The presentation used for the workshop on the Downtown Improvement Project held on 5/12/10.
The video recording of the workshop is available on Franklin Matters.
3. Downtown Improvement Project
Project Description
HPP Project
• West Central – Union to Main Street
• East Central – Main Street to Ruggles Street
• Main Street – Moore Ave to East Cenral Street
• Emmons Street – West Central to Main Street
PWED Project
• Emmons Street – Main Street to Hillside North
• Dean Avenue – Main to Ray Street
• Depot Street – Main St. to Dean Ave (Incl. Mun. Lot)
• Ray Street – Dean Ave to Depot Street
4. Downtown Improvement Project
High Priority Project (HPP) Project Area Project Area
Improvement Area
Public Works Economic
Development (PWED)
Improvement Area
High Priority Project (HPP)
Improvement Area
27. Downtown Improvement Project
Design Solutions - Parking
Location Existing Proposed
HPP
W. Central (Emmons to Main): 0 0
E. Central (Main to Ruggles): 25 26 (+1)
Emmons (W. Central to Main): 0 8 (+8)
Main (Emmons to E. Central): 35 26 (-9)
PWED
Emmons (Main to Ray): 3 3
Dean: 5 7 (+2)
Depot: 15 20 (+5)
Municipal Parking (Includes 2 HC Spaces): 59 63 (+4)
Total = 142 153 (+11)
28. Downtown Improvement Project
Schedule Moving Forward
Spring 2010
• Coordination with Utilities | MBTA | MassDOT
• Prepare 25% Design (HPP)
• Prepare Preliminary Design (PWED)
Summer 2010
• Submit 25% Design (HPP) to MassDOT
• Submit Preliminary Design (PWED) to Town
• Water Main Improvements by Town
Fall 2010
• Submit Final Design (PWED) to Town
• 25% Design Public Hearing (HPP) by MassDOT
29. Downtown Improvement Project
Schedule Moving Forward
Fall 2010
• Submit 75% Design (HPP) to MassDOT
• Prepare Bid Documents (PWED)
• Advertise/Bid/Award PWED Project
Spring 2011
• Submit Final Design (HPP) to MassDOT
• Begin Construction of PWED Project
Summer 2011
• Prepare Bid Documents (HPP)
• Advertise of HPP Project by MassDOT
Fall 2011
• Bid & Award HPP Project – Begin Construction Spring 2012