SlideShare une entreprise Scribd logo
1  sur  23
MS Project 2010 Training -Vinit Kumar Singh
Welcome, we have assembled to learn to use MS Project 2010 from effort estimations to planning. Welcome and Introduction
Templates would provide examples for almost all kind of plans, so its good to go through those first. Templates
You can import tasks from Excel and Word. You can also simply copy the list and paste in MPP. You need to map the fields between excel and MPP to import the tasks. You can similarly export to pdf, excel etc. Import & Export
Date would automatically start from today for Project plan, which can be changed as needed. You can change things using proect>project information tool. Start date should only be provided, let MPP decide the end date. Defining project information
Either new calendar can be made or existing can be changed using Project>Change Working time. Either holidays can be accommodated using Exceptions, or overtime can be added using Work weeks tab Defining project calendar
Manually and auto scheduled task With manual task, we can put any text instead of duration Tasks can be organized using Summary tasks. We can also have recurring tasks, if need be. A non-budgeted task can be made inactive Tasks, Inactive tasks & Summary tasks
Milestone represents a work accomplished like customer acceptance etc., milestone do not have any duration. Milestone
Either new calendar can be made or existing can be changed using Project>Change Working time. Either holidays can be accommodated using Exceptions, or overtime can be added using Work weeks tab Summary tasks
Each task can be associated with a WBS (work breakdown structure) code. We can define our own WBS codes. Highest WBS code should be added as project code in the SEPITS for tracking. Summary tasks can be shown and hidden from Gant chart tools>Format>Summary tasks checkbox WBS Codes, Showide summary
Tasks can be linked to have dependency between them Link tasks
All resources can be seen at View>Resource sheet Resources work availability should be set in maximum unit column e.g. 70% of leads. Also cost of resources can be put here. Resources could be work, cost or material. Resources normally gets added automatically but its not a good way. If you want new resources not to be added to the resource pool automatically, open, file>options>advanced and deselect add new resources and tasks check box Resources
Duration = Work units E.g. if resource works for 50% units then task of 40 hrs is calculated to 80 hrs by MPP     Thus, 80 hours = 40 hours 50% Work = Duration X Units E.g. If we enter task duration for 5 days at 40% resource usage, MPP would give output of 16 hours  	Thus, 2 days = 5 days X 40% Units = work duration E.g. MPP calculates units if work is provided 40 hrs and duration 160hrs.    Thus,  0.25 = 40 hours 160 hours Duration, work and units
If hours assigned are higher than the maximum available time for a resource, over-allocation occurs. Resource over-allocations can be analyzed using resource usage and resource sheet. In resource usage view, all over allocated resources can be filtered. It can be fixed using task inspector, team planner etc. Resource over-allocations
Whenever resource assignments are changed, MPP will trigger to select one of the three options. We need to click the correct option, as per our requirement there. Resource assignments modifications
Using team planner, one can assign tasks to users using drag and drop. This can also be used to fix over-allocations of resources. Team planner
Timeline can be viewed at View>timeline. We can add milestones on timeline and then copy that on email for providing visual treat to client. Timeline
One can create multiple project plans and then to analyze across the projects, one can create master plan and then add all projects plan as sub projects to that. Master & Sub projects
Resources can be leveled, however it can dangerously change the whole if whole project leveling is requested. Leveling delays and splits tasks to remove over-allocations.  For that leveling should be done small portion of plan. Leveling resources
Plan can be baselined from Project>Set baseline. There could be 11 baselines for a plan. Scheduled is current plan, that may be same or changed per the progress going on. Also actual can be used for inputting actual values, and then when required variance reports can be generated. Baselined, scheduled and actual
Project > Project information >statistics View > tables > variance etc Project > reports > overview > summary Using other text based and visual reports Project Status & Reports
http://office.microsoft.com/en-us/project-help/ http://www.microsoft.com/project/en/us/default.aspx http://www.profsr.com/msproject/msproj01.htm http://blogs.msdn.com/b/project/ More information
Thank You!

Contenu connexe

Tendances

MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
Khem Singh
 

Tendances (20)

MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 
MS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouMS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for You
 
MS Project
MS ProjectMS Project
MS Project
 
Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training ppt
 
Uses of Project Status field
Uses of  Project Status field Uses of  Project Status field
Uses of Project Status field
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
MS Project
MS ProjectMS Project
MS Project
 
Ms project 2010 tutorial 1
Ms project 2010 tutorial   1Ms project 2010 tutorial   1
Ms project 2010 tutorial 1
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
 
Primavara
PrimavaraPrimavara
Primavara
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
PM Project-Charter.pptx
PM Project-Charter.pptxPM Project-Charter.pptx
PM Project-Charter.pptx
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project scheduling
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 

Similaire à MS Project 2010 Training

Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
Jason Koo
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
성철 박
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
carolinef5
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
donaldp2
 

Similaire à MS Project 2010 Training (20)

Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handout
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must know
 
Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007
 
Project Management Quick Reference Guide
Project Management Quick Reference GuideProject Management Quick Reference Guide
Project Management Quick Reference Guide
 
Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007
 
How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?
 
Scrum With Ms Project
Scrum With Ms ProjectScrum With Ms Project
Scrum With Ms Project
 
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
Schedule management
Schedule managementSchedule management
Schedule management
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and Traps
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
Microsoft Project Foundations Course.pptx
Microsoft Project Foundations Course.pptxMicrosoft Project Foundations Course.pptx
Microsoft Project Foundations Course.pptx
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 

Dernier

Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
vineshkumarsajnani12
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 

Dernier (20)

Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
 
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTSDurg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableBerhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 

MS Project 2010 Training

  • 1. MS Project 2010 Training -Vinit Kumar Singh
  • 2. Welcome, we have assembled to learn to use MS Project 2010 from effort estimations to planning. Welcome and Introduction
  • 3. Templates would provide examples for almost all kind of plans, so its good to go through those first. Templates
  • 4. You can import tasks from Excel and Word. You can also simply copy the list and paste in MPP. You need to map the fields between excel and MPP to import the tasks. You can similarly export to pdf, excel etc. Import & Export
  • 5. Date would automatically start from today for Project plan, which can be changed as needed. You can change things using proect>project information tool. Start date should only be provided, let MPP decide the end date. Defining project information
  • 6. Either new calendar can be made or existing can be changed using Project>Change Working time. Either holidays can be accommodated using Exceptions, or overtime can be added using Work weeks tab Defining project calendar
  • 7. Manually and auto scheduled task With manual task, we can put any text instead of duration Tasks can be organized using Summary tasks. We can also have recurring tasks, if need be. A non-budgeted task can be made inactive Tasks, Inactive tasks & Summary tasks
  • 8. Milestone represents a work accomplished like customer acceptance etc., milestone do not have any duration. Milestone
  • 9. Either new calendar can be made or existing can be changed using Project>Change Working time. Either holidays can be accommodated using Exceptions, or overtime can be added using Work weeks tab Summary tasks
  • 10. Each task can be associated with a WBS (work breakdown structure) code. We can define our own WBS codes. Highest WBS code should be added as project code in the SEPITS for tracking. Summary tasks can be shown and hidden from Gant chart tools>Format>Summary tasks checkbox WBS Codes, Showide summary
  • 11. Tasks can be linked to have dependency between them Link tasks
  • 12. All resources can be seen at View>Resource sheet Resources work availability should be set in maximum unit column e.g. 70% of leads. Also cost of resources can be put here. Resources could be work, cost or material. Resources normally gets added automatically but its not a good way. If you want new resources not to be added to the resource pool automatically, open, file>options>advanced and deselect add new resources and tasks check box Resources
  • 13. Duration = Work units E.g. if resource works for 50% units then task of 40 hrs is calculated to 80 hrs by MPP Thus, 80 hours = 40 hours 50% Work = Duration X Units E.g. If we enter task duration for 5 days at 40% resource usage, MPP would give output of 16 hours Thus, 2 days = 5 days X 40% Units = work duration E.g. MPP calculates units if work is provided 40 hrs and duration 160hrs. Thus, 0.25 = 40 hours 160 hours Duration, work and units
  • 14. If hours assigned are higher than the maximum available time for a resource, over-allocation occurs. Resource over-allocations can be analyzed using resource usage and resource sheet. In resource usage view, all over allocated resources can be filtered. It can be fixed using task inspector, team planner etc. Resource over-allocations
  • 15. Whenever resource assignments are changed, MPP will trigger to select one of the three options. We need to click the correct option, as per our requirement there. Resource assignments modifications
  • 16. Using team planner, one can assign tasks to users using drag and drop. This can also be used to fix over-allocations of resources. Team planner
  • 17. Timeline can be viewed at View>timeline. We can add milestones on timeline and then copy that on email for providing visual treat to client. Timeline
  • 18. One can create multiple project plans and then to analyze across the projects, one can create master plan and then add all projects plan as sub projects to that. Master & Sub projects
  • 19. Resources can be leveled, however it can dangerously change the whole if whole project leveling is requested. Leveling delays and splits tasks to remove over-allocations. For that leveling should be done small portion of plan. Leveling resources
  • 20. Plan can be baselined from Project>Set baseline. There could be 11 baselines for a plan. Scheduled is current plan, that may be same or changed per the progress going on. Also actual can be used for inputting actual values, and then when required variance reports can be generated. Baselined, scheduled and actual
  • 21. Project > Project information >statistics View > tables > variance etc Project > reports > overview > summary Using other text based and visual reports Project Status & Reports