SlideShare une entreprise Scribd logo
1  sur  9
Télécharger pour lire hors ligne
The Magazine Of 
The Institution Of Engineers, Singapore 
August 2014 MCI (P) 157/01/2014 
www.ies.org.sg 
THE 
SINGAPORE ENGINEER 
COVER STORY: 
CIVIL & STRUCTURAL ENGINEERING 
NUH Medical Centre 
FEATURES: 
Construction Technology • Health & Safety Engineering • Project Application
COVER STORY 
NUH Medical Centre 
The project won a BCA Design and Engineering Safety Excellence Award (Merit) under 
the Institutional & Industrial Category, at BCA AWARDS 2014. By adopting innovative 
engineering solutions to overcome the site and design challenges, the structural works 
were completed and delivered on time, despite tight schedules, to enable commencement 
of other trades. 
NUH Medical Centre is the latest, and one of three buildings 
serving hospital patients within the NUH campus. It houses 190 
consultation rooms, more than 200 treatment and procedure 
rooms, 10 day surgery operating theatres, as well as dedicated 
space for teaching and clinical trials. 
It is also home to the National University Cancer Institute, 
Singapore (Yong Siew Yoon Wing) which provides one-stop, 
comprehensive care for both adult and pediatric oncology 
patients. The NUH Medical Centre is fully integrated with 
infrastructure for support services, such as clinical laboratories; 
14 THE SINGAPORE ENGINEER August 2014 
facilities for dietetics services and imaging; pharmacy; and a health 
resource centre, designed to provide patients with holistic care. 
The 19-storey NUH Medical Centre was completed in 2013 
and started serving patients in July the same year. 
Generating a total GFA of 72,000 m2, the NUH Medical Centre 
was a fast-track project completed in 28 months. The consultant 
team was required to carry out thorough project planning, 
design coordination and review of construction methodology, 
to ensure engineering safety during project implementation as 
well as timely completion. 
NUH Medical Centre. Image by Penta Ocean Construction Co Ltd.
COVER STORY 
August 2014 THE SINGAPORE ENGINEER 15 
The main contract commenced on 16 December 2010. 
T.O.P. was obtained on 26 April 2013. 
As Structural Designer, T.Y. Lin International Pte Ltd (TYLI) 
collaborated with the NUH Medical Centre’s consultant team, 
drawing on TYLI Singapore’s expertise in engineering design 
for healthcare structures and complex buildings, to develop 
the optimum structural solution. The process encompassed the 
consideration of both design and construction methodologies 
for the structure. Er. Ng Swee Tong oversaw the project delivery 
as the Project Manager and Qualifi ed Person. 
PROJECT HIGHLIGHTS 
A steel truss system was selected as the optimum structural 
system for the facility. This incorporated six sets of double 
steel transfer trusses located in between Levels 12 and 13. 
The transfer truss system is a key feature of this project, as this 
concept allowed the expansion of the Gross Floor Area (GFA) 
to 72,000 m², by supporting eight additional fl oors over the 
MRT station box. 
There are six elevated radiation bunkers located on Level 8. 
Each has a 2.5 m thick concrete enclosure. 
The stringent requirement for radiation shielding demanded 
effective temperature control of the large volume concrete 
casting, so as to eliminate micro-cracking of the bunker 
structures. The adequacy of the formwork system to support 
the massive wet concrete during construction of these bunkers 
was a key design consideration in locating the bunkers on 
Level 8, for the operational effi ciency of the cancer centre. 
SITE CHALLENGES 
The NUH Medical Centre is located directly above Kent Ridge 
MRT Station, within the fi rst reserve of the railway protection 
zone and adjacent to the NUH Kent Ridge Wing in operation. 
This presented a number of challenges that the team had to 
overcome, for timely completion of the project. 
• The undulating site terrain, with the existing ground levels 
varying from 127.5 m to 141.95 m demanded careful design 
consideration and planning. 
• Mitigating the potential traffi c impacts throughout the 
construction phase was crucial. The road network in the 
vicinity of the hospital experiences heavy traffi c movement 
especially during peak hours. 
Development commencement and completion 
Figure 3: Elevated radiation bunkers 
LINAC bunkers formwork 
The site plan
COVER STORY 
• Rigorous control processes were considered at the design 
stage and implemented stringently during construction, to 
safeguard the structural integrity of Kent Ridge MRT Station 
and the tunnels. 
DESIGN CHALLENGES 
The Kent Ridge Station structure was designed with provision 
for a future building, with 24 column stumps on top of the 
central zone of the station, that would house seven levels of 
medical units. A difference in levels of 14 m at two sides of the 
spiral ramp and the close proximity of the MRT tunnels posed 
challenges in construction. 
MRT station structure 
16 THE SINGAPORE ENGINEER August 2014 
The primary considerations in the selection of the structural 
system for the healthcare facility included: 
• Structural stiffness to meet the operational requirements of 
various types of sensitive medical equipment. 
• Building robustness to resist accidental loads. 
• Ease of construction. 
Special consideration was given to achieving high buildability 
scores, despite the above stringent requirements. 
CONSTRUCTION CHALLENGES 
Heavy transfer structures are typically long-span and massive, 
and they pose challenges for quality control during fabrication 
and installation. As the site was in close proximity to the hospital 
wards, mitigation of noise and vibration generated during 
construction were essential, to avoid any inconvenience or 
disruption to the hospital operations. 
SITE SOLUTIONS 
In anticipating various weathering grades of undulating rock 
formation (from completely weathered to highly weathered 
sedimentary rocks), extensive soil investigation was conducted 
to map out the contours of rocks with SPT values greater than 
100, for the entire site. 
Structural system. Images by Penta Ocean Construction Co Ltd.
COVER STORY 
August 2014 THE SINGAPORE ENGINEER 17 
A total of 14 bore holes were completed for the site. With the 
mapping of the rock contours, the pile design depths and socket 
lengths could be predicted more accurately. 
The site investigation revealed some areas with possible 
existence of minor cavities in the limestone and these were 
demarcated. Cavity probing and provision for grouting were 
included in the piling contract, to detect the presence of fi ssures 
or cavities, prior to the installation of bored piles. 
Substantial earthworks for site formation were necessary before 
commencement of the piling work and basement construction. 
The installation of foundation and contiguous bored piles began 
after the successful completion of two instrumented ultimate 
load tests. 
A total of 270 foundation bored piles and 537 secant bored 
piles were installed. The bored piles range from 0.8 m to 2.2 
m in diameter. The larger piles near the MRT station adit, with 
plunge-in steel columns, were designed to facilitate the top-down 
method of basement construction. To socket the foundation 
piles into fresh rock stratum, in order to mobilise adequate skin 
friction and end-bearing, BG-35 and BG-40 boring machines 
were specifi ed in the contract. 
Proper scheduling of construction works was done, with traffi c 
diversions deemed necessary, to ensure there was no disruption 
to the traffi c fl ow along Lower Kent Ridge Road. 
To ensure no adverse effects on the structural integrity of 
the MRT station and tunnels, a number of measures were 
incorporated into the design and construction phase, including 
real-time monitoring within MRT tunnels. In addition to installing 
seven clusters of monitoring instruments, extensive ground 
settlement points were identifi ed and monitored on site by an 
independent specialist contractor during the construction. 
In compliance with LTA’s requirements on railway protection 
during construction, the stress effects due to excavation and 
piling work carried out were assessed. 
Boring machines 
Stress changes
COVER STORY 
Estimated movements. Images by Penta Ocean Construction Co Ltd. 
18 THE SINGAPORE ENGINEER August 2014 
• All movements 
within limits 
• Justifi ed that 
90% of bored 
piles within 
MRT reserves 
need not be 
de-bonded.
COVER STORY 
August 2014 THE SINGAPORE ENGINEER 19 
The results indicated that the stresses induced were within 
the allowable limit of 15 kN/m², as per the LTA specifi cations. 
Real-time monitoring instruments were installed in the north-and 
south-bound tunnels. The MRT tunnels were found to be 
safe and the track alignment was not affected during piling and 
basement construction. 
DESIGN SOLUTIONS 
Special consideration was given to the development of the 
structural systems to meet the robustness criteria for the 
building, in order to prevent disproportionate collapse under 
accidental loads. 
The structural design options were determined by the 
performance requirements of the vital operational facilities of 
the hospital, including the delivery paths of medical equipment, 
the structural stiffness for stringent control of vibration of 
sensitive medical equipment and the need for radiation shielding. 
The steel truss system was the optimum structural system in the 
design of the transfer structure. The design took consideration 
of effi ciency in fabrication and installation of the trusses, the QA/ 
QC procedure and the reduction of the Concrete Usage Index 
(CUI), for sustainable construction. 
The slab at Level 11 was checked for the construction loads of 
the temporary platform and construction equipment. 
The transfer structure allowed a column-free space at Level 11 
under the trusses for high fl exibility in layout confi guration. 
CONSTRUCTION METHODOLOGY 
A difference in levels of 14 m at two sides of the spiral ramp 
and the close proximity of the MRT tunnels posed challenges in 
construction. The top-down construction method was adopted 
in the design, to eliminate extensive strutting or ground anchors. 
This provided better control of ground movement during 
excavation. The design provision with plunge-in steel columns was 
implemented by the piling contractor. The same method was also 
used for basement excavation next to the MRT adit structure. 
Transfer structure. Images by Penta Ocean Construction Co Ltd. 
Design of 11th storey slab Level 11 layout confi guration
COVER STORY 
Top-down construction methodology 
Spiral ramp 
20 THE SINGAPORE ENGINEER August 2014 
Top-down Construction
COVER STORY 
All images by T.Y.Lin International Pte Ltd, 
unless otherwise stated. 
August 2014 THE SINGAPORE ENGINEER 21 
The 2.5 m thick bunker slabs at Level 8 were cast in seven layers, 
using ice, water and cement replacements, for effective control 
of the peak and differential temperatures. Additional protective 
measures were taken, in case of adverse weather during the 
curing process. 
CONCLUSION 
The adoption of an innovative approach and in-depth design 
with appropriate construction methodology, was essential 
to overcoming the site constraints and design challenges. The 
design considerations encompassed structural safety, buildability 
and sustainability. 
An effi cient and cost-effective structural system and team effort 
during the construction stage, as well as a strong safety culture 
shared by all project team members, including the developer, 
contractor and consultants, contributed to the achievement of 
safety and excellence in engineering design and construction. 
Construction work in progress 
Level 8 radiation bunkers. Image by Penta Ocean Construction Co Ltd. Casting sequence and thermal insulation 
PROJECT CREDITS 
Qualifi ed Person 
Er. Ng Swee Tong 
C&S Consultant 
T.Y. Lin International Pte Ltd 
Builder 
Penta-Ocean Construction Co Ltd 
Developer 
National University Hospital (Singapore) Pte Ltd 
Architectural Consultant 
Consultants Incorporated Architects + Planners 
CORRECTION 
With reference to the news article ‘Er. Dr Tan Guan 
receives Lifetime Achievement Award from ACES’, 
that appeared on Page 48 of the June 2014 Issue of 
‘The Singapore Engineer’, T.Y. Lin International Pte Ltd 
wishes to clarify that whilst Er. Dr Tan was the Project 
Director for the project, Er. Ng Swee Tong was the QP 
and Project Manager.

Contenu connexe

Tendances

Muhammad Aamir Javed
Muhammad Aamir JavedMuhammad Aamir Javed
Muhammad Aamir JavedAamir Javed
 
L&t PARKCIRCUS
L&t PARKCIRCUSL&t PARKCIRCUS
L&t PARKCIRCUSRajdip Das
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeTong Seng Chua
 
Ms for concrete repairing
Ms for concrete repairingMs for concrete repairing
Ms for concrete repairingPham Dinh Thac
 
Culvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsCulvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsPath Marketing Inc.
 
vikash kumar NOV 2014 - project - Commissioning
vikash kumar NOV 2014 - project - Commissioningvikash kumar NOV 2014 - project - Commissioning
vikash kumar NOV 2014 - project - Commissioningvikash kumar
 
2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENABenoit Latapie
 
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)Resume and Project History - Jim Herrmann (Rev. 05-11-2016)
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)James Herrmann
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 
OTC Asia 2014 Petronas
OTC Asia 2014 PetronasOTC Asia 2014 Petronas
OTC Asia 2014 PetronasSteven Kennedy
 

Tendances (20)

Muhammad Aamir Javed
Muhammad Aamir JavedMuhammad Aamir Javed
Muhammad Aamir Javed
 
L&t PARKCIRCUS
L&t PARKCIRCUSL&t PARKCIRCUS
L&t PARKCIRCUS
 
Resume CV
Resume CVResume CV
Resume CV
 
chris's CV
chris's CVchris's CV
chris's CV
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, Singapore
 
DETAILED CV - Aug 16 v3
DETAILED CV - Aug 16 v3DETAILED CV - Aug 16 v3
DETAILED CV - Aug 16 v3
 
Ms for concrete repairing
Ms for concrete repairingMs for concrete repairing
Ms for concrete repairing
 
OSAS-CV5
OSAS-CV5OSAS-CV5
OSAS-CV5
 
Ronald-Smith
Ronald-SmithRonald-Smith
Ronald-Smith
 
Ahmd Mahmoud c.v
Ahmd Mahmoud c.vAhmd Mahmoud c.v
Ahmd Mahmoud c.v
 
Culvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsCulvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & Applications
 
ind brochure
ind brochureind brochure
ind brochure
 
khizar hayat cv.
khizar hayat cv.khizar hayat cv.
khizar hayat cv.
 
vikash kumar NOV 2014 - project - Commissioning
vikash kumar NOV 2014 - project - Commissioningvikash kumar NOV 2014 - project - Commissioning
vikash kumar NOV 2014 - project - Commissioning
 
2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA
 
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)Resume and Project History - Jim Herrmann (Rev. 05-11-2016)
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)
 
Jbeil subsea brochure
Jbeil subsea brochureJbeil subsea brochure
Jbeil subsea brochure
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
OTC Asia 2014 Petronas
OTC Asia 2014 PetronasOTC Asia 2014 Petronas
OTC Asia 2014 Petronas
 
CV_mki2015Nov
CV_mki2015NovCV_mki2015Nov
CV_mki2015Nov
 

En vedette

Final case zpmc_group10 by Brian
Final case zpmc_group10 by BrianFinal case zpmc_group10 by Brian
Final case zpmc_group10 by BrianZhiyuan Ma
 
ZPMC Product Range
ZPMC Product RangeZPMC Product Range
ZPMC Product Rangetonytomasouw
 
Final case zpmc_group10
Final case zpmc_group10Final case zpmc_group10
Final case zpmc_group10Zhiyuan Ma
 
Porter's Five Forces
Porter's Five ForcesPorter's Five Forces
Porter's Five ForcesMayur Khatri
 

En vedette (6)

Cargotec in brazil
Cargotec in brazilCargotec in brazil
Cargotec in brazil
 
Final case zpmc_group10 by Brian
Final case zpmc_group10 by BrianFinal case zpmc_group10 by Brian
Final case zpmc_group10 by Brian
 
ZPMC Product Range
ZPMC Product RangeZPMC Product Range
ZPMC Product Range
 
Final case zpmc_group10
Final case zpmc_group10Final case zpmc_group10
Final case zpmc_group10
 
Porter's Five Forces
Porter's Five ForcesPorter's Five Forces
Porter's Five Forces
 
Porter's 5 Force Model
Porter's 5 Force ModelPorter's 5 Force Model
Porter's 5 Force Model
 

Similaire à The Singapore Engineer Aug 2014: National University Hospital

Final Hi Tech Broucher New 12 Page
Final Hi Tech Broucher New 12 PageFinal Hi Tech Broucher New 12 Page
Final Hi Tech Broucher New 12 PageGirish Damle
 
IJSRED-V2I5P8
IJSRED-V2I5P8IJSRED-V2I5P8
IJSRED-V2I5P8IJSRED
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridgesCivil Engineers
 
Unistrut Construction Brochure
Unistrut Construction BrochureUnistrut Construction Brochure
Unistrut Construction BrochureRICHARD GORDON
 
Modern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionModern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionStefan Lammert
 
S nikkhah CV Oil Gas CSG LNG
S nikkhah CV Oil Gas CSG LNGS nikkhah CV Oil Gas CSG LNG
S nikkhah CV Oil Gas CSG LNGsiavashn
 
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET Journal
 
building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)rahul jangid
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Whitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyWhitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyAndrew White
 

Similaire à The Singapore Engineer Aug 2014: National University Hospital (20)

Final Hi Tech Broucher New 12 Page
Final Hi Tech Broucher New 12 PageFinal Hi Tech Broucher New 12 Page
Final Hi Tech Broucher New 12 Page
 
AFF Full New Template CV.Revision F
AFF Full New Template CV.Revision FAFF Full New Template CV.Revision F
AFF Full New Template CV.Revision F
 
IJSRED-V2I5P8
IJSRED-V2I5P8IJSRED-V2I5P8
IJSRED-V2I5P8
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
 
KWKCV16
KWKCV16KWKCV16
KWKCV16
 
Unistrut Construction Brochure
Unistrut Construction BrochureUnistrut Construction Brochure
Unistrut Construction Brochure
 
Modern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionModern fastening systems in tunnel construction
Modern fastening systems in tunnel construction
 
JUNDEE MAR TEJEDO
JUNDEE MAR TEJEDOJUNDEE MAR TEJEDO
JUNDEE MAR TEJEDO
 
StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)
 
StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)
 
StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)
 
S nikkhah CV Oil Gas CSG LNG
S nikkhah CV Oil Gas CSG LNGS nikkhah CV Oil Gas CSG LNG
S nikkhah CV Oil Gas CSG LNG
 
Presentation
PresentationPresentation
Presentation
 
Salakidis Savvas
Salakidis SavvasSalakidis Savvas
Salakidis Savvas
 
OJB Resume 2016
OJB Resume 2016OJB Resume 2016
OJB Resume 2016
 
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
 
building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Whitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyWhitescape Civil Engineering Case Study
Whitescape Civil Engineering Case Study
 

Plus de T.Y. Lin International

APWA Reporter - Cermak-McCormick Place Elevated Green Line Station
APWA Reporter - Cermak-McCormick Place Elevated Green Line StationAPWA Reporter - Cermak-McCormick Place Elevated Green Line Station
APWA Reporter - Cermak-McCormick Place Elevated Green Line StationT.Y. Lin International
 
USTDA 2015 Annual Report - El Dorado International Airport in Colombia, South...
USTDA 2015 Annual Report - El Dorado International Airport in Colombia, South...USTDA 2015 Annual Report - El Dorado International Airport in Colombia, South...
USTDA 2015 Annual Report - El Dorado International Airport in Colombia, South...T.Y. Lin International
 
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, ChinaSoutheast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, ChinaT.Y. Lin International
 
Southeast Asia Construction - NTU Learning Hub
Southeast Asia Construction - NTU Learning HubSoutheast Asia Construction - NTU Learning Hub
Southeast Asia Construction - NTU Learning HubT.Y. Lin International
 
The Singapore Engineer - NTU Sports Hall Cover Story
The Singapore Engineer - NTU Sports Hall Cover StoryThe Singapore Engineer - NTU Sports Hall Cover Story
The Singapore Engineer - NTU Sports Hall Cover StoryT.Y. Lin International
 
Building Review Journal - NTU Learning Hub, Sports Hall, Woodlands Integrated...
Building Review Journal - NTU Learning Hub, Sports Hall, Woodlands Integrated...Building Review Journal - NTU Learning Hub, Sports Hall, Woodlands Integrated...
Building Review Journal - NTU Learning Hub, Sports Hall, Woodlands Integrated...T.Y. Lin International
 
Southeast Asia Building July/August Issue
Southeast Asia Building July/August IssueSoutheast Asia Building July/August Issue
Southeast Asia Building July/August IssueT.Y. Lin International
 
T.Y. Lin International wins $1.9 million state contract
T.Y. Lin International wins $1.9 million state contractT.Y. Lin International wins $1.9 million state contract
T.Y. Lin International wins $1.9 million state contractT.Y. Lin International
 
The Singapore Engineer - Nanyang Technological University Learning Hub
The Singapore Engineer - Nanyang Technological University Learning HubThe Singapore Engineer - Nanyang Technological University Learning Hub
The Singapore Engineer - Nanyang Technological University Learning HubT.Y. Lin International
 
Southeast Asia Building March/April Issue
Southeast Asia Building March/April IssueSoutheast Asia Building March/April Issue
Southeast Asia Building March/April IssueT.Y. Lin International
 
Southeast Asia Construction Magazine Jan-Feb 2015 ft. Victoria Theatre
Southeast Asia Construction Magazine Jan-Feb 2015 ft. Victoria TheatreSoutheast Asia Construction Magazine Jan-Feb 2015 ft. Victoria Theatre
Southeast Asia Construction Magazine Jan-Feb 2015 ft. Victoria TheatreT.Y. Lin International
 
The Zweig Letter 2015 - Alvaro Piedrahita
The Zweig Letter 2015 - Alvaro PiedrahitaThe Zweig Letter 2015 - Alvaro Piedrahita
The Zweig Letter 2015 - Alvaro PiedrahitaT.Y. Lin International
 
The Singapore Engineer - Hledean Flyover in Myanmar (December 2014)
The Singapore Engineer - Hledean Flyover in Myanmar (December 2014)The Singapore Engineer - Hledean Flyover in Myanmar (December 2014)
The Singapore Engineer - Hledean Flyover in Myanmar (December 2014)T.Y. Lin International
 
Singapore Business Review - Top 15 Engineering Firms
Singapore Business Review - Top 15 Engineering FirmsSingapore Business Review - Top 15 Engineering Firms
Singapore Business Review - Top 15 Engineering FirmsT.Y. Lin International
 
Design and Construction of North Halawa Valley Vidaduct
Design and Construction of North Halawa Valley VidaductDesign and Construction of North Halawa Valley Vidaduct
Design and Construction of North Halawa Valley VidaductT.Y. Lin International
 

Plus de T.Y. Lin International (20)

APWA Reporter - Cermak-McCormick Place Elevated Green Line Station
APWA Reporter - Cermak-McCormick Place Elevated Green Line StationAPWA Reporter - Cermak-McCormick Place Elevated Green Line Station
APWA Reporter - Cermak-McCormick Place Elevated Green Line Station
 
USTDA 2015 Annual Report - El Dorado International Airport in Colombia, South...
USTDA 2015 Annual Report - El Dorado International Airport in Colombia, South...USTDA 2015 Annual Report - El Dorado International Airport in Colombia, South...
USTDA 2015 Annual Report - El Dorado International Airport in Colombia, South...
 
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, ChinaSoutheast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
 
Southeast Asia Construction - NTU Learning Hub
Southeast Asia Construction - NTU Learning HubSoutheast Asia Construction - NTU Learning Hub
Southeast Asia Construction - NTU Learning Hub
 
The Singapore Engineer - NTU Sports Hall Cover Story
The Singapore Engineer - NTU Sports Hall Cover StoryThe Singapore Engineer - NTU Sports Hall Cover Story
The Singapore Engineer - NTU Sports Hall Cover Story
 
Obras - The Learning Hub in Singapore
Obras - The Learning Hub in SingaporeObras - The Learning Hub in Singapore
Obras - The Learning Hub in Singapore
 
Building Review Journal - NTU Learning Hub, Sports Hall, Woodlands Integrated...
Building Review Journal - NTU Learning Hub, Sports Hall, Woodlands Integrated...Building Review Journal - NTU Learning Hub, Sports Hall, Woodlands Integrated...
Building Review Journal - NTU Learning Hub, Sports Hall, Woodlands Integrated...
 
Southeast Asia Building July/August Issue
Southeast Asia Building July/August IssueSoutheast Asia Building July/August Issue
Southeast Asia Building July/August Issue
 
T.Y. Lin International wins $1.9 million state contract
T.Y. Lin International wins $1.9 million state contractT.Y. Lin International wins $1.9 million state contract
T.Y. Lin International wins $1.9 million state contract
 
The Singapore Engineer - Nanyang Technological University Learning Hub
The Singapore Engineer - Nanyang Technological University Learning HubThe Singapore Engineer - Nanyang Technological University Learning Hub
The Singapore Engineer - Nanyang Technological University Learning Hub
 
Southeast Asia Building March/April Issue
Southeast Asia Building March/April IssueSoutheast Asia Building March/April Issue
Southeast Asia Building March/April Issue
 
Southeast Asia Construction Magazine Jan-Feb 2015 ft. Victoria Theatre
Southeast Asia Construction Magazine Jan-Feb 2015 ft. Victoria TheatreSoutheast Asia Construction Magazine Jan-Feb 2015 ft. Victoria Theatre
Southeast Asia Construction Magazine Jan-Feb 2015 ft. Victoria Theatre
 
The Zweig Letter 2015 - Alvaro Piedrahita
The Zweig Letter 2015 - Alvaro PiedrahitaThe Zweig Letter 2015 - Alvaro Piedrahita
The Zweig Letter 2015 - Alvaro Piedrahita
 
The Singapore Engineer - Hledean Flyover in Myanmar (December 2014)
The Singapore Engineer - Hledean Flyover in Myanmar (December 2014)The Singapore Engineer - Hledean Flyover in Myanmar (December 2014)
The Singapore Engineer - Hledean Flyover in Myanmar (December 2014)
 
Singapore Business Review - Top 15 Engineering Firms
Singapore Business Review - Top 15 Engineering FirmsSingapore Business Review - Top 15 Engineering Firms
Singapore Business Review - Top 15 Engineering Firms
 
RBJ Daily - T.Y. Lin International
RBJ Daily - T.Y. Lin InternationalRBJ Daily - T.Y. Lin International
RBJ Daily - T.Y. Lin International
 
Obras - The Interlace in Singapore
Obras - The Interlace in Singapore Obras - The Interlace in Singapore
Obras - The Interlace in Singapore
 
The Jiayue Bridge in Chongqing, China
The Jiayue Bridge in Chongqing, ChinaThe Jiayue Bridge in Chongqing, China
The Jiayue Bridge in Chongqing, China
 
Design and Construction of North Halawa Valley Vidaduct
Design and Construction of North Halawa Valley VidaductDesign and Construction of North Halawa Valley Vidaduct
Design and Construction of North Halawa Valley Vidaduct
 
Puente en la represa Hoover
Puente en la represa Hoover Puente en la represa Hoover
Puente en la represa Hoover
 

Dernier

Call Girls in Adil Nagar 7001305949 Free Delivery at Your Door Model
Call Girls in Adil Nagar 7001305949 Free Delivery at Your Door ModelCall Girls in Adil Nagar 7001305949 Free Delivery at Your Door Model
Call Girls in Adil Nagar 7001305949 Free Delivery at Your Door ModelCall Girls Lucknow
 
Call Girls Hyderabad Krisha 9907093804 Independent Escort Service Hyderabad
Call Girls Hyderabad Krisha 9907093804 Independent Escort Service HyderabadCall Girls Hyderabad Krisha 9907093804 Independent Escort Service Hyderabad
Call Girls Hyderabad Krisha 9907093804 Independent Escort Service Hyderabaddelhimodelshub1
 
Call Girls Hyderabad Kirti 9907093804 Independent Escort Service Hyderabad
Call Girls Hyderabad Kirti 9907093804 Independent Escort Service HyderabadCall Girls Hyderabad Kirti 9907093804 Independent Escort Service Hyderabad
Call Girls Hyderabad Kirti 9907093804 Independent Escort Service Hyderabaddelhimodelshub1
 
Basics of Anatomy- Language of Anatomy.pptx
Basics of Anatomy- Language of Anatomy.pptxBasics of Anatomy- Language of Anatomy.pptx
Basics of Anatomy- Language of Anatomy.pptxAyushGupta813444
 
Hi,Fi Call Girl In Marathahalli - 7001305949 with real photos and phone numbers
Hi,Fi Call Girl In Marathahalli - 7001305949 with real photos and phone numbersHi,Fi Call Girl In Marathahalli - 7001305949 with real photos and phone numbers
Hi,Fi Call Girl In Marathahalli - 7001305949 with real photos and phone numbersnarwatsonia7
 
Single Assessment Framework - What We Know So Far
Single Assessment Framework - What We Know So FarSingle Assessment Framework - What We Know So Far
Single Assessment Framework - What We Know So FarCareLineLive
 
Russian Escorts Delhi | 9711199171 | all area service available
Russian Escorts Delhi | 9711199171 | all area service availableRussian Escorts Delhi | 9711199171 | all area service available
Russian Escorts Delhi | 9711199171 | all area service availablesandeepkumar69420
 
Gurgaon Sector 90 Call Girls ( 9873940964 ) Book Hot And Sexy Girls In A Few ...
Gurgaon Sector 90 Call Girls ( 9873940964 ) Book Hot And Sexy Girls In A Few ...Gurgaon Sector 90 Call Girls ( 9873940964 ) Book Hot And Sexy Girls In A Few ...
Gurgaon Sector 90 Call Girls ( 9873940964 ) Book Hot And Sexy Girls In A Few ...ggsonu500
 
Russian Call Girls Hyderabad Saloni 9907093804 Independent Escort Service Hyd...
Russian Call Girls Hyderabad Saloni 9907093804 Independent Escort Service Hyd...Russian Call Girls Hyderabad Saloni 9907093804 Independent Escort Service Hyd...
Russian Call Girls Hyderabad Saloni 9907093804 Independent Escort Service Hyd...delhimodelshub1
 
College Call Girls Mumbai Alia 9910780858 Independent Escort Service Mumbai
College Call Girls Mumbai Alia 9910780858 Independent Escort Service MumbaiCollege Call Girls Mumbai Alia 9910780858 Independent Escort Service Mumbai
College Call Girls Mumbai Alia 9910780858 Independent Escort Service Mumbaisonalikaur4
 
Call Girls Service Bommasandra - Call 7001305949 Rs-3500 with A/C Room Cash o...
Call Girls Service Bommasandra - Call 7001305949 Rs-3500 with A/C Room Cash o...Call Girls Service Bommasandra - Call 7001305949 Rs-3500 with A/C Room Cash o...
Call Girls Service Bommasandra - Call 7001305949 Rs-3500 with A/C Room Cash o...narwatsonia7
 
Russian Call Girls in Chandigarh Ojaswi ❤️🍑 9907093804 👄🫦 Independent Escort ...
Russian Call Girls in Chandigarh Ojaswi ❤️🍑 9907093804 👄🫦 Independent Escort ...Russian Call Girls in Chandigarh Ojaswi ❤️🍑 9907093804 👄🫦 Independent Escort ...
Russian Call Girls in Chandigarh Ojaswi ❤️🍑 9907093804 👄🫦 Independent Escort ...High Profile Call Girls Chandigarh Aarushi
 
Book Call Girls in Noida Pick Up Drop With Cash Payment 9711199171 Call Girls
Book Call Girls in Noida Pick Up Drop With Cash Payment 9711199171 Call GirlsBook Call Girls in Noida Pick Up Drop With Cash Payment 9711199171 Call Girls
Book Call Girls in Noida Pick Up Drop With Cash Payment 9711199171 Call GirlsCall Girls Noida
 
Kukatpally Call Girls Services 9907093804 High Class Babes Here Call Now
Kukatpally Call Girls Services 9907093804 High Class Babes Here Call NowKukatpally Call Girls Services 9907093804 High Class Babes Here Call Now
Kukatpally Call Girls Services 9907093804 High Class Babes Here Call NowHyderabad Call Girls Services
 
Hi,Fi Call Girl In Whitefield - [ Cash on Delivery ] Contact 7001305949 Escor...
Hi,Fi Call Girl In Whitefield - [ Cash on Delivery ] Contact 7001305949 Escor...Hi,Fi Call Girl In Whitefield - [ Cash on Delivery ] Contact 7001305949 Escor...
Hi,Fi Call Girl In Whitefield - [ Cash on Delivery ] Contact 7001305949 Escor...narwatsonia7
 

Dernier (20)

Call Girls in Adil Nagar 7001305949 Free Delivery at Your Door Model
Call Girls in Adil Nagar 7001305949 Free Delivery at Your Door ModelCall Girls in Adil Nagar 7001305949 Free Delivery at Your Door Model
Call Girls in Adil Nagar 7001305949 Free Delivery at Your Door Model
 
Call Girls Hyderabad Krisha 9907093804 Independent Escort Service Hyderabad
Call Girls Hyderabad Krisha 9907093804 Independent Escort Service HyderabadCall Girls Hyderabad Krisha 9907093804 Independent Escort Service Hyderabad
Call Girls Hyderabad Krisha 9907093804 Independent Escort Service Hyderabad
 
VIP Call Girls Lucknow Isha 🔝 9719455033 🔝 🎶 Independent Escort Service Lucknow
VIP Call Girls Lucknow Isha 🔝 9719455033 🔝 🎶 Independent Escort Service LucknowVIP Call Girls Lucknow Isha 🔝 9719455033 🔝 🎶 Independent Escort Service Lucknow
VIP Call Girls Lucknow Isha 🔝 9719455033 🔝 🎶 Independent Escort Service Lucknow
 
Call Girls Hyderabad Kirti 9907093804 Independent Escort Service Hyderabad
Call Girls Hyderabad Kirti 9907093804 Independent Escort Service HyderabadCall Girls Hyderabad Kirti 9907093804 Independent Escort Service Hyderabad
Call Girls Hyderabad Kirti 9907093804 Independent Escort Service Hyderabad
 
College Call Girls Dehradun Kavya 🔝 7001305949 🔝 📍 Independent Escort Service...
College Call Girls Dehradun Kavya 🔝 7001305949 🔝 📍 Independent Escort Service...College Call Girls Dehradun Kavya 🔝 7001305949 🔝 📍 Independent Escort Service...
College Call Girls Dehradun Kavya 🔝 7001305949 🔝 📍 Independent Escort Service...
 
Basics of Anatomy- Language of Anatomy.pptx
Basics of Anatomy- Language of Anatomy.pptxBasics of Anatomy- Language of Anatomy.pptx
Basics of Anatomy- Language of Anatomy.pptx
 
Hi,Fi Call Girl In Marathahalli - 7001305949 with real photos and phone numbers
Hi,Fi Call Girl In Marathahalli - 7001305949 with real photos and phone numbersHi,Fi Call Girl In Marathahalli - 7001305949 with real photos and phone numbers
Hi,Fi Call Girl In Marathahalli - 7001305949 with real photos and phone numbers
 
Single Assessment Framework - What We Know So Far
Single Assessment Framework - What We Know So FarSingle Assessment Framework - What We Know So Far
Single Assessment Framework - What We Know So Far
 
Russian Escorts Delhi | 9711199171 | all area service available
Russian Escorts Delhi | 9711199171 | all area service availableRussian Escorts Delhi | 9711199171 | all area service available
Russian Escorts Delhi | 9711199171 | all area service available
 
Gurgaon Sector 90 Call Girls ( 9873940964 ) Book Hot And Sexy Girls In A Few ...
Gurgaon Sector 90 Call Girls ( 9873940964 ) Book Hot And Sexy Girls In A Few ...Gurgaon Sector 90 Call Girls ( 9873940964 ) Book Hot And Sexy Girls In A Few ...
Gurgaon Sector 90 Call Girls ( 9873940964 ) Book Hot And Sexy Girls In A Few ...
 
Russian Call Girls Hyderabad Saloni 9907093804 Independent Escort Service Hyd...
Russian Call Girls Hyderabad Saloni 9907093804 Independent Escort Service Hyd...Russian Call Girls Hyderabad Saloni 9907093804 Independent Escort Service Hyd...
Russian Call Girls Hyderabad Saloni 9907093804 Independent Escort Service Hyd...
 
College Call Girls Mumbai Alia 9910780858 Independent Escort Service Mumbai
College Call Girls Mumbai Alia 9910780858 Independent Escort Service MumbaiCollege Call Girls Mumbai Alia 9910780858 Independent Escort Service Mumbai
College Call Girls Mumbai Alia 9910780858 Independent Escort Service Mumbai
 
Call Girls Service Bommasandra - Call 7001305949 Rs-3500 with A/C Room Cash o...
Call Girls Service Bommasandra - Call 7001305949 Rs-3500 with A/C Room Cash o...Call Girls Service Bommasandra - Call 7001305949 Rs-3500 with A/C Room Cash o...
Call Girls Service Bommasandra - Call 7001305949 Rs-3500 with A/C Room Cash o...
 
Call Girls Guwahati Aaradhya 👉 7001305949👈 🎶 Independent Escort Service Guwahati
Call Girls Guwahati Aaradhya 👉 7001305949👈 🎶 Independent Escort Service GuwahatiCall Girls Guwahati Aaradhya 👉 7001305949👈 🎶 Independent Escort Service Guwahati
Call Girls Guwahati Aaradhya 👉 7001305949👈 🎶 Independent Escort Service Guwahati
 
Russian Call Girls Lucknow Khushi 🔝 7001305949 🔝 🎶 Independent Escort Service...
Russian Call Girls Lucknow Khushi 🔝 7001305949 🔝 🎶 Independent Escort Service...Russian Call Girls Lucknow Khushi 🔝 7001305949 🔝 🎶 Independent Escort Service...
Russian Call Girls Lucknow Khushi 🔝 7001305949 🔝 🎶 Independent Escort Service...
 
Russian Call Girls South Delhi 9711199171 discount on your booking
Russian Call Girls South Delhi 9711199171 discount on your bookingRussian Call Girls South Delhi 9711199171 discount on your booking
Russian Call Girls South Delhi 9711199171 discount on your booking
 
Russian Call Girls in Chandigarh Ojaswi ❤️🍑 9907093804 👄🫦 Independent Escort ...
Russian Call Girls in Chandigarh Ojaswi ❤️🍑 9907093804 👄🫦 Independent Escort ...Russian Call Girls in Chandigarh Ojaswi ❤️🍑 9907093804 👄🫦 Independent Escort ...
Russian Call Girls in Chandigarh Ojaswi ❤️🍑 9907093804 👄🫦 Independent Escort ...
 
Book Call Girls in Noida Pick Up Drop With Cash Payment 9711199171 Call Girls
Book Call Girls in Noida Pick Up Drop With Cash Payment 9711199171 Call GirlsBook Call Girls in Noida Pick Up Drop With Cash Payment 9711199171 Call Girls
Book Call Girls in Noida Pick Up Drop With Cash Payment 9711199171 Call Girls
 
Kukatpally Call Girls Services 9907093804 High Class Babes Here Call Now
Kukatpally Call Girls Services 9907093804 High Class Babes Here Call NowKukatpally Call Girls Services 9907093804 High Class Babes Here Call Now
Kukatpally Call Girls Services 9907093804 High Class Babes Here Call Now
 
Hi,Fi Call Girl In Whitefield - [ Cash on Delivery ] Contact 7001305949 Escor...
Hi,Fi Call Girl In Whitefield - [ Cash on Delivery ] Contact 7001305949 Escor...Hi,Fi Call Girl In Whitefield - [ Cash on Delivery ] Contact 7001305949 Escor...
Hi,Fi Call Girl In Whitefield - [ Cash on Delivery ] Contact 7001305949 Escor...
 

The Singapore Engineer Aug 2014: National University Hospital

  • 1. The Magazine Of The Institution Of Engineers, Singapore August 2014 MCI (P) 157/01/2014 www.ies.org.sg THE SINGAPORE ENGINEER COVER STORY: CIVIL & STRUCTURAL ENGINEERING NUH Medical Centre FEATURES: Construction Technology • Health & Safety Engineering • Project Application
  • 2. COVER STORY NUH Medical Centre The project won a BCA Design and Engineering Safety Excellence Award (Merit) under the Institutional & Industrial Category, at BCA AWARDS 2014. By adopting innovative engineering solutions to overcome the site and design challenges, the structural works were completed and delivered on time, despite tight schedules, to enable commencement of other trades. NUH Medical Centre is the latest, and one of three buildings serving hospital patients within the NUH campus. It houses 190 consultation rooms, more than 200 treatment and procedure rooms, 10 day surgery operating theatres, as well as dedicated space for teaching and clinical trials. It is also home to the National University Cancer Institute, Singapore (Yong Siew Yoon Wing) which provides one-stop, comprehensive care for both adult and pediatric oncology patients. The NUH Medical Centre is fully integrated with infrastructure for support services, such as clinical laboratories; 14 THE SINGAPORE ENGINEER August 2014 facilities for dietetics services and imaging; pharmacy; and a health resource centre, designed to provide patients with holistic care. The 19-storey NUH Medical Centre was completed in 2013 and started serving patients in July the same year. Generating a total GFA of 72,000 m2, the NUH Medical Centre was a fast-track project completed in 28 months. The consultant team was required to carry out thorough project planning, design coordination and review of construction methodology, to ensure engineering safety during project implementation as well as timely completion. NUH Medical Centre. Image by Penta Ocean Construction Co Ltd.
  • 3. COVER STORY August 2014 THE SINGAPORE ENGINEER 15 The main contract commenced on 16 December 2010. T.O.P. was obtained on 26 April 2013. As Structural Designer, T.Y. Lin International Pte Ltd (TYLI) collaborated with the NUH Medical Centre’s consultant team, drawing on TYLI Singapore’s expertise in engineering design for healthcare structures and complex buildings, to develop the optimum structural solution. The process encompassed the consideration of both design and construction methodologies for the structure. Er. Ng Swee Tong oversaw the project delivery as the Project Manager and Qualifi ed Person. PROJECT HIGHLIGHTS A steel truss system was selected as the optimum structural system for the facility. This incorporated six sets of double steel transfer trusses located in between Levels 12 and 13. The transfer truss system is a key feature of this project, as this concept allowed the expansion of the Gross Floor Area (GFA) to 72,000 m², by supporting eight additional fl oors over the MRT station box. There are six elevated radiation bunkers located on Level 8. Each has a 2.5 m thick concrete enclosure. The stringent requirement for radiation shielding demanded effective temperature control of the large volume concrete casting, so as to eliminate micro-cracking of the bunker structures. The adequacy of the formwork system to support the massive wet concrete during construction of these bunkers was a key design consideration in locating the bunkers on Level 8, for the operational effi ciency of the cancer centre. SITE CHALLENGES The NUH Medical Centre is located directly above Kent Ridge MRT Station, within the fi rst reserve of the railway protection zone and adjacent to the NUH Kent Ridge Wing in operation. This presented a number of challenges that the team had to overcome, for timely completion of the project. • The undulating site terrain, with the existing ground levels varying from 127.5 m to 141.95 m demanded careful design consideration and planning. • Mitigating the potential traffi c impacts throughout the construction phase was crucial. The road network in the vicinity of the hospital experiences heavy traffi c movement especially during peak hours. Development commencement and completion Figure 3: Elevated radiation bunkers LINAC bunkers formwork The site plan
  • 4. COVER STORY • Rigorous control processes were considered at the design stage and implemented stringently during construction, to safeguard the structural integrity of Kent Ridge MRT Station and the tunnels. DESIGN CHALLENGES The Kent Ridge Station structure was designed with provision for a future building, with 24 column stumps on top of the central zone of the station, that would house seven levels of medical units. A difference in levels of 14 m at two sides of the spiral ramp and the close proximity of the MRT tunnels posed challenges in construction. MRT station structure 16 THE SINGAPORE ENGINEER August 2014 The primary considerations in the selection of the structural system for the healthcare facility included: • Structural stiffness to meet the operational requirements of various types of sensitive medical equipment. • Building robustness to resist accidental loads. • Ease of construction. Special consideration was given to achieving high buildability scores, despite the above stringent requirements. CONSTRUCTION CHALLENGES Heavy transfer structures are typically long-span and massive, and they pose challenges for quality control during fabrication and installation. As the site was in close proximity to the hospital wards, mitigation of noise and vibration generated during construction were essential, to avoid any inconvenience or disruption to the hospital operations. SITE SOLUTIONS In anticipating various weathering grades of undulating rock formation (from completely weathered to highly weathered sedimentary rocks), extensive soil investigation was conducted to map out the contours of rocks with SPT values greater than 100, for the entire site. Structural system. Images by Penta Ocean Construction Co Ltd.
  • 5. COVER STORY August 2014 THE SINGAPORE ENGINEER 17 A total of 14 bore holes were completed for the site. With the mapping of the rock contours, the pile design depths and socket lengths could be predicted more accurately. The site investigation revealed some areas with possible existence of minor cavities in the limestone and these were demarcated. Cavity probing and provision for grouting were included in the piling contract, to detect the presence of fi ssures or cavities, prior to the installation of bored piles. Substantial earthworks for site formation were necessary before commencement of the piling work and basement construction. The installation of foundation and contiguous bored piles began after the successful completion of two instrumented ultimate load tests. A total of 270 foundation bored piles and 537 secant bored piles were installed. The bored piles range from 0.8 m to 2.2 m in diameter. The larger piles near the MRT station adit, with plunge-in steel columns, were designed to facilitate the top-down method of basement construction. To socket the foundation piles into fresh rock stratum, in order to mobilise adequate skin friction and end-bearing, BG-35 and BG-40 boring machines were specifi ed in the contract. Proper scheduling of construction works was done, with traffi c diversions deemed necessary, to ensure there was no disruption to the traffi c fl ow along Lower Kent Ridge Road. To ensure no adverse effects on the structural integrity of the MRT station and tunnels, a number of measures were incorporated into the design and construction phase, including real-time monitoring within MRT tunnels. In addition to installing seven clusters of monitoring instruments, extensive ground settlement points were identifi ed and monitored on site by an independent specialist contractor during the construction. In compliance with LTA’s requirements on railway protection during construction, the stress effects due to excavation and piling work carried out were assessed. Boring machines Stress changes
  • 6. COVER STORY Estimated movements. Images by Penta Ocean Construction Co Ltd. 18 THE SINGAPORE ENGINEER August 2014 • All movements within limits • Justifi ed that 90% of bored piles within MRT reserves need not be de-bonded.
  • 7. COVER STORY August 2014 THE SINGAPORE ENGINEER 19 The results indicated that the stresses induced were within the allowable limit of 15 kN/m², as per the LTA specifi cations. Real-time monitoring instruments were installed in the north-and south-bound tunnels. The MRT tunnels were found to be safe and the track alignment was not affected during piling and basement construction. DESIGN SOLUTIONS Special consideration was given to the development of the structural systems to meet the robustness criteria for the building, in order to prevent disproportionate collapse under accidental loads. The structural design options were determined by the performance requirements of the vital operational facilities of the hospital, including the delivery paths of medical equipment, the structural stiffness for stringent control of vibration of sensitive medical equipment and the need for radiation shielding. The steel truss system was the optimum structural system in the design of the transfer structure. The design took consideration of effi ciency in fabrication and installation of the trusses, the QA/ QC procedure and the reduction of the Concrete Usage Index (CUI), for sustainable construction. The slab at Level 11 was checked for the construction loads of the temporary platform and construction equipment. The transfer structure allowed a column-free space at Level 11 under the trusses for high fl exibility in layout confi guration. CONSTRUCTION METHODOLOGY A difference in levels of 14 m at two sides of the spiral ramp and the close proximity of the MRT tunnels posed challenges in construction. The top-down construction method was adopted in the design, to eliminate extensive strutting or ground anchors. This provided better control of ground movement during excavation. The design provision with plunge-in steel columns was implemented by the piling contractor. The same method was also used for basement excavation next to the MRT adit structure. Transfer structure. Images by Penta Ocean Construction Co Ltd. Design of 11th storey slab Level 11 layout confi guration
  • 8. COVER STORY Top-down construction methodology Spiral ramp 20 THE SINGAPORE ENGINEER August 2014 Top-down Construction
  • 9. COVER STORY All images by T.Y.Lin International Pte Ltd, unless otherwise stated. August 2014 THE SINGAPORE ENGINEER 21 The 2.5 m thick bunker slabs at Level 8 were cast in seven layers, using ice, water and cement replacements, for effective control of the peak and differential temperatures. Additional protective measures were taken, in case of adverse weather during the curing process. CONCLUSION The adoption of an innovative approach and in-depth design with appropriate construction methodology, was essential to overcoming the site constraints and design challenges. The design considerations encompassed structural safety, buildability and sustainability. An effi cient and cost-effective structural system and team effort during the construction stage, as well as a strong safety culture shared by all project team members, including the developer, contractor and consultants, contributed to the achievement of safety and excellence in engineering design and construction. Construction work in progress Level 8 radiation bunkers. Image by Penta Ocean Construction Co Ltd. Casting sequence and thermal insulation PROJECT CREDITS Qualifi ed Person Er. Ng Swee Tong C&S Consultant T.Y. Lin International Pte Ltd Builder Penta-Ocean Construction Co Ltd Developer National University Hospital (Singapore) Pte Ltd Architectural Consultant Consultants Incorporated Architects + Planners CORRECTION With reference to the news article ‘Er. Dr Tan Guan receives Lifetime Achievement Award from ACES’, that appeared on Page 48 of the June 2014 Issue of ‘The Singapore Engineer’, T.Y. Lin International Pte Ltd wishes to clarify that whilst Er. Dr Tan was the Project Director for the project, Er. Ng Swee Tong was the QP and Project Manager.