SlideShare une entreprise Scribd logo
1  sur  38
Project Management with Certain Time Estimates Summary of steps: Determine activities that need to be accomplished Determine precedence relationships and completion times Construct network diagram Determine the critical path Determine early start and late start schedules
Project Management: Scheduling Projects with Certain Time Estimates Create Network Diagram Based on order of precedence among activities
3 5 1 2 6 7 8 4 Calculation of the Critical Path Network approach helps calculate project duration A “path” is a sequence of activities that begins at the start of the project and goes to the end of the project 1,2,3,5,6,7,8 1,2,4,6,7,8 The “critical path” is the path that takes the longest to complete and thus determines the minimum duration of the project
Calculation of the Critical Path
3 5 1 2 6 7 8 4 2 weeks 3 weeks 4 weeks 10 weeks 16 weeks 4 weeks 1 week 4 weeks Calculation of the Critical Path Critical Path The path that takes the longest to complete
2 weeks 3 weeks 3 5 4 weeks 10 weeks 16 weeks 4 weeks 1 week 1 2 6 7 8 4 weeks 4 Calculation of the Critical Path Critical Path The path that takes the longest to complete C.P. = 40 weeks
3 5 1 2 6 7 8 5 X 4 2 weeks 3 weeks 4 weeks 10 weeks 16 weeks 4 weeks 1 week 4 weeks Calculation of the Critical Path It is possible for multiple Critical Paths to exist New information suggests that Activity 4 will take 5 weeks instead of 4
5 X 2 weeks 3 weeks 3 5 4 weeks 10 weeks 16 weeks 4 weeks 1 week 1 2 6 7 8 5 weeks 4 Calculation of the Critical Path It is possible for multiple Critical Paths to exist New information suggests that Activity 4 will take 5 weeks instead of 4 C.P. = 40 weeks
3 5 1 2 6 7 8 6 X 4 Calculation of the Critical Path Critical Path may also shift if non-critical activity is lengthened or Critical Path activity is shortened Another update indicates it will actually take 6 weeks for Activity 4 2 weeks 3 weeks 4 weeks 10 weeks 16 weeks 4 weeks 1 week 4 weeks
6 X Calculation of the Critical Path Critical Path may also shift if non-critical activity is lengthened or Critical Path activity is shortened Another update indicates it will actually take 6 weeks for Activity 4 2 weeks 3 weeks 3 5 4 weeks 10 weeks 16 weeks 4 weeks 1 week 1 2 6 7 8 6 weeks 4 C.P. = 41 weeks
Determining Slack Slack - The amount of time an activity on a non-critical path can be delayed without affecting the duration of the project (i.e., without putting it on the critical path) Uses four calculated values Early start - Earliest an activity can start (based on prerequisites) Early finish - Earliest it can finish (based on prerequisites & duration) Late start - Latest an activity can start and not delay the project Late finish - Latest an activity can finish and not delay the project
Calculating Early Start (ES) and Early  Finish (EF) Move from left to right in network ES for 1st activity usually zero EF equals ES plus activity duration ES is latest of the EF times of an activity’s predecessors THIS IS CALLED THE FORWARD PASS
Calculating Late Start (LS) and Late Finish (LF) ,[object Object]
LF for last activity equals EF for last activity
Or target date if different
LS equals LF minus activity duration
LF is earliest of the LS times of an activity’s followersTHIS IS CALLED THE BACKWARD PASS
Calculating Slack Slack - The amount of time an activity on a non-critical path can be delayed without affecting the duration of the project (i.e., putting it on the critical path) Computed by either: 	Late Start - Early Start or 	Late Finish - Early Finish ,[object Object],[object Object]
Project Scheduling with Time Uncertainty Take three time estimates Optimistic - What is the (realistic) fastest we can get an activity done? Pessimistic - What is the (realistic) worst case scenario for delay? Most likely - What is our “most likely” estimate?
Project Scheduling with Time Uncertainty Calculate the “expected time” for the activity Where: Te 	=  Expected Time o 	=  Optimistic estimate m	=  Most likely estimate p 	=  Worst-case (pessimistic) estimate
weeks Activity #1 weeks Activity #2 weeks Activity #3 Project Scheduling with Time Uncertainty
2.17 weeks 3 weeks 3 5 4 weeks 10 weeks 16.17 weeks 4.17 weeks 1.17 weeks 1 2 6 7 8 4.17 weeks 4 Using Variation in Time Estimates to Assess Duration Probabilities How do we interpret this estimate??? Probability theory (“central limit theorem”) dictates that we assume that finish times across entire project are distributed “normally” Probabilistically: 50% chance we will finish faster, 50% chance we will finish slower C.P. = 40.68 weeks
Using Variation in Time Estimates to Access Duration Probabilities Note that this is , not 2 , We have to take the square root of the “variance” to get the standard deviation Where: Z 	= Number of standard deviations D is from Te Te 	= Expected Time D 	= Project duration I am thinking about
Using Variation in Time Estimates to Access Duration Probabilities We recognize that there is variation around our estimates We are estimating “most likely” or “expected” not “exact” Commonly assume a “Beta” distribution Another asymmetric distribution (because duration is never less than zero) Calculating variance of the activity’s duration estimate:
Activity #2 weeks Activity #3 weeks Using Variation in Time Estimates to Access Duration Probabilities Activity #1 weeks
Using Variation in Time Estimates to Assess Duration Probabilities Calculate Critical Path using Te Accumulate the variances of the individual activities Apply formula to estimate project duration probabilities Where: Z = Number of standard deviations D is from Te Te 	= Expected Time D = Activity duration I am thinking about
Using Variation in Time Estimates to Assess Duration Probabilities
3 5 1 2 6 7 8 4 2.17 weeks 3 weeks 4 weeks 10 weeks 16.17 weeks 4.17 weeks 1.17 weeks 4.17 weeks Using Variation in Time Estimates to Assess Duration Probabilities What is the probability of finishing in 39 weeks or less?
2.17 weeks 3 weeks 3 5 4 weeks 10 weeks 16.17 weeks 4.17 weeks 1.17 weeks 1 2 6 7 8 4.17 weeks 4 Using Variation in Time Estimates to Assess Duration Probabilities Exhibit 8.22: Expected Values and Variances of Time Estimates What is the probability of finishing in 39 weeks or less? Critical Path = 40.68 weeks Sum of Variances = 2.56 weeks
Standard deviation difference between “most likely” and desired duration 1.6 = the square root of 2.56!!! Using Variation in Time Estimates to Assess Duration Probabilities Where: Z = Number of standard deviations D is from Te Te 	= Expected Time D = Activity duration I am thinking about So, I look up the cumulative probability [G(z)] of the activity being completed before -1.05 standard deviations from the “most likely” estimate…  … and find out I have a 85.314% chance of finishing within 39 weeks!! FROM APPENDIX A PAGE A3
Find probability under G(z) in Appendix B and translate to number of standard deviations weeks!!! Using Variation in Time Estimates to Access Duration Probabilities So,  what if I want to be 90 percent sure that I hit the project duration that I tell my boss I will (or she will fire me)? Reconfigure “Z” equation to solve for D Pick the value of “Z” that corresponds to the level of certainty I want (90% = +1.30)  Solve What if I can stand to be only 80% sure??
Crashing Projects A methodical approach to reducing project duration Focus on the time of activities on the critical path Looking for greatest improvement with least cost Additional labor, machinery Overtime and temporary employees Premiums paid to outside contractors for early delivery Steps Create network Identify critical path Identify costs of reducing each activity on path Reduce most cost effective activity Look for critical path changes Beware of multiple critical paths Crash next activity
Crashing Projects: Create the Network
Crashing Projects: Identify the Critical Path B 7 C 7 A 8 D 10 F 8 H 5 E 12 G 9 A-B-C-F-H Critical Path = 35 days
Crashing Projects: Identify Costs of Crashing Each Activity
Crashing Projects: Reduce Most Cost Effective Activity 6 B 7 C 7 X A 8 D 10 F 8 H 5 E 12 G 9
Crashing Projects: Look for Critical Path Changes  6 B 7 C 7 X A 8 D 10 F 8 H 5 E 12 G 9 Old Critical Path Completion = 35 days Activity C Crashed by 1 day project completion    = 34 days Did that effect the critical path?
Crashing Projects: Look for Critical Path Changes  6 B 7 C 7 X A 8 D 10 F 8 H 5 E 12 G 9 Multiple Critical Paths Appear!!! Critical Path = 34 days

Contenu connexe

En vedette

Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)Ron Gill
 
Integrated Marketing Communications
Integrated Marketing CommunicationsIntegrated Marketing Communications
Integrated Marketing CommunicationsJeff Hilton
 
Session 4 critical path method upload
Session 4   critical path method uploadSession 4   critical path method upload
Session 4 critical path method uploadArun
 
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisLesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisHoly Angel University
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysissimu_mihai
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path AnalysisDavid Zaki
 
Year 12 Maths A Textbook - Chapter 8
Year 12 Maths A Textbook - Chapter 8Year 12 Maths A Textbook - Chapter 8
Year 12 Maths A Textbook - Chapter 8westy67968
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path methodPrathima Girish
 
Project Management CH9 Project Scheduling
Project Management CH9 Project SchedulingProject Management CH9 Project Scheduling
Project Management CH9 Project SchedulingIzah Asmadi
 
Critical Path Analysis Notes
Critical Path Analysis NotesCritical Path Analysis Notes
Critical Path Analysis Notesmattbentley34
 

En vedette (19)

Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
 
Critical Path Analysis for a New Product Release
Critical Path Analysis for a New Product ReleaseCritical Path Analysis for a New Product Release
Critical Path Analysis for a New Product Release
 
Integrated Marketing Communications
Integrated Marketing CommunicationsIntegrated Marketing Communications
Integrated Marketing Communications
 
Network Anaysis_ critical path methods
Network Anaysis_ critical path methodsNetwork Anaysis_ critical path methods
Network Anaysis_ critical path methods
 
Bpp 3213 lecture 2
Bpp 3213 lecture 2Bpp 3213 lecture 2
Bpp 3213 lecture 2
 
Session 4 critical path method upload
Session 4   critical path method uploadSession 4   critical path method upload
Session 4 critical path method upload
 
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisLesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Data Handling.
Data Handling. Data Handling.
Data Handling.
 
Year 12 Maths A Textbook - Chapter 8
Year 12 Maths A Textbook - Chapter 8Year 12 Maths A Textbook - Chapter 8
Year 12 Maths A Textbook - Chapter 8
 
Pictographs
PictographsPictographs
Pictographs
 
5. entr lesson 13
5. entr   lesson 135. entr   lesson 13
5. entr lesson 13
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path method
 
Project Management CH9 Project Scheduling
Project Management CH9 Project SchedulingProject Management CH9 Project Scheduling
Project Management CH9 Project Scheduling
 
Critical Path Analysis Notes
Critical Path Analysis NotesCritical Path Analysis Notes
Critical Path Analysis Notes
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
Chapter 15
Chapter 15 Chapter 15
Chapter 15
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 

Similaire à Syam critical path cpa

PertGanttchart
PertGanttchartPertGanttchart
PertGanttchartlearnt
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxannettsparrow
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling Reema
 
Project Scheduling
Project SchedulingProject Scheduling
Project SchedulingReema
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPHOEBEANNEARTECHE1
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management UploadBhuWan Khadka
 
Assignment 1 Identify elements of concern (e.g. resources.docx
Assignment 1 Identify elements of concern (e.g. resources.docxAssignment 1 Identify elements of concern (e.g. resources.docx
Assignment 1 Identify elements of concern (e.g. resources.docxsherni1
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 RevisionJoyce Wong
 

Similaire à Syam critical path cpa (20)

PertGanttchart
PertGanttchartPertGanttchart
PertGanttchart
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptx
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Ch08 pm2ndhalf
Ch08 pm2ndhalfCh08 pm2ndhalf
Ch08 pm2ndhalf
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
Assignment 1 Identify elements of concern (e.g. resources.docx
Assignment 1 Identify elements of concern (e.g. resources.docxAssignment 1 Identify elements of concern (e.g. resources.docx
Assignment 1 Identify elements of concern (e.g. resources.docx
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Chap03
Chap03Chap03
Chap03
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 Revision
 

Syam critical path cpa

  • 1. Project Management with Certain Time Estimates Summary of steps: Determine activities that need to be accomplished Determine precedence relationships and completion times Construct network diagram Determine the critical path Determine early start and late start schedules
  • 2. Project Management: Scheduling Projects with Certain Time Estimates Create Network Diagram Based on order of precedence among activities
  • 3. 3 5 1 2 6 7 8 4 Calculation of the Critical Path Network approach helps calculate project duration A “path” is a sequence of activities that begins at the start of the project and goes to the end of the project 1,2,3,5,6,7,8 1,2,4,6,7,8 The “critical path” is the path that takes the longest to complete and thus determines the minimum duration of the project
  • 4. Calculation of the Critical Path
  • 5. 3 5 1 2 6 7 8 4 2 weeks 3 weeks 4 weeks 10 weeks 16 weeks 4 weeks 1 week 4 weeks Calculation of the Critical Path Critical Path The path that takes the longest to complete
  • 6. 2 weeks 3 weeks 3 5 4 weeks 10 weeks 16 weeks 4 weeks 1 week 1 2 6 7 8 4 weeks 4 Calculation of the Critical Path Critical Path The path that takes the longest to complete C.P. = 40 weeks
  • 7. 3 5 1 2 6 7 8 5 X 4 2 weeks 3 weeks 4 weeks 10 weeks 16 weeks 4 weeks 1 week 4 weeks Calculation of the Critical Path It is possible for multiple Critical Paths to exist New information suggests that Activity 4 will take 5 weeks instead of 4
  • 8. 5 X 2 weeks 3 weeks 3 5 4 weeks 10 weeks 16 weeks 4 weeks 1 week 1 2 6 7 8 5 weeks 4 Calculation of the Critical Path It is possible for multiple Critical Paths to exist New information suggests that Activity 4 will take 5 weeks instead of 4 C.P. = 40 weeks
  • 9. 3 5 1 2 6 7 8 6 X 4 Calculation of the Critical Path Critical Path may also shift if non-critical activity is lengthened or Critical Path activity is shortened Another update indicates it will actually take 6 weeks for Activity 4 2 weeks 3 weeks 4 weeks 10 weeks 16 weeks 4 weeks 1 week 4 weeks
  • 10. 6 X Calculation of the Critical Path Critical Path may also shift if non-critical activity is lengthened or Critical Path activity is shortened Another update indicates it will actually take 6 weeks for Activity 4 2 weeks 3 weeks 3 5 4 weeks 10 weeks 16 weeks 4 weeks 1 week 1 2 6 7 8 6 weeks 4 C.P. = 41 weeks
  • 11. Determining Slack Slack - The amount of time an activity on a non-critical path can be delayed without affecting the duration of the project (i.e., without putting it on the critical path) Uses four calculated values Early start - Earliest an activity can start (based on prerequisites) Early finish - Earliest it can finish (based on prerequisites & duration) Late start - Latest an activity can start and not delay the project Late finish - Latest an activity can finish and not delay the project
  • 12. Calculating Early Start (ES) and Early Finish (EF) Move from left to right in network ES for 1st activity usually zero EF equals ES plus activity duration ES is latest of the EF times of an activity’s predecessors THIS IS CALLED THE FORWARD PASS
  • 13.
  • 14. LF for last activity equals EF for last activity
  • 15. Or target date if different
  • 16. LS equals LF minus activity duration
  • 17. LF is earliest of the LS times of an activity’s followersTHIS IS CALLED THE BACKWARD PASS
  • 18.
  • 19. Project Scheduling with Time Uncertainty Take three time estimates Optimistic - What is the (realistic) fastest we can get an activity done? Pessimistic - What is the (realistic) worst case scenario for delay? Most likely - What is our “most likely” estimate?
  • 20. Project Scheduling with Time Uncertainty Calculate the “expected time” for the activity Where: Te = Expected Time o = Optimistic estimate m = Most likely estimate p = Worst-case (pessimistic) estimate
  • 21. weeks Activity #1 weeks Activity #2 weeks Activity #3 Project Scheduling with Time Uncertainty
  • 22. 2.17 weeks 3 weeks 3 5 4 weeks 10 weeks 16.17 weeks 4.17 weeks 1.17 weeks 1 2 6 7 8 4.17 weeks 4 Using Variation in Time Estimates to Assess Duration Probabilities How do we interpret this estimate??? Probability theory (“central limit theorem”) dictates that we assume that finish times across entire project are distributed “normally” Probabilistically: 50% chance we will finish faster, 50% chance we will finish slower C.P. = 40.68 weeks
  • 23. Using Variation in Time Estimates to Access Duration Probabilities Note that this is , not 2 , We have to take the square root of the “variance” to get the standard deviation Where: Z = Number of standard deviations D is from Te Te = Expected Time D = Project duration I am thinking about
  • 24. Using Variation in Time Estimates to Access Duration Probabilities We recognize that there is variation around our estimates We are estimating “most likely” or “expected” not “exact” Commonly assume a “Beta” distribution Another asymmetric distribution (because duration is never less than zero) Calculating variance of the activity’s duration estimate:
  • 25. Activity #2 weeks Activity #3 weeks Using Variation in Time Estimates to Access Duration Probabilities Activity #1 weeks
  • 26. Using Variation in Time Estimates to Assess Duration Probabilities Calculate Critical Path using Te Accumulate the variances of the individual activities Apply formula to estimate project duration probabilities Where: Z = Number of standard deviations D is from Te Te = Expected Time D = Activity duration I am thinking about
  • 27. Using Variation in Time Estimates to Assess Duration Probabilities
  • 28. 3 5 1 2 6 7 8 4 2.17 weeks 3 weeks 4 weeks 10 weeks 16.17 weeks 4.17 weeks 1.17 weeks 4.17 weeks Using Variation in Time Estimates to Assess Duration Probabilities What is the probability of finishing in 39 weeks or less?
  • 29. 2.17 weeks 3 weeks 3 5 4 weeks 10 weeks 16.17 weeks 4.17 weeks 1.17 weeks 1 2 6 7 8 4.17 weeks 4 Using Variation in Time Estimates to Assess Duration Probabilities Exhibit 8.22: Expected Values and Variances of Time Estimates What is the probability of finishing in 39 weeks or less? Critical Path = 40.68 weeks Sum of Variances = 2.56 weeks
  • 30. Standard deviation difference between “most likely” and desired duration 1.6 = the square root of 2.56!!! Using Variation in Time Estimates to Assess Duration Probabilities Where: Z = Number of standard deviations D is from Te Te = Expected Time D = Activity duration I am thinking about So, I look up the cumulative probability [G(z)] of the activity being completed before -1.05 standard deviations from the “most likely” estimate… … and find out I have a 85.314% chance of finishing within 39 weeks!! FROM APPENDIX A PAGE A3
  • 31. Find probability under G(z) in Appendix B and translate to number of standard deviations weeks!!! Using Variation in Time Estimates to Access Duration Probabilities So, what if I want to be 90 percent sure that I hit the project duration that I tell my boss I will (or she will fire me)? Reconfigure “Z” equation to solve for D Pick the value of “Z” that corresponds to the level of certainty I want (90% = +1.30) Solve What if I can stand to be only 80% sure??
  • 32. Crashing Projects A methodical approach to reducing project duration Focus on the time of activities on the critical path Looking for greatest improvement with least cost Additional labor, machinery Overtime and temporary employees Premiums paid to outside contractors for early delivery Steps Create network Identify critical path Identify costs of reducing each activity on path Reduce most cost effective activity Look for critical path changes Beware of multiple critical paths Crash next activity
  • 34. Crashing Projects: Identify the Critical Path B 7 C 7 A 8 D 10 F 8 H 5 E 12 G 9 A-B-C-F-H Critical Path = 35 days
  • 35. Crashing Projects: Identify Costs of Crashing Each Activity
  • 36. Crashing Projects: Reduce Most Cost Effective Activity 6 B 7 C 7 X A 8 D 10 F 8 H 5 E 12 G 9
  • 37. Crashing Projects: Look for Critical Path Changes 6 B 7 C 7 X A 8 D 10 F 8 H 5 E 12 G 9 Old Critical Path Completion = 35 days Activity C Crashed by 1 day project completion = 34 days Did that effect the critical path?
  • 38. Crashing Projects: Look for Critical Path Changes 6 B 7 C 7 X A 8 D 10 F 8 H 5 E 12 G 9 Multiple Critical Paths Appear!!! Critical Path = 34 days
  • 39. Path 1 Only Path 2 Only Both C.P. Crashing Projects: Crash Next Activity Exhibit 8.25: Crash Time and Costs
  • 40. Crashing Projects: Summary Exhibit 8.26: Crashing Summary Solution
  • 41. Caveats Time estimates are frequently wrong Early finishes are absorbed Cushions get wasted Resources aren’t always available when needed