SlideShare une entreprise Scribd logo
1  sur  34
Télécharger pour lire hors ligne
   Project Background/Planning Perspective
   Review UWMP Supply and Demand Projections
   Master Planning Process
    ◦ Scenario Development
    ◦ Supply/Facility Alternatives
    ◦ Evaluation Criteria
   Overview of Programmatic EIR and Climate
    Action Plan
   Schedule for Remaining Work



                                                2
3
   In-System Storage
    ◦ Olivenhain Reservoir
      24,000 AF held for
       emergency storage
    ◦ Local Reservoirs
      Currently 20,000 AF held
       in member agency reservoirs
       for drought carryover
    ◦ ESP/CSP
      Hodges - 20,000 AF for emergency storage (2013)
      San Vicente – 150,000 AF for emergency and carryover
       (2013)


                                                              4
Twin Oaks Valley (SDCWA)              David C. McCollom (OMWD)
                                      (member agency agreement)




                     R. M. Levy (Helix)
                     (member agency agreement)
                                                                  5
San Diego Regional Treatment Capacity
(MGD)
                                                                             2012
Total Regional Water Treatment Plant Capacity                                866
Miramar          City of San Diego                                           215
Alvarado         City of San Diego                                           200
Levy             Helix Water District                                        106
Twin Oaks Valley San Diego County Water Authority                            100
Escondido-Vista City of Escondido                                             62
Badger           San Dieguito Water District/Santa Fe Irrigation Districts    36
Olivenhain       Olivenhain Municipal Water District                          34
Otay             City of San Diego                                            36
Perdue           Sweetwater Authority                                         28
Berglund         City of Poway                                                24
Weese            City of Oceanside                                            25


                                     • Untreated Conveyance Capacity 500 MGD
                                     • Untreated/Treated Split 70%/30% (2011)
                                                                                6
 North to south gravity flow pipeline system
 Reliance on MWD / SDCWA to supplement
  local water
 Local WTPs in place to primarily treat local
  supplies
‣ System improvements for            Local Supplies 5%

   added imported water
   capacity
‣ Identified a need for new              MWD 95%


   storage facilities
                                              1991

                                                         7
2003 Quantification Settlement Agreement
                                                                                          IID water transfer, 35-yr take or pay, 4.88 maf
                                                                                            • $1.45 billion
                                                                                          Canal linings, 110 yrs, 4.32 maf
                                                                                            • $175 million

                                                  1997 Water Resource Plan
                                                  • Add IID water transfer                             2005 Urban Water Management Plan
                                                                                                       • Add 56kaf desalination
                                  1995 Urban Water
                                                                                                                     2006 Comprehensive Reliability and
                                  Management Plan
                                                                      2000 Urban Water                               Cost Assessment “CRACA”
                                                                      Management Plan                                •Analyze cost/reliability of CIP
                      1993 Water                                                                                     •Validate storage decisions
                      Resource Plan                                                                                  •Carlsbad desal is local project


  89     90     91    92     93     94       95   96     97     98     99     00    01     02    03    04      05    06     07     08       09   10       11


1989 Water Distribution Plan                                                                                                   2009 CRACA “lite”
• Increase system capacity and reliability         Emergency Storage Project                                                   •Validate CIP scope/cost
• 10 projects                                      • Add 92 kaf of emergency storage                                           •Drought mgmt impacts
• $530 million CIP budget                          • Add $730 million to CIP
                                                   • $1.594 billion CIP budget    2002 Water Facilities Master Plan
                                                                                  • Preferred alternative “supply from the west”
                                                                                  • Add up to 89 kaf of regional desalination
                                                                                  • Add 100 kaf of carryover storage
                                                                                  • Add 50-100 MGD of treatment capacity
                                                                                  • $3.229 billion CIP budget




                                                                                                                                                          8
Options Considered in 2002 Master Plan

                           Conveyance from the North


    Supply from the West




                                        Conveyance from the East




                                                              9
   Develop up to 80 MGD of
    seawater desal (supply
    from the west)
   Develop 50 to 100 MGD of
    new WTP capacity
    ◦ New treatment needed to
      maintain regional reliability




                                      10
   Develop 100,000 AF carryover pool to manage
    seasonal peaks and drought conditions
   Implement internal system improvements
   Reaffirmed local supply development
   If all the above is achieved, Pipeline 6 may be
    postponed for several years




                                                      11
   Reduced demands/increased conservation
   Supply uncertainties
   Increased supply diversification
   Water rates and increasing price sensitivity
                             850                                             2005 UWMP Projected Demand
                                                                             (with BMP based conservation)
                             800                      1990-2011
                                                   Historic Demand
                             750
         Tota Demand (TAF)




                             700
                             650
                             600                                                                  2010 UWMP Projected Demand
                                                                                                  (after SBX7-7 retail compliance)
                             550
                             500
                             450
                                   1990

                                          1993

                                                 1996

                                                        1999

                                                               2002

                                                                      2005

                                                                             2008

                                                                                    2011

                                                                                           2017

                                                                                                     2020

                                                                                                            2023

                                                                                                                   2026

                                                                                                                          2029

                                                                                                                                 2032

                                                                                                                                        2035
                                                                                                                                               12
Member
   Agency                  2010
   Facility                UWMP
    Plans
               2012
              Master
2002           Plan           Asset
Master        Update       Management
 Plan                       Program



                 Current
                   CIP
                                        13
Water Use                     Water
Demand                        Water                       Scenario
              Efficiency                   Resource
Forecast                     Supplies                     Planning
               Target                        Mix


Econometric                                                Process to
                                 Water     Resource mix
   Model          Retail                                     manage
                              Authority       to meet
  utilizing   Compliance                                     supply
                             and member     demands in
  SANDAG      with SBX7-7:                                uncertainties
                                agency      normal and
  Regional    20% savings                                  associated
                              verifiable     dry water
   Growth       by 2020                                   with resource
                               supplies        years
  Forecast                                                     mix




                                                                          14
900
                        Demands 786 TAF   MWD
800
700
      Demands 527 TAF
600                         336 TAF
                                          Regional Seawater
500                                       Desalination (Carlsbad)
                            56 TAF
400      262 TAF
                            126 TAF
300                                       Member Agency Local
200      110 TAF                          Supplies
                            280 TAF
100
         155 TAF
                                          QSA Transfer Supplies
  0
       2011 Actual      2035 Projected
        Fiscal Year      Normal Year


                                                                15
   Manage untreated and treated water supplies
   Maximize use of existing assets
   Integration of desalination supplies
   Treatment plant utilization
   Cost-effective facility implementation
   Optimize utilization of regional water
    resources
   Coordination with member agency facility
    plans
   Characterization of member agency demands


                                                  16
   Strategic long range plan for surface water
    storage
   Characterization of local supply development
   Energy use and renewable energy
    opportunities
   Prioritization of ongoing/new CIP projects
   Facility cost/rate implications




                                                   17
1
1.   Pipeline 6/P3/P4 switch           3
2.   Camp Pendleton                        4
     Desalination              2
3.   ESP North County Pump
                                       8
     Station                               5
4.   Twin Oaks Valley WTP          7
     Expanded Service Area
5.   Crossover Pipeline
6.   Mission Trails Flow
     Regulatory Structure
7.   Carlsbad Desalination
     integration
                                           6
8.   System Regulatory
     Storage



                                               18
UWMP Scenarios   UWMP Scenarios    Lead Supply          Facility              Facility Sensitivity
                 Supplies          Alternatives         Requirements          analysis
Demands

    •Normal          •Verifiable        •Baseline           •Current Water         • P6 versus
                                                             Authority CIP          P3/P4
     Demands          mix               •Expanded                                   conversion
    •Dry Year        •Additional         Regional           •ESP Facilities
                                                                                   •Camp
     Demands          Planned            Desalination       •Carlsbad               Pendleton 50
                                                             Desal                  MGD or more
    •High            •Conceptual        •Maximize
                                                            •MA Verifiable         •Additional
     Demands                             Storage
                                                             Local Supply           Planned and
                                        •Balanced            Mix                    Conceptual
                                         Supply             •Current
                                                                                    local
                                         Options             Reservoir             •Alternative
                                                                                    Reservoir
                                                             Operations
                                                                                    Operations
                                                                                   •Other Facilities
                                                                                    to test for
                                                                                    regional
                                                                                    benefits
                                                                                   •Alternative
                                                                                    Demand Paths




                                                                                                     19
   Build from UWMP scenarios
      Single/multiple dry years
      Limited MWD Supplies
      Local supply mix
   Master Plan scenario
    considerations
        Daily demand patterns – peak season
        Local supply variability
        Hydrology
        Climate impacts
   Each scenario attempts to
    explore an aspect of supply
    and demand uncertainty



                                               20
   Identify alternatives to address performance gaps
    ◦ Facility constraints
    ◦ Supply constraints
   Initial strategies for crafting Alternatives:
    ◦   Maximize imported water
    ◦   Expanded regional desalination
    ◦   Maximized storage options
    ◦   Balanced supply options
   Test performance of baseline aqueduct system against
    Master Plan Scenarios




                                                           21
   Scenario A – Current Trends
    ◦ Current estimates for supply and demand consistent with UWMP
      assumptions
   Scenario B – Reduced Imported Supplies, Climate
    Change and Lower Local Supply Development
    ◦ Increased imported water uncertainty, especially in dry years,
      coupled with factors that may slow the reduction in demands or
      the development of local projects. Presents an important upper
      boundary bracketing scenario.
   Scenario C – Enhanced Local Resource
    Management
    ◦ Local supply development and demand management is the focus.
      Presents an important lower boundary bracketing scenario.
   Scenario D – Adjusted Local Supply Development
    ◦ A limited achievement level (50%) of local supply development and
      demand management. Presents a scenario positioned between
      Scenarios A and C.

                                                                          22
Master Plan Analysis
Scenarios                                 Alternatives
                                               Existing
       Scenario
                                              Aqueduct
          A
                                               System

                                                Alt 1
                                           Imported Water
Scenario
                                              Strategy
   B
                       Model Results
                      Deterministic and        Alt 2
                         Stochastic         Max Seawater
                                            Desalination
Scenario
   C                                           Alt 3
                                            Max Storage
                                            Operations
           Scenario
                                                Alt 4
              D
                                           Balanced Supply
                                               Option

                                                             23
   System capacity
   Supply reliability
   Costs of capital improvement program
   Environmental impacts
   Energy use and production optimization
   Supports WA diversification goals
   Improves water quality
   Feasibility
   Minimizes rate impacts
   Maximizes use of existing facilities

                                             24
Scenario B1
              Higher demands, slow member
              agency supply development or
              conservation measures                     Scenario B2

                                                        Scenario D

                                                        Scenario A2   Adaptive Process
                                                                       Monitoring
                                                        Scenario A1     metrics
    Early Actions            Mainline demand projections,
                                                                         Implementation
                             verifiable member agency
                             projects and conservation                    timelines and
                                                                          phasing
Today                                                    Scenario C      Risk-based and
                          Slower growth in demands, more rapid            adaptive
                          member agency supply development or             decision-making
                          conservation measures
Decision Timelines

  Near-Term Actions                               Long-Term Actions


                          Mid-Term Actions                                                 25
   With the 2010 UWMP expected demand
    forecasts and normal or wet cycle hydrology
    shortages are minimal
   Carlsbad desalination production is important in
    managing shortages in all hydrological cycles
   If demands exceed UWMP expected demand
    forecasts, developing local or imported supplies
    is important for continued reliability
   In dry years - greater vulnerably until QSA
    supplies are ramped up
   Pipeline 6 appears to be beyond the 2035
    planning horizon


                                                       26
   Feb 2012: Board workshop
   Spring 2012: Second board workshop
   Summer 2012: Release draft report to
    member agencies
   Oct 2012: Release Draft Program EIR
   Mar 2013: Board Certify Program EIR and
    Accept Final Master Plan Update




                                              27
Master    Climate
 Plan    Action Plan

                       28
‣ Inventory GHG sources (facilities, buildings,
  fleet)
‣ Estimate emission changes over time,
  including new facilities from Master Plan
‣ Identify mitigation actions to reduce GHGs
‣ Document GHG reduction feasibility and
  implementation
‣ Serve as significance thresholds for future
  actions
‣ Allow for periodic updates

                                                  29
‣ Global Warming Solutions Act (AB 32)
 ‣ Requires GHG emission reductions
   o   1990 levels by 2020
   o   80% below 1990 levels by 2050
‣ CEQA Guideline Revisions (SB 97)
 ‣ Requires analysis of GHG emissions
 ‣ Provides comprehensive approach through
   development of GHG emission reduction plan
   (Climate Action Plan)
‣ Water Authority not required to comply with
  AB32
 ‣ Cannot hinder the State from achieving the goals
 ‣ Must make CEQA determination on GHG emissions

                                                      30
‣ CEQA streamlining for future projects
‣ Can look at the “big” picture through
  comprehensive analysis of cumulative
  impacts
‣ Provides broad list of mitigation measures
‣ Possible cost savings through energy
  efficiency and water conservation
‣ Contributes to regional sustainability goals
‣ Demonstrates leadership within the
  community

                                                 31
Program
        EIR

Master    Climate
 Plan    Action Plan

                       32
‣ Provide Board, agencies, and public with:
 o   Comprehensive environmental analysis of
     Master Plan
 o   Opportunity for input into the decision-making
     process
‣ Develop program-wide mitigation measures
  to reduce or eliminate potential impacts
‣ Assist Water Authority and other agencies in
  determining future CEQA documents that
  may be needed to implement future project
  components
‣ Serve as starting point for future site-
  specific environmental findings


                                                      33
   Feb 2012: Board workshop
   Spring 2012: Second board workshop
   Summer 2012: Release draft report to
    member agencies
   Oct 2012: Release Draft Program EIR
   Mar 2013: Board Certify Program EIR and
    Accept Final Master Plan Update




                                              34

Contenu connexe

Tendances

PA's Nutrient Trading Program
PA's Nutrient Trading ProgramPA's Nutrient Trading Program
PA's Nutrient Trading ProgramCleanH2O
 
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...San Diego County Water Authority
 
The Use of Nutrient Credits in Virginia
The Use of Nutrient Credits in Virginia The Use of Nutrient Credits in Virginia
The Use of Nutrient Credits in Virginia CleanH2O
 
Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...
Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...
Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...San Diego County Water Authority
 
Water Talks: Water Rates: Funding a Reliable Future Overview
Water Talks: Water Rates: Funding a Reliable Future OverviewWater Talks: Water Rates: Funding a Reliable Future Overview
Water Talks: Water Rates: Funding a Reliable Future OverviewSan Diego County Water Authority
 
Sydney Water Guidelines for Rainwater Tanks
Sydney Water Guidelines for Rainwater TanksSydney Water Guidelines for Rainwater Tanks
Sydney Water Guidelines for Rainwater TanksD6Z
 
TX: Efficient Irrigation for Water Conservation in the Rio Grande Basin
TX: Efficient Irrigation for Water Conservation in the Rio Grande BasinTX: Efficient Irrigation for Water Conservation in the Rio Grande Basin
TX: Efficient Irrigation for Water Conservation in the Rio Grande BasinSotirakou964
 
ES&E Magazine - Dawson Creek
ES&E Magazine - Dawson CreekES&E Magazine - Dawson Creek
ES&E Magazine - Dawson CreekKevin Vieira
 
Nuts and Bolts of Restoration Implementation
Nuts and Bolts of Restoration ImplementationNuts and Bolts of Restoration Implementation
Nuts and Bolts of Restoration ImplementationBuzzards Bay Coalition
 
Policy Context and Sustainable Drainage Issues and Application - Paul Stewart...
Policy Context and Sustainable Drainage Issues and Application - Paul Stewart...Policy Context and Sustainable Drainage Issues and Application - Paul Stewart...
Policy Context and Sustainable Drainage Issues and Application - Paul Stewart...the Environment Centre (tEC)
 
NJ Redevelopment Forum 2020 - Mahon
NJ Redevelopment Forum 2020 - MahonNJ Redevelopment Forum 2020 - Mahon
NJ Redevelopment Forum 2020 - MahonNew Jersey Future
 
C2VSim Workshop 2 - Overview of C2VSim
C2VSim Workshop 2 - Overview of C2VSimC2VSim Workshop 2 - Overview of C2VSim
C2VSim Workshop 2 - Overview of C2VSimCharlie Brush
 

Tendances (20)

Water Education Foundation San Diego Tour, by Kelley Gage
Water Education Foundation San Diego Tour, by Kelley GageWater Education Foundation San Diego Tour, by Kelley Gage
Water Education Foundation San Diego Tour, by Kelley Gage
 
May 1 Water Talks - Halla Razak, P.E.
May 1 Water Talks - Halla Razak, P.E. May 1 Water Talks - Halla Razak, P.E.
May 1 Water Talks - Halla Razak, P.E.
 
PA's Nutrient Trading Program
PA's Nutrient Trading ProgramPA's Nutrient Trading Program
PA's Nutrient Trading Program
 
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
Other Actions Related to Board Consideration of the Carlsbad Desalination Pro...
 
The Use of Nutrient Credits in Virginia
The Use of Nutrient Credits in Virginia The Use of Nutrient Credits in Virginia
The Use of Nutrient Credits in Virginia
 
Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...
Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...
Bay-Delta Conservation Plan (BDCP) Supply and Demand Risk Assessment - Jan. 9...
 
Wp mp-update-camp pendleton.-april_25_2013
Wp   mp-update-camp pendleton.-april_25_2013Wp   mp-update-camp pendleton.-april_25_2013
Wp mp-update-camp pendleton.-april_25_2013
 
ORP FY13 Budget Workshop
ORP FY13 Budget WorkshopORP FY13 Budget Workshop
ORP FY13 Budget Workshop
 
Lake Conroe Dock Fees Presentation
Lake Conroe Dock Fees PresentationLake Conroe Dock Fees Presentation
Lake Conroe Dock Fees Presentation
 
Water Talks: Water Rates: Funding a Reliable Future Overview
Water Talks: Water Rates: Funding a Reliable Future OverviewWater Talks: Water Rates: Funding a Reliable Future Overview
Water Talks: Water Rates: Funding a Reliable Future Overview
 
Sydney Water Guidelines for Rainwater Tanks
Sydney Water Guidelines for Rainwater TanksSydney Water Guidelines for Rainwater Tanks
Sydney Water Guidelines for Rainwater Tanks
 
Bay Delta Overview - March 28, 2013
Bay Delta Overview - March 28, 2013Bay Delta Overview - March 28, 2013
Bay Delta Overview - March 28, 2013
 
TX: Efficient Irrigation for Water Conservation in the Rio Grande Basin
TX: Efficient Irrigation for Water Conservation in the Rio Grande BasinTX: Efficient Irrigation for Water Conservation in the Rio Grande Basin
TX: Efficient Irrigation for Water Conservation in the Rio Grande Basin
 
ES&E Magazine - Dawson Creek
ES&E Magazine - Dawson CreekES&E Magazine - Dawson Creek
ES&E Magazine - Dawson Creek
 
Nuts and Bolts of Restoration Implementation
Nuts and Bolts of Restoration ImplementationNuts and Bolts of Restoration Implementation
Nuts and Bolts of Restoration Implementation
 
Policy Context and Sustainable Drainage Issues and Application - Paul Stewart...
Policy Context and Sustainable Drainage Issues and Application - Paul Stewart...Policy Context and Sustainable Drainage Issues and Application - Paul Stewart...
Policy Context and Sustainable Drainage Issues and Application - Paul Stewart...
 
NJ Redevelopment Forum 2020 - Mahon
NJ Redevelopment Forum 2020 - MahonNJ Redevelopment Forum 2020 - Mahon
NJ Redevelopment Forum 2020 - Mahon
 
Civil Works Transformation
Civil Works TransformationCivil Works Transformation
Civil Works Transformation
 
WHCRWA Town Hall 2012 - Fall
WHCRWA Town Hall 2012 - FallWHCRWA Town Hall 2012 - Fall
WHCRWA Town Hall 2012 - Fall
 
C2VSim Workshop 2 - Overview of C2VSim
C2VSim Workshop 2 - Overview of C2VSimC2VSim Workshop 2 - Overview of C2VSim
C2VSim Workshop 2 - Overview of C2VSim
 

En vedette

En vedette (19)

Pure Water San Diego
Pure Water San DiegoPure Water San Diego
Pure Water San Diego
 
Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...
Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...
Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...
 
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
 
Notification of a Drought Alert Condition and Declare Supply Enhancement Stag...
Notification of a Drought Alert Condition and Declare Supply Enhancement Stag...Notification of a Drought Alert Condition and Declare Supply Enhancement Stag...
Notification of a Drought Alert Condition and Declare Supply Enhancement Stag...
 
Water Talks: City of San Diego IPR
Water Talks: City of San Diego IPRWater Talks: City of San Diego IPR
Water Talks: City of San Diego IPR
 
Tilcara
TilcaraTilcara
Tilcara
 
Power seguridad 001
Power seguridad 001Power seguridad 001
Power seguridad 001
 
Santo tomas moro
Santo tomas moroSanto tomas moro
Santo tomas moro
 
FFISFlyerFullPage
FFISFlyerFullPageFFISFlyerFullPage
FFISFlyerFullPage
 
Coletiva mobilidade 20.05
Coletiva mobilidade   20.05Coletiva mobilidade   20.05
Coletiva mobilidade 20.05
 
el relievee de españa
el relievee de españael relievee de españa
el relievee de españa
 
Servicios en unsistema_e_learning
Servicios en unsistema_e_learningServicios en unsistema_e_learning
Servicios en unsistema_e_learning
 
Cómo se hace un blog
Cómo se hace un blogCómo se hace un blog
Cómo se hace un blog
 
PPM
PPMPPM
PPM
 
Windows seven (7)
Windows seven (7)Windows seven (7)
Windows seven (7)
 
La fotografia
La fotografiaLa fotografia
La fotografia
 
Blogs empresa
Blogs empresaBlogs empresa
Blogs empresa
 
Henry narvaez 10 b
Henry narvaez 10 bHenry narvaez 10 b
Henry narvaez 10 b
 
Normas para los alumnos relativas a la pau
Normas para los alumnos relativas a la pauNormas para los alumnos relativas a la pau
Normas para los alumnos relativas a la pau
 

Similaire à February 9, 2012

GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICTGREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICTU.S. Water Alliance
 
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...San Diego County Water Authority
 
The Drought’s Affect on Dallas Water Utilities
The Drought’s Affect on Dallas Water UtilitiesThe Drought’s Affect on Dallas Water Utilities
The Drought’s Affect on Dallas Water UtilitiesThe Texas Network, LLC
 
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...San Diego County Water Authority
 
San Diego County's Water Supply - SD Regional EDC Presentation Sept. 21
San Diego County's Water Supply - SD Regional EDC Presentation Sept. 21San Diego County's Water Supply - SD Regional EDC Presentation Sept. 21
San Diego County's Water Supply - SD Regional EDC Presentation Sept. 21San Diego County Water Authority
 
Asian Business Association Sept. 28 Rice Club Luncheon - Maureen Stapleton
Asian Business Association Sept. 28 Rice Club Luncheon - Maureen StapletonAsian Business Association Sept. 28 Rice Club Luncheon - Maureen Stapleton
Asian Business Association Sept. 28 Rice Club Luncheon - Maureen StapletonSan Diego County Water Authority
 
C2VSim Workshop 6 - Closing
C2VSim Workshop 6 - ClosingC2VSim Workshop 6 - Closing
C2VSim Workshop 6 - ClosingCharlie Brush
 
An approach to safe drinking water 'RWH'_Subhash (water.org)_2013
An approach to safe drinking water 'RWH'_Subhash (water.org)_2013An approach to safe drinking water 'RWH'_Subhash (water.org)_2013
An approach to safe drinking water 'RWH'_Subhash (water.org)_2013India Water Portal
 
Southwestern Division Pacesetters - Transforming the Corps of Engineers Civil...
Southwestern Division Pacesetters - Transforming the Corps of Engineers Civil...Southwestern Division Pacesetters - Transforming the Corps of Engineers Civil...
Southwestern Division Pacesetters - Transforming the Corps of Engineers Civil...The Texas Network, LLC
 
Presentation - GWI Coastal Water treatment programme 2021 2025.pdf
Presentation - GWI Coastal Water treatment programme 2021 2025.pdfPresentation - GWI Coastal Water treatment programme 2021 2025.pdf
Presentation - GWI Coastal Water treatment programme 2021 2025.pdfSwatiGautam62
 
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...San Diego County Water Authority
 
Cincinnati's approach for a city of the future
Cincinnati's approach for a city of the futureCincinnati's approach for a city of the future
Cincinnati's approach for a city of the futureU.S. Water Alliance
 
Water Talks: A Bay-Delta Fix: Impacts to Your Water Supply and Wallet Overview
Water Talks: A Bay-Delta Fix: Impacts to Your Water Supply and Wallet OverviewWater Talks: A Bay-Delta Fix: Impacts to Your Water Supply and Wallet Overview
Water Talks: A Bay-Delta Fix: Impacts to Your Water Supply and Wallet OverviewSan Diego County Water Authority
 
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisState & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisDan Arthur
 

Similaire à February 9, 2012 (20)

GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICTGREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
 
From Drought Response to Center Stage
From Drought Response to Center StageFrom Drought Response to Center Stage
From Drought Response to Center Stage
 
INFORM: Adel Hagekhalil
INFORM: Adel HagekhalilINFORM: Adel Hagekhalil
INFORM: Adel Hagekhalil
 
Water Talks: Emergency Storage Project
Water Talks: Emergency Storage ProjectWater Talks: Emergency Storage Project
Water Talks: Emergency Storage Project
 
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...
 
Water Talks: Investments in Water Reliability
Water Talks: Investments in Water ReliabilityWater Talks: Investments in Water Reliability
Water Talks: Investments in Water Reliability
 
The Drought’s Affect on Dallas Water Utilities
The Drought’s Affect on Dallas Water UtilitiesThe Drought’s Affect on Dallas Water Utilities
The Drought’s Affect on Dallas Water Utilities
 
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...
Public Workshop/Special Water Planning Committee Meeting - Carlsbad Desalinat...
 
San Diego County's Water Supply - SD Regional EDC Presentation Sept. 21
San Diego County's Water Supply - SD Regional EDC Presentation Sept. 21San Diego County's Water Supply - SD Regional EDC Presentation Sept. 21
San Diego County's Water Supply - SD Regional EDC Presentation Sept. 21
 
Asian Business Association Sept. 28 Rice Club Luncheon - Maureen Stapleton
Asian Business Association Sept. 28 Rice Club Luncheon - Maureen StapletonAsian Business Association Sept. 28 Rice Club Luncheon - Maureen Stapleton
Asian Business Association Sept. 28 Rice Club Luncheon - Maureen Stapleton
 
C2VSim Workshop 6 - Closing
C2VSim Workshop 6 - ClosingC2VSim Workshop 6 - Closing
C2VSim Workshop 6 - Closing
 
An approach to safe drinking water 'RWH'_Subhash (water.org)_2013
An approach to safe drinking water 'RWH'_Subhash (water.org)_2013An approach to safe drinking water 'RWH'_Subhash (water.org)_2013
An approach to safe drinking water 'RWH'_Subhash (water.org)_2013
 
Southwestern Division Pacesetters - Transforming the Corps of Engineers Civil...
Southwestern Division Pacesetters - Transforming the Corps of Engineers Civil...Southwestern Division Pacesetters - Transforming the Corps of Engineers Civil...
Southwestern Division Pacesetters - Transforming the Corps of Engineers Civil...
 
Water Talks: Introduction
Water Talks: IntroductionWater Talks: Introduction
Water Talks: Introduction
 
Presentation - GWI Coastal Water treatment programme 2021 2025.pdf
Presentation - GWI Coastal Water treatment programme 2021 2025.pdfPresentation - GWI Coastal Water treatment programme 2021 2025.pdf
Presentation - GWI Coastal Water treatment programme 2021 2025.pdf
 
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
 
Cincinnati's approach for a city of the future
Cincinnati's approach for a city of the futureCincinnati's approach for a city of the future
Cincinnati's approach for a city of the future
 
Save the Rain Presentation - NYSAC 2012
Save the Rain Presentation - NYSAC 2012Save the Rain Presentation - NYSAC 2012
Save the Rain Presentation - NYSAC 2012
 
Water Talks: A Bay-Delta Fix: Impacts to Your Water Supply and Wallet Overview
Water Talks: A Bay-Delta Fix: Impacts to Your Water Supply and Wallet OverviewWater Talks: A Bay-Delta Fix: Impacts to Your Water Supply and Wallet Overview
Water Talks: A Bay-Delta Fix: Impacts to Your Water Supply and Wallet Overview
 
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisState & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
 

Plus de San Diego County Water Authority

Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015 Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015 San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015 Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015 San Diego County Water Authority
 
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...San Diego County Water Authority
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...San Diego County Water Authority
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...San Diego County Water Authority
 
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...San Diego County Water Authority
 
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...San Diego County Water Authority
 
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response ActivitiesUpdate on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response ActivitiesSan Diego County Water Authority
 
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...San Diego County Water Authority
 

Plus de San Diego County Water Authority (20)

Session 2 presentation
Session 2 presentationSession 2 presentation
Session 2 presentation
 
Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015
 
Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015 Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015
 
Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015
 
Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015
 
Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016
 
Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015
 
Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015 Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
 
Bay-Delta Activities Update
Bay-Delta Activities UpdateBay-Delta Activities Update
Bay-Delta Activities Update
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...
 
2015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 20152015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 2015
 
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
 
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
 
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
 
Update on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response ActivitiesUpdate on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response Activities
 
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
 

Dernier

422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdflambardar420420
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)Delhi Call girls
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsVoterMood
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...Andy (Avraham) Blumenthal
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreiebhavenpr
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfssuser5750e1
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...IT Industry
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeRahatulAshafeen
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPsychicRuben LoveSpells
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhbhavenpr
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Developmentnarsireddynannuri1
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...Faga1939
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Delhi Call girls
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...srinuseo15
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptxYasinAhmad20
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Delhi Call girls
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...anjanibaddipudi1
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkobhavenpr
 

Dernier (20)

422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full Details
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the trade
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
 

February 9, 2012

  • 1.
  • 2. Project Background/Planning Perspective  Review UWMP Supply and Demand Projections  Master Planning Process ◦ Scenario Development ◦ Supply/Facility Alternatives ◦ Evaluation Criteria  Overview of Programmatic EIR and Climate Action Plan  Schedule for Remaining Work 2
  • 3. 3
  • 4. In-System Storage ◦ Olivenhain Reservoir  24,000 AF held for emergency storage ◦ Local Reservoirs  Currently 20,000 AF held in member agency reservoirs for drought carryover ◦ ESP/CSP  Hodges - 20,000 AF for emergency storage (2013)  San Vicente – 150,000 AF for emergency and carryover (2013) 4
  • 5. Twin Oaks Valley (SDCWA) David C. McCollom (OMWD) (member agency agreement) R. M. Levy (Helix) (member agency agreement) 5
  • 6. San Diego Regional Treatment Capacity (MGD) 2012 Total Regional Water Treatment Plant Capacity 866 Miramar City of San Diego 215 Alvarado City of San Diego 200 Levy Helix Water District 106 Twin Oaks Valley San Diego County Water Authority 100 Escondido-Vista City of Escondido 62 Badger San Dieguito Water District/Santa Fe Irrigation Districts 36 Olivenhain Olivenhain Municipal Water District 34 Otay City of San Diego 36 Perdue Sweetwater Authority 28 Berglund City of Poway 24 Weese City of Oceanside 25 • Untreated Conveyance Capacity 500 MGD • Untreated/Treated Split 70%/30% (2011) 6
  • 7.  North to south gravity flow pipeline system  Reliance on MWD / SDCWA to supplement local water  Local WTPs in place to primarily treat local supplies ‣ System improvements for Local Supplies 5% added imported water capacity ‣ Identified a need for new MWD 95% storage facilities 1991 7
  • 8. 2003 Quantification Settlement Agreement IID water transfer, 35-yr take or pay, 4.88 maf • $1.45 billion Canal linings, 110 yrs, 4.32 maf • $175 million 1997 Water Resource Plan • Add IID water transfer 2005 Urban Water Management Plan • Add 56kaf desalination 1995 Urban Water 2006 Comprehensive Reliability and Management Plan 2000 Urban Water Cost Assessment “CRACA” Management Plan •Analyze cost/reliability of CIP 1993 Water •Validate storage decisions Resource Plan •Carlsbad desal is local project 89 90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 1989 Water Distribution Plan 2009 CRACA “lite” • Increase system capacity and reliability Emergency Storage Project •Validate CIP scope/cost • 10 projects • Add 92 kaf of emergency storage •Drought mgmt impacts • $530 million CIP budget • Add $730 million to CIP • $1.594 billion CIP budget 2002 Water Facilities Master Plan • Preferred alternative “supply from the west” • Add up to 89 kaf of regional desalination • Add 100 kaf of carryover storage • Add 50-100 MGD of treatment capacity • $3.229 billion CIP budget 8
  • 9. Options Considered in 2002 Master Plan Conveyance from the North Supply from the West Conveyance from the East 9
  • 10. Develop up to 80 MGD of seawater desal (supply from the west)  Develop 50 to 100 MGD of new WTP capacity ◦ New treatment needed to maintain regional reliability 10
  • 11. Develop 100,000 AF carryover pool to manage seasonal peaks and drought conditions  Implement internal system improvements  Reaffirmed local supply development  If all the above is achieved, Pipeline 6 may be postponed for several years 11
  • 12. Reduced demands/increased conservation  Supply uncertainties  Increased supply diversification  Water rates and increasing price sensitivity 850 2005 UWMP Projected Demand (with BMP based conservation) 800 1990-2011 Historic Demand 750 Tota Demand (TAF) 700 650 600 2010 UWMP Projected Demand (after SBX7-7 retail compliance) 550 500 450 1990 1993 1996 1999 2002 2005 2008 2011 2017 2020 2023 2026 2029 2032 2035 12
  • 13. Member Agency 2010 Facility UWMP Plans 2012 Master 2002 Plan Asset Master Update Management Plan Program Current CIP 13
  • 14. Water Use Water Demand Water Scenario Efficiency Resource Forecast Supplies Planning Target Mix Econometric Process to Water Resource mix Model Retail manage Authority to meet utilizing Compliance supply and member demands in SANDAG with SBX7-7: uncertainties agency normal and Regional 20% savings associated verifiable dry water Growth by 2020 with resource supplies years Forecast mix 14
  • 15. 900 Demands 786 TAF MWD 800 700 Demands 527 TAF 600 336 TAF Regional Seawater 500 Desalination (Carlsbad) 56 TAF 400 262 TAF 126 TAF 300 Member Agency Local 200 110 TAF Supplies 280 TAF 100 155 TAF QSA Transfer Supplies 0 2011 Actual 2035 Projected Fiscal Year Normal Year 15
  • 16. Manage untreated and treated water supplies  Maximize use of existing assets  Integration of desalination supplies  Treatment plant utilization  Cost-effective facility implementation  Optimize utilization of regional water resources  Coordination with member agency facility plans  Characterization of member agency demands 16
  • 17. Strategic long range plan for surface water storage  Characterization of local supply development  Energy use and renewable energy opportunities  Prioritization of ongoing/new CIP projects  Facility cost/rate implications 17
  • 18. 1 1. Pipeline 6/P3/P4 switch 3 2. Camp Pendleton 4 Desalination 2 3. ESP North County Pump 8 Station 5 4. Twin Oaks Valley WTP 7 Expanded Service Area 5. Crossover Pipeline 6. Mission Trails Flow Regulatory Structure 7. Carlsbad Desalination integration 6 8. System Regulatory Storage 18
  • 19. UWMP Scenarios UWMP Scenarios Lead Supply Facility Facility Sensitivity Supplies Alternatives Requirements analysis Demands •Normal •Verifiable •Baseline •Current Water • P6 versus Authority CIP P3/P4 Demands mix •Expanded conversion •Dry Year •Additional Regional •ESP Facilities •Camp Demands Planned Desalination •Carlsbad Pendleton 50 Desal MGD or more •High •Conceptual •Maximize •MA Verifiable •Additional Demands Storage Local Supply Planned and •Balanced Mix Conceptual Supply •Current local Options Reservoir •Alternative Reservoir Operations Operations •Other Facilities to test for regional benefits •Alternative Demand Paths 19
  • 20. Build from UWMP scenarios  Single/multiple dry years  Limited MWD Supplies  Local supply mix  Master Plan scenario considerations  Daily demand patterns – peak season  Local supply variability  Hydrology  Climate impacts  Each scenario attempts to explore an aspect of supply and demand uncertainty 20
  • 21. Identify alternatives to address performance gaps ◦ Facility constraints ◦ Supply constraints  Initial strategies for crafting Alternatives: ◦ Maximize imported water ◦ Expanded regional desalination ◦ Maximized storage options ◦ Balanced supply options  Test performance of baseline aqueduct system against Master Plan Scenarios 21
  • 22. Scenario A – Current Trends ◦ Current estimates for supply and demand consistent with UWMP assumptions  Scenario B – Reduced Imported Supplies, Climate Change and Lower Local Supply Development ◦ Increased imported water uncertainty, especially in dry years, coupled with factors that may slow the reduction in demands or the development of local projects. Presents an important upper boundary bracketing scenario.  Scenario C – Enhanced Local Resource Management ◦ Local supply development and demand management is the focus. Presents an important lower boundary bracketing scenario.  Scenario D – Adjusted Local Supply Development ◦ A limited achievement level (50%) of local supply development and demand management. Presents a scenario positioned between Scenarios A and C. 22
  • 23. Master Plan Analysis Scenarios Alternatives Existing Scenario Aqueduct A System Alt 1 Imported Water Scenario Strategy B Model Results Deterministic and Alt 2 Stochastic Max Seawater Desalination Scenario C Alt 3 Max Storage Operations Scenario Alt 4 D Balanced Supply Option 23
  • 24. System capacity  Supply reliability  Costs of capital improvement program  Environmental impacts  Energy use and production optimization  Supports WA diversification goals  Improves water quality  Feasibility  Minimizes rate impacts  Maximizes use of existing facilities 24
  • 25. Scenario B1 Higher demands, slow member agency supply development or conservation measures Scenario B2 Scenario D Scenario A2 Adaptive Process  Monitoring Scenario A1 metrics Early Actions Mainline demand projections,  Implementation verifiable member agency projects and conservation timelines and phasing Today Scenario C  Risk-based and Slower growth in demands, more rapid adaptive member agency supply development or decision-making conservation measures Decision Timelines Near-Term Actions Long-Term Actions Mid-Term Actions 25
  • 26. With the 2010 UWMP expected demand forecasts and normal or wet cycle hydrology shortages are minimal  Carlsbad desalination production is important in managing shortages in all hydrological cycles  If demands exceed UWMP expected demand forecasts, developing local or imported supplies is important for continued reliability  In dry years - greater vulnerably until QSA supplies are ramped up  Pipeline 6 appears to be beyond the 2035 planning horizon 26
  • 27. Feb 2012: Board workshop  Spring 2012: Second board workshop  Summer 2012: Release draft report to member agencies  Oct 2012: Release Draft Program EIR  Mar 2013: Board Certify Program EIR and Accept Final Master Plan Update 27
  • 28. Master Climate Plan Action Plan 28
  • 29. ‣ Inventory GHG sources (facilities, buildings, fleet) ‣ Estimate emission changes over time, including new facilities from Master Plan ‣ Identify mitigation actions to reduce GHGs ‣ Document GHG reduction feasibility and implementation ‣ Serve as significance thresholds for future actions ‣ Allow for periodic updates 29
  • 30. ‣ Global Warming Solutions Act (AB 32) ‣ Requires GHG emission reductions o 1990 levels by 2020 o 80% below 1990 levels by 2050 ‣ CEQA Guideline Revisions (SB 97) ‣ Requires analysis of GHG emissions ‣ Provides comprehensive approach through development of GHG emission reduction plan (Climate Action Plan) ‣ Water Authority not required to comply with AB32 ‣ Cannot hinder the State from achieving the goals ‣ Must make CEQA determination on GHG emissions 30
  • 31. ‣ CEQA streamlining for future projects ‣ Can look at the “big” picture through comprehensive analysis of cumulative impacts ‣ Provides broad list of mitigation measures ‣ Possible cost savings through energy efficiency and water conservation ‣ Contributes to regional sustainability goals ‣ Demonstrates leadership within the community 31
  • 32. Program EIR Master Climate Plan Action Plan 32
  • 33. ‣ Provide Board, agencies, and public with: o Comprehensive environmental analysis of Master Plan o Opportunity for input into the decision-making process ‣ Develop program-wide mitigation measures to reduce or eliminate potential impacts ‣ Assist Water Authority and other agencies in determining future CEQA documents that may be needed to implement future project components ‣ Serve as starting point for future site- specific environmental findings 33
  • 34. Feb 2012: Board workshop  Spring 2012: Second board workshop  Summer 2012: Release draft report to member agencies  Oct 2012: Release Draft Program EIR  Mar 2013: Board Certify Program EIR and Accept Final Master Plan Update 34