Contenu connexe
Similaire à Pmi june 5th 2007
Similaire à Pmi june 5th 2007 (20)
Pmi june 5th 2007
- 2. Agenda
• Parks Reservation Service Project
- The client
- The challenge
- The consortium
- The project
- The solution
- The results
• Lean Software Development
- Principles
- Practices
- How Project Management is different
- How Project Leadership is different
• Questions?
©2007 Protegra Inc. All rights reserved.
- 3. Park Reservation Service – The client
• Manitoba Conservation is comprised of 4 divisions as follows:
- Regional Operations – delivers departmental programs on a regional
basis (park and campground operations)
- Programs – provides the policy direction and systems support for program
thrusts of department (parks)
- Environmental Stewardship – legislation, policies, plans, and programs to
sustainably manage resources and the environment (Exec Sponsor for
PRS)
- Corporate Services – management of cross division services such as
human resources, financial, computer and administrative support (IT
support and financial management for PRS)
- Each is responsible for a part of PRS!
©2007 Protegra Inc. All rights reserved.
- 4. Park Reservation Service – The client
• Dimensions of Parks and Campgrounds
- 57 Campgrounds
- About 5,500 campsites
- 11 Campgrounds currently computerized
• Bakers Narrows, Big Whiteshell, Birds Hill, Falcon Beach, Falcon Lakeshore,
Grand Beach, Gull Harbour, Kiche Manitou, Otter Falls, St. Malo and West
Hawk
©2007 Protegra Inc. All rights reserved.
- 6. Park Reservation Service – The challenge
• Government committed to have a “ made in Manitoba solution “
for Spring 2006.
• The RFP was released in early December with a closing date of
Mid-December.
• Protegra proposed a consortium approach to deliver the solution
by the opening day of April 3rd.
• Protegra was awarded the contract in early January 2006.
©2007 Protegra Inc. All rights reserved.
- 7. Park Reservation Service – The challenge
• Challenges faced:
- Time line
- Client new to Protegra, Protegra new to provincial government
- Consortium approach – time and complexity
- Complex Government Environment
©2007 Protegra Inc. All rights reserved.
- 11. Park Reservation Service – The consortium
• To address the timelines and challenges a consortium approach
was created. The consortium involved the following companies
- Function Four – GIS/Mapping Technology and Training Expertise
- ManLab – Government of Manitoba Graphics Design Experience
- IDFusion – long time development partner of Protegra’s
- NexTechnologies – Domain Expert in Reservations
• This offered the team a unique balance of expertise, but also had
the following implications
- More time was spent early on in contract negotiations and teaming
agreements
- More time was spent determining how to communicate, report and work
well together
- More time was spent determining to create a consolidated report for the
client that represented all work easily
©2007 Protegra Inc. All rights reserved.
- 12. Park Reservation Service – The project
• The Parks Reservation System (PRS) was developed in 2006 to replace
the existing campground reservation.
• Requirements included:
-
self-initiated reservations over the Internet,
-
campground attendants to make reservations on behalf of
clients, and;
-
call centre employees to mke reservations on behalf of
campers.
ALSO, to provide administrative and management tools for Manitoba Parks
head office staff.
- Phase 1 – Public and Call Centre Focused
- Phase 2 – Campground focused
- Phase 3 – Admin site enhancements
- Phase 4 – Jan 07 launched thru to end of 07
©2007 Protegra Inc. All rights reserved.
- 13. Park Reservation Service – The project
• Project details
- Project team included over 20 developers at maximum
- First Phase was delivered in 3 months, On Time!
- Included investigation and integration of GIS mapping technology
- Phase 1 alone was over 7,400 hours of development work, all three
Phases were over 12,000 hours.
- Quality of the application has exceeded industry standards with only a few
defects since go live
- Project had to achieve PCI certification to go live. PRS was first of
government applications to pass on the first test.
©2007 Protegra Inc. All rights reserved.
- 17. Park Reservation Service – The results
• The PRS was delivered in three phases:
- Phase 1 – Public and Call Centre Focus
• Deployed on April 10th to the public, call centre, and Parks head office
• Functionality that focused primarily on the reservation process and reservation
maintenance (i.e. change, cancel, refund, etc.)
- Phase 2 – Campground focused
• Deployed on May 1st to Birds Hill Campground, with subsequent deployments
to ten other campgrounds over the next six weeks.
• Focused on supporting management of campground (i.e. check campers in,
check campers out, move campers, generate permits, end of day
reconciliation, etc.)
- Phase 3 – Admin site enhancements
• Deployed in installments from July 2006 through November 2006.
• Focused primarily on providing more back office support to Parks head office
users
©2007 Protegra Inc. All rights reserved.
- 19. Lean Software Development - Principles
• Serialization of Project Phases
• Significant focus is on protection of scope
• Many handoffs between different phases and departments. Many
documents are produced because of these handoffs.
• Delivery of working code sometime waits until just before UAT
©2007 Protegra Inc. All rights reserved.
- 20. Lean Software Development - Principles
• Lean Software development emphasizes customer satisfaction through
continuous delivery of functional software, unlike traditional methods,
lean developers liaise daily/continuously with business clients.
• Deliver working software as frequently as every two weeks during a
project, and encourage changes to the requirements in response to
evolving business needs
(business users are more able to know what will work when they
have something to test)
• The most crucial aspect is the execution of the project in iterations
which enable quick feedback loops.
NOTE: The iterations apply to the following tasks:
- Project Management and Planning
- Analysis
- Technical Design
- Testing
- Deployment
©2007 Protegra Inc. All rights reserved.
- 21. Lean Software Development - Principles
• Iteration planning is the key planning initiative. Iterations need to
be planned in conjunction with the client to accomplish the
following:
- Deliver functionality to define the tempo of the project
- Deliver functionality to deliver real value to the client (working
code)
- Deliver functionality to minimize risk for the entire project
- Lessons learned from one iteration must feed into subsequent
iterations so that we don’t (just) execute the project in iterations
with similar results, but that we execute the project in iterations
with better results.
• The project team executes better, smarter, and quicker
• The project team goes through the process of forming, storming, and
performing
©2007 Protegra Inc. All rights reserved.
- 22. Lean Software Development - Principles
• Eliminate Waste
• Build Quality In
• Create Knowledge
• Defer Commitment
• Deliver Fast
• Respect People (Empower the Team)
• Optimize the Whole
Copyright©2006 Poppendieck.LLC
©2007 Protegra Inc. All rights reserved.
- 23. Lean Software Development - Principles
• Most deliverables are enhanced in every iteration (except for
project plan)
• Every iteration uncovers new opportunities for improvement and
learning
• Opportunities for improvement are evaluated at the end of each
phase and incorporated into the tool and documentation
©2007 Protegra Inc. All rights reserved.
- 24. Park Reservation Service – The results
• Benefits Realized from Lean Development Process
- Client decision maker on site is key to a Lean project.
- Liaise with the clients as much as possible
- Empowering the development team was crucial, even more would have
been better
- Traceability of requirements is key with formal organizations
• Potential Improvements
Quality could be further improved with the use of TDD, automated
test and build tools
Form in sub-teams of 6-8 to maximize efficiency. Assign a Client
decision maker to each one of these sub teams.
©2007 Protegra Inc. All rights reserved.
- 25. Lean Software Development - Practices
• Requirements for a Lean Software Development Project
- Define Vision before iterations start. Defining the vision can be iteration 0.
- Defined iteration length
- High Feedback loops
• Client representative on site and working with the team
• Client representative empowered to make decisions
• Daily project team meetings
- Visual Project Management
- Frequent Builds
- Test Case Driven Development and Documentation. (May be TDD)
- Refocus requirement discussions on how not what
- Relationship Contract
©2007 Protegra Inc. All rights reserved.
- 26. Lean Software Development - Practices
• Refocus requirements discussion on how not what
- Waterfall (Point based)
• Document the scope or the what before we start
• Use the scope document to manage change control
• Discussions on new and modified scope can be difficult as these requests
usually occur later in the project and require additional budget and schedule.
Changes are avoided for these reasons.
• Discussions become adversarial
- Lean (Set based)
• Document the process on how we will define the scope and make decisions.
Define at a high level what you need and how you will refine it.
• Use the process agreement to manage change control
• Joint Collaborative discussions on new and modified scope and how we can
manage them in the project. Because we deliver in iterations, changes can be
specified earlier and can often be accommodated without additional budget
and schedule. Changes are welcomed.
©2007 Protegra Inc. All rights reserved.
- 27. Lean Software Development - Practices
• Traditional view of contracts
- Companies are protecting their own interests and assuming that if they don’t the
partner will take advantage of them
• Relational Contracts
- Both parties assume the other will operate to the common good of the contract
- Set up penalties to limit opportunism
- Set up bonuses to reward joint success
- Ensure that the contract protects the right things. Focus on the protection of value
that each party will receive from the successful project.
Copyright©2006 Poppendieck.LLC
©2007 Protegra Inc. All rights reserved.
- 28. Lean Software Development - Practices
• Relational Contracts
- Start with a contract that defines how the project will be executed
• Communication
• Escalation
• Interactions
• Agreements
• Arbitration
- Release work in iterations
• Learn what works and what doesn’t work
• Both the client and the vendor execute better
• Scope beyond the next two stages is negotiable
• Don’t force the client to agree to details when they aren’t ready to
Copyright©2006 Poppendieck.LLC
©2007 Protegra Inc. All rights reserved.
- 29. Lean Software Development - Practices
• Relational Contract
- Contract Characteristics
• Describes the how, not the what.
- Interactions versus deliverables
• Defines a framework that can be revised and build upon
• Provides an escalation framework and arbitration process when agreement can not be
reached
Copyright©2006 Poppendieck.LLC
©2007 Protegra Inc. All rights reserved.
- 30. Lean Software Development - How Project
Management is different
• Lean Software Development Waterfall Project Lean Project
Project Manager Management Management Skills
Characteristics Skills
- Traditional Project Management Detail oriented Adaptable, encourages
manages the known, Lean or Agile change
Project Management manages the
Manages at a lower level Comfortable with ambiguity
unknown
- There are distinctly different ways
Resistant to change Able to delegate
how you manage the unknown
versus the known
Controlling Trust or faith in team mates
- There are distinctly different people
and styles that are more suited to
managing the unknown versus the Company Focus Client Focus
known Transaction Manager Relationship Manager
Manages Scope, schedule, Manages Value
budget
Temperment: Guardian Temperment: Idealist
©2007 Protegra Inc. All rights reserved.
- 31. Lean Software Development - How Project
Management is different
• Idealist
- These are big picture people who lead followers to pursue great
dreams. They thrive on people issues and gravitate toward the soft
skills: conflict resolution, negotiation, team building, facilitating.
Diplomacy and strategy are their strong suits
• Guardian
- People with this dominant temperament like to play by the rules.
These are the stabilizers in the organization, working to keep the
boat on an even keel. Meeting budgets and deadlines and following
the plan are important to Guardians.
Keirsey, D. Please Understand Me II. Del Mar, Calif: Prometheus Nemesis Book Company, 1998
©2007 Protegra Inc. All rights reserved.
- 32. Lean Software Development - How Project
Management is different
• Theory X Project Manager
- believes that people really don’t want to work, can’t be trusted on their
own and will get away with what they can.
- use command and control as their operating style, an approach akin to the
Newtonian view of the world.
• Theory Y Project Manager
- This manager believes that people are intrinsically motivated to do good
work, want to make a difference and can be relied on to solve problems
and make decisions.
- Theory Y manager is a relationship manager, akin to the quantum view of
the world.
McGregor, Douglas. The Human side of the Enterprise. McGraw-Hill/Irwin , 1985
©2007 Protegra Inc. All rights reserved.
- 33. Lean Software Development - How Project
Management is different
• In waterfall projects you focus on managing people and tasks, in
Lean projects you focus on leading the process
- Facilitate decision making versus making the decisions
©2007 Protegra Inc. All rights reserved.
- 34. Lean Software Development - How Project
Management is different
• One-on-one skills required:
- Effective listening
- Establishing rapport
- Negotiation
- Conflict resolution
- Emotional intelligence
- Partnering
- Influencing without authority
- Assertiveness
• Group skills required:
- Team leadership
- Meeting management
- Problem solving and decision reaching
- Facilitation
- Presentation and persuasion
Doug DeCarlo, Principal, The Doug DeCarlo Group, Copyright © 2006 gantthead.com
©2007 Protegra Inc. All rights reserved.
- 35. Lean Software Development - How Project
Leadership is different
• Project Manager and Client Project Manager must work even
more closely together than a waterfall project
- Both must focus on the long term relationship
- Both must trust each other
- Both must encourage their companies to focus on value and the long term
relationship
- Both must define a common understanding together for
• Escalation
• Change Request Process
• Issue Tracking
• Reporting
• Formal versus Informal policies and procedures
©2007 Protegra Inc. All rights reserved.
- 36. Lean Software Development - How Project
Leadership is different
• All members of the team need to share the focus the Lean Project
Manager has
• The best Lean Project Manager can not manage a Lean project if
his/her team does not believe in the process
• The best members of the project leadership team are also those
that share the same recommended skill set for Lean Project
Managers. Everyone is delegated authority and the team
manages the project together
• It is recommended that other members of the team be traditional,
waterfall, detail-level personalities. It is best to have a mix of the
different perspectives on every project. These skilled people
usually force decisions to be made on the critical issues.
©2007 Protegra Inc. All rights reserved.
- 37. Questions
• Thank you for your time and interest
• Any questions?
©2007 Protegra Inc. All rights reserved.