What Are The Drone Anti-jamming Systems Technology?
Wp mp-update-camp pendleton.-april_25_2013
1. Report on Evaluation of
Proposed Camp Pendleton
Seawater Desalination Project
Water Planning Committee
APRIL 25, 2013
Cesar Lopez
Senior Water Resources Specialist
2. Presentation Outline
Background
Report on latest planning and technical
studies
Off-Shore Technical Studies
Site Development Evaluations
Product Water Conveyance Analyses
Preliminary Cost Estimates
2
3. Proposed Desalination Project
• 50 - 150 mgd seawater RO Project
• Phased implementation
• Unique, large coastal site at top of
Aqueduct system
• 2 potential sites approved by the
Base for further study
• Unlike Carlsbad, project would
require new seawater intake and
discharge facilities
3
4. Potential Project Benefits to Camp Pendleton
• RELIABILITY
– Drought-proof water supply located on the base
• WATER QUALITY
– High quality product water
– Potential blending opportunity
• OCEAN OUTFALL
– Potential for dual-use outfall for treated wastewater and concentrate
from desalination plant
4
5. Project Background
• Conceptual feasibility study completed
• Board added additional technical and environmental studies to CIP
in 2009
• Planning MOU between SDCWA and MCBCP executed in 2010
established framework for cooperation during performance of
studies
• Consultant contracts executed in 2011 for:
• Technical Studies – Issues and impacts of offshore facilities
• Site Development Evaluations – Plant and onshore infrastructure
• Product Water Conveyance System Analyses
5
6. Technical Studies Objectives
Intakes:
• Determine viability of subsurface intake
• Permitting agencies will require evaluation of alternative intake
methods
• Considered to have least impact to marine life
• Locate and configure open ocean intake
• Can be designed to minimize marine impacts
Brine Discharge:
• Locate and configure discharge system
• Minimize marine impacts
6
7. Technical Studies - Geologic / Hydrogeologic
Investigations
• Conducted Geophysical Survey using seismic reflection
• Drilled exploratory boreholes
• Constructed test well and pump tested offshore aquifer
• Built Groundwater
Model
Key Findings:
• Large sub-seafloor ancient river channel
• Potential favorable geology to support
large subsurface intake system
7
8. Technical Studies - Marine Environment
Investigations
• Physical Oceanography
– Ocean currents
– Wave pressure
• Water Quality Monitoring and Sampling
– Temperature
– Salinity
– Boron / Bromide
– Etc.
• Marine Biology Monitoring and Sampling
– Ichthyoplankton (larvae)
– Phytoplankton (algae)
– Demersal Species (fish)
– Infauna Invertebrate (sea-floor habitants)
Key Findings:
• Typical marine environment –
nothing unusual
• No fatal flaws to siting open
ocean intake and discharge
8
9. • Ancient river channel provides favorable
geology for developing a sub-surface intake
• Open ocean intakes are feasible with low and
manageable marine environment impacts
• Potential lower cost
• Oceanographic conditions (i.e. ocean currents,
wave action) and marine habitat in project area
are favorable for siting a brine discharge
diffuser system at approx. 40 ft. depth
• Geotechnical conditions are suitable for soft-
ground tunnel construction
Technical Studies – Key Conclusions
9
12. Site Development Evaluations Objectives
• Analyze site access, traffic flow, space availability and security
• Determine optimal and reliable treatment processes for project
• For maximum utilization, consider producing “untreated” water
• Determine power requirements, supply source and transmission
• Screened
Open Ocean
• Subsurface
Prepare water for
desalination process
• Conventional or
membrane process
• Desalination
Process
• Re-hardening
• Disinfection
Residual
• Treated Water System
• Untreated Water System
Pre-
treatment
Intake
System
Reverse
Osmosis
Post
Treatment
Key Treatment Process Design Elements
12
15. • Both sites are viable for construction and operation
• SRTTP Site offers the best site access
• “Untreated” water production possible
• Maximum plant utilization
• Eliminates any potential overlap with treatment plant production
• Increased cost of “re-treatment”
• Cost savings likely due to reduced chemical requirements and potential
elimination of second pass RO
• Phase 1 (50 mgd) project can be supported by existing power supply
infrastructure.
• Future phases would require new power supply infrastructure ($91 - $164 million)
Site Evaluations – Key Conclusions
15
17. Product Water Conveyance
Key Conclusions
• The southern alignment provides the best opportunity for efficient
integration into the Water Authority Aqueduct system
• Shorter alignment
• Best alignment for both untreated and treated water integration
• least direct impact to MCBCP
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
Elevation(ft)
Length (ft)
Pipeline Reach
HGL of Pipeline 4
EL 1242
150 MGD – EL 1300
100 MGD – EL 1272
50 MGD – EL 1254
2A 2B 2C 2D 2E 2F 2G
Proposed Forebay and
Pump Station
EL 650Proposed Desalination
Facilities and Pump
Station
EL 60
150 MGD – EL 892
100 MGD – EL 767
50 MGD – EL 686
Ground Profile
17
18. Capital Cost Summary
50 mgd Initial Phase
Plant
Site
Seawater
Intake
Desalination
Plant
Brine
Discharge
Conveyance
System
Total
MCTSSA $218 - $360 $670 - $698 $184 $328 $1,428 - $1,542
SRTTP $241 - $369 $636 - $663 $207 $317 $1,429 - $1,529
Based on supply integration into the untreated system.
Costs include oversizing buried project components for the 150 mgd ultimate capacity.
Costs in million $
18