1. Project Planning
Project Planning
Planning in General : SWOT analysis
S: Strengths
W: Weaknesses
O: Opportunities
T: Threats
Objectives should be: SMART
S: Specific
M: Measurable
A: Achievable
R: Realistic
T: Timely
24/09/2006 Emad Elbeltagi 2
1
2. Project Planning
Somebody Anybody
TASK
Everybody Nobody
24/09/2006 Emad Elbeltagi 3
Project Planning
Characteristics of a good plan
Based on clearly definite and practical objectives
Simple
Flexible
Easy to control
Provide proper standards
Exploit existing resources, etc.
24/09/2006 Emad Elbeltagi 4
2
3. Project Planning
Planning Inputs and Outputs
INPUTS OUTPUTS
Contract information Activities
Drawings Relationships among activities
Specifications Method statement
Available resources Responsibility
PLANNING Reporting levels
Bills of quantities
Project network diagram
Site reports
Activities duration
Organizational data
Activities cost
Construction methods
24/09/2006 Emad Elbeltagi 5
Project Planning
Planning Major steps
Determination of Project Activities (WHAT)
Establishment of Logic; Relationships and overlap (WHEN)
Presentation (Table, Network, Chart, …)
Estimate Activities’ Duration and Cost (HOW)
24/09/2006 Emad Elbeltagi 6
3
4. Project Planning
Work Breakdown Structure (WBS)
The WBS is a hierarchical structure which is designed to
logically sub-divide all the work-elements of the project into
smaller elements.
House
Civil Plumping Electrical
Foundations Walls/ Pipin H/C Wiring Finishing
Roof g Water
24/09/2006 Emad Elbeltagi 7
Project Planning
Work Breakdown Structure (Why)
Prepare project plan
Identifying Activities
Scheduling
Identifying cost & schedule at various levels of
details
Time & cost control
Identifying individual or departmental responsibilities
24/09/2006 Emad Elbeltagi 8
4
5. Project Planning
WBS & Organizational Breakdown Structure (OBS)
WBS (Work elements)
Project
Area 1 Area 2 Area 3 ……
Beams Columns Slabs ……
Electrical
Formwork Reinforcement Concreting ……
Subcontr superinte
actor B ndent
Concrete
foreman
OBS
(Responsibility Project General Civil Control account
Formwork
& reporting) manager contractor superinte
ndent foreman
Rebar
Subcontr foreman
actor A Mechanic
al
superinte
ndent
24/09/2006 Emad Elbeltagi 9
Project Planning
WBS Coding
Each work package or activity in a WBS is given a
unique code that is used in project planning and
control Identifying Activities
24/09/2006 Emad Elbeltagi 10
5
6. Project Planning
Project Activities
Project is divided into segments of work called activities
Activity: Time-consuming single work element
Guidelines for project breakdown: by: area of
responsibility, structural element, category of work, etc.
Level of details depends on: planning stage, size of the
project, complexity of the work, etc.
24/09/2006 Emad Elbeltagi 11
Project Planning
Project Activities
Types of construction activities:
Production: taken directly from drawings and/or
specifications
Management (Approvals, site establishment, …etc).
Procurement (equipment delivery, material
procurement)
24/09/2006 Emad Elbeltagi 12
6
7. Project Planning
Project Activities
Example (Double Span Bridge):
24/09/2006 Emad Elbeltagi 13
Project Planning
Activities Relationships
The order in which project activities are to be performed
Which activity(ies) must be completed before an activity
can start
Which activity(ies) can not start until activity completion
Which activity(ies) have no logical relations
Logic constraints: Physical, and Resources
24/09/2006 Emad Elbeltagi 14
7
8. Code Description Predecessors
10 Set-up site ---
14 Procure RFT ---
16 Procure P.C. Beams ---
20 Excavate left abutment 10
30 Excavate right abutment 10
40 Excavate central pier 10
50 Foundation left abutment 14, 20
60 Foundation right abutment 14, 30
70 Foundation central pier 14, 40
80 Construct left abutment 50
90 Construct right abutment 60
100 Construct central pier 70
110 Erect left P.C. Beams 16, 80, 100
120 Erect right P.C. Beams 16, 90, 100
140 Fill left embankment 80
150 Fill right embankment 90
155 Construct deck slab 110, 120
160 Left road base 140
170 Right road base 150
180 Road surface 155, 160, 170
190 Bridge railing 155
200 Clear site 180, 190
Project Planning
Type of Activities Relationships
Four Types:
Finish to Start (FS) Finish to Finish (FF)
Start to Start (SS) Start to Finish (SF)
FS FF
SS SF
24/09/2006 Emad Elbeltagi 16
8
9. Project Planning
Overlaps
how much a particular activity must be completed
before a succeeding activity may start
Used for activities not using the same type of resources
With a value less than the duration of the preceding activity
+ve overlap (-ve lag) -ve overlap (+ve lag)
24/09/2006 Emad Elbeltagi 17
Project Planning
Overlaps
Example
Consider the construction of the following sequential activities of
a bridge consists of 19 bays
Pile manufacturing with duration 2.5 wks/pier
Pile driving with duration 1.5 wks/pier
Pile cap with duration 2.0 wks/pier
Pier shaft with duration 2.5 wks/pier
Determine the appropriate overlap between activities
24/09/2006 Emad Elbeltagi 18
9
10. Project Planning
Relationships Considering Resource Constraints
Predecessors Predecessors
Activity description (unconstrained (constrained
resources) resources)
A1 Excavate unit 1 - -
B1 Concreting unit 1 A1 A1
C1 Brickwork unit 1 B1 B1
A2 Excavate unit 2 - A1
B2 Concreting unit 2 A2 B1, A2
C2 Brickwork unit 2 B2 C1, B2
A3 Excavate unit 3 - A2
B3 Concreting unit 3 A3 B2, A3
C3 Brickwork unit 3 B3 C2, B3
24/09/2006 Emad Elbeltagi 19
Project Planning
Project networks: AOA
Two Types:
Activity-On-Arrow; AOA (Arrow Networks).
Activity-On-Node; AON (Precedence Networks):
AOA
Activity represented as arrows with start and finish nodes called
Events
Activity A
i j
j>i
24/09/2006 Emad Elbeltagi 20
10
11. Project Planning
Project networks: AOA
A B
5 10 15 B depends on A
A C
5 10 15 C depends on A and B
B
5
15
B B depends on A
5
A
10
C
15 C depends on A
5 15
A C B depends on A and B
D depends on A and B
B 10 D
5 15
24/09/2006 Emad Elbeltagi 21
Project Planning
Project networks: AOA
Dummy activity
Activity with zero duration and no resources to adjust the network
A C A C
5 15 20 5 20 25
B D Dummy
25 B D
10 C depends on A and B 10 15 30
D depends on B only
A
A 5 15
5 15
B
Dummy
B
10
Incorrect representation Correct representation
24/09/2006 Emad Elbeltagi 22
11
12. Project Planning
Project networks: AON
AOA
Activity represented as nodes
Activity number
10
A
Activity name
24/09/2006 Emad Elbeltagi 23
Project Planning
Project networks: AON
10 20
B depends on A
A B
10 30 40 C depends on A and B
A C D
D depends on C
20
B
30
C
10 20 B depends on A
A B C depends on B
D depends on B
40
D
24/09/2006 Emad Elbeltagi 24
12
13. Project Planning
Project networks: Example
Activity Predecessors
A -
B -
C A, B
D C
E C
F D
G D, E
24/09/2006 Emad Elbeltagi 25
Project Planning
Project networks: Example (AOA)
24/09/2006 Emad Elbeltagi 26
13
14. Project Planning
Project networks: Example (AON)
Calculate the Sequence step
Activity Predecessors Sequence step (SS)
Start - SS(Start)=1
A Start 2=SS(Start)+1
B Start 2=SS(Start)+1
C A, B 3=Highest of [SS(B), SS(A)]
D C 4=SS(C)+1
E C 4=SS(C)+1
F D 5=SS(D)+1
G D, E 5=Highest of [SS(D), SS(E)]
Finish F, G 6= Highest of [SS(F), SS(G)]
24/09/2006 Emad Elbeltagi 27
Project Planning
Project networks: Example (AON)
Sequence step 1 2 3 4 5 6
24/09/2006 Emad Elbeltagi 28
14
15. Project Planning
Activity Duration & Direct Cost
Planning time unit (hours, days, weeks, months)
Establish method statement (method of construction)
Specify number of resources, and hence output
Duration = Quantity of work / No. of Res. x Res. Output
24/09/2006 Emad Elbeltagi 29
Project Planning
Activity Duration & Direct Cost
Productivity can be estimated:
From published data ()اﻟﻤﻮﺳﻮﻋﺔ اﻟﻬﻨﺪﺳﻴﺔ
Previous records of a company
Productivity data
Daily production Man-hours/ unit
Units/day Mhrs/unit
How many units can be done How long it takes form one
in one time unit labor to finish one unit
Applies to a given crew Applies to any crew formation
24/09/2006 Emad Elbeltagi 30
15
16. Project Planning
Activity Duration & Direct Cost
Example
What is the duration to install 6000 square feet of walls shuttering if:
Crew of 2 carpenters is used, output of 200 square feet/day
Productivity is measured as 0.008 man-hour/square feet. Number
of carpenters =3, and number of working hours/day = 8 hours
a. Duration = 6000 / 200 = 3 days
b. Total man-hours needed = 6000 x 0.008 = 48 man-hours (if one man
used)
Duration = 48 / 8 = 6 days (if one man used)
Duration using 3 men = 6 / 3 = 2 days
24/09/2006 Emad Elbeltagi 31
Project Planning
Activity Duration & Direct Cost
Example (balanced mix of resources)
A wall involves 660 m3 concrete, 50 tone of steel, and 790 m2 of formwork.
- A 6 man concrete crew can place 16 m3 of concrete/day.
- A steel-fixer and assistant can fix 0.5 ton of reinforcement/day.
- A carpenter and assistant can fix and remove 16 m2 of shuttering/day
- using one steel-fixer: duration = 50 / 0.5 = 100 days
- using one carpenter: duration = 790 / 16 = 49.4 days
- using one concreting crew: duration = 660 / 16 = 41.25 days.
2 steel-fixer crews, one carpenter crew, and cone concreting crew.
duration = 50 / 0.5 x 2 = 50 days
24/09/2006 Emad Elbeltagi 32
16
17. Project Planning
Activity Duration & Direct Cost
Activity direct cost:
Duration, resources, and cost are interrelated elements
Direct cost comprises: labor, material, equipment, and/or
subcontractors
Unit cost = total cost / quantity
24/09/2006 Emad Elbeltagi 33
17