SlideShare a Scribd company logo
1 of 56
GDAS PM Professions:
PMP Study Group
                                           Session #5: Time Management




Monique Howard
October 16, 2008

© 2005 Hewlett-Packard Development Company, L.P.
The information contained herein is subject to change without notice
1. Please refer to the diagram given below: (all units are in days)




What is the project float if management wants to do this project within ten days?
A. 0 days
B. -4 days
C. 2 days
D. Cannot be determined because information in the question is inconsistent
Correct Choice:     B  (-4 days)
Justification:     The different paths possible are as follows:

    * Start -> Task1 -> Task2 -> Task3 -> End : 10
    * Start -> Task1 -> Task2 -> Task3 -> Task6 -> End : 14
    * Start -> Task4 -> Task5 -> Task6 -> End: 13
    * Start -> Task4 -> Task5 -> Task3 -> Task6 -> End: 14
    * Start -> Task4 -> Task5 -> Task3 -> End: 10

    So, the critical path is 14.

    If the project has to be completed within 10 days, the project float is - 4 days (i.e 10 - 14)

    Please note: A project may have a negative project float. To deal with such conditions, if the
    project has to be completed on time, the project manager will have to either fast-track or crash
    the project schedule.

Reference: pmstudy.com notes as mentioned above
2. All the following are advantages of GERT (Graphical Evaluation and Review
   Techniques) as compared with PERT (Project Evaluation and Review Technique)
   EXCEPT:

A.   Allows looping
B.   Allows for dummy tasks
C.   Allows branching
D.   Allows multiple project end results
2. All the following are advantages of GERT (Graphical Evaluation and Review
    Techniques) as compared with PERT (Project Evaluation and Review Technique)
    EXCEPT:

 A.   Allows looping
 B.   Allows for dummy tasks
 C.   Allows branching
 D.   Allows multiple project end results



Correct Choice:     B 
Justification:     Graphical Evaluation and Review techniques are similar to PERT but have the
distinct advantages of allowing for looping, branching, and multiple project end results.

Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling,
Page Number: 679
3. It is important to identify and document the specific work that is planned to be
   performed and also identify deliverables at the work package level. This is done as
   part of:

A.   Activity Definition
B.   Decomposition
C.   Scope Definition
D.   Activity Sequencing
3. It is important to identify and document the specific work that is planned to be
   performed and also identify deliverables at the work package level. This is done as
   part of:

A.   Activity Definition
B.   Decomposition
C.   Scope Definition
D.   Activity Sequencing




 Correct Choice:     A 
 Justification:     Activity Definition: Defining the schedule activities involves identifying and
 documenting the work that is planned to be performed. The activity definition process will identify
 the deliverables at the lowest level in the WBS, which is called the work package.

 Reference: PMBOK Third Edition, Page Number: 127
4. In schedule development, mathematical analysis often produces a preliminary early-
   start schedule that shows peaks and valleys in the resource requirements. Resource
   leveling done to take care of this issue may result in all of the following EXCEPT:

A.   Increase in project duration
B.   Utilization of weekends, extended hours or multiple shifts
C.   Productivity increases by using different technologies and/or methodologies
D.   Reduction in project cost 
4. In schedule development, mathematical analysis often produces a preliminary early-
   start schedule that shows peaks and valleys in the resource requirements. Resource
   leveling done to take care of this issue may result in all of the following EXCEPT:

A.   Increase in project duration
B.   Utilization of weekends, extended hours or multiple shifts
C.   Productivity increases by using different technologies and/or methodologies
D.   Reduction in project cost 




 Correct Choice:     D  
 Justification:     pmstudy.com comments: As different techniques like crashing, fast tracking,
 resource reallocation etc. are being considered for resource leveling, there is a real possibility of
 an increase in costs.

 Reference: PMBOK Third Edition, Page Number: 147
5. All the following statements regarding the creation of Time Estimates are correct
   EXCEPT:

A. Mathematical analysis like CPM, GERT and PERT indicate the dates on which the
   activity can be scheduled given resource limits and other constraints.
B. Duration compression techniques including fast tracking and crashing can help in
   decreasing the project schedule
C. WBS classification allows for useful activity ordering and sorting.
D. The duration of the project is the sum of the duration of all the tasks in the project. 
5. All the following statements regarding the creation of Time Estimates are correct
   EXCEPT:

A. Mathematical analysis like CPM, GERT and PERT indicate the dates on which the
   activity can be scheduled given resource limits and other constraints.
B. Duration compression techniques including fast tracking and crashing can help in
   decreasing the project schedule
C. WBS classification allows for useful activity ordering and sorting.
D. The duration of the project is the sum of the duration of all the tasks in the project. 


Correct Choice:     D  
Justification:     The duration of the project should be calculated after drawing a network diagram
and determining the critical path. The duration of the project is the length of the critical path, and
not the sum of the duration of all the tasks in the project.

Reference: pmstudy.com notes as mentioned above
6. A management control point can be placed at selected management points (specific
   components at selected levels) of the WBS above the work package level. These control
   points can be:

A.   Used for rolling wave planning  
B.   Decomposed further to help in the creation of Work Authorization System  
C.   Used for planning known work content that does not have detailed schedule activities  
D.   Used as a basis for planning when associated work packages have not yet been planned 
6. A management control point can be placed at selected management points (specific
   components at selected levels) of the WBS above the work package level. These control
   points can be:

A.   Used for rolling wave planning  
B.   Decomposed further to help in the creation of Work Authorization System  
C.   Used for planning known work content that does not have detailed schedule activities  
D.   Used as a basis for planning when associated work packages have not yet been planned 



Correct Choice:     D  
Justification:     Control Account : .... A management control point can be placed at selected
management points (specific components at selected levels) of the WBS above the work package
level. These control points are used as a basis for planning when associated work packages have
not yet been planned.

Reference: PMBOK Third Edition, Page Number: 129
7. In your project, some requested changes were generated from the Activity
   Definition Process. These changes will be processed through:

A.   Activity Change Control System 
B.   Corrective Action 
C.   Integrated Change Control System 
D.   Activity Sequencing
7. In your project, some requested changes were generated from the Activity
   Definition Process. These changes will be processed through:

A.   Activity Change Control System 
B.   Corrective Action 
C.   Integrated Change Control System 
D.   Activity Sequencing




Correct Choice:     C 
Justification:     Requested changes are processed for review and disposition through the
Integrated Change Control process.

Reference: PMBOK Third Edition, Page Number: 130
8. Please refer to this diagram:




What is the effect on the project if the duration of task J is increased to 9 weeks?  

A.   No effect since task J is not on the critical path   
B.   Risk of the project will increase  
C.   The overall time-frame required to complete the project will increase by 1 week  
D.   None of the above
Correct Choice:     B (Risk of the project will increase)
Justification: If the duration of task J is increased by 1 week, Start -> G -> I -> J ->
End = 23 weeks; this also lies on the critical path (23 days).

Since there are 3 critical paths now, a delay in any of the critical paths will delay
the overall project - this increases the overall risk for the project.

Reference: pmstudy.com notes as mentioned above
9. A project has a critical path of twenty-three weeks. What is the impact on the
   critical path if the management wants you to complete the project in twenty weeks?

A.   Duration of the critical path increases by three weeks.   
B.   Duration of the critical path decreases by three weeks.   
C.   Duration of the critical path remains same.   
D.   Duration of the critical path cannot be determined. 
9. A project has a critical path of twenty-three weeks. What is the impact on the
   critical path if the management wants you to complete the project in twenty weeks?

A.   Duration of the critical path increases by three weeks.   
B.   Duration of the critical path decreases by three weeks.   
C.   Duration of the critical path remains same.   
D.   Duration of the critical path cannot be determined. 




Correct Choice:     C  
Justification:     Duration of critical path = 23 weeks

If the management wants to complete the project in twenty weeks, then the project float will be : 20 -
23 = -3 weeks The project float compares the critical path with an externally imposed date and may
be negative. (you may be forced to fast-track or perform crashing to ensure that the project is
completed within the dates required by the management)

But, there will be no change to the critical path.

Reference: pmstudy.com notes as mentioned above
10. You are doing a Monte Carlo Analysis in which you are defining a distribution of
    possible activity durations for each schedule activity and calculating a
    distribution of possible outcomes for the total project. Monte Carlo analysis is an
    example of:

A.   Resource Leveling 
B.   What-if Scenario Analysis 
C.   Schedule Network Analysis 
D.   Critical Path Method
10. You are doing a Monte Carlo Analysis in which you are defining a distribution of
    possible activity durations for each schedule activity and calculating a
    distribution of possible outcomes for the total project. Monte Carlo analysis is an
    example of:

A.   Resource Leveling 
B.   What-if Scenario Analysis 
C.   Schedule Network Analysis 
D.   Critical Path Method


 Correct Choice:     B 
 Justification:     What-if Scenario Analysis: ... Simulation involves calculating multiple project
 durations with different set of activity assumptions. The most common technique is Monte Carlo
 Analysis

 Reference: PMBOK Third Edition, Page Number: 146
11. Your project SPI is 0.86 and the management has recommended that you should fast-
    track the project. You agree with the management but warn them that fast-tracking
    could: 

A.   Facilitate duration compression 
B.   Increase risk 
C.   Ensure activities are done in parallel which would normally be done in sequence 
D.   Help shorten the project schedule without changing the project scope
11. Your project SPI is 0.86 and the management has recommended that you should fast-
    track the project. You agree with the management but warn them that fast-tracking
    could: 

A.   Facilitate duration compression 
B.   Increase risk 
C.   Ensure activities are done in parallel which would normally be done in sequence 
D.   Help shorten the project schedule without changing the project scope



Correct Choice:     B  
Justification:     Fast Tracking can result in rework and increased risk

Reference: PMBOK Third Edition, Page Number: 146

pmstudy.com comments: Since increase in risk is a negative outcome of fast-tracking, you should
warn your management about the increased risk. All the other options are benefits of fast-
tracking.
12. 12. In schedule development, you create a distribution of probable results for each
    activity and use it to calculate the distribution of probable results for the total
    project. The technique that you are using is:

A.   What-if Analysis 
B.   Mathematical Analysis 
C.   Monte Carlo Analysis 
D.   Resource Leveling Heuristic
12. In schedule development, you create a distribution of probable results for each
    activity and use it to calculate the distribution of probable results for the total
    project. The technique that you are using is:

A.   What-if Analysis 
B.   Mathematical Analysis 
C.   Monte Carlo Analysis 
D.   Resource Leveling Heuristic




Correct Choice:     C  
Justification:     Simulation involves calculating multiple project durations with different sets of
activity assumptions. The most common technique is called Monte Carlo Analysis, in which a
distribution of probable results is defined for each activity and is used to calculate a distribution of
probable results for the whole project.

Reference: PMBOK Third Edition, Page Number: 146
13. You are going to make a presentation on the project to the senior management. In this
    context, the difference of a milestone chart as compared with a bar chart when making
    presentations is that unlike bar charts, milestones:

A. Show activity start and end dates 
B. Show dependencies among tasks 
C. Only identify the scheduled start or completion of major deliverables, and not all the
   tasks 
D. Show supporting details
13. You are going to make a presentation on the project to the senior management. In this
    context, the difference of a milestone chart as compared with a bar chart when making
    presentations is that unlike bar charts, milestones:

A. Show activity start and end dates 
B. Show dependencies among tasks 
C. Only identify the scheduled start or completion of major deliverables, and not all the
   tasks 
D. Show supporting details


 Correct Choice:     C  
 Justification:     Milestone charts (see Figure 6-10) are similar to bar charts, but only identify the
 scheduled start or completion of major deliverables and key external interfaces.

 Reference: PMBOK Third Edition, Page Number: 149
14. Please refer to the figure below:




If these three tasks (i.e. Task A, Task B, Task C) are not part of the critical path of a project,
     what is the PERT estimate for the duration of the project?

A.   22.5 
B.   10.33 
C.   32 
D.   Cannot be determined
Correct Choice:     D  
Justification:     Since the tasks are not on the critical path of the project, we cannot determine
the PERT estimate for the duration of the project. The PERT estimate can only be calculated for
the critical path of the project.

Reference: pmstudy.com notes as mentioned above
15. In your project, you are in the process of creating an activity list. This should
    contain all the following EXCEPT: 

A.   Activities that are not required as part of the project scope  
B.   Activities that are to be performed as part of the project  
C.   Activity identifiers and scope of work descriptions for each schedule activity  
D.   Activities that are required as part of the project scope 
15. In your project, you are in the process of creating an activity list. This should
    contain all the following EXCEPT: 

A.   Activities that are not required as part of the project scope  
B.   Activities that are to be performed as part of the project  
C.   Activity identifiers and scope of work descriptions for each schedule activity  
D.   Activities that are required as part of the project scope 




Correct Choice:     A  
Justification:     The activity list does not include any schedule activities that are required as
part of the project scope.

Reference: PMBOK Third Edition, Page Number: 129
16. Since you are in the preliminary stages of your project, you estimate that your
    project will last one year. However, an optimistic scenario is that it will get over
    within six months and a pessimistic scenario is eighteen months. This kind of
    estimate is also called:

A.   Definitive   
B.   Capital Cost   
C.   Order of Magnitude   
D.   Feasibility 
16. Since you are in the preliminary stages of your project, you estimate that your
    project will last one year. However, an optimistic scenario is that it will get over
    within six months and a pessimistic scenario is eighteen months. This kind of
    estimate is also called:

A.   Definitive   
B.   Capital Cost   
C.   Order of Magnitude   
D.   Feasibility 


Correct Choice:     C  
Justification:     The classes of estimates and their accuracy % is as follows:

* Definitive (+- 5%)
* Capital Cost (+- 10% - 15%)
* Appropriation ( +- 15% - 25%)
* Feasibility (+_ 25% - 35 %)
* Order of Magnitude ( > +- 35%)



Reference: Project Management - A Systems Approach to Planning,
Scheduling and Controlling, Page Number: 745
17. If you are calculating an early start and early finish for each task, you are using:
    (choose the best answer)

A.   PERT   
B.   CPM   
C.   GERT   
D.   PDM 
17. If you are calculating an early start and early finish for each task, you are using:
    (choose the best answer)

A.   PERT   
B.   CPM   
C.   GERT   
D.   PDM 




 Correct Choice:     B  
 Justification:     The critical path method calculates the theoretical early start and finish dates,
 and the late start and finish dates, for all schedule activities without regard for any resource
 limitations, by performing a forward pass analysis and a backward pass analysis through the
 project schedule network paths.

 Reference: PMBOK Third Edition, Page Number: 145

 pmstudy.com comments: Critical Path Method(CPM) calculates a single, deterministic early
 and late start and finish date for each activity based on specified, sequential network logic and a
 single duration estimate.
18. Float is the amount of time an activity can be delayed without delaying the project
    finish date. It can also be called: 


A.   Slack  
B.   Total Float  
C.   Path Float  
D.   Critical Path
18. Float is the amount of time an activity can be delayed without delaying the project
    finish date. It can also be called: 


A.   Slack  
B.   Total Float  
C.   Path Float  
D.   Critical Path



Correct Choice:     A  
Justification:     Float is also called slack

Reference: PMBOK Third Edition, Page Number: 361
19. An activity has an optimistic estimate of ten days, pessimistic estimate of sixteen
    days, and most likely estimate of thirteen days. Assuming a normal distribution,
    what is the probability that the task will be completed within 10 - 16 days?

A.   99.99 % 
B.   99.73 % 
C.   95.46 % 
D.   68.26%
19. An activity has an optimistic estimate of ten days, pessimistic estimate of sixteen
    days, and most likely estimate of thirteen days. Assuming a normal distribution,
    what is the probability that the task will be completed within 10 - 16 days?

A.   99.99 % 
B.   99.73 % 
C.   95.46 % 
D.   68.26%

Correct Choice:     B 
Justification:     Please refer to Diagram about 6 Sigma below:

In a Normal Distribution, the PERT duration (also called mean)
= (Pessimistic + 4* (Most Likely) + Optimistic)/6
= (10 + 4 * 13 + 16)/6
= 13

1 Standard Deviation (sigma)
= (Pessimistic - Optimistic) / 6
= (16 - 10) / 6
=1

So, if the task has to be completed within 10 days and 16 days, then the probability of completion within the
timeframe is 99.73%(3 sigma) as shown in the exhibit.

Reference: pmstudy.com notes as mentioned above; pmstudy.com comments: To know more about 6 sigma
calculations, please refer to Project Management - A Systems Approach to Planning, Scheduling and
Controlling, Page 693 - Page 695
20. Critical chain is a schedule network analysis technique that modifies the project
    schedule to account for limited resources. The critical chain combines
    deterministic and probabilistic approaches. Initially, the project schedule network
    diagram is built using non-conservative estimates for activity durations within the
    schedule model, with required dependencies and defined constraints as inputs.
    The critical path is then calculated. After the critical path is identified, resource
    availability is entered and the resource-limited schedule result is determined. The
    resulting schedule often has an altered critical path.

The critical chain method adds non-work schedule activities to maintain focus on the
   planned activity durations, also referred to as:

A.   Duration Buffers
B.   Resource Leveling
C.   Reverse Resource Leveling
D.   Crashing
20. Critical chain is a schedule network analysis technique that modifies the project
    schedule to account for limited resources. The critical chain combines
    deterministic and probabilistic approaches. Initially, the project schedule network
    diagram is built using non-conservative estimates for activity durations within the
    schedule model, with required dependencies and defined constraints as inputs.
    The critical path is then calculated. After the critical path is identified, resource
    availability is entered and the resource-limited schedule result is determined. The
    resulting schedule often has an altered critical path.

The critical chain method adds non-work schedule activities to maintain focus on the
   planned activity durations, also referred to as:

A.   Duration Buffers
B.   Resource Leveling
C.   Reverse Resource Leveling
D.   Crashing


 Correct Choice:     A 
 Justification:     The critical chain method adds duration buffers that are non-work
 schedule activities to maintain focus on the planned activity durations.

 Reference: PMBOK Third Edition, Page Number: 147
21. If the number of critical paths in the project increases, but the duration of the project
    remains the same, what should the project manager do?

A.   Perform crashing to complete project on time
B.   Fast track the project
C.   Perform additional risk planning
D.   Decrease the scope of the project
21. If the number of critical paths in the project increases, but the duration of the project
    remains the same, what should the project manager do?

A.   Perform crashing to complete project on time
B.   Fast track the project
C.   Perform additional risk planning
D.   Decrease the scope of the project




Correct Choice:     C  
Justification:      If the number of critical paths increases for the project, delay in any one of the
critical paths has the potential for delaying the project. So, the risk of the project (in meeting the
project schedule) increases. Hence additional risk planning has to be performed.

Reference: pmstudy.com notes as mentioned above
22. You got news that because of bad weather, your shipment has got delayed by two
    weeks. What should be the FIRST step that you should take?   

A. Fast track the project to ensure that the project schedule is not delayed.  
B. Review the performance reports to determine which planned dates have not been met,
   and the impact on the critical path.  
C. Try to get additional supplies from an alternate location as soon as possible.  
D. Take corrective action to minimize the impact of the delay.
22. You got news that because of bad weather, your shipment has got delayed by two
    weeks. What should be the FIRST step that you should take?   

A. Fast track the project to ensure that the project schedule is not delayed.  
B. Review the performance reports to determine which planned dates have not been met,
   and the impact on the critical path.  
C. Try to get additional supplies from an alternate location as soon as possible.  
D. Take corrective action to minimize the impact of the delay.



Correct Choice:     B  
Justification:     Performance reports provide information on schedule performance, such as
which planned dates have been met and which have not.

Reference: PMBOK Third Edition, Page Number: 153

pmstudy comments: Since performance reports are used to track project execution, they should
be consulted first when there is a delay in the project to determine the potential impacts
23. A planning package is a:

A.   Unit of the project plan  
B.   Unit of the scope management plan 
C.   WBS component below the control account  
D.   Template used for the project
23. A planning package is a:

A.   Unit of the project plan  
B.   Unit of the scope management plan 
C.   WBS component below the control account  
D.   Template used for the project




Correct Choice:     C  
Justification:     A planning package is a WBS component below the control account, but
above the work package

Reference: PMBOK Third Edition, Page Number: 129
24. Please refer to this diagram:




What is the slack of task G?
A. 0 weeks
B. 1 week
C. -1 week
D. Cannot be determined
Correct Choice:     A  
Justification:     Justification: Please refer to this diagram:




START -> G -> I -> C -> D -> END: 23 lies on the critical path. So, slack of task G = 0

Reference: pmstudy.com notes as mentioned above
25. In your project, you realize the importance of determining the start and finish dates
    for project activities. If the project start or end dates are not realistic, then the project
    may not be completed on time. This is done as part of:

A.   Activity Sequencing 
B.   Activity Duration Estimating 
C.   Schedule Development 
D.   Activity Definition
25. In your project, you realize the importance of determining the start and finish dates
    for project activities. If the project start or end dates are not realistic, then the project
    may not be completed on time. This is done as part of:

A.   Activity Sequencing 
B.   Activity Duration Estimating 
C.   Schedule Development 
D.   Activity Definition



Correct Choice:     C  
Justification:     Project Schedule Development, an iterative process, determines the planned start
and finish dates for project activities. Schedule development can require that duration estimates and
resource estimates are reviewed and revised to create an approved project schedule

Reference: PMBOK Third Edition, Page Number: 143
26. You have taken information on project scope and resources and then developed
    duration of activities for input to schedules. Since there was very limited information
    about the project, you used the actual duration of a previous, similar activity as the
    basis for estimating future activity. What should you do next?

A.   Use diagramming techniques like GERT and Systems Dynamics 
B.   Calculate theoretical early and late start and finish dates for all project activities 
C.   Use Standardized Networks to expedite preparation of Project Network Diagrams 
D.   Subdivide project work packages into smaller more manageable components for better
     management control
26. You have taken information on project scope and resources and then developed
    duration of activities for input to schedules. Since there was very limited information
    about the project, you used the actual duration of a previous, similar activity as the
    basis for estimating future activity. What should you do next?

A.   Use diagramming techniques like GERT and Systems Dynamics 
B.   Calculate theoretical early and late start and finish dates for all project activities 
C.   Use Standardized Networks to expedite preparation of Project Network Diagrams 
D.   Subdivide project work packages into smaller more manageable components for better
     management control


Correct Choice:     B  
Justification:     Analogous Duration Estimating means using the actual duration of a previous
similar schedule activity as the basis for estimating the duration of a future schedule activity - this is
done as part of Activity Duration Estimating.

Reference: PMBOK Third Edition, Page Number: 141

pmstudy.com comments: Activity Duration Estimating will be followed by Schedule Development -
one tool and technique used is Schedule Network Analysis (which involves calculating theoretical
early and late start and finish dates : Refer PMBOK Page 145) - so, correct choice is # 2
27. Activity definition involves identifying and documenting the specific activities that
    must be performed to produce the deliverables and sub-deliverables identified in the
    work breakdown structure (WBS). All the following statements about the activity list
    produced as an output from activity definition are true EXCEPT: 

A. The activity list must include all activities that will be performed on the project  
B. The activity list may include some activities that are not required as part of the project  
C. The activity list should include descriptions of each activity to ensure that the project
   team members will understand how the work is to be done  
D. The activity list is used in the schedule model and is a component of the project
   management plan
27. Activity definition involves identifying and documenting the specific activities that
    must be performed to produce the deliverables and sub-deliverables identified in the
    work breakdown structure (WBS). All the following statements about the activity list
    produced as an output from activity definition are true EXCEPT: 

A. The activity list must include all activities that will be performed on the project  
B. The activity list may include some activities that are not required as part of the project  
C. The activity list should include descriptions of each activity to ensure that the project
   team members will understand how the work is to be done  
D. The activity list is used in the schedule model and is a component of the project
   management plan

 Correct Choice:     B  
 Justification:     The activity list does not include any schedule activities that are
 required as part of the project scope.

 Reference: PMBOK Third Edition, Page Number: 129

 pmstudy.com comments: Option 2 refers to "Gold Plating" or adding features
 not mentioned in the project scope - this practice is not recommended by PMI
Wrap Up
Conference Number: 547-941-6414 or 866-547-8978
Passcode: Leader – 844306338, Participant – 370670831

6   Cost Management      October 23   2:00pm EST   Presenter:       https://
    (PMBOK Chapters 7)
                                                      www.rooms.hp.com/attend/default.aspx?key=EHKYYTFNGJ
                                                   Participant:     https://
                                                      www.rooms.hp.com/attend/default.aspx?key=EPBJY3JEZ4

More Related Content

What's hot

Project managemenet knowledge areas
Project managemenet knowledge areasProject managemenet knowledge areas
Project managemenet knowledge areaslinajarruti
 
Leadership in construction
Leadership in constructionLeadership in construction
Leadership in constructionAditya Ghumare
 
Defining and documenting a project
Defining and documenting a projectDefining and documenting a project
Defining and documenting a projectJing Fan Koh
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Construction project delivery methods
Construction project delivery methodsConstruction project delivery methods
Construction project delivery methodsNitin Kumar
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
Cost management
Cost managementCost management
Cost managementshkadry
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJTapesh Ajmera
 
Green pmp exam prep questions answers explanations 2013 edition by christophe...
Green pmp exam prep questions answers explanations 2013 edition by christophe...Green pmp exam prep questions answers explanations 2013 edition by christophe...
Green pmp exam prep questions answers explanations 2013 edition by christophe...mohamed mostafa
 
M& e slide share
M& e   slide shareM& e   slide share
M& e slide shareSelf
 
Primavera vs Microsoft project
Primavera vs Microsoft projectPrimavera vs Microsoft project
Primavera vs Microsoft projectWigene Tabamo
 
Writing Project Proposals
Writing Project ProposalsWriting Project Proposals
Writing Project ProposalsDanaaan
 

What's hot (15)

Project managemenet knowledge areas
Project managemenet knowledge areasProject managemenet knowledge areas
Project managemenet knowledge areas
 
Leadership in construction
Leadership in constructionLeadership in construction
Leadership in construction
 
Defining and documenting a project
Defining and documenting a projectDefining and documenting a project
Defining and documenting a project
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Construction project delivery methods
Construction project delivery methodsConstruction project delivery methods
Construction project delivery methods
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Cost management
Cost managementCost management
Cost management
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
 
Green pmp exam prep questions answers explanations 2013 edition by christophe...
Green pmp exam prep questions answers explanations 2013 edition by christophe...Green pmp exam prep questions answers explanations 2013 edition by christophe...
Green pmp exam prep questions answers explanations 2013 edition by christophe...
 
M& e slide share
M& e   slide shareM& e   slide share
M& e slide share
 
Primavera vs Microsoft project
Primavera vs Microsoft projectPrimavera vs Microsoft project
Primavera vs Microsoft project
 
Program Management Office (PMO)
Program Management Office (PMO)Program Management Office (PMO)
Program Management Office (PMO)
 
PgMP 02 - Program Performance Domainv1
PgMP 02 - Program Performance Domainv1PgMP 02 - Program Performance Domainv1
PgMP 02 - Program Performance Domainv1
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Writing Project Proposals
Writing Project ProposalsWriting Project Proposals
Writing Project Proposals
 

Viewers also liked

Viewers also liked (20)

Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
4.contracting
4.contracting4.contracting
4.contracting
 
01 project management framework
01 project management framework01 project management framework
01 project management framework
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Pmp risk chapter 11
Pmp risk chapter 11Pmp risk chapter 11
Pmp risk chapter 11
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 

Similar to Session 5 gdas pmp study group presentation

PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxstilliegeorgiana
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answersMohamed Saeed
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxalfred4lewis58146
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2Narayan Mane
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docxdorishigh
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxIRESH3
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management Joshua Miranda
 
1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdfsuhshbhosale
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project ReportRISHABHSIINGH
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Engineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualEngineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualSummerfieldTBL
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
No matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxNo matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxhenrymartin15260
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1Daniel Hucks
 

Similar to Session 5 gdas pmp study group presentation (20)

Pmp6
Pmp6Pmp6
Pmp6
 
Self test engine PSP-PMI-SP
Self test engine PSP-PMI-SPSelf test engine PSP-PMI-SP
Self test engine PSP-PMI-SP
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
 
CAPM Study Session 3
CAPM Study Session 3CAPM Study Session 3
CAPM Study Session 3
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management
 
1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf
 
Chap03
Chap03Chap03
Chap03
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project Report
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Engineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualEngineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manual
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
No matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxNo matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docx
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 

More from Tu Nguyen, PMP®,PMI-RMP® (20)

3.estimating
3.estimating3.estimating
3.estimating
 
2.tendering
2.tendering2.tendering
2.tendering
 
1.introduction
1.introduction1.introduction
1.introduction
 
Node
NodeNode
Node
 
Contract
ContractContract
Contract
 
Cash flow
Cash flowCash flow
Cash flow
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
Time cost-control
Time cost-controlTime cost-control
Time cost-control
 
Resources
ResourcesResources
Resources
 
Pert
PertPert
Pert
 
Organization
OrganizationOrganization
Organization
 
Ch 6 construction progress control
Ch 6 construction progress controlCh 6 construction progress control
Ch 6 construction progress control
 
Ch 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisalCh 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisal
 
Ch 3 contract strategy
Ch 3 contract strategyCh 3 contract strategy
Ch 3 contract strategy
 
Ch 2 planning and scheduling
Ch 2 planning and schedulingCh 2 planning and scheduling
Ch 2 planning and scheduling
 
Ch 1 organization of construction projects
Ch 1 organization of construction projectsCh 1 organization of construction projects
Ch 1 organization of construction projects
 

Session 5 gdas pmp study group presentation

  • 1. GDAS PM Professions: PMP Study Group Session #5: Time Management Monique Howard October 16, 2008 © 2005 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice
  • 2. 1. Please refer to the diagram given below: (all units are in days) What is the project float if management wants to do this project within ten days? A. 0 days B. -4 days C. 2 days D. Cannot be determined because information in the question is inconsistent
  • 3. Correct Choice:     B  (-4 days) Justification:     The different paths possible are as follows: * Start -> Task1 -> Task2 -> Task3 -> End : 10 * Start -> Task1 -> Task2 -> Task3 -> Task6 -> End : 14 * Start -> Task4 -> Task5 -> Task6 -> End: 13 * Start -> Task4 -> Task5 -> Task3 -> Task6 -> End: 14 * Start -> Task4 -> Task5 -> Task3 -> End: 10 So, the critical path is 14. If the project has to be completed within 10 days, the project float is - 4 days (i.e 10 - 14) Please note: A project may have a negative project float. To deal with such conditions, if the project has to be completed on time, the project manager will have to either fast-track or crash the project schedule. Reference: pmstudy.com notes as mentioned above
  • 4. 2. All the following are advantages of GERT (Graphical Evaluation and Review Techniques) as compared with PERT (Project Evaluation and Review Technique) EXCEPT: A. Allows looping B. Allows for dummy tasks C. Allows branching D. Allows multiple project end results
  • 5. 2. All the following are advantages of GERT (Graphical Evaluation and Review Techniques) as compared with PERT (Project Evaluation and Review Technique) EXCEPT: A. Allows looping B. Allows for dummy tasks C. Allows branching D. Allows multiple project end results Correct Choice:     B  Justification:     Graphical Evaluation and Review techniques are similar to PERT but have the distinct advantages of allowing for looping, branching, and multiple project end results. Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, Page Number: 679
  • 6. 3. It is important to identify and document the specific work that is planned to be performed and also identify deliverables at the work package level. This is done as part of: A. Activity Definition B. Decomposition C. Scope Definition D. Activity Sequencing
  • 7. 3. It is important to identify and document the specific work that is planned to be performed and also identify deliverables at the work package level. This is done as part of: A. Activity Definition B. Decomposition C. Scope Definition D. Activity Sequencing Correct Choice:     A  Justification:     Activity Definition: Defining the schedule activities involves identifying and documenting the work that is planned to be performed. The activity definition process will identify the deliverables at the lowest level in the WBS, which is called the work package. Reference: PMBOK Third Edition, Page Number: 127
  • 8. 4. In schedule development, mathematical analysis often produces a preliminary early- start schedule that shows peaks and valleys in the resource requirements. Resource leveling done to take care of this issue may result in all of the following EXCEPT: A. Increase in project duration B. Utilization of weekends, extended hours or multiple shifts C. Productivity increases by using different technologies and/or methodologies D. Reduction in project cost 
  • 9. 4. In schedule development, mathematical analysis often produces a preliminary early- start schedule that shows peaks and valleys in the resource requirements. Resource leveling done to take care of this issue may result in all of the following EXCEPT: A. Increase in project duration B. Utilization of weekends, extended hours or multiple shifts C. Productivity increases by using different technologies and/or methodologies D. Reduction in project cost  Correct Choice:     D   Justification:     pmstudy.com comments: As different techniques like crashing, fast tracking, resource reallocation etc. are being considered for resource leveling, there is a real possibility of an increase in costs. Reference: PMBOK Third Edition, Page Number: 147
  • 10. 5. All the following statements regarding the creation of Time Estimates are correct EXCEPT: A. Mathematical analysis like CPM, GERT and PERT indicate the dates on which the activity can be scheduled given resource limits and other constraints. B. Duration compression techniques including fast tracking and crashing can help in decreasing the project schedule C. WBS classification allows for useful activity ordering and sorting. D. The duration of the project is the sum of the duration of all the tasks in the project. 
  • 11. 5. All the following statements regarding the creation of Time Estimates are correct EXCEPT: A. Mathematical analysis like CPM, GERT and PERT indicate the dates on which the activity can be scheduled given resource limits and other constraints. B. Duration compression techniques including fast tracking and crashing can help in decreasing the project schedule C. WBS classification allows for useful activity ordering and sorting. D. The duration of the project is the sum of the duration of all the tasks in the project.  Correct Choice:     D   Justification:     The duration of the project should be calculated after drawing a network diagram and determining the critical path. The duration of the project is the length of the critical path, and not the sum of the duration of all the tasks in the project. Reference: pmstudy.com notes as mentioned above
  • 12. 6. A management control point can be placed at selected management points (specific components at selected levels) of the WBS above the work package level. These control points can be: A. Used for rolling wave planning   B. Decomposed further to help in the creation of Work Authorization System   C. Used for planning known work content that does not have detailed schedule activities   D. Used as a basis for planning when associated work packages have not yet been planned 
  • 13. 6. A management control point can be placed at selected management points (specific components at selected levels) of the WBS above the work package level. These control points can be: A. Used for rolling wave planning   B. Decomposed further to help in the creation of Work Authorization System   C. Used for planning known work content that does not have detailed schedule activities   D. Used as a basis for planning when associated work packages have not yet been planned  Correct Choice:     D   Justification:     Control Account : .... A management control point can be placed at selected management points (specific components at selected levels) of the WBS above the work package level. These control points are used as a basis for planning when associated work packages have not yet been planned. Reference: PMBOK Third Edition, Page Number: 129
  • 14. 7. In your project, some requested changes were generated from the Activity Definition Process. These changes will be processed through: A. Activity Change Control System  B. Corrective Action  C. Integrated Change Control System  D. Activity Sequencing
  • 15. 7. In your project, some requested changes were generated from the Activity Definition Process. These changes will be processed through: A. Activity Change Control System  B. Corrective Action  C. Integrated Change Control System  D. Activity Sequencing Correct Choice:     C  Justification:     Requested changes are processed for review and disposition through the Integrated Change Control process. Reference: PMBOK Third Edition, Page Number: 130
  • 16. 8. Please refer to this diagram: What is the effect on the project if the duration of task J is increased to 9 weeks?   A. No effect since task J is not on the critical path    B. Risk of the project will increase   C. The overall time-frame required to complete the project will increase by 1 week   D. None of the above
  • 17. Correct Choice:     B (Risk of the project will increase) Justification: If the duration of task J is increased by 1 week, Start -> G -> I -> J -> End = 23 weeks; this also lies on the critical path (23 days). Since there are 3 critical paths now, a delay in any of the critical paths will delay the overall project - this increases the overall risk for the project. Reference: pmstudy.com notes as mentioned above
  • 18. 9. A project has a critical path of twenty-three weeks. What is the impact on the critical path if the management wants you to complete the project in twenty weeks? A. Duration of the critical path increases by three weeks.    B. Duration of the critical path decreases by three weeks.    C. Duration of the critical path remains same.    D. Duration of the critical path cannot be determined. 
  • 19. 9. A project has a critical path of twenty-three weeks. What is the impact on the critical path if the management wants you to complete the project in twenty weeks? A. Duration of the critical path increases by three weeks.    B. Duration of the critical path decreases by three weeks.    C. Duration of the critical path remains same.    D. Duration of the critical path cannot be determined.  Correct Choice:     C   Justification:     Duration of critical path = 23 weeks If the management wants to complete the project in twenty weeks, then the project float will be : 20 - 23 = -3 weeks The project float compares the critical path with an externally imposed date and may be negative. (you may be forced to fast-track or perform crashing to ensure that the project is completed within the dates required by the management) But, there will be no change to the critical path. Reference: pmstudy.com notes as mentioned above
  • 20. 10. You are doing a Monte Carlo Analysis in which you are defining a distribution of possible activity durations for each schedule activity and calculating a distribution of possible outcomes for the total project. Monte Carlo analysis is an example of: A. Resource Leveling  B. What-if Scenario Analysis  C. Schedule Network Analysis  D. Critical Path Method
  • 21. 10. You are doing a Monte Carlo Analysis in which you are defining a distribution of possible activity durations for each schedule activity and calculating a distribution of possible outcomes for the total project. Monte Carlo analysis is an example of: A. Resource Leveling  B. What-if Scenario Analysis  C. Schedule Network Analysis  D. Critical Path Method Correct Choice:     B  Justification:     What-if Scenario Analysis: ... Simulation involves calculating multiple project durations with different set of activity assumptions. The most common technique is Monte Carlo Analysis Reference: PMBOK Third Edition, Page Number: 146
  • 22. 11. Your project SPI is 0.86 and the management has recommended that you should fast- track the project. You agree with the management but warn them that fast-tracking could:  A. Facilitate duration compression  B. Increase risk  C. Ensure activities are done in parallel which would normally be done in sequence  D. Help shorten the project schedule without changing the project scope
  • 23. 11. Your project SPI is 0.86 and the management has recommended that you should fast- track the project. You agree with the management but warn them that fast-tracking could:  A. Facilitate duration compression  B. Increase risk  C. Ensure activities are done in parallel which would normally be done in sequence  D. Help shorten the project schedule without changing the project scope Correct Choice:     B   Justification:     Fast Tracking can result in rework and increased risk Reference: PMBOK Third Edition, Page Number: 146 pmstudy.com comments: Since increase in risk is a negative outcome of fast-tracking, you should warn your management about the increased risk. All the other options are benefits of fast- tracking.
  • 24. 12. 12. In schedule development, you create a distribution of probable results for each activity and use it to calculate the distribution of probable results for the total project. The technique that you are using is: A. What-if Analysis  B. Mathematical Analysis  C. Monte Carlo Analysis  D. Resource Leveling Heuristic
  • 25. 12. In schedule development, you create a distribution of probable results for each activity and use it to calculate the distribution of probable results for the total project. The technique that you are using is: A. What-if Analysis  B. Mathematical Analysis  C. Monte Carlo Analysis  D. Resource Leveling Heuristic Correct Choice:     C   Justification:     Simulation involves calculating multiple project durations with different sets of activity assumptions. The most common technique is called Monte Carlo Analysis, in which a distribution of probable results is defined for each activity and is used to calculate a distribution of probable results for the whole project. Reference: PMBOK Third Edition, Page Number: 146
  • 26. 13. You are going to make a presentation on the project to the senior management. In this context, the difference of a milestone chart as compared with a bar chart when making presentations is that unlike bar charts, milestones: A. Show activity start and end dates  B. Show dependencies among tasks  C. Only identify the scheduled start or completion of major deliverables, and not all the tasks  D. Show supporting details
  • 27. 13. You are going to make a presentation on the project to the senior management. In this context, the difference of a milestone chart as compared with a bar chart when making presentations is that unlike bar charts, milestones: A. Show activity start and end dates  B. Show dependencies among tasks  C. Only identify the scheduled start or completion of major deliverables, and not all the tasks  D. Show supporting details Correct Choice:     C   Justification:     Milestone charts (see Figure 6-10) are similar to bar charts, but only identify the scheduled start or completion of major deliverables and key external interfaces. Reference: PMBOK Third Edition, Page Number: 149
  • 28. 14. Please refer to the figure below: If these three tasks (i.e. Task A, Task B, Task C) are not part of the critical path of a project, what is the PERT estimate for the duration of the project? A. 22.5  B. 10.33  C. 32  D. Cannot be determined
  • 29. Correct Choice:     D   Justification:     Since the tasks are not on the critical path of the project, we cannot determine the PERT estimate for the duration of the project. The PERT estimate can only be calculated for the critical path of the project. Reference: pmstudy.com notes as mentioned above
  • 30. 15. In your project, you are in the process of creating an activity list. This should contain all the following EXCEPT:  A. Activities that are not required as part of the project scope   B. Activities that are to be performed as part of the project   C. Activity identifiers and scope of work descriptions for each schedule activity   D. Activities that are required as part of the project scope 
  • 31. 15. In your project, you are in the process of creating an activity list. This should contain all the following EXCEPT:  A. Activities that are not required as part of the project scope   B. Activities that are to be performed as part of the project   C. Activity identifiers and scope of work descriptions for each schedule activity   D. Activities that are required as part of the project scope  Correct Choice:     A   Justification:     The activity list does not include any schedule activities that are required as part of the project scope. Reference: PMBOK Third Edition, Page Number: 129
  • 32. 16. Since you are in the preliminary stages of your project, you estimate that your project will last one year. However, an optimistic scenario is that it will get over within six months and a pessimistic scenario is eighteen months. This kind of estimate is also called: A. Definitive    B. Capital Cost    C. Order of Magnitude    D. Feasibility 
  • 33. 16. Since you are in the preliminary stages of your project, you estimate that your project will last one year. However, an optimistic scenario is that it will get over within six months and a pessimistic scenario is eighteen months. This kind of estimate is also called: A. Definitive    B. Capital Cost    C. Order of Magnitude    D. Feasibility  Correct Choice:     C   Justification:     The classes of estimates and their accuracy % is as follows: * Definitive (+- 5%) * Capital Cost (+- 10% - 15%) * Appropriation ( +- 15% - 25%) * Feasibility (+_ 25% - 35 %) * Order of Magnitude ( > +- 35%) Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, Page Number: 745
  • 34. 17. If you are calculating an early start and early finish for each task, you are using: (choose the best answer) A. PERT    B. CPM    C. GERT    D. PDM 
  • 35. 17. If you are calculating an early start and early finish for each task, you are using: (choose the best answer) A. PERT    B. CPM    C. GERT    D. PDM  Correct Choice:     B   Justification:     The critical path method calculates the theoretical early start and finish dates, and the late start and finish dates, for all schedule activities without regard for any resource limitations, by performing a forward pass analysis and a backward pass analysis through the project schedule network paths. Reference: PMBOK Third Edition, Page Number: 145 pmstudy.com comments: Critical Path Method(CPM) calculates a single, deterministic early and late start and finish date for each activity based on specified, sequential network logic and a single duration estimate.
  • 36. 18. Float is the amount of time an activity can be delayed without delaying the project finish date. It can also be called:  A. Slack   B. Total Float   C. Path Float   D. Critical Path
  • 37. 18. Float is the amount of time an activity can be delayed without delaying the project finish date. It can also be called:  A. Slack   B. Total Float   C. Path Float   D. Critical Path Correct Choice:     A   Justification:     Float is also called slack Reference: PMBOK Third Edition, Page Number: 361
  • 38. 19. An activity has an optimistic estimate of ten days, pessimistic estimate of sixteen days, and most likely estimate of thirteen days. Assuming a normal distribution, what is the probability that the task will be completed within 10 - 16 days? A. 99.99 %  B. 99.73 %  C. 95.46 %  D. 68.26%
  • 39. 19. An activity has an optimistic estimate of ten days, pessimistic estimate of sixteen days, and most likely estimate of thirteen days. Assuming a normal distribution, what is the probability that the task will be completed within 10 - 16 days? A. 99.99 %  B. 99.73 %  C. 95.46 %  D. 68.26% Correct Choice:     B  Justification:     Please refer to Diagram about 6 Sigma below: In a Normal Distribution, the PERT duration (also called mean) = (Pessimistic + 4* (Most Likely) + Optimistic)/6 = (10 + 4 * 13 + 16)/6 = 13 1 Standard Deviation (sigma) = (Pessimistic - Optimistic) / 6 = (16 - 10) / 6 =1 So, if the task has to be completed within 10 days and 16 days, then the probability of completion within the timeframe is 99.73%(3 sigma) as shown in the exhibit. Reference: pmstudy.com notes as mentioned above; pmstudy.com comments: To know more about 6 sigma calculations, please refer to Project Management - A Systems Approach to Planning, Scheduling and Controlling, Page 693 - Page 695
  • 40. 20. Critical chain is a schedule network analysis technique that modifies the project schedule to account for limited resources. The critical chain combines deterministic and probabilistic approaches. Initially, the project schedule network diagram is built using non-conservative estimates for activity durations within the schedule model, with required dependencies and defined constraints as inputs. The critical path is then calculated. After the critical path is identified, resource availability is entered and the resource-limited schedule result is determined. The resulting schedule often has an altered critical path. The critical chain method adds non-work schedule activities to maintain focus on the planned activity durations, also referred to as: A. Duration Buffers B. Resource Leveling C. Reverse Resource Leveling D. Crashing
  • 41. 20. Critical chain is a schedule network analysis technique that modifies the project schedule to account for limited resources. The critical chain combines deterministic and probabilistic approaches. Initially, the project schedule network diagram is built using non-conservative estimates for activity durations within the schedule model, with required dependencies and defined constraints as inputs. The critical path is then calculated. After the critical path is identified, resource availability is entered and the resource-limited schedule result is determined. The resulting schedule often has an altered critical path. The critical chain method adds non-work schedule activities to maintain focus on the planned activity durations, also referred to as: A. Duration Buffers B. Resource Leveling C. Reverse Resource Leveling D. Crashing Correct Choice:     A  Justification:     The critical chain method adds duration buffers that are non-work schedule activities to maintain focus on the planned activity durations. Reference: PMBOK Third Edition, Page Number: 147
  • 42. 21. If the number of critical paths in the project increases, but the duration of the project remains the same, what should the project manager do? A. Perform crashing to complete project on time B. Fast track the project C. Perform additional risk planning D. Decrease the scope of the project
  • 43. 21. If the number of critical paths in the project increases, but the duration of the project remains the same, what should the project manager do? A. Perform crashing to complete project on time B. Fast track the project C. Perform additional risk planning D. Decrease the scope of the project Correct Choice:     C   Justification:      If the number of critical paths increases for the project, delay in any one of the critical paths has the potential for delaying the project. So, the risk of the project (in meeting the project schedule) increases. Hence additional risk planning has to be performed. Reference: pmstudy.com notes as mentioned above
  • 44. 22. You got news that because of bad weather, your shipment has got delayed by two weeks. What should be the FIRST step that you should take?    A. Fast track the project to ensure that the project schedule is not delayed.   B. Review the performance reports to determine which planned dates have not been met, and the impact on the critical path.   C. Try to get additional supplies from an alternate location as soon as possible.   D. Take corrective action to minimize the impact of the delay.
  • 45. 22. You got news that because of bad weather, your shipment has got delayed by two weeks. What should be the FIRST step that you should take?    A. Fast track the project to ensure that the project schedule is not delayed.   B. Review the performance reports to determine which planned dates have not been met, and the impact on the critical path.   C. Try to get additional supplies from an alternate location as soon as possible.   D. Take corrective action to minimize the impact of the delay. Correct Choice:     B   Justification:     Performance reports provide information on schedule performance, such as which planned dates have been met and which have not. Reference: PMBOK Third Edition, Page Number: 153 pmstudy comments: Since performance reports are used to track project execution, they should be consulted first when there is a delay in the project to determine the potential impacts
  • 46. 23. A planning package is a: A. Unit of the project plan   B. Unit of the scope management plan  C. WBS component below the control account   D. Template used for the project
  • 47. 23. A planning package is a: A. Unit of the project plan   B. Unit of the scope management plan  C. WBS component below the control account   D. Template used for the project Correct Choice:     C   Justification:     A planning package is a WBS component below the control account, but above the work package Reference: PMBOK Third Edition, Page Number: 129
  • 48. 24. Please refer to this diagram: What is the slack of task G? A. 0 weeks B. 1 week C. -1 week D. Cannot be determined
  • 49. Correct Choice:     A   Justification:     Justification: Please refer to this diagram: START -> G -> I -> C -> D -> END: 23 lies on the critical path. So, slack of task G = 0 Reference: pmstudy.com notes as mentioned above
  • 50. 25. In your project, you realize the importance of determining the start and finish dates for project activities. If the project start or end dates are not realistic, then the project may not be completed on time. This is done as part of: A. Activity Sequencing  B. Activity Duration Estimating  C. Schedule Development  D. Activity Definition
  • 51. 25. In your project, you realize the importance of determining the start and finish dates for project activities. If the project start or end dates are not realistic, then the project may not be completed on time. This is done as part of: A. Activity Sequencing  B. Activity Duration Estimating  C. Schedule Development  D. Activity Definition Correct Choice:     C   Justification:     Project Schedule Development, an iterative process, determines the planned start and finish dates for project activities. Schedule development can require that duration estimates and resource estimates are reviewed and revised to create an approved project schedule Reference: PMBOK Third Edition, Page Number: 143
  • 52. 26. You have taken information on project scope and resources and then developed duration of activities for input to schedules. Since there was very limited information about the project, you used the actual duration of a previous, similar activity as the basis for estimating future activity. What should you do next? A. Use diagramming techniques like GERT and Systems Dynamics  B. Calculate theoretical early and late start and finish dates for all project activities  C. Use Standardized Networks to expedite preparation of Project Network Diagrams  D. Subdivide project work packages into smaller more manageable components for better management control
  • 53. 26. You have taken information on project scope and resources and then developed duration of activities for input to schedules. Since there was very limited information about the project, you used the actual duration of a previous, similar activity as the basis for estimating future activity. What should you do next? A. Use diagramming techniques like GERT and Systems Dynamics  B. Calculate theoretical early and late start and finish dates for all project activities  C. Use Standardized Networks to expedite preparation of Project Network Diagrams  D. Subdivide project work packages into smaller more manageable components for better management control Correct Choice:     B   Justification:     Analogous Duration Estimating means using the actual duration of a previous similar schedule activity as the basis for estimating the duration of a future schedule activity - this is done as part of Activity Duration Estimating. Reference: PMBOK Third Edition, Page Number: 141 pmstudy.com comments: Activity Duration Estimating will be followed by Schedule Development - one tool and technique used is Schedule Network Analysis (which involves calculating theoretical early and late start and finish dates : Refer PMBOK Page 145) - so, correct choice is # 2
  • 54. 27. Activity definition involves identifying and documenting the specific activities that must be performed to produce the deliverables and sub-deliverables identified in the work breakdown structure (WBS). All the following statements about the activity list produced as an output from activity definition are true EXCEPT:  A. The activity list must include all activities that will be performed on the project   B. The activity list may include some activities that are not required as part of the project   C. The activity list should include descriptions of each activity to ensure that the project team members will understand how the work is to be done   D. The activity list is used in the schedule model and is a component of the project management plan
  • 55. 27. Activity definition involves identifying and documenting the specific activities that must be performed to produce the deliverables and sub-deliverables identified in the work breakdown structure (WBS). All the following statements about the activity list produced as an output from activity definition are true EXCEPT:  A. The activity list must include all activities that will be performed on the project   B. The activity list may include some activities that are not required as part of the project   C. The activity list should include descriptions of each activity to ensure that the project team members will understand how the work is to be done   D. The activity list is used in the schedule model and is a component of the project management plan Correct Choice:     B   Justification:     The activity list does not include any schedule activities that are required as part of the project scope. Reference: PMBOK Third Edition, Page Number: 129 pmstudy.com comments: Option 2 refers to "Gold Plating" or adding features not mentioned in the project scope - this practice is not recommended by PMI
  • 56. Wrap Up Conference Number: 547-941-6414 or 866-547-8978 Passcode: Leader – 844306338, Participant – 370670831 6 Cost Management October 23 2:00pm EST Presenter: https:// (PMBOK Chapters 7) www.rooms.hp.com/attend/default.aspx?key=EHKYYTFNGJ Participant: https:// www.rooms.hp.com/attend/default.aspx?key=EPBJY3JEZ4