for those involved in high risk or D&B projects. It should also act as a warning as the claim for £110m arose out of a contract for the design and supply of equipment costing a mere £9,000. The tips, quotes and lessons have been collated into a series of recommendations for partners entering into contracts for construction projects, particularly those involving hazardous processes. Risk Analysis You Should:               Assess and appreciate the risk of each project separately: in this case, the buyer “never fully appreciated the increased risk” that the project would bring. [55]2 Assess “the risks before the project workscope was defined.” [77] Avoid preparing “a specification based on a 'minimum spend'” which decision could be exacerbated by “a refusal to consider any recommendation which might add to the workscope, even if they provided the only way of truly controlling the risk.” [77] Never assume that a similar system is appropriate for a similar project. {21} Ascertain or communicate any history of risk events occurring on similar projects, especially to the designer of a system intended to protect or minimise the consequences of those risk events. Your designer should appreciate all significant risks. [140] {21} Carry out a proper technical appraisal of the risks, ideally in conjunction with the supplier of relevant risk protection equipment. [75] Identify precisely the risks and hazards on each project “and/or how those risks could be best dealt with.”3 This should be done in detail. [61, 367] Make sure one person within your organisation ‘owns the risk.’ Often this is the project manager who is responsible for “recognising and then minimising all the risks created by that project.”62] Check all assumptions made for significant risk factors (i.e. those with potentially catastrophic consequences). “This erroneous assumption gave rise to the conclusion that there was no health and safety issue; it follows that, if the [buyers] had bothered to check the as-built drawings, they would have seen that the assumption was wrong, and that therefore there was a major health and safety issue.”[88]4 Take advice from risk professionals, but make sure their advice is based on evidence and not assumptions. [68-69] Ensure all recommendations from risk managers are properly followed through: “one significant recommendation made by the [buyer’s own risk managers]…was not followed” and that none are ignored. [7, 36] Where the best option to protect against a risk event is not adopted, ensure that the alternative means of protecting against risk events are adopted. [72] Keep records of meetings with Fire Officers. [121] Not “decide what to do and then assess the risk” but the other way round. [77-78] Page 1© 500 Word Contracts, 2014
  • 2.   Not determine the significance of risks on the “value of the proposed works”5 but on “the value of the building and equipment at risk if those works were not properly specified and designed.” [85] Not assume that Certification by the Fire Brigade is sufficient to establish risks have been managed and the process is not hazardous, such as “an industrial process involving naked flames.” [44] Specifying the Works You Should:      Decide your objective – you cannot have both high quality, low price and tight timescales: “The timing was very tight… it was imperative that the new lines were up and running by Christmas 2003, in order to meet the surge in demand for popcorn, particularly for the cinema trade, over the Christmas period. This timetable could not be changed.” But the same project was costed “on a requirement of minimum spend to introduce a safe system of work.” [54, 58] Agree what design responsibility each partner will have: “the most important element of the workscope was that done by the [sellers’] designers: the decision to use a particular piece of equipment in a particular place, with the intention of achieving a particular effect.” [215] Specify the works based on the needs of the project, not on existing experience. [92-96] Ensure the partners work together on producing the design and specification: “the [buyers’] haphazard approach at the outset was not picked by the [sellers], and was compounded by the [sellers’] rather cavalier attitude to what they were being asked to do.” [113] Avoid using standard form specifications for bespoke projects with significant risks. [107] Specifying Standards of Quality You should:  Understand the general standards of quality. A contractor providing design services “will not generally owe a higher obligation than the duty to use reasonable skill and care.” If you want a higher standard, you will have to say so, clearly. [217]  Be specific if you want quality guaranteed: “one would need to identify with much more specificity precisely what it is that [the sellers were] alleged to have been impliedly asked to do and, in consequence, what result it is that it is said to have undertaken to bring about.” {56}  State the standards you require. If your contract states ‘good quality’, the court will not imply a  term what the goods will be of satisfactory quality.6 [218-220] Ensure, in a contract for the sale of goods, where you want to rely on an implied obligation as to fitness for purpose, that you: o State your particular purpose “must have been made clear… At no stage did the [buyers] ever indicate any particular purpose” for which the system was being acquired; [223224]7 o rely on the sellers’ advice or expertise; in the case, the buyers “did not rely on the defendant's skill or judgment at all.” [226] Page 2© 500 Word Contracts, 2014
  • 3.    Set out the standards on quality in the specification: “The specification, with its reference to British Standard 5306 and other assumptions and requirements, formed the benchmark against which the [sellers’] obligations were to be performed.” [264] Understand what any relevant British Standard requires – often it is more a set of recommendations, which is not sufficient for a guarantee or warranty. [243] Set out any promise or guarantee in clear words: “[T]he fact that the system had been designed ‘to suit the specific requirements of the risks to be protected’ (to use the words of the specification) does not mean that the system was guaranteed to eliminate those risks every time. It was designed, manufactured and installed with those risks in mind, but the obligation as to design was to take reasonable skill and care and there was nothing in these words to impose upon the defendant a more onerous obligation. A design intended 'to suit the specific requirements of the risks' may or may not be done with reasonable skill and care, but it was not a promise that the design would eliminate all risks. A promise that a particular risk will be eliminated must say so in clear terms. The specification did not do so.” [242] Designing and Commissioning the Works As a designer/D&B contractor, you should:         Use correct and detailed drawings in order to prepare your design. In this case, “the working documents should have identified the relevant hazards.” [105,111] Seek “as much information” as you can. Do not design “on assumptions [but]… find out the facts for itself.” [509] As your first step, “identify the risks which were to be protected and to design a system that suited the specific requirements of the risks to be protected.” [510] Ensure, as “a specialist was providing a design, and then manufacturing and installing the product so designed…that there was proper communication between the designer and the installer.” [511] Ensure any checks of design assumptions by the installer or buyers are followed up: “if the design engineer worked from drawings, he would need the installing engineer to check that his design assumptions were well-founded.” [112-113, 138] Ensure your design is based on detailed accurate information, reviewed and checked. [113] Obtain good information and corroborate with your partners, to avoid: “the patently inadequate information which the [sellers] had, and the difference of approach between its two designers which was its probable result, demonstrates a fundamental flaw at the heart of the [sellers’] work on this contract.” [140] Do more than just check “the system had been installed in accordance with the drawings” where the drawings are inadequate. [145] Agreeing the Terms and Conditions You Should:  Keep records to show that previous contracts have been agreed on the same basis, if you want to establish a course of dealing, and that your T&C are incorporated as a result. [161] Page 3© 500 Word Contracts, 2014
  • 4.    Ask for a copy of any T&C referred to on any contract document, especially where it states “already supplied… Additional copies available on request”. You must also respond to any terms with which you disagree. {27} Understand the rules relating to incorporation of terms and conditions. 8 [172-173] Ensure your terms and conditions are sensible and certain: a clause limiting liability to a multiple of an annual service charge is not effective in a contract for the provision of goods and services. Such a limit “was meaningless, because the limitation was calculable only by reference to the value of a non-existent contract. That was too uncertain to be enforceable.” [197-198] Training Staff You Should:             Use risk identification processes to establish standard operating procedures. [367] Create clear safety procedures and train operatives accordingly. [367] Ensure all relevant staff are given a detailed demonstration of all relevant systems as part of the commissioning or post-commissioning follow-up. Do not leave it to one person. [270-286] Ensure all operatives are aware of any safety features or procedures on newly installed or altered equipment: “very few of the operatives in the 'oil pop' popcorn production area were aware that the CO2 suppression system protecting the elevator and the hopper could be manually activated, and even fewer knew how that manual activation was to be triggered.”[8] Ensure the procedures approved by managers are appropriate. [10] Ensure there is a satisfactory and safe working environment for operatives, and a satisfactory system to detect and respond to risk events such as fires. [264-266] Follow up when risks events occur. [269] Ensure checks required by a manual or users’ handbook are completed as required. [311] Check whether training is reflected in changed behaviours. [333-335] Write down all approved procedures for dealing with risk events. [338] Act on knowledge that operatives are not aware of safety procedures. [346] Undertake structured and systematic evaluations of processes to identify risk to personnel and equipment, in a HAZOP format. [349] The Author Sarah Fox of Enjoy Legal Learning wrote this note. She is a speaker and trainer who cuts through the complexities of construction law. She provides confidence to construction companies to read, use and understand their contracts. She is also author of the 500 Word Contract™. To find out how Sarah can help you love your terms and conditions, contact her on: 07767 342747 or by email: sarah@enjoylegallearning.co.uk Footnotes 1 2 3 The first was by Mr Justice Coulson in Trebor Bassett Holdings Ltd & Anor v ADT Fire and Security Plc [2011] EWHC 1936 (TCC) and the second by the Court of Appeal [2012] EWCA Civ 1158. References in square brackets are to the TCC judgment and in curly brackets are to the Court of Appeal judgment. TCC, 56. Page 4© 500 Word Contracts, 2014
  • 5. 4 5 6 7 8 See also paragraphs 7 “A critical assumption about the existence of fire segregation turned out to be entirely misplaced”, and 45-49. See e.g. the comments at paragraph 91: the suggestion from the claimant that they “might be overspending, by installing a system costing a few thousand pounds, in order to protect building and equipment now said to be worth £110 million, is unfathomable. It betrays an absence of understanding of what the fire risks really were, and restates the false cost=significance proposition.” This term is implied under s4 of the Supply of Goods and Services Act 1982. In the Court of Appeal judgment, Tomlinson LJ said, at paragraph 57: “[The buyers] cannot, for the purposes of s.4(4) of the 1982 Act, show that it made known to [the sellers] a particular purpose for which the system was being acquired. {The buyers] did not sufficiently explain the process or its hazardous nature…no such absolute but undefined obligation could be undertaken or guarantee given.” A quotation is an offer, and a purchase order with a different set of terms and conditions is a counteroffer. If this is the ‘last-shot’, then the buyers’ terms and conditions apply. The fact that the buyers’ terms and conditions were not enclosed with their purchase order does not prevent their incorporation if (1) they were incorporated by notice (2) there was no requirement for specific or particular notice as none of the terms and conditions were unduly onerous. [191-192] Page 5© 500 Word Contracts, 2014