ERP Project
   Management
     Primer
Quick reference guide to best
practice templates and tips to
jumpstart your ERP projects
  (Enterprise Resource Planning)


       Suresh Gopalakrishnan
        sgk_00@yahoo.com
Introduction
This document will help jumpstart projects and keep
 a good control over its life cycle with best practice
 templates and tips
It is divided into four sections – Initiation/Planning,
 Execution/Control, System deployment, and Post-
 Production/Transition
All critical activities are listed in the sequence it will
 occur during a project lifecycle
Screenshot of all critical deliverable templates are in
 backup slide section



                                                              2
Not matter how much we plan this often happens..




                                               3
Project Life Cycle Activities & Milestones
                                                                        Execution and Control
   Initiation /Planning Phase                                                                                                   System Deployment
                                                                   (Design & System Configuration)
         Requirements
           Mapping                                                               Roles & Responsibilities                                  Production           GO
           BR.035                              Solution                                                                                   Cut Over Plan        LIVE
                                                Design                                  Application         Train-The-Trainer
                                                                                        Setup and
                                               BR.010                                  Configuration        End User Training
      Functional                                                                         BR.100
                                                                                                                                    Cutover
                                                                                                                                   Approach
     Deliverables                                                                                                                  Document
                                                                                     Develop Solution,      C
                                            Test                                     Data Conversion
                                         Scripts /                                    and Validation        R
                                         Sand-Box           C                                               P
                                          creation                                                                         U                  M
                                 W                          R            Functional Specs for Extension,    2
                                                                              Interfaces & Reports                         A                  G
                                 T                          P                                               /
                                                                                   MD.050                                  T                  L
                                 P                          1                                               S
     Conversion Plan
                                                                               Technical Specs for
                                                                                                            I
        CV.010                                                            Extension, Interfaces & Reports   T
                                                                                    MD.070
    Instance Strategy
        Document                                                                                                                  Setups/Data
                                                  Conversion Mapping                                                               conversion/
       Technical                                          CV.055                                                                 Code migration
                                                   (Or templates used)                                                               to PROD
      Deliverables

                         WTP; Requirements                                                                                    User
                                                                 CRP Complete                               CRP2/SIT                                      CUTOVER
                        Validation & Mapping                                                                               Acceptance
Milestones                    Complete
                                                           Solution Design Complete                         Complete
                                                                                                                            Complete
                                                                                                                                                           GO-LIVE


WTP – Workshop Test Pilot / CRP – Conference Room Pilot / SIT- System Integration Test / UAT - User Acceptance Test / MGL - Mock Go Live                   4
Initiation/Planning Phase
Prepare project management plan. Ensure it includes
  Clear list of deliverables
  RACI chart (Responsible/Accountable/Consult/Inform)
Prepare detailed MS Project Plan – with base line and
 share with the team
  Ensure each task in the plan has a clearly identified
   deliverable
  For functional resources use 35 hr work week – keep 5 hrs
   for meetings, SR (Service Request) related work etc.
Discuss with client and establish communication plan
 (Status calls, Status update emails etc..)
Get agreement on using deliverable status log for
 signoff (to monitor the time taken to get approvals)
                                                               5
Initiation/Planning Phase contd..
Discuss with client and come to an agreement on
 steering committee participants and presentation
 contents/format
Recommend using benefit map (or something similar)
 to help control scope (Note: Based on a PMI survey, every
 month 2-3% new requirement is added)
Discuss with the team and prepare an instance plan
Discuss with the team and prepare list of risks
Schedule 1-1 with each team member at a minimum
 once in two weeks
Prepare clear roles and responsibilities and discuss
 with each team member individually
                                                         6
Initiation/Planning Phase contd..
Recommend using an issue tracking system that has
 audit trail feature – Will help track time taken
 between status changes (ability to improve later)
  For e.g. Bugzilla
Discuss the usage of user survey tool to measure the
 risk
Start maintaining
  RAAIO log (Risks, Assumptions, Action Items, Issues, Out of
   scope)
  Key decision log




                                                                 7
Define Phase contd..
Why Key Decision Log?
Below email is from a real project
  Decision was taken during project start in Jul/2008
  Email is dated Feb.2011




                                                         8
Initiation/Planning Phase contd..
Conduct kick off meeting. It should include a
 minimum
  Change management process
  “Change Requests” are often seen by business as a “miss”
   from their side and could become offensive
     Work with client manager to send a positive message
  How are we drawing line between ‘In Scope’ and ‘Out of
   Scope’?
  Clear project objective (or Benefit Map)
  Test scenario expectation from business
  Document review process and expected turnaround time


                                                              9
Initiation/Planning Phase contd..
Conduct kick off meeting (Contd..)
  Major milestone, deliverables, timeline
  RACI chart (Responsible/Assist/Consult/Inform)
  Risks/Issues/Assumptions/Constraints
  CRP/UAT Entrance/Exit criteria
  Agree on a document approval timeline (sample below)




                                                          10
Initiation/Planning Phase contd..
Show the interdependency and emphasize criticality
 of getting sign off on documents on-time




                                                      11
Initiation/Planning Phase contd..
Discuss and come to an agreement with the client on:
  ‘Ballpark’ work estimates will NOT be given based on high
   level requirement
  Alternately, define slab based estimate to indicate variance.
   For e.g. Class100/50/10:
       Class 50 means ballpark estimate can be plus or minus
        50% after functional document is signed off
       This approach is better than giving an estimate with
        assumptions. Assumptions are always forgotten
  Work estimate for each requirement (unless planned
   together) will be presented as an independent project – it
   should include time to write documents, testing, re-testing
   etc
  Use Oracle AIM MD020 or other tools for estimation
                                                               12
Initiation/Planning Phase contd..
Prepare initial version of project cost/revenue
 tracking
Ensure business users have started preparing test
 scenarios/cases (Both within a track and cross-track)
Get time commitment from business on various
 activities like document review, testing etc.
Ensure “As-Is” process diagrams are mapped to “To-
 Be” – Samples in next 4 slides
Always remember the quote from Abraham Lincoln:
  “If I had six hours to chop down a tree, I’d spend the first
  four hour sharpening the ax”


                                                                  13
AS-IS Diagram – (Monthly Train Schedule)
              Part 1 of 2




                                                A




                                           14
AS-IS Diagram – (Monthly Train Schedule)
                  Part 2 of 2




A




                                               15
TO-BE Diagram – (Monthly Train Schedule)
              Part 1 of 2




                                                A




                                           16
TO-BE Diagram – (Monthly Train Schedule)
                  Part 2 of 2




A




                                               17
Initiation/Planning Phase contd..
Critical Path 101
  Critical path is tasks B-C-F-G
  Any delay will push the project dates out




                                               18
Initiation/Planning Phase contd..
Critical path with variability
  Adding mean estimates  21 days
  Adding worst case  32 days




                                         19
Initiation/Planning Phase contd..
    Randomness
         If our estimate is close to the mean then there is equal
          chance of being late as of being early
         Pretty much zero chance of ending on time!!




 50% of the             50% of the
time we will           time we will
  be early                be late



                                                                     20
Initiation/Planning Phase contd..
Randomness on critical path
  Situation when early completion is not possible
  Only chance is being late




                                                     21
Initiation/Planning Phase contd..
How do we reduce variability?
  Add buffer to each task
  But this doesn’t work due to “student syndrome” and/or
   “let’s make sure” approach




                                                            22
Initiation/Planning Phase contd..
Approach 1
  Early finish never propagates, but late finish surely will !!




                                                                   23
Initiation/Planning Phase contd..
 Approach 2 – Include design assumptions
RICEW* LIST




                                                         24
*Reports, Interfaces, Conversion, Extension, Workflows
Project Deliverable - Initiation/Planning Phase
                                                                       Project Management Related
                            Solution Related Deliverables
                                                                               Deliverables
Requirements
                           To be business process flow (new or
Definition Assessment                                                  Project management plan
                           mapped on “As-Is” flow)
Workshops
                           Workshop Findings, recommendations          Workshop Agendas and Materials
                           Initial Requirements Mapping / Gap
                                                                       MS Project Management plan
                           Documents (BR035)
                                                                       Communication plan
                                                                       Steering committee participants and
                                                                       presentation format
Solution Design and                                                    Overall benefit map for the project
                           Finalized Gap Document (BR035)
Functional Specification                                               (Optional)
                           Initial Oracle To-Be Process Flow (Future
                                                                       Initial risk log
                           Process Document-BR010)
                           Data Migration Strategy and Conversion
                                                                       Setup/Initiate issue tracking system
                           Plan (CV055 Conversion Data)
                           Instance Strategy Document                  Team member roles/responsibilities
                           Integration Strategy (TA.040)               RAAIO Log
                           Initial Functional Specifications (MD050)   On-boarding document
                                                                       Key decision log
                                                                       Project finance tracking (Monthly)
                                                                       RICEW List/Estimation Matrix

                                                                                                        25
Execution and Control Phase
After requirement session use prioritization
 worksheet
Use Object Tracking Tool for maintaining deliverable
 status
Development should not be started unless business
 provides test scenarios
Prepare entrance/exit criteria for each test cycles




Issue disposition during test cycles  Defect / Training
 log / Parking lot
                                                            26
Execution and Control Phase contd.
Ensure risk log is updated on a weekly basis
Do not use % completion field in MS Project Plan.
 Instead use actual work and remaining duration fields
  Earned value is calculated accurately with actual/remaining
   work
Start preparing training plan and content
Use Change Request and Log for new requirements
Start preparing methods to tie up converted data
 between source and target systems
Few critical concepts in next few slides
  Customer should always give the exact requirement – is it
   true?
  Customer perspective of the system
                                                                 27
Conflicting Approaches
                     Scene 1


                                                                    Scene 2



                                          Client
Customer tells exactly
what is needed and
the shopkeeper
delivers it
                          Consultant



                                                   Customer tells the “symptoms” and the doctor
                                                   diagnose the issue and prescribes a medicine

                            Both Scene 1 and 2 alone will not work
                          Best practice is to take a blended approach
                                                                                                  28
Customer Perspective - Example
                               Insurance company#1
DAY

      You are in a car accident. Called the company. Company want you to call the agent. You
 1
      call the agent and could only reach voice mail


DAY


 2    Able to reach the agent. Someone from claim office will call you


DAY


 3    Claim is not yet assigned to a rep yet



DAY

      You have a pain in the neck. Friend helps you to get medicine. Claim rep had left a v/mail
 4
      on your home phone


                                                                                                   29
Customer Perspective - Example
                        Insurance company#1 – Contd..
DAY

      You get connected to claim rep. But he handles only auto claim, not medical issues.
 5


DAY


 6    Car is taken to a mechanic and received a rental car. Neck is still hurting


DAY


 7    It is a Sunday



DAY


 8    Call from second claim rep who handles medical issues



                                                                                            30
Customer Perspective - Example
                           Insurance company#1 – Contd..

        SUCCESS# 1     All calls should be reported through agents




        SUCCESS# 2
                       Assignment must occur within one business day of
                       being reported by the agent




        SUCCESS# 3    Claim rep should contact the customer within one
                      business day                                                 100%
                                                                                 SUCCESS IN
                                                                                   CLAIM
                                                                                 HANDLING

                       Claim should be assigned based on specialty
        SUCCESS# 4
                       (auto/medical)

But customer is already looking for another insurance. Key take away is system thinking vs. silo
                                            thinking                                       31
Customer Perspective - Example
                          Insurance company# 2
DAY



 1    You are in a car accident. Called the company. Claim rep called in 10 minutes
      and arrived at scene in another 10 minutes.
        Rep arranged an appointment with doctor next day
        Rental car arrived in next 30 minutes
        Tow truck arrived in 30 minutes and took the car
        End of 1 hr all issues have been taken care!!




                                                                                      32
Project Deliverable – Execution and Control Phase
                                                        Project Management Related
             Solution Related Deliverables
                                                                Deliverables
CRP I       Data Conversion Templates (CV.060)          Validate entrance criteria for CRP I
                                                        Deliverable status log (End of each test
                                                        cycle)
            CRP I Configuration Documents (Set-Up       Initial survey using Value at risk
            Document BR100).                            assessment tool (Optional)
                                                        CRP I Test Results and document
            Final Functional Specifications (MD050)
                                                        findings and issues
            Business flow scenarios based on the
            solution design given in the signed BR010   MS Project Plan updates (Weekly)
            document
            Test data setup                             Change Request and Log as needed
            First version for Configuration Documents
                                                        Validate exit criteria for CRP I and get
            for each functional project track (BR100
                                                        sign off from business
            Set up document)
            Updated Business Test Scenarios
            Final Oracle To-Be Process Flow BR010
            (Solution Design Doc)
            MD050 for all RICEW components
            Work estimation (Oracle AIM - MD020)
            Begin MD070 preparation
            Begin development of RICEW components
                                                                                           33
Project Deliverable – Execution and Control Phase
                      Solution Related Deliverables           Project Management Related Deliverables

CRP2/System
                   Configured SIT Instance                       Validate entrance criteria for CRP II/SIT
Integration Test

                   Finalize technical specification (MD070)
                                                                 Start preparing training plan
                   for R.I.C.E
                                                                 CRP II Test Results and document
                   Load validate converted data
                                                                 findings and issues
                   Updated version for Configuration
                                                                 Validate exit criteria for CRP II and get
                   Documents for each functional project
                                                                 sign off from business
                   track (BR100 Set up document)
                   Updated Business Test Scenarios (if
                   needed)

                   Complete documentation for technical
                   specification (MD070)

                   Rework of RICEW components as needed




                                                                                                    34
System Deployment Phase
Prepare project readiness checklist and cutover plan
 before final UAT
  Plan for an intranet website to publish hr to hr status of the
   cutover process so that the organization can view progress
  Document contingency plan (for e.g. how to ship materials
   manually if the system crashes on go live day)
Ensure mock cutover activities are performed to
 perfect the timing
  Include month end financial close
Always plan for a mock go live before go live – copy
 gold instance with full data and setups


                                                                    35
System Deployment Phase
Ensure at least one day of testing in UAT is performed
 with all automated programs scheduled as in
 production along with other manual transactional
 activities
   Many issues during first week of go live attributes to one
    program stepping on another when they were launched
    simultaneously
   During test cycles programs are launched manually and
    hence the chances of 2 or more programs running
    simultaneously are pretty low
Ensure business users are 100% trained on the
 system and they drive the UAT testing
 Last but not the least, drink plenty of water during cutover and
  go live week 
                                                                 36
Project Deliverable – System Deployment Phase
                                                               Project Management Related
                    Solution Related Deliverables
                                                                       Deliverables
                    Configured UAT Instance with converted
UAT                                                            Validate entrance criteria for UAT
                    data and custom objects installed

                                                               Complete findings for UAT Test Results
                    Train Client super users (trainers)
                                                               Document

                    Complete final version for Configuration
                                                               Finalize cutover plan
                    Documents (Set-Up Document BR100)

                    Lead the creation and execution of the     Prepare and publish project readiness
                    Cut-Over plan                              checklist
                                                               Get cutover status intranet website
                                                               ready (optional)

                                                               Validate exit criteria for UAT and get
End User Training   Training Materials
                                                               sign off from business

                    Train the Trainer program execution
                    Execute final end user training




                                                                                                    37
Post Production/Transition
Prepare “PM.010 Transition Strategy” and/or “PM.030
 Transition And Contingency Plan” (Oracle AIM)
  Make it clear how client team will acquire knowledge and what
   documents will be provided as a part of knowledge transfer
  Ensure tier 1 support is provided by project team during first 3-4
   weeks
Prepare lessons learned with input from client business
 and IT
Prepare project completion report
Establish a workflow for issue resolution (see samples in
 next 2 slides)

                                                                  38
Issue resolution workflow – Sample 1




                                       39
Issue resolution workflow – Sample 2


                                   Having an issue
                                  tracking software
                                    (like Remedy)
                                  helps track these
                                       lead times




                                              40
End goal is to avoid the below




       B                                  C




                                                                                A
                                                                                      41
When A = B, but B not=C, we have defect       When A not = B we have change request
…and certainly this !




                        42
Backup Slides
Project Plan
           If milestone is due within 3 days and the progress
           >= 80% then status = Yellow

           If milestone is due within 3 days and the progress
           < 80% then status = Red

           For tasks If today (date) is past the start date of the
           task and progress is reported < (days since
           start/duration) then Yellow to indicate a task with
           insufficient progress.




                                                             44
Instance Plan



                Zero slack. Any
                delay will push
                the timeline.
                Only alternate
                plan is to run
                UAT in CRP3
                instance




                                   Mock Go
                                  Live – Final
                                  test before
                                    cutover



                                           45
Instance Plan




                46
Status Dashboard




                   47
Sample Benefit Map




Complete                             Desired
Project or                         Result of the
 part of a                           program
  project




             Outcome
                                                   48
Risk Log




           49
RACI Chart




             50
Requirement Prioritization




                             51
Deliverable Status Log




   Advance notice to
    indicate when a    Keeps track of #
   document will be    of days taken for
     sent for review      review and
                           approval
                                           52
Key Decision Log




                   53
Test Script Within a Track (Summary)




                                       54
Test Script Within a Track (Detail)




                                      55
Cross Track Test Script




                          56
Project Readiness Scorecard




                            Green when
                       High Priority Issue=0 and
                          medium issue < 5
                            Yellow when
                           High > 0 but < 3
                       and medium >5 and < 10
                              Red when
                                High >3




                                               57
Cutover Plan (Hr by Hr)




                          58
Contingency Plan Template




                            59
Thank you for inputs:
- Ramesh Doraiswamy (rdoraiswamy@gmail.com)




                                              60

Contenu connexe

Tendances

Sap table relations
Sap table relationsSap table relations
Sap table relationsPhong Ho
 
Hana for copa
Hana for copaHana for copa
Hana for copanc27770
 
Dialog Programming Overview
Dialog Programming OverviewDialog Programming Overview
Dialog Programming Overviewsapdocs. info
 
Procure to Pay Cycle Overview
Procure to Pay Cycle OverviewProcure to Pay Cycle Overview
Procure to Pay Cycle OverviewAbdullah Galal
 
Kumaresan Resume_SAP SD & LE
Kumaresan Resume_SAP SD & LEKumaresan Resume_SAP SD & LE
Kumaresan Resume_SAP SD & LEKumaresh .R
 
Sap fi-gl-step-by-step-material
Sap fi-gl-step-by-step-materialSap fi-gl-step-by-step-material
Sap fi-gl-step-by-step-materialkotakonda Murali
 
Resume of Sugavanan - Oracle Apps Technical Consultant
Resume of Sugavanan - Oracle Apps Technical ConsultantResume of Sugavanan - Oracle Apps Technical Consultant
Resume of Sugavanan - Oracle Apps Technical ConsultantSugavanan Arunachalam
 
Monetizing Postal Services with SAP Hybris Billing
Monetizing Postal Services with SAP Hybris BillingMonetizing Postal Services with SAP Hybris Billing
Monetizing Postal Services with SAP Hybris BillingIsabelle Roussin
 
Oracle Financial with 8 years 4 months
Oracle Financial with 8 years 4 monthsOracle Financial with 8 years 4 months
Oracle Financial with 8 years 4 monthsSundar Venkatachalam
 
Sap Implementation Life Cycle Complete Process
Sap Implementation Life Cycle Complete ProcessSap Implementation Life Cycle Complete Process
Sap Implementation Life Cycle Complete ProcessSrinath Maharana
 
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.infoSAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.infosapdocs. info
 
T codes
T codesT codes
T codesRAJ P
 
User Status Profile (SAP PS)
User Status Profile (SAP PS)User Status Profile (SAP PS)
User Status Profile (SAP PS)Soumya De
 
Abhishek Sengupta SAP SD Resume
Abhishek Sengupta SAP SD ResumeAbhishek Sengupta SAP SD Resume
Abhishek Sengupta SAP SD ResumeAbhishek Sengupta
 
SAMBIT Resume-SAP PM & PP Consultant
SAMBIT Resume-SAP PM & PP ConsultantSAMBIT Resume-SAP PM & PP Consultant
SAMBIT Resume-SAP PM & PP ConsultantSambit Sahoo
 
Chapter 02 sap script forms
Chapter 02 sap script formsChapter 02 sap script forms
Chapter 02 sap script formsKranthi Kumar
 

Tendances (20)

Sap table relations
Sap table relationsSap table relations
Sap table relations
 
Hana for copa
Hana for copaHana for copa
Hana for copa
 
Resume_SAP_SD_completed
Resume_SAP_SD_completedResume_SAP_SD_completed
Resume_SAP_SD_completed
 
Dialog Programming Overview
Dialog Programming OverviewDialog Programming Overview
Dialog Programming Overview
 
Procure to Pay Cycle Overview
Procure to Pay Cycle OverviewProcure to Pay Cycle Overview
Procure to Pay Cycle Overview
 
Kumaresan Resume_SAP SD & LE
Kumaresan Resume_SAP SD & LEKumaresan Resume_SAP SD & LE
Kumaresan Resume_SAP SD & LE
 
Field symbols
Field symbolsField symbols
Field symbols
 
Sap fi-gl-step-by-step-material
Sap fi-gl-step-by-step-materialSap fi-gl-step-by-step-material
Sap fi-gl-step-by-step-material
 
Resume of Sugavanan - Oracle Apps Technical Consultant
Resume of Sugavanan - Oracle Apps Technical ConsultantResume of Sugavanan - Oracle Apps Technical Consultant
Resume of Sugavanan - Oracle Apps Technical Consultant
 
Monetizing Postal Services with SAP Hybris Billing
Monetizing Postal Services with SAP Hybris BillingMonetizing Postal Services with SAP Hybris Billing
Monetizing Postal Services with SAP Hybris Billing
 
Oracle Financial with 8 years 4 months
Oracle Financial with 8 years 4 monthsOracle Financial with 8 years 4 months
Oracle Financial with 8 years 4 months
 
Sap Implementation Life Cycle Complete Process
Sap Implementation Life Cycle Complete ProcessSap Implementation Life Cycle Complete Process
Sap Implementation Life Cycle Complete Process
 
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.infoSAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
 
T codes
T codesT codes
T codes
 
User Status Profile (SAP PS)
User Status Profile (SAP PS)User Status Profile (SAP PS)
User Status Profile (SAP PS)
 
Sap infosys fico
Sap infosys ficoSap infosys fico
Sap infosys fico
 
Abhishek Sengupta SAP SD Resume
Abhishek Sengupta SAP SD ResumeAbhishek Sengupta SAP SD Resume
Abhishek Sengupta SAP SD Resume
 
SAMBIT Resume-SAP PM & PP Consultant
SAMBIT Resume-SAP PM & PP ConsultantSAMBIT Resume-SAP PM & PP Consultant
SAMBIT Resume-SAP PM & PP Consultant
 
SAP CRM Overview
SAP CRM OverviewSAP CRM Overview
SAP CRM Overview
 
Chapter 02 sap script forms
Chapter 02 sap script formsChapter 02 sap script forms
Chapter 02 sap script forms
 

En vedette

Oracle Implementation Project Template
Oracle Implementation Project TemplateOracle Implementation Project Template
Oracle Implementation Project Templateacribe
 
Project report erp success
Project report erp successProject report erp success
Project report erp successSurajeet Singh
 
ERP Implementation A Complete Guide
ERP Implementation A Complete GuideERP Implementation A Complete Guide
ERP Implementation A Complete Guideguest42d52b7c
 
Oracle Unified Method (OUM)
Oracle Unified Method (OUM) Oracle Unified Method (OUM)
Oracle Unified Method (OUM) UBC Corporation
 
Aim vs oum documents
Aim vs oum documentsAim vs oum documents
Aim vs oum documentsjaydezr
 
Project organisation and erp implementation method
Project organisation and erp implementation methodProject organisation and erp implementation method
Project organisation and erp implementation methodGaurav Kumar
 
Enterprise Resource Planning- BEST PPT
Enterprise Resource Planning- BEST PPTEnterprise Resource Planning- BEST PPT
Enterprise Resource Planning- BEST PPTSiddharth Modi
 
Concepts of cutover planning and management
Concepts of cutover planning and managementConcepts of cutover planning and management
Concepts of cutover planning and managementSanjay Choubey
 
5 Types of USER ACCEPTANCE TESTING (UAT)
5 Types of USER ACCEPTANCE TESTING (UAT)5 Types of USER ACCEPTANCE TESTING (UAT)
5 Types of USER ACCEPTANCE TESTING (UAT)Usersnap
 
Test Estimation using Test Case Point Analysis method
Test Estimation using Test Case Point Analysis methodTest Estimation using Test Case Point Analysis method
Test Estimation using Test Case Point Analysis methodKMS Technology
 

En vedette (20)

Oracle Implementation Project Template
Oracle Implementation Project TemplateOracle Implementation Project Template
Oracle Implementation Project Template
 
Project Plan ERP Sample by ijaz haider malik weboriez@hotmail
Project Plan ERP Sample by ijaz haider malik weboriez@hotmailProject Plan ERP Sample by ijaz haider malik weboriez@hotmail
Project Plan ERP Sample by ijaz haider malik weboriez@hotmail
 
Erp final proj report slideshare
Erp final proj report slideshareErp final proj report slideshare
Erp final proj report slideshare
 
ERP PROJECT
ERP PROJECTERP PROJECT
ERP PROJECT
 
Cutover Plan V2
Cutover Plan V2Cutover Plan V2
Cutover Plan V2
 
Project report erp success
Project report erp successProject report erp success
Project report erp success
 
Cutover plan template Tool
Cutover plan template ToolCutover plan template Tool
Cutover plan template Tool
 
ERP Implementation A Complete Guide
ERP Implementation A Complete GuideERP Implementation A Complete Guide
ERP Implementation A Complete Guide
 
Oracle Aim Methodology
Oracle Aim MethodologyOracle Aim Methodology
Oracle Aim Methodology
 
Oracle Unified Method (OUM)
Oracle Unified Method (OUM) Oracle Unified Method (OUM)
Oracle Unified Method (OUM)
 
Aim vs oum documents
Aim vs oum documentsAim vs oum documents
Aim vs oum documents
 
Project organisation and erp implementation method
Project organisation and erp implementation methodProject organisation and erp implementation method
Project organisation and erp implementation method
 
Application Implementation Methodology (AIM)
Application Implementation Methodology (AIM)Application Implementation Methodology (AIM)
Application Implementation Methodology (AIM)
 
Enterprise Resource Planning- BEST PPT
Enterprise Resource Planning- BEST PPTEnterprise Resource Planning- BEST PPT
Enterprise Resource Planning- BEST PPT
 
Risk Management Framework
Risk Management FrameworkRisk Management Framework
Risk Management Framework
 
ERP Project Scope
ERP Project ScopeERP Project Scope
ERP Project Scope
 
Concepts of cutover planning and management
Concepts of cutover planning and managementConcepts of cutover planning and management
Concepts of cutover planning and management
 
5 Types of USER ACCEPTANCE TESTING (UAT)
5 Types of USER ACCEPTANCE TESTING (UAT)5 Types of USER ACCEPTANCE TESTING (UAT)
5 Types of USER ACCEPTANCE TESTING (UAT)
 
ASAP 8.0 Methodology
ASAP 8.0 MethodologyASAP 8.0 Methodology
ASAP 8.0 Methodology
 
Test Estimation using Test Case Point Analysis method
Test Estimation using Test Case Point Analysis methodTest Estimation using Test Case Point Analysis method
Test Estimation using Test Case Point Analysis method
 

Similaire à ERP Project Management Primer

Oracle aim-project-management-methodology
Oracle aim-project-management-methodologyOracle aim-project-management-methodology
Oracle aim-project-management-methodologygsmy02
 
An ASAP Validation Implementation Approach by Qualit Consulting
An ASAP Validation Implementation Approach by  Qualit ConsultingAn ASAP Validation Implementation Approach by  Qualit Consulting
An ASAP Validation Implementation Approach by Qualit Consultingaesww
 
Aras How To Think About Aras Integrations
Aras How To Think About Aras IntegrationsAras How To Think About Aras Integrations
Aras How To Think About Aras IntegrationsProdeos
 
Aras how-to-think-about-aras-integrations
Aras how-to-think-about-aras-integrationsAras how-to-think-about-aras-integrations
Aras how-to-think-about-aras-integrationshisatsugum
 
IdealECP presentation for Novo Nordisk
IdealECP presentation for Novo NordiskIdealECP presentation for Novo Nordisk
IdealECP presentation for Novo Nordiskcbiddle2
 
Walley.tina
Walley.tinaWalley.tina
Walley.tinaNASAPMC
 
Automating user provisioning with SAP NW BPM
Automating user provisioning with SAP NW BPMAutomating user provisioning with SAP NW BPM
Automating user provisioning with SAP NW BPMBalakrishnan Bala B
 
HP Service Delivery Platform 3.0 Launch
HP Service Delivery Platform 3.0 LaunchHP Service Delivery Platform 3.0 Launch
HP Service Delivery Platform 3.0 Launchgrahamwright
 
Saa S Scio Engagement Model V2 2 Generic
Saa S Scio Engagement Model V2 2  GenericSaa S Scio Engagement Model V2 2  Generic
Saa S Scio Engagement Model V2 2 GenericScioSales
 
Sla Model 2002 Jvk
Sla Model 2002 JvkSla Model 2002 Jvk
Sla Model 2002 JvkDrJVK
 
Software enginnering unit 01 by manoj kumar soni
Software enginnering unit 01 by manoj kumar soniSoftware enginnering unit 01 by manoj kumar soni
Software enginnering unit 01 by manoj kumar sonimanojsonikgn
 
Upgrades and enhancement_packs_explained_mar_2008
Upgrades and enhancement_packs_explained_mar_2008Upgrades and enhancement_packs_explained_mar_2008
Upgrades and enhancement_packs_explained_mar_2008sissie1234
 
Aras PLM Software Integration Basics
Aras PLM Software Integration BasicsAras PLM Software Integration Basics
Aras PLM Software Integration BasicsAras
 
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud AdoptionCloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud AdoptionNewvewm
 
Are good SharePoint solutions only a myth?
Are good SharePoint solutions only a myth?Are good SharePoint solutions only a myth?
Are good SharePoint solutions only a myth?Adis Jugo
 
Are you geared for Outsourcing Governance?
Are you geared for Outsourcing Governance?Are you geared for Outsourcing Governance?
Are you geared for Outsourcing Governance?Digite Inc
 
Brief Intro to Aras PLM Solutions
Brief Intro to Aras PLM SolutionsBrief Intro to Aras PLM Solutions
Brief Intro to Aras PLM SolutionsAras
 

Similaire à ERP Project Management Primer (20)

Oracle aim-project-management-methodology
Oracle aim-project-management-methodologyOracle aim-project-management-methodology
Oracle aim-project-management-methodology
 
LQB Busniess plan
LQB Busniess planLQB Busniess plan
LQB Busniess plan
 
PLM - ERP integration
PLM - ERP integrationPLM - ERP integration
PLM - ERP integration
 
An ASAP Validation Implementation Approach by Qualit Consulting
An ASAP Validation Implementation Approach by  Qualit ConsultingAn ASAP Validation Implementation Approach by  Qualit Consulting
An ASAP Validation Implementation Approach by Qualit Consulting
 
Aras How To Think About Aras Integrations
Aras How To Think About Aras IntegrationsAras How To Think About Aras Integrations
Aras How To Think About Aras Integrations
 
Aras how-to-think-about-aras-integrations
Aras how-to-think-about-aras-integrationsAras how-to-think-about-aras-integrations
Aras how-to-think-about-aras-integrations
 
IdealECP presentation for Novo Nordisk
IdealECP presentation for Novo NordiskIdealECP presentation for Novo Nordisk
IdealECP presentation for Novo Nordisk
 
Walley.tina
Walley.tinaWalley.tina
Walley.tina
 
Automating user provisioning with SAP NW BPM
Automating user provisioning with SAP NW BPMAutomating user provisioning with SAP NW BPM
Automating user provisioning with SAP NW BPM
 
HP Service Delivery Platform 3.0 Launch
HP Service Delivery Platform 3.0 LaunchHP Service Delivery Platform 3.0 Launch
HP Service Delivery Platform 3.0 Launch
 
Saa S Scio Engagement Model V2 2 Generic
Saa S Scio Engagement Model V2 2  GenericSaa S Scio Engagement Model V2 2  Generic
Saa S Scio Engagement Model V2 2 Generic
 
Sla Model 2002 Jvk
Sla Model 2002 JvkSla Model 2002 Jvk
Sla Model 2002 Jvk
 
Software enginnering unit 01 by manoj kumar soni
Software enginnering unit 01 by manoj kumar soniSoftware enginnering unit 01 by manoj kumar soni
Software enginnering unit 01 by manoj kumar soni
 
Upgrades and enhancement_packs_explained_mar_2008
Upgrades and enhancement_packs_explained_mar_2008Upgrades and enhancement_packs_explained_mar_2008
Upgrades and enhancement_packs_explained_mar_2008
 
Aras PLM Software Integration Basics
Aras PLM Software Integration BasicsAras PLM Software Integration Basics
Aras PLM Software Integration Basics
 
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud AdoptionCloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
 
NetWeaver Gateway- Service Builder
NetWeaver Gateway- Service BuilderNetWeaver Gateway- Service Builder
NetWeaver Gateway- Service Builder
 
Are good SharePoint solutions only a myth?
Are good SharePoint solutions only a myth?Are good SharePoint solutions only a myth?
Are good SharePoint solutions only a myth?
 
Are you geared for Outsourcing Governance?
Are you geared for Outsourcing Governance?Are you geared for Outsourcing Governance?
Are you geared for Outsourcing Governance?
 
Brief Intro to Aras PLM Solutions
Brief Intro to Aras PLM SolutionsBrief Intro to Aras PLM Solutions
Brief Intro to Aras PLM Solutions
 

Plus de sureshgk

Ashvin emorysummerprogram
Ashvin emorysummerprogramAshvin emorysummerprogram
Ashvin emorysummerprogramsureshgk
 
MBA takeaways
MBA takeawaysMBA takeaways
MBA takeawayssureshgk
 
CTY High Honors
CTY High HonorsCTY High Honors
CTY High Honorssureshgk
 
Essence Of Project Management In Ten Bullets
Essence Of Project Management In Ten BulletsEssence Of Project Management In Ten Bullets
Essence Of Project Management In Ten Bulletssureshgk
 
Six point approach to managing transformations
Six point approach to managing transformationsSix point approach to managing transformations
Six point approach to managing transformationssureshgk
 
On Boarding
On Boarding On Boarding
On Boarding sureshgk
 
Pre planning for large ERP/CRM initiative
Pre planning for large ERP/CRM  initiativePre planning for large ERP/CRM  initiative
Pre planning for large ERP/CRM initiativesureshgk
 
Four segments of mind
Four segments of mindFour segments of mind
Four segments of mindsureshgk
 

Plus de sureshgk (8)

Ashvin emorysummerprogram
Ashvin emorysummerprogramAshvin emorysummerprogram
Ashvin emorysummerprogram
 
MBA takeaways
MBA takeawaysMBA takeaways
MBA takeaways
 
CTY High Honors
CTY High HonorsCTY High Honors
CTY High Honors
 
Essence Of Project Management In Ten Bullets
Essence Of Project Management In Ten BulletsEssence Of Project Management In Ten Bullets
Essence Of Project Management In Ten Bullets
 
Six point approach to managing transformations
Six point approach to managing transformationsSix point approach to managing transformations
Six point approach to managing transformations
 
On Boarding
On Boarding On Boarding
On Boarding
 
Pre planning for large ERP/CRM initiative
Pre planning for large ERP/CRM  initiativePre planning for large ERP/CRM  initiative
Pre planning for large ERP/CRM initiative
 
Four segments of mind
Four segments of mindFour segments of mind
Four segments of mind
 

Dernier

International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 

Dernier (20)

Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 

ERP Project Management Primer

  • 1. ERP Project Management Primer Quick reference guide to best practice templates and tips to jumpstart your ERP projects (Enterprise Resource Planning) Suresh Gopalakrishnan sgk_00@yahoo.com
  • 2. Introduction This document will help jumpstart projects and keep a good control over its life cycle with best practice templates and tips It is divided into four sections – Initiation/Planning, Execution/Control, System deployment, and Post- Production/Transition All critical activities are listed in the sequence it will occur during a project lifecycle Screenshot of all critical deliverable templates are in backup slide section 2
  • 3. Not matter how much we plan this often happens.. 3
  • 4. Project Life Cycle Activities & Milestones Execution and Control Initiation /Planning Phase System Deployment (Design & System Configuration) Requirements Mapping Roles & Responsibilities Production GO BR.035 Solution Cut Over Plan LIVE Design Application Train-The-Trainer Setup and BR.010 Configuration End User Training Functional BR.100 Cutover Approach Deliverables Document Develop Solution, C Test Data Conversion Scripts / and Validation R Sand-Box C P creation U M W R Functional Specs for Extension, 2 Interfaces & Reports A G T P / MD.050 T L P 1 S Conversion Plan Technical Specs for I CV.010 Extension, Interfaces & Reports T MD.070 Instance Strategy Document Setups/Data Conversion Mapping conversion/ Technical CV.055 Code migration (Or templates used) to PROD Deliverables WTP; Requirements User CRP Complete CRP2/SIT CUTOVER Validation & Mapping Acceptance Milestones Complete Solution Design Complete Complete Complete GO-LIVE WTP – Workshop Test Pilot / CRP – Conference Room Pilot / SIT- System Integration Test / UAT - User Acceptance Test / MGL - Mock Go Live 4
  • 5. Initiation/Planning Phase Prepare project management plan. Ensure it includes  Clear list of deliverables  RACI chart (Responsible/Accountable/Consult/Inform) Prepare detailed MS Project Plan – with base line and share with the team  Ensure each task in the plan has a clearly identified deliverable  For functional resources use 35 hr work week – keep 5 hrs for meetings, SR (Service Request) related work etc. Discuss with client and establish communication plan (Status calls, Status update emails etc..) Get agreement on using deliverable status log for signoff (to monitor the time taken to get approvals) 5
  • 6. Initiation/Planning Phase contd.. Discuss with client and come to an agreement on steering committee participants and presentation contents/format Recommend using benefit map (or something similar) to help control scope (Note: Based on a PMI survey, every month 2-3% new requirement is added) Discuss with the team and prepare an instance plan Discuss with the team and prepare list of risks Schedule 1-1 with each team member at a minimum once in two weeks Prepare clear roles and responsibilities and discuss with each team member individually 6
  • 7. Initiation/Planning Phase contd.. Recommend using an issue tracking system that has audit trail feature – Will help track time taken between status changes (ability to improve later)  For e.g. Bugzilla Discuss the usage of user survey tool to measure the risk Start maintaining  RAAIO log (Risks, Assumptions, Action Items, Issues, Out of scope)  Key decision log 7
  • 8. Define Phase contd.. Why Key Decision Log? Below email is from a real project  Decision was taken during project start in Jul/2008  Email is dated Feb.2011 8
  • 9. Initiation/Planning Phase contd.. Conduct kick off meeting. It should include a minimum  Change management process  “Change Requests” are often seen by business as a “miss” from their side and could become offensive  Work with client manager to send a positive message  How are we drawing line between ‘In Scope’ and ‘Out of Scope’?  Clear project objective (or Benefit Map)  Test scenario expectation from business  Document review process and expected turnaround time 9
  • 10. Initiation/Planning Phase contd.. Conduct kick off meeting (Contd..)  Major milestone, deliverables, timeline  RACI chart (Responsible/Assist/Consult/Inform)  Risks/Issues/Assumptions/Constraints  CRP/UAT Entrance/Exit criteria  Agree on a document approval timeline (sample below) 10
  • 11. Initiation/Planning Phase contd.. Show the interdependency and emphasize criticality of getting sign off on documents on-time 11
  • 12. Initiation/Planning Phase contd.. Discuss and come to an agreement with the client on:  ‘Ballpark’ work estimates will NOT be given based on high level requirement  Alternately, define slab based estimate to indicate variance. For e.g. Class100/50/10:  Class 50 means ballpark estimate can be plus or minus 50% after functional document is signed off  This approach is better than giving an estimate with assumptions. Assumptions are always forgotten  Work estimate for each requirement (unless planned together) will be presented as an independent project – it should include time to write documents, testing, re-testing etc  Use Oracle AIM MD020 or other tools for estimation 12
  • 13. Initiation/Planning Phase contd.. Prepare initial version of project cost/revenue tracking Ensure business users have started preparing test scenarios/cases (Both within a track and cross-track) Get time commitment from business on various activities like document review, testing etc. Ensure “As-Is” process diagrams are mapped to “To- Be” – Samples in next 4 slides Always remember the quote from Abraham Lincoln:  “If I had six hours to chop down a tree, I’d spend the first four hour sharpening the ax” 13
  • 14. AS-IS Diagram – (Monthly Train Schedule) Part 1 of 2 A 14
  • 15. AS-IS Diagram – (Monthly Train Schedule) Part 2 of 2 A 15
  • 16. TO-BE Diagram – (Monthly Train Schedule) Part 1 of 2 A 16
  • 17. TO-BE Diagram – (Monthly Train Schedule) Part 2 of 2 A 17
  • 18. Initiation/Planning Phase contd.. Critical Path 101  Critical path is tasks B-C-F-G  Any delay will push the project dates out 18
  • 19. Initiation/Planning Phase contd.. Critical path with variability  Adding mean estimates  21 days  Adding worst case  32 days 19
  • 20. Initiation/Planning Phase contd.. Randomness  If our estimate is close to the mean then there is equal chance of being late as of being early  Pretty much zero chance of ending on time!! 50% of the 50% of the time we will time we will be early be late 20
  • 21. Initiation/Planning Phase contd.. Randomness on critical path  Situation when early completion is not possible  Only chance is being late 21
  • 22. Initiation/Planning Phase contd.. How do we reduce variability?  Add buffer to each task  But this doesn’t work due to “student syndrome” and/or “let’s make sure” approach 22
  • 23. Initiation/Planning Phase contd.. Approach 1  Early finish never propagates, but late finish surely will !! 23
  • 24. Initiation/Planning Phase contd.. Approach 2 – Include design assumptions RICEW* LIST 24 *Reports, Interfaces, Conversion, Extension, Workflows
  • 25. Project Deliverable - Initiation/Planning Phase Project Management Related Solution Related Deliverables Deliverables Requirements To be business process flow (new or Definition Assessment Project management plan mapped on “As-Is” flow) Workshops Workshop Findings, recommendations Workshop Agendas and Materials Initial Requirements Mapping / Gap MS Project Management plan Documents (BR035) Communication plan Steering committee participants and presentation format Solution Design and Overall benefit map for the project Finalized Gap Document (BR035) Functional Specification (Optional) Initial Oracle To-Be Process Flow (Future Initial risk log Process Document-BR010) Data Migration Strategy and Conversion Setup/Initiate issue tracking system Plan (CV055 Conversion Data) Instance Strategy Document Team member roles/responsibilities Integration Strategy (TA.040) RAAIO Log Initial Functional Specifications (MD050) On-boarding document Key decision log Project finance tracking (Monthly) RICEW List/Estimation Matrix 25
  • 26. Execution and Control Phase After requirement session use prioritization worksheet Use Object Tracking Tool for maintaining deliverable status Development should not be started unless business provides test scenarios Prepare entrance/exit criteria for each test cycles Issue disposition during test cycles  Defect / Training log / Parking lot 26
  • 27. Execution and Control Phase contd. Ensure risk log is updated on a weekly basis Do not use % completion field in MS Project Plan. Instead use actual work and remaining duration fields  Earned value is calculated accurately with actual/remaining work Start preparing training plan and content Use Change Request and Log for new requirements Start preparing methods to tie up converted data between source and target systems Few critical concepts in next few slides  Customer should always give the exact requirement – is it true?  Customer perspective of the system 27
  • 28. Conflicting Approaches Scene 1 Scene 2 Client Customer tells exactly what is needed and the shopkeeper delivers it Consultant Customer tells the “symptoms” and the doctor diagnose the issue and prescribes a medicine Both Scene 1 and 2 alone will not work Best practice is to take a blended approach 28
  • 29. Customer Perspective - Example Insurance company#1 DAY You are in a car accident. Called the company. Company want you to call the agent. You 1 call the agent and could only reach voice mail DAY 2 Able to reach the agent. Someone from claim office will call you DAY 3 Claim is not yet assigned to a rep yet DAY You have a pain in the neck. Friend helps you to get medicine. Claim rep had left a v/mail 4 on your home phone 29
  • 30. Customer Perspective - Example Insurance company#1 – Contd.. DAY You get connected to claim rep. But he handles only auto claim, not medical issues. 5 DAY 6 Car is taken to a mechanic and received a rental car. Neck is still hurting DAY 7 It is a Sunday DAY 8 Call from second claim rep who handles medical issues 30
  • 31. Customer Perspective - Example Insurance company#1 – Contd.. SUCCESS# 1 All calls should be reported through agents SUCCESS# 2 Assignment must occur within one business day of being reported by the agent SUCCESS# 3 Claim rep should contact the customer within one business day 100% SUCCESS IN CLAIM HANDLING Claim should be assigned based on specialty SUCCESS# 4 (auto/medical) But customer is already looking for another insurance. Key take away is system thinking vs. silo thinking 31
  • 32. Customer Perspective - Example Insurance company# 2 DAY 1 You are in a car accident. Called the company. Claim rep called in 10 minutes and arrived at scene in another 10 minutes. Rep arranged an appointment with doctor next day Rental car arrived in next 30 minutes Tow truck arrived in 30 minutes and took the car End of 1 hr all issues have been taken care!! 32
  • 33. Project Deliverable – Execution and Control Phase Project Management Related Solution Related Deliverables Deliverables CRP I Data Conversion Templates (CV.060) Validate entrance criteria for CRP I Deliverable status log (End of each test cycle) CRP I Configuration Documents (Set-Up Initial survey using Value at risk Document BR100). assessment tool (Optional) CRP I Test Results and document Final Functional Specifications (MD050) findings and issues Business flow scenarios based on the solution design given in the signed BR010 MS Project Plan updates (Weekly) document Test data setup Change Request and Log as needed First version for Configuration Documents Validate exit criteria for CRP I and get for each functional project track (BR100 sign off from business Set up document) Updated Business Test Scenarios Final Oracle To-Be Process Flow BR010 (Solution Design Doc) MD050 for all RICEW components Work estimation (Oracle AIM - MD020) Begin MD070 preparation Begin development of RICEW components 33
  • 34. Project Deliverable – Execution and Control Phase Solution Related Deliverables Project Management Related Deliverables CRP2/System Configured SIT Instance Validate entrance criteria for CRP II/SIT Integration Test Finalize technical specification (MD070) Start preparing training plan for R.I.C.E CRP II Test Results and document Load validate converted data findings and issues Updated version for Configuration Validate exit criteria for CRP II and get Documents for each functional project sign off from business track (BR100 Set up document) Updated Business Test Scenarios (if needed) Complete documentation for technical specification (MD070) Rework of RICEW components as needed 34
  • 35. System Deployment Phase Prepare project readiness checklist and cutover plan before final UAT  Plan for an intranet website to publish hr to hr status of the cutover process so that the organization can view progress  Document contingency plan (for e.g. how to ship materials manually if the system crashes on go live day) Ensure mock cutover activities are performed to perfect the timing  Include month end financial close Always plan for a mock go live before go live – copy gold instance with full data and setups 35
  • 36. System Deployment Phase Ensure at least one day of testing in UAT is performed with all automated programs scheduled as in production along with other manual transactional activities  Many issues during first week of go live attributes to one program stepping on another when they were launched simultaneously  During test cycles programs are launched manually and hence the chances of 2 or more programs running simultaneously are pretty low Ensure business users are 100% trained on the system and they drive the UAT testing  Last but not the least, drink plenty of water during cutover and go live week  36
  • 37. Project Deliverable – System Deployment Phase Project Management Related Solution Related Deliverables Deliverables Configured UAT Instance with converted UAT Validate entrance criteria for UAT data and custom objects installed Complete findings for UAT Test Results Train Client super users (trainers) Document Complete final version for Configuration Finalize cutover plan Documents (Set-Up Document BR100) Lead the creation and execution of the Prepare and publish project readiness Cut-Over plan checklist Get cutover status intranet website ready (optional) Validate exit criteria for UAT and get End User Training Training Materials sign off from business Train the Trainer program execution Execute final end user training 37
  • 38. Post Production/Transition Prepare “PM.010 Transition Strategy” and/or “PM.030 Transition And Contingency Plan” (Oracle AIM)  Make it clear how client team will acquire knowledge and what documents will be provided as a part of knowledge transfer  Ensure tier 1 support is provided by project team during first 3-4 weeks Prepare lessons learned with input from client business and IT Prepare project completion report Establish a workflow for issue resolution (see samples in next 2 slides) 38
  • 39. Issue resolution workflow – Sample 1 39
  • 40. Issue resolution workflow – Sample 2 Having an issue tracking software (like Remedy) helps track these lead times 40
  • 41. End goal is to avoid the below B C A 41 When A = B, but B not=C, we have defect When A not = B we have change request
  • 44. Project Plan If milestone is due within 3 days and the progress >= 80% then status = Yellow If milestone is due within 3 days and the progress < 80% then status = Red For tasks If today (date) is past the start date of the task and progress is reported < (days since start/duration) then Yellow to indicate a task with insufficient progress. 44
  • 45. Instance Plan Zero slack. Any delay will push the timeline. Only alternate plan is to run UAT in CRP3 instance Mock Go Live – Final test before cutover 45
  • 48. Sample Benefit Map Complete Desired Project or Result of the part of a program project Outcome 48
  • 49. Risk Log 49
  • 52. Deliverable Status Log Advance notice to indicate when a Keeps track of # document will be of days taken for sent for review review and approval 52
  • 54. Test Script Within a Track (Summary) 54
  • 55. Test Script Within a Track (Detail) 55
  • 56. Cross Track Test Script 56
  • 57. Project Readiness Scorecard Green when High Priority Issue=0 and medium issue < 5 Yellow when High > 0 but < 3 and medium >5 and < 10 Red when High >3 57
  • 58. Cutover Plan (Hr by Hr) 58
  • 60. Thank you for inputs: - Ramesh Doraiswamy (rdoraiswamy@gmail.com) 60