SlideShare une entreprise Scribd logo
1  sur  20
Commercial Application of the Physics-Based Test Strip and Seeding Approach Ryan Steigerwalt, P.G., Weston Solutions, Inc. Jim Austreng, P.E., California Department of Toxic Substances Control C. Scott Goulart, Aerojet-General Corporation UXO/Countermine/Range Forum 2009 Orlando, Florida
TALKING POINTS Introduction and Conceptual Site Model  Project planning and requirements Implementation of the Geophysical System Verification (GSV) process Planning and development Test Strip construction Seeding program Operations Results
INTRODUCTION Project site located in Chino Hills, CA Facility owned by Aerojet-General Corporation Perform MEC detection and removal in areas not previously investigated Use DGM in all accessible areas Perform mag & dig surveys in all other areas where possible Work was conducted with DTSC oversight Dec 2008 – Feb 2009
CONCEPTUAL SITE MODEL CSM identified anticipated munitions and facility uses Extensive geophysical prove-outs were conducted at the facility in 2004 Evaluated detection capabilities of various instruments and techniques Reported the type and quality of data required for subsequent MEC detection and removal activities
WORK PLAN Use results from previous GPO Develop data collection parameters and quality control Perform a limited GPO and gain concurrence Mobilize remainder of crew Collect data
PROJECT REQUIREMENTS In November 2008, wildfire struck the facility and cleared vegetation Need to perform technically defensible work, quickly, before vegetation returned Mobilize ASAP
FIELD VARIANCE Began site setup Preparing to perform limited GPO Project team discussed GSV and potential application No GPO grid construction Start collecting data immediately No required review cycle Joint QC/QA Can continuously monitor performance Developed a brief field variance to document GSV approach- test strip construction and seeding Gained regulatory concurrence
GSV DESIGN Test Strip Construction Seed anticipated munitions items at detection depth objectives Place seeds at least favorable orientation Establish multiple Test Strips if necessary to increase efficiency Perform daily to evaluate equipment functionality
GSV DESIGN Seeding Program Use similar items and burial depths as Test Strips Initially place one seed within each 100-ft x 100-ft grid block Relax seed frequency to one seed per acre if performance is acceptable
GSV IMPLEMENTATION Equipment EM61-MK2 towed sled 4 sensor RTK-GPS Navigation Test Strip Perform background and baseline survey prior to production mapping Run Test Strip daily with instrumentation Perform concurrent with standardized QC function tests Evaluate response and monitor results
SURVEY SUMMARY Digital Geophysical Mapping Summary Completed approximately 9 total acres Includes rough and steep terrain Spanned several weeks All DGM was performed using a towed array sled
TEST STRIP 1 RESULTS Day 1 (Baseline) Day 2 Day 3 Day 4 Day 5 Day 6
TEST STRIP 2 RESULTS Day 8 Day 9 Day 10 Day 11
TEST STRIP SUMMARY Direction of Travel
SEEDING RESULTS 19 total seeds (30mm, 25mm, 20mm) Check response against Test Strip results Test Strip Avg ~8 mV Response (mV) Test Strip Avg ~6 mV Test Strip Avg ~12 mV Seed + x Target Response (mV) Response (mV)
QUALITY ASSURANCE Regulatory site visits Industry Standard Targets and inert items 1-inch by 4-inch pipe nipples Vertical (most favorable) at 11-inches Horizontal (least favorable) at 7-inches
SENSOR RESPONSE CURVE
BENEFITS Means to monitor geophysical system performance daily and consistently Shortened schedule Re-allocated resources to risk reduction efforts Planning variance drafted onsite No duplicate QC/QA Began production mapping next day
LESSONS LEARNED Still need to plan ahead Define objectives Seeding program Schedule Ensure Test Strip seeds are isolated from other influence Use Industry Standard Targets to reduce variability Reality works
QUESTIONS? Montauk Monster

Contenu connexe

Similaire à Geophysical System Verification - A Commercial Application

PetroSync - Advanced Seismic Data Acquisition and Processing
PetroSync - Advanced Seismic Data Acquisition and ProcessingPetroSync - Advanced Seismic Data Acquisition and Processing
PetroSync - Advanced Seismic Data Acquisition and ProcessingPetroSync
 
IGARSS 2011_Priestley.ppt
IGARSS 2011_Priestley.pptIGARSS 2011_Priestley.ppt
IGARSS 2011_Priestley.pptgrssieee
 
Charger Rocket Works PDR: 2009-2010
Charger Rocket Works PDR: 2009-2010Charger Rocket Works PDR: 2009-2010
Charger Rocket Works PDR: 2009-2010Seiya Shimizu
 
Sean Blanchette Resume - Summary
Sean Blanchette Resume - SummarySean Blanchette Resume - Summary
Sean Blanchette Resume - Summarysean blanchette
 
raptr_trr.pptx
raptr_trr.pptxraptr_trr.pptx
raptr_trr.pptxTESTFALTU
 
Performance testing reference model
Performance testing reference modelPerformance testing reference model
Performance testing reference modelEduards Salnikovs
 
Semester_2_team51_poster
Semester_2_team51_posterSemester_2_team51_poster
Semester_2_team51_posterNathan Helwig
 
2b intro num-cube_sat_v3
2b   intro num-cube_sat_v32b   intro num-cube_sat_v3
2b intro num-cube_sat_v3GeoMedeelel
 
Cucumber spec - a tool takes your bdd to the next level
Cucumber spec - a tool takes your bdd to the next levelCucumber spec - a tool takes your bdd to the next level
Cucumber spec - a tool takes your bdd to the next levelnextbuild
 
Testing process
Testing processTesting process
Testing processTerry Cho
 
Software Testing Process
Software Testing ProcessSoftware Testing Process
Software Testing Processguest1f2740
 
First Presentation
First PresentationFirst Presentation
First PresentationDarren Koh
 
2017 PLSC Track: Positional Accuracy Comparison of a DII Inspire 1 and a Sens...
2017 PLSC Track: Positional Accuracy Comparison of a DII Inspire 1 and a Sens...2017 PLSC Track: Positional Accuracy Comparison of a DII Inspire 1 and a Sens...
2017 PLSC Track: Positional Accuracy Comparison of a DII Inspire 1 and a Sens...GIS in the Rockies
 
UAVmapping_11111.ppt
UAVmapping_11111.pptUAVmapping_11111.ppt
UAVmapping_11111.pptBismaJZ
 

Similaire à Geophysical System Verification - A Commercial Application (20)

PetroSync - Advanced Seismic Data Acquisition and Processing
PetroSync - Advanced Seismic Data Acquisition and ProcessingPetroSync - Advanced Seismic Data Acquisition and Processing
PetroSync - Advanced Seismic Data Acquisition and Processing
 
IGARSS 2011_Priestley.ppt
IGARSS 2011_Priestley.pptIGARSS 2011_Priestley.ppt
IGARSS 2011_Priestley.ppt
 
Charger Rocket Works PDR: 2009-2010
Charger Rocket Works PDR: 2009-2010Charger Rocket Works PDR: 2009-2010
Charger Rocket Works PDR: 2009-2010
 
Sean Blanchette Resume - Summary
Sean Blanchette Resume - SummarySean Blanchette Resume - Summary
Sean Blanchette Resume - Summary
 
Frank resume 20150707
Frank resume 20150707Frank resume 20150707
Frank resume 20150707
 
raptr_trr.pptx
raptr_trr.pptxraptr_trr.pptx
raptr_trr.pptx
 
Performance testing reference model
Performance testing reference modelPerformance testing reference model
Performance testing reference model
 
AURA: Aerial Unpaved Roads Assessment System Demonstration - October 20, 2015
AURA: Aerial Unpaved Roads Assessment System Demonstration - October 20, 2015AURA: Aerial Unpaved Roads Assessment System Demonstration - October 20, 2015
AURA: Aerial Unpaved Roads Assessment System Demonstration - October 20, 2015
 
Semester_2_team51_poster
Semester_2_team51_posterSemester_2_team51_poster
Semester_2_team51_poster
 
2b intro num-cube_sat_v3
2b   intro num-cube_sat_v32b   intro num-cube_sat_v3
2b intro num-cube_sat_v3
 
Cucumber spec - a tool takes your bdd to the next level
Cucumber spec - a tool takes your bdd to the next levelCucumber spec - a tool takes your bdd to the next level
Cucumber spec - a tool takes your bdd to the next level
 
Testing process
Testing processTesting process
Testing process
 
Software Testing Process
Software Testing ProcessSoftware Testing Process
Software Testing Process
 
First Presentation
First PresentationFirst Presentation
First Presentation
 
2017 PLSC Track: Positional Accuracy Comparison of a DII Inspire 1 and a Sens...
2017 PLSC Track: Positional Accuracy Comparison of a DII Inspire 1 and a Sens...2017 PLSC Track: Positional Accuracy Comparison of a DII Inspire 1 and a Sens...
2017 PLSC Track: Positional Accuracy Comparison of a DII Inspire 1 and a Sens...
 
Presentation
PresentationPresentation
Presentation
 
Presentation
PresentationPresentation
Presentation
 
Presentation
PresentationPresentation
Presentation
 
Presentation
PresentationPresentation
Presentation
 
UAVmapping_11111.ppt
UAVmapping_11111.pptUAVmapping_11111.ppt
UAVmapping_11111.ppt
 

Geophysical System Verification - A Commercial Application

  • 1. Commercial Application of the Physics-Based Test Strip and Seeding Approach Ryan Steigerwalt, P.G., Weston Solutions, Inc. Jim Austreng, P.E., California Department of Toxic Substances Control C. Scott Goulart, Aerojet-General Corporation UXO/Countermine/Range Forum 2009 Orlando, Florida
  • 2. TALKING POINTS Introduction and Conceptual Site Model Project planning and requirements Implementation of the Geophysical System Verification (GSV) process Planning and development Test Strip construction Seeding program Operations Results
  • 3. INTRODUCTION Project site located in Chino Hills, CA Facility owned by Aerojet-General Corporation Perform MEC detection and removal in areas not previously investigated Use DGM in all accessible areas Perform mag & dig surveys in all other areas where possible Work was conducted with DTSC oversight Dec 2008 – Feb 2009
  • 4. CONCEPTUAL SITE MODEL CSM identified anticipated munitions and facility uses Extensive geophysical prove-outs were conducted at the facility in 2004 Evaluated detection capabilities of various instruments and techniques Reported the type and quality of data required for subsequent MEC detection and removal activities
  • 5. WORK PLAN Use results from previous GPO Develop data collection parameters and quality control Perform a limited GPO and gain concurrence Mobilize remainder of crew Collect data
  • 6. PROJECT REQUIREMENTS In November 2008, wildfire struck the facility and cleared vegetation Need to perform technically defensible work, quickly, before vegetation returned Mobilize ASAP
  • 7. FIELD VARIANCE Began site setup Preparing to perform limited GPO Project team discussed GSV and potential application No GPO grid construction Start collecting data immediately No required review cycle Joint QC/QA Can continuously monitor performance Developed a brief field variance to document GSV approach- test strip construction and seeding Gained regulatory concurrence
  • 8. GSV DESIGN Test Strip Construction Seed anticipated munitions items at detection depth objectives Place seeds at least favorable orientation Establish multiple Test Strips if necessary to increase efficiency Perform daily to evaluate equipment functionality
  • 9. GSV DESIGN Seeding Program Use similar items and burial depths as Test Strips Initially place one seed within each 100-ft x 100-ft grid block Relax seed frequency to one seed per acre if performance is acceptable
  • 10. GSV IMPLEMENTATION Equipment EM61-MK2 towed sled 4 sensor RTK-GPS Navigation Test Strip Perform background and baseline survey prior to production mapping Run Test Strip daily with instrumentation Perform concurrent with standardized QC function tests Evaluate response and monitor results
  • 11. SURVEY SUMMARY Digital Geophysical Mapping Summary Completed approximately 9 total acres Includes rough and steep terrain Spanned several weeks All DGM was performed using a towed array sled
  • 12. TEST STRIP 1 RESULTS Day 1 (Baseline) Day 2 Day 3 Day 4 Day 5 Day 6
  • 13. TEST STRIP 2 RESULTS Day 8 Day 9 Day 10 Day 11
  • 14. TEST STRIP SUMMARY Direction of Travel
  • 15. SEEDING RESULTS 19 total seeds (30mm, 25mm, 20mm) Check response against Test Strip results Test Strip Avg ~8 mV Response (mV) Test Strip Avg ~6 mV Test Strip Avg ~12 mV Seed + x Target Response (mV) Response (mV)
  • 16. QUALITY ASSURANCE Regulatory site visits Industry Standard Targets and inert items 1-inch by 4-inch pipe nipples Vertical (most favorable) at 11-inches Horizontal (least favorable) at 7-inches
  • 18. BENEFITS Means to monitor geophysical system performance daily and consistently Shortened schedule Re-allocated resources to risk reduction efforts Planning variance drafted onsite No duplicate QC/QA Began production mapping next day
  • 19. LESSONS LEARNED Still need to plan ahead Define objectives Seeding program Schedule Ensure Test Strip seeds are isolated from other influence Use Industry Standard Targets to reduce variability Reality works