What is Criticality ?
A tool used to evaluate how equipment
failures impact organizational
performance in order to systematically
rank plant assets for the purpose of :

PM /PdM
Development

To prioritize
activities dedicated
to PM / PdM
development or
optimization

Material
Classification

To better
prioritize work
out of the
maintenance
backlog

2

Reliability
Improvement
Initiatives

To support MRO
initiatives to
identify critical
spares

Work
Prioritization

To ensure that
reliability
improvements are
made based on risk
rather than
perception
The Process
Cross-functional analysis and input from
Operations and Maintenance, and as
required, input from Engineering,
Material Management, Environment and
Health and Safety representatives

Weigh the impact of a failure on each
asset across all 4 criteria

Impact on
safety
(0 to 4)

x

Impact on
environment
(0 to 4)

x

Impact on
quality
(0 to 4)

3

x

Impact on cost
or production
(0 to 4)

=

0 to 256
Impact on Safety
0

Potential to cause death or permanent injuries

1

Potential to cause non-permanent bodily injuries

2

Potential to cause significant inconvenience to personnel

3

Potential to cause minor inconvenience to personnel

4

Will have no significant impact on personnel

4
Deploying Criticality Analysis in
a Multi-Plant Reliability Program

5
One of the Major Tissue Producers
in North America
• Quebec (4)
• Ontario (2)

• Wisconsin (1)
• Pennsylvania (2)
• North Carolina (1)
• New York (2)
• Oregon (1)
• Arizona (1)
• Tennessee (1)

Mills located in the United States

Mills located in Canada
6
The Objective
• For all of the 15 mills, associate a criticality ranking to each
asset in the CMMS.

The Challenge
• Have the criticality ranking done for all of the 15 mills within
a schedule of 8 to 12 weeks.
• A total of 45,000 assets, ranging from 600 to 16,000 per mill.

7
Criticality Ranking
The criticality ranking is calculated by multiplying each of the scores (from 0 to 4) obtained
for each of the 4 criteria.
The total is then converted into one of the following 4 criticality rankings, namely A,B,C or D.
Equipment
Number
PE-002
PE-005
VE-100
AG-201
CL-403

Description
Pump xyz
Pump ABC
Blower YYZ
Agitator DBC
Air Conditionning

Criticality Evaluation
Environment
Quality
Economical
4
4
1
4
4
2
4
4
3
1
4
4
4
4
4

Safety
4
4
4
0
4

Evaluation Score

Criticality Ranking

0 ≤ Criticality ≤ 96

Extreme

97 ≤ Criticality ≤ 145

High

146 ≤ Criticality ≤ 193

Moderate

194 ≤ Criticality ≤ 256

Low

=A
=B
=C
=D

8

Total =
64
128
192
0
256

Criticality
Ranking
A
B
C
A
D
Lessons Learned
• Prevent mill personnel from taking shortcuts –this is an
objective and quantitative process
• Avoid entering rankings one by one - work with IT to import
the criticality rankings in the CMMS
• Take the time to explain the advantages of a criticality
ranking system
• Make sure equipment hierarchy is adequate before you start

9
Keys to Success
• There is a wide variety of criticality tools and methods out there,
Keep it simple!
• Make sure to adapt the matrix with the operational context of each
facility
• It is OK to use the copy/paste method for identical or very similar
equipment in a facility
• Make sure you arrive prepared and organized

10
Questions ?
Michel Cote: mcote@prosygma.ca
Serge Mathieu: smathieu@prosygma.ca

WWW.PROSYGMA.CA

11

More Related Content

What's hot

Reliability Centered Maintenance
Reliability Centered MaintenanceReliability Centered Maintenance
Reliability Centered MaintenanceRonald Shewchuk
 
Rcm of compressor
Rcm of compressorRcm of compressor
Rcm of compressorKaram Ali
 
Asset Performance Management_Deepak Sahoo_v0.2
Asset Performance Management_Deepak Sahoo_v0.2Asset Performance Management_Deepak Sahoo_v0.2
Asset Performance Management_Deepak Sahoo_v0.2DEEPAK SAHOO
 
Rcm 4 hour overview for rcm teams
Rcm 4 hour overview for rcm teamsRcm 4 hour overview for rcm teams
Rcm 4 hour overview for rcm teamsMatthew Clemens
 
Spares criticality assessment methods & equipment overhaul replacementrepairs...
Spares criticality assessment methods & equipment overhaul replacementrepairs...Spares criticality assessment methods & equipment overhaul replacementrepairs...
Spares criticality assessment methods & equipment overhaul replacementrepairs...Amirul Faiz Amil Azman
 
Maintenance strategy
Maintenance strategyMaintenance strategy
Maintenance strategygumma alsgier
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment EffectivenessAnand Subramaniam
 
Maintenance Costs Reduction Strategy Presentation
Maintenance Costs  Reduction Strategy PresentationMaintenance Costs  Reduction Strategy Presentation
Maintenance Costs Reduction Strategy Presentationweshumba
 
Basics in Maintenance
Basics in MaintenanceBasics in Maintenance
Basics in Maintenanceraghuttam
 
Predictive Maintenance
Predictive MaintenancePredictive Maintenance
Predictive Maintenancefljungbe
 
Reliability centred maintenance
Reliability centred maintenanceReliability centred maintenance
Reliability centred maintenanceSHIVAJI CHOUDHURY
 
Best Practices in Maintenance and Reliability
Best Practices in Maintenance and ReliabilityBest Practices in Maintenance and Reliability
Best Practices in Maintenance and ReliabilityRicky Smith CMRP, CMRT
 
Checklist Asset Management for educational purposes - ISO55000
Checklist Asset Management for educational purposes - ISO55000Checklist Asset Management for educational purposes - ISO55000
Checklist Asset Management for educational purposes - ISO55000Cyrus Sorab
 
Maintenance Metrics
Maintenance MetricsMaintenance Metrics
Maintenance Metricskaskerrigan
 
Introduction to maintenance
Introduction to maintenanceIntroduction to maintenance
Introduction to maintenanceTanveer Hussain
 

What's hot (20)

Reliability Centered Maintenance
Reliability Centered MaintenanceReliability Centered Maintenance
Reliability Centered Maintenance
 
Rcm of compressor
Rcm of compressorRcm of compressor
Rcm of compressor
 
TPM Implementation Strategy
TPM Implementation StrategyTPM Implementation Strategy
TPM Implementation Strategy
 
Asset Performance Management_Deepak Sahoo_v0.2
Asset Performance Management_Deepak Sahoo_v0.2Asset Performance Management_Deepak Sahoo_v0.2
Asset Performance Management_Deepak Sahoo_v0.2
 
Rcm 4 hour overview for rcm teams
Rcm 4 hour overview for rcm teamsRcm 4 hour overview for rcm teams
Rcm 4 hour overview for rcm teams
 
Spares criticality assessment methods & equipment overhaul replacementrepairs...
Spares criticality assessment methods & equipment overhaul replacementrepairs...Spares criticality assessment methods & equipment overhaul replacementrepairs...
Spares criticality assessment methods & equipment overhaul replacementrepairs...
 
Reliability centered maintenance
Reliability centered maintenanceReliability centered maintenance
Reliability centered maintenance
 
Maintenance strategy
Maintenance strategyMaintenance strategy
Maintenance strategy
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
 
Maintenance Costs Reduction Strategy Presentation
Maintenance Costs  Reduction Strategy PresentationMaintenance Costs  Reduction Strategy Presentation
Maintenance Costs Reduction Strategy Presentation
 
Basics in Maintenance
Basics in MaintenanceBasics in Maintenance
Basics in Maintenance
 
Predictive Maintenance
Predictive MaintenancePredictive Maintenance
Predictive Maintenance
 
[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)
 
Reliability centred maintenance
Reliability centred maintenanceReliability centred maintenance
Reliability centred maintenance
 
Best Practices in Maintenance and Reliability
Best Practices in Maintenance and ReliabilityBest Practices in Maintenance and Reliability
Best Practices in Maintenance and Reliability
 
TPM: Planned Maintenance
TPM: Planned MaintenanceTPM: Planned Maintenance
TPM: Planned Maintenance
 
My machine camp
My machine campMy machine camp
My machine camp
 
Checklist Asset Management for educational purposes - ISO55000
Checklist Asset Management for educational purposes - ISO55000Checklist Asset Management for educational purposes - ISO55000
Checklist Asset Management for educational purposes - ISO55000
 
Maintenance Metrics
Maintenance MetricsMaintenance Metrics
Maintenance Metrics
 
Introduction to maintenance
Introduction to maintenanceIntroduction to maintenance
Introduction to maintenance
 

Viewers also liked

Tool Box Talk - Developing Equipment Criticality
Tool Box Talk - Developing Equipment CriticalityTool Box Talk - Developing Equipment Criticality
Tool Box Talk - Developing Equipment CriticalityRicky Smith CMRP, CMRT
 
Criticality Analysis WIRAM Webinar Nov 17
Criticality Analysis WIRAM Webinar Nov 17 Criticality Analysis WIRAM Webinar Nov 17
Criticality Analysis WIRAM Webinar Nov 17 Jennifer Zach
 
FMEA Criticality analysis
FMEA Criticality analysisFMEA Criticality analysis
FMEA Criticality analysisMichael Herman
 
Introduction to FMEA/FMECA
Introduction to FMEA/FMECAIntroduction to FMEA/FMECA
Introduction to FMEA/FMECAMichael Herman
 
Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)DEEPAK SAHOO
 
Reliability Centered Commissioning Maturity Matrix
Reliability Centered Commissioning Maturity MatrixReliability Centered Commissioning Maturity Matrix
Reliability Centered Commissioning Maturity MatrixRicky Smith CMRP, CMRT
 
a clients most influential dimension to make bim fly
a clients most influential dimension to make bim flya clients most influential dimension to make bim fly
a clients most influential dimension to make bim flySimon Richardson
 
Knowledge based asset integrity for wind farms
Knowledge based asset integrity for wind farmsKnowledge based asset integrity for wind farms
Knowledge based asset integrity for wind farmsLloyd's Register Energy
 
Allied Reliability Phase II EMP Development Overview (March 2009)
Allied Reliability Phase II EMP Development Overview (March 2009)Allied Reliability Phase II EMP Development Overview (March 2009)
Allied Reliability Phase II EMP Development Overview (March 2009)Chris Colson
 
FMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysisFMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysisSoumyajit Bhuin
 
Strategy Planning and Deployment Process Training Module
Strategy Planning and Deployment Process Training ModuleStrategy Planning and Deployment Process Training Module
Strategy Planning and Deployment Process Training ModuleFrank-G. Adler
 
Reliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleReliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleRicky Smith CMRP, CMRT
 
Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Anand Subramaniam
 
Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]ExerciseLeanLLC
 
FMEA Introduction.ppt
FMEA Introduction.pptFMEA Introduction.ppt
FMEA Introduction.pptbowerj
 
FMEA and FMECA
FMEA and FMECAFMEA and FMECA
FMEA and FMECASjur
 

Viewers also liked (20)

Criticality Analysis
Criticality AnalysisCriticality Analysis
Criticality Analysis
 
Tool Box Talk - Developing Equipment Criticality
Tool Box Talk - Developing Equipment CriticalityTool Box Talk - Developing Equipment Criticality
Tool Box Talk - Developing Equipment Criticality
 
Criticality Analysis WIRAM Webinar Nov 17
Criticality Analysis WIRAM Webinar Nov 17 Criticality Analysis WIRAM Webinar Nov 17
Criticality Analysis WIRAM Webinar Nov 17
 
FMEA Criticality analysis
FMEA Criticality analysisFMEA Criticality analysis
FMEA Criticality analysis
 
PdM Maturity Matrix Poster
PdM Maturity Matrix PosterPdM Maturity Matrix Poster
PdM Maturity Matrix Poster
 
Introduction to FMEA/FMECA
Introduction to FMEA/FMECAIntroduction to FMEA/FMECA
Introduction to FMEA/FMECA
 
Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)
 
Reliability Centered Commissioning Maturity Matrix
Reliability Centered Commissioning Maturity MatrixReliability Centered Commissioning Maturity Matrix
Reliability Centered Commissioning Maturity Matrix
 
a clients most influential dimension to make bim fly
a clients most influential dimension to make bim flya clients most influential dimension to make bim fly
a clients most influential dimension to make bim fly
 
Knowledge based asset integrity for wind farms
Knowledge based asset integrity for wind farmsKnowledge based asset integrity for wind farms
Knowledge based asset integrity for wind farms
 
Allied Reliability Phase II EMP Development Overview (March 2009)
Allied Reliability Phase II EMP Development Overview (March 2009)Allied Reliability Phase II EMP Development Overview (March 2009)
Allied Reliability Phase II EMP Development Overview (March 2009)
 
F.M.E.C.A pdf
F.M.E.C.A pdfF.M.E.C.A pdf
F.M.E.C.A pdf
 
FMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysisFMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysis
 
Strategy Planning and Deployment Process Training Module
Strategy Planning and Deployment Process Training ModuleStrategy Planning and Deployment Process Training Module
Strategy Planning and Deployment Process Training Module
 
Reliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleReliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made Simple
 
Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)
 
Process F.M.E.A
Process F.M.E.AProcess F.M.E.A
Process F.M.E.A
 
Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]
 
FMEA Introduction.ppt
FMEA Introduction.pptFMEA Introduction.ppt
FMEA Introduction.ppt
 
FMEA and FMECA
FMEA and FMECAFMEA and FMECA
FMEA and FMECA
 

Similar to Equipment Criticality

Electrical Department Maintenance Management Vision
Electrical Department Maintenance Management VisionElectrical Department Maintenance Management Vision
Electrical Department Maintenance Management VisionFouad Ghoneim, PMP®, SSYB®
 
Risk Management integrated pub
Risk Management integrated pubRisk Management integrated pub
Risk Management integrated pubManfred Walder
 
Lecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.pptLecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.pptThushan9
 
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...FMMUG
 
Training Prog :: Vendor quality Management system-Vendor development
Training Prog :: Vendor quality Management system-Vendor developmentTraining Prog :: Vendor quality Management system-Vendor development
Training Prog :: Vendor quality Management system-Vendor developmentVarmahk
 
Quality management and quality planning
Quality management and quality planningQuality management and quality planning
Quality management and quality planningAmartya Talukdar
 
Reliability Engineering in Biomanufacturing - Presentation by Michael Andrews
Reliability Engineering in Biomanufacturing - Presentation by Michael AndrewsReliability Engineering in Biomanufacturing - Presentation by Michael Andrews
Reliability Engineering in Biomanufacturing - Presentation by Michael AndrewsWPICPE
 
Safety life cycle seminar IEC61511
Safety life cycle seminar IEC61511Safety life cycle seminar IEC61511
Safety life cycle seminar IEC61511Luis Atencio
 
A ORAM 06-2016Eshi
A ORAM 06-2016EshiA ORAM 06-2016Eshi
A ORAM 06-2016EshiAl Oram
 
TPM - Total Productive Maintenance
TPM - Total Productive MaintenanceTPM - Total Productive Maintenance
TPM - Total Productive MaintenanceRAHMAT EIE
 
Track 2 Tuesday Michael Rose and Chris Gould- pres.
Track 2 Tuesday Michael Rose and Chris Gould- pres.Track 2 Tuesday Michael Rose and Chris Gould- pres.
Track 2 Tuesday Michael Rose and Chris Gould- pres.Mike Poland, CMRP
 
BAHAN PRESENTASI RCM.pptx
BAHAN PRESENTASI RCM.pptxBAHAN PRESENTASI RCM.pptx
BAHAN PRESENTASI RCM.pptxQienKing
 
Clorox at the_eastern_ergonomics_conference_jun_23_2005
Clorox at the_eastern_ergonomics_conference_jun_23_2005Clorox at the_eastern_ergonomics_conference_jun_23_2005
Clorox at the_eastern_ergonomics_conference_jun_23_2005Remedy Interactive
 
Achieving Excellence in OH&S performance through OH&S Management Systems
Achieving Excellence in OH&S performance through OH&S Management SystemsAchieving Excellence in OH&S performance through OH&S Management Systems
Achieving Excellence in OH&S performance through OH&S Management SystemsDQS India
 

Similar to Equipment Criticality (20)

Araz041410Resume
Araz041410ResumeAraz041410Resume
Araz041410Resume
 
Electrical Department Maintenance Management Vision
Electrical Department Maintenance Management VisionElectrical Department Maintenance Management Vision
Electrical Department Maintenance Management Vision
 
Risk Management integrated pub
Risk Management integrated pubRisk Management integrated pub
Risk Management integrated pub
 
RCM
RCMRCM
RCM
 
Lecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.pptLecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.ppt
 
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
Learn how to use Maximo HSE to Add a Layer of Control on Top of your Work Pro...
 
Training Prog :: Vendor quality Management system-Vendor development
Training Prog :: Vendor quality Management system-Vendor developmentTraining Prog :: Vendor quality Management system-Vendor development
Training Prog :: Vendor quality Management system-Vendor development
 
Quality management and quality planning
Quality management and quality planningQuality management and quality planning
Quality management and quality planning
 
Reliability Engineering in Biomanufacturing - Presentation by Michael Andrews
Reliability Engineering in Biomanufacturing - Presentation by Michael AndrewsReliability Engineering in Biomanufacturing - Presentation by Michael Andrews
Reliability Engineering in Biomanufacturing - Presentation by Michael Andrews
 
Quality 2.pptx
Quality 2.pptxQuality 2.pptx
Quality 2.pptx
 
Asset Managment
Asset ManagmentAsset Managment
Asset Managment
 
Safety life cycle seminar IEC61511
Safety life cycle seminar IEC61511Safety life cycle seminar IEC61511
Safety life cycle seminar IEC61511
 
A ORAM 06-2016Eshi
A ORAM 06-2016EshiA ORAM 06-2016Eshi
A ORAM 06-2016Eshi
 
TPM - Total Productive Maintenance
TPM - Total Productive MaintenanceTPM - Total Productive Maintenance
TPM - Total Productive Maintenance
 
Track 2 Tuesday Michael Rose and Chris Gould- pres.
Track 2 Tuesday Michael Rose and Chris Gould- pres.Track 2 Tuesday Michael Rose and Chris Gould- pres.
Track 2 Tuesday Michael Rose and Chris Gould- pres.
 
BAHAN PRESENTASI RCM.pptx
BAHAN PRESENTASI RCM.pptxBAHAN PRESENTASI RCM.pptx
BAHAN PRESENTASI RCM.pptx
 
Clorox at the_eastern_ergonomics_conference_jun_23_2005
Clorox at the_eastern_ergonomics_conference_jun_23_2005Clorox at the_eastern_ergonomics_conference_jun_23_2005
Clorox at the_eastern_ergonomics_conference_jun_23_2005
 
Achieving Excellence in OH&S performance through OH&S Management Systems
Achieving Excellence in OH&S performance through OH&S Management SystemsAchieving Excellence in OH&S performance through OH&S Management Systems
Achieving Excellence in OH&S performance through OH&S Management Systems
 
Cv 30032015 3
Cv 30032015 3Cv 30032015 3
Cv 30032015 3
 
TPM 8 Pillars
TPM 8 PillarsTPM 8 Pillars
TPM 8 Pillars
 

Recently uploaded

Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture conceptP&CO
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 

Recently uploaded (20)

Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 

Equipment Criticality

  • 1. Deploying Criticality Analysis in Multi-Plant Reliability Improvement Programs Michel Cote & Serge Mathieu Prosygma Reliability and Maintenance Professional Services 1
  • 2. What is Criticality ? A tool used to evaluate how equipment failures impact organizational performance in order to systematically rank plant assets for the purpose of : PM /PdM Development To prioritize activities dedicated to PM / PdM development or optimization Material Classification To better prioritize work out of the maintenance backlog 2 Reliability Improvement Initiatives To support MRO initiatives to identify critical spares Work Prioritization To ensure that reliability improvements are made based on risk rather than perception
  • 3. The Process Cross-functional analysis and input from Operations and Maintenance, and as required, input from Engineering, Material Management, Environment and Health and Safety representatives Weigh the impact of a failure on each asset across all 4 criteria Impact on safety (0 to 4) x Impact on environment (0 to 4) x Impact on quality (0 to 4) 3 x Impact on cost or production (0 to 4) = 0 to 256
  • 4. Impact on Safety 0 Potential to cause death or permanent injuries 1 Potential to cause non-permanent bodily injuries 2 Potential to cause significant inconvenience to personnel 3 Potential to cause minor inconvenience to personnel 4 Will have no significant impact on personnel 4
  • 5. Deploying Criticality Analysis in a Multi-Plant Reliability Program 5
  • 6. One of the Major Tissue Producers in North America • Quebec (4) • Ontario (2) • Wisconsin (1) • Pennsylvania (2) • North Carolina (1) • New York (2) • Oregon (1) • Arizona (1) • Tennessee (1) Mills located in the United States Mills located in Canada 6
  • 7. The Objective • For all of the 15 mills, associate a criticality ranking to each asset in the CMMS. The Challenge • Have the criticality ranking done for all of the 15 mills within a schedule of 8 to 12 weeks. • A total of 45,000 assets, ranging from 600 to 16,000 per mill. 7
  • 8. Criticality Ranking The criticality ranking is calculated by multiplying each of the scores (from 0 to 4) obtained for each of the 4 criteria. The total is then converted into one of the following 4 criticality rankings, namely A,B,C or D. Equipment Number PE-002 PE-005 VE-100 AG-201 CL-403 Description Pump xyz Pump ABC Blower YYZ Agitator DBC Air Conditionning Criticality Evaluation Environment Quality Economical 4 4 1 4 4 2 4 4 3 1 4 4 4 4 4 Safety 4 4 4 0 4 Evaluation Score Criticality Ranking 0 ≤ Criticality ≤ 96 Extreme 97 ≤ Criticality ≤ 145 High 146 ≤ Criticality ≤ 193 Moderate 194 ≤ Criticality ≤ 256 Low =A =B =C =D 8 Total = 64 128 192 0 256 Criticality Ranking A B C A D
  • 9. Lessons Learned • Prevent mill personnel from taking shortcuts –this is an objective and quantitative process • Avoid entering rankings one by one - work with IT to import the criticality rankings in the CMMS • Take the time to explain the advantages of a criticality ranking system • Make sure equipment hierarchy is adequate before you start 9
  • 10. Keys to Success • There is a wide variety of criticality tools and methods out there, Keep it simple! • Make sure to adapt the matrix with the operational context of each facility • It is OK to use the copy/paste method for identical or very similar equipment in a facility • Make sure you arrive prepared and organized 10
  • 11. Questions ? Michel Cote: mcote@prosygma.ca Serge Mathieu: smathieu@prosygma.ca WWW.PROSYGMA.CA 11