Introduction
This information sheet is aimed at those responsible
for selecting, specifying and managing mobile
elevating work platforms (MEWPs) on site and should
be read alongside Preventing falls from boom­type
mobile elevating work platforms.1
It tells you what you should consider before selecting
a MEWP to gain access to work at height and the risks
that need to be managed while the MEWP is in use.
All types of MEWPs are covered by this guidance,
including ones that are:
■	
■	
■	
■	

vertical ‘scissor’ lift;
self­propelled boom;
vehicle­mounted boom; and
trailer­mounted boom.

This information sheet has been produced in
consultation with the International Powered Access
Federation Ltd (IPAF), the Construction Plant­hire
Association and the British Constructional Steelwork
Association.

What the law requires
The Work at Height Regulations 2005 require an
assessment to be carried out before starting any work
at height. If the assessment says that the work can be
carried out in a way that avoids having someone
working at height then this must be done.

Construction Information Sheet No 58

The Provision and Use of Work Equipment
Regulations 1998 (PUWER) require the risks from
using equipment at work to be prevented or controlled
and Part III of PUWER specifically focuses on
minimising the overturning risks associated with
mobile work equipment such as MEWPs. This is
particularly relevant when considering the ground
conditions that the MEWP will cross and be used on,
and how it will be used, eg to install long or heavy
materials.
The Lifting Operations and Lifting Equipment
Regulations 1998 (LOLER) require that any equipment
used for lifting or lowering loads or people should have
been designed to a recognised standard and
thoroughly examined at regular intervals thereafter.

Assessing the risk
MEWPs are increasingly being used as temporary
working platforms that provide a safe place of work at
height. In relation to the fall protection hierarchy, they are
considered to be work equipment that prevents a fall.
It is important for employers and others responsible for
selecting, specifying and managing MEWPs on site to
understand the risks associated with the use of a
MEWP and take adequate precautions to eliminate or
control those risks. Planning is crucial to their safe
operation and the stages below are designed to help
you with your planning.

Selection criteria
However, if the assessment confirms that there is no
alternative to working at height then the work must be
properly planned and organised in advance by a
competent person to make sure that the most suitable
work equipment is chosen, taking into account the
nature of the work.
When choosing the most suitable work equipment,
you must follow the fall protection hierarchy. This
states the order in which protective measures should
be taken to prevent and mitigate the risks where you
cannot avoid working at height.2

There are several different types of MEWP with various
rated capacities, working heights and outreaches.
Before you decide which type of MEWP is the most
suitable for the job, think about the following (this list is
not exhaustive):
■	 What work needs to be done?
■	 Who is going to operate the MEWP?
■	 At what stage in the job will the MEWP be needed

and what will the ground conditions be like at that
1 of 6 pages
Health and Safety
Executive

■	
■	
■	

■	

■	
■	
■	
■	
■	
■	
■	
■	

■	
■	

stage (ie rough, prepared, poured slab, finished
surface etc)?
What access is there to the site?
How much base area is available at the work
position?
What terrain and gradient will the MEWP have to
cross to get to the work position and is visibility
and segregation adequate for the manoeuvre?
What is the maximum ground bearing capacity at
the work area and along the route to and from the
work positions?
How many people need to be lifted?
What height/outreach is required?
Will the MEWP be expected to move in the
elevated position?
Are there any overhead power lines on site?
Are there likely to be any overhead structures
which the operator could be crushed against?
Are there any materials to be lifted and if so how
heavy/long are they?
Are there any manual handling issues?
What interface is there with other vehicles and
pedestrians and are there any unusual issues, eg
aircraft or rail traffic?
What fuel type is allowed on site and where will
refuelling take place?
What wind loads can be expected?

parking position and the brakes applied. If it has to be
parked on a gradient, the wheels should be chocked.
When not in use, all keys should be removed from the
MEWP to make sure it cannot be used by
unauthorised persons. Alternatively, the MEWP can be
isolated using a security keypad with a designated PIN
number.
Positioning before and during work
■	 What type of ground will the MEWP have to travel

■	

■	

■	

Thinking about the points above should help you to
select the most suitable MEWP for the job.
■	

Managing the risk
Once you have chosen the most suitable type and
size of MEWP for the job you need to look at the
hazards associated with using it, assess the risks and
identify control measures to develop a safe working
method. The following areas should be considered:
Transport and delivery to site
Think about what size of delivery vehicle or vehicle­
mounted MEWP will need access to site or whether a
self­propelled MEWP will have to be offloaded on the
public highway:
■	 What time of day will be most appropriate and

what additional measures will be required?

across before reaching its work position, eg hard,
firm, soft, sloping, uneven terrain, soft spots,
subterranean hazards (such as tanks, cellars and
culverts, inspection covers, sewers and service
trenches), paved areas, footpaths, waterlogged
areas, frozen ground etc?
What is the ground bearing capacity at the work
position and along the route to and from it? Is
there enough space for the outriggers to be
deployed and what is the maximum point load
(under a wheel, outrigger or jack pad)? Are
spreader plates required?
Will the MEWP have to pass beneath any
overhead power lines? If so is there enough
clearance and has the area been demarcated?
Will the MEWP have to be lifted into position by
crane? Are the MEWP lifting points well indicated
and is the weight known?
Will the MEWP have to operate on elevated floor
slabs? Has the risk of the MEWP running off the
edge of an elevated floor slab been considered?
How will the risk be controlled?

Handling materials
If MEWPs are to be used directly to install materials, it
is essential to know the weight and dimensions of
those materials and to properly consider any manual
handling and load distribution issues.
Boom­type MEWPs generally have smaller baskets
and lower lift capacities than scissor­type MEWPs and
their platforms can ‘bounce’ at height due to the
boom structure flexing. This usually makes them
unsuitable to use for installing long or heavy materials,
or bulky materials that may obstruct the function
controls.

■	 Will the MEWP need to be reversed off the carrier

or, if vehicle­mounted, reversed onto site? What
size turning circle will be needed?
Storage/charging area
Wherever possible, keep MEWPs in a secure
compound or in a designated area with the engine or
motor switched off, the working platform lowered to its

In these cases, consider using a scissor lift, crane or a
telehandler of appropriate capacity in conjunction with
an appropriate material handling attachment where
necessary. This combination reduces the risk of
overturning, removes the need to balance materials on
the MEWP’s handrails and minimises the risk of injury
due to manual handling.

2 of 6 pages
Health and Safety
Executive

Figure 1

If you plan the work properly the need for outreach
may be avoided by, for example, preparing or
reinstating the ground conditions in the area directly
beneath planned overhead work or by adjusting the
work schedule to delay the construction of low­level
structures until work overhead has been completed.
Hazards during use
Look out for localised ground features, such as
trenches, manholes and uncompacted backfill, which
could lead to overturning?
If operating on a pre­cast concrete slab, check the
slab loading limits and how this compares with the
maximum weight of the MEWP. Has enough time been
allowed for the concrete to cure? What measures are
in place to stop the MEWP running off the edge of the
slab onto soft ground?
Think about wet, cold and windy weather:
■	 What is the manufacturer’s maximum wind speed

in which the MEWP can operate safely?
■	 How will the wind speed be checked (usually with

an anemometer) and by whom?
■	 Is the MEWP being operated between buildings

can be a particular problem?
■	 What about the potential for wind chill, which can

affect the operator’s dexterity and concentration?
On some MEWPs fitted with proportional controls
there can be an element of ‘run­on’ when the controls
are released. This is designed to create a smoother
operation but can mean that the MEWP continues to
move after the controls have been released. Therefore
particular care must be taken when working close to
overhead structures to avoid the risk crushing.
If there are overhead structures against which an
operator could be trapped and then pushed onto the
MEWP controls causing sustained involuntary
operation of the platform, consider selecting a MEWP
which has been designed to prevent such accidental
contact with the controls. MEWPs with shrouded or
otherwise protected controls are available.
Extra care must be taken if MEWPs are used to
manoeuvre up through several levels of steelwork as
there is a risk of the operator being trapped should the
boom or basket strike the steelwork. This risk
increases with the number of levels the MEWP
operates through and if materials are loaded out onto
the lower levels which can reduce clearance.

where increased wind speed and/or turbulence
3 of 6 pages
Health and Safety
Executive

Manoeuvring the basket with the operator crouched
over the control panel to try to avoid overhead
obstructions is dangerous and should not be done.
Is there a risk of trapping other workers between the
counterweight and an adjacent structure during
slewing?
Look for any overhead hazards such as power lines,
pipe bridges, arches or trees.
Think about how the MEWP interacts with other site
traffic and personnel:
■	 Does the operator have limited visibility, particularly

during reversing?
■	 What is required in terms of vehicle route signage,

pedestrian segregation barriers, cones, crossings
etc?
■	 Does any part of the MEWP protrude out of the
confines of the site?
■	 Are people below protected from the risk of falling
objects?
■	 When working in an area used by other workers or
vehicles, the entire MEWP work area (based on
reach distances and not just base structure
footprint) should be barricaded using cones and
warning signs etc.
Maintenance
The trained operator is responsible for carrying out a
basic daily/pre­use inspection and function check and
records of these checks should be kept.
The operator should also be fully aware of the
procedure you expect to be followed should they
identify a fault with the MEWP, ie isolate the controls,
tag the machine and report the defect to the person in
control.
You should request a copy of the maintenance records
as evidence that the MEWP and any related materials
handling attachments that are going to be used on
your site have been properly maintained.
Thorough examination
MEWPs, and any material handling attachments, must
be thoroughly examined at least every six months by a
competent person or in accordance with an
examination scheme drawn up by such a competent
person. You should ask to see and retain the report of
the thorough examination for the equipment you are
going to allow to be used on your site. If the report
shows any defects seek confirmation from the supplier
that they have been remedied.

Figure 2

Operator training and certification
All MEWP operators should have attended a
recognised operator training course. On successful
completion of the course they will receive a certificate,
card or ‘licence’, eg IPAF’s Powered Access Licence
(PAL) or Construction Skills’ CPCS card, which clearly
identifies the bearer and lists the categories of MEWP
they are trained to operate. This document can be
updated as the operator undergoes further training.
You should check the expiry date of the training
licence or card.
Operators using material handling attachments should
have received additional training in accordance with
the attachment manufacturer’s recommendations.
Familiarisation
Before being authorised to operate a particular make
or model of MEWP, the operator should be familiarised
with it by a competent person. Familiarisation should
follow on from basic training and should cover:
■	 manufacturer’s warnings and safety instructions;
■	 the control functions specific to the particular

MEWP;
■	 the function of each safety device specific to the

particular MEWP;
■	 operating limitations such as limiting wind speed,

wheel and outrigger loadings, set up requirements,
maximum operating slope etc;
■	 emergency lowering procedures;

4 of 6 pages
Health and Safety
Executive

■	 safe working loads or load charts;
■	 the maximum number of people who can be

changes in site access, ground conditions, the task to
be carried out, the weather conditions etc.

carried; and
■	 the maximum safe operating speed.

All of the above can be found in the information
supplied with the machine.
On completion of their familiarisation, the operator
should know whether or not that particular MEWP is
designed for the operator to travel on with the work
platform in the elevated position and whether or not
the controls are protected to prevent accidental
contact with the operator’s torso.
It is important that you allow enough time for your
operator to check, inspect, function test and
familiarise themself with every new MEWP.
All familiarisations should be recorded.
Personal protective equipment
One of the biggest risks in using boom­type platforms
is being thrown out of the basket if the boom swings,
jolts or tilts away from the machine’s centre of gravity,
or if the operator overreaches (usually by standing on
the guard rails). Precautions are described elsewhere
in this guidance to minimise the chances of this
happening but any risk assessment must still consider
the use of personal fall protection equipment. This is
covered in more detail in Preventing falls from boom­
type mobile elevating work platforms.1
A hard hat with chinstrap and cold/wet weather high­
visibility clothing should also be worn.

Make a record of who has been briefed and issued
with the plan.
Tell those involved in the work to report any problems
with the plan immediately. Should they need to deviate
from the plan, this should be agreed with the
competent person before any changes are made.

Further reading and references
1 Preventing falls from boom­type mobile elevating
work platforms Information Sheet MISC614 HSE
Books 2003 www.hse.gov.uk/pubns/misc614.pdf
2 The Work at Height Regulations 2005 (as
amended): A brief guide Leaflet INDG401(rev1) HSE
Books 2007 (single copy free or priced packs of 10
ISBN 978 0 7176 6231 9)
www.hse.gov.uk/pubns/indg401.pdf
Inspecting fall arrest equipment made from webbing or
rope Leaflet INDG367 HSE Books 2002 (single copy
free or priced packs of 10 ISBN 978 0 7176 2552 9)
www.hse.gov.uk/pubns/indg367.pdf
BS 8460:2005 Safe use of MEWPs. Code of Practice
British Standards Institution
Crane stability on site C703 (Second edition) CIRIA
2003 ISBN 978 0 86017 703 6
ISO 18878:2004 Mobile elevating work platforms.
Operator (driver) training British Standards Institution

Emergency and rescue procedure
The emergency and rescue plan should identify
trained, site­based personnel who would be available
to lower the work platform using the control panel or
emergency descent system situated at ground level.
These people should be included in the familiarisation
training for the specific machines being used on site.
The plan should also include the call­out details for the
service engineer or other person who is competent
and authorised to lower the work platform in the event
of an emergency.

Avoidance of danger from overhead electric
powerlines General Guidance Note GS6 (Third edition)
HSE Books 1997 ISBN 978 0 7176 1348 9
Managing health and safety in construction.
Construction (Design and Management) Regulations
2007. Approved Code of Practice L144 HSE Books
2007 ISBN 978 0 7176 6223 4
Management of health and safety at
work. Management of Health and Safety at Work
Regulations 1999. Approved Code of Practice and
guidance L21 (Second edition) HSE Books 2000
ISBN 978 0 7176 2488 1

Documenting what you have done
The next stage is to record the planning and
communicate it to all those involved with the work.

Safe use of work equipment. Provision and Use of
Work Equipment Regulations 1998. Approved Code of
Practice and guidance L22 (Third edition) HSE Books
2008 ISBN 978 0 7176 6295 1

Before work starts the plan should be reviewed to
allow for any changes in circumstances, such as
5 of 6 pages
Health and Safety
Executive

Safe use of lifting equipment. Lifting Operations and
Lifting Equipment Regulations 1998. Approved Code
of Practice and guidance L113 HSE Books 1998
ISBN 978 0 7176 1628 2
Manual handling. Manual Handling Operations
Regulations 1992 (as amended). Guidance on
Regulations L23 (Third edition) HSE Books 2004
ISBN 978 0 7176 2823 0
Safety harnesses in mobile elevating work platforms
Technical Guidance Note H1 IPAF 2005
Familiarisation of MEWPs Technical Guidance Note F1
IPAF 2007

Further information
HSE priced and free publications are available by mail
order from HSE Books, PO Box 1999, Sudbury,
Suffolk CO10 2WA Tel: 01787 881165 Fax: 01787
313995 Website: www.hsebooks.co.uk (HSE priced
publications are also available from bookshops and
free leaflets can be downloaded from HSE’s website:
www.hse.gov.uk.)
For information about health and safety ring HSE’s
Infoline Tel: 0845 345 0055 Fax: 0845 408 9566
Textphone: 0845 408 9577 e­mail:
hse.infoline@natbrit.com or write to HSE Information
Services, Caerphilly Business Park, Caerphilly CF83 3GG.
British Standards are available from BSI Customer
Services, 389 Chiswick High Road, London W4 4AL
Tel: 020 8996 9001 Fax: 020 8996 7001 e­mail:
cservices@bsi­global.com Website: www.bsi­global.com
This leaflet contains notes on good practice which
are not compulsory but which you may find helpful
in considering what you need to do.
© Crown copyright This publication may be freely
reproduced, except for advertising, endorsement or
commercial purposes. First published 08/08. Please
acknowledge the source as HSE.

Printed and published by the Health and Safety Executive

CIS58

08/08

C250

6 of 6 pages

Contenu connexe

Tendances (18)

Assessing facilities
Assessing facilitiesAssessing facilities
Assessing facilities
 
Aerial Lift Training by EHSDB
Aerial Lift Training by EHSDBAerial Lift Training by EHSDB
Aerial Lift Training by EHSDB
 
Ergonomic lifting and handling
Ergonomic lifting and handling Ergonomic lifting and handling
Ergonomic lifting and handling
 
Aerial and scissor lift safety 2
Aerial and scissor lift safety 2Aerial and scissor lift safety 2
Aerial and scissor lift safety 2
 
Youngman India presentation safe work at height
Youngman India presentation safe work at heightYoungman India presentation safe work at height
Youngman India presentation safe work at height
 
Aerial Lifts Training by University of Wisconsin
Aerial Lifts Training by University of WisconsinAerial Lifts Training by University of Wisconsin
Aerial Lifts Training by University of Wisconsin
 
07 work at height
07 work at height07 work at height
07 work at height
 
Beware of Scaffolding Dangers on Construction Sites
Beware of Scaffolding Dangers on Construction SitesBeware of Scaffolding Dangers on Construction Sites
Beware of Scaffolding Dangers on Construction Sites
 
Forllift safety
Forllift safetyForllift safety
Forllift safety
 
Boom lift training
Boom lift trainingBoom lift training
Boom lift training
 
Aerial and scissor lift safety
Aerial and scissor lift safetyAerial and scissor lift safety
Aerial and scissor lift safety
 
working at height1
working at height1working at height1
working at height1
 
Safe Work at Heights by Queensland
Safe Work at Heights by QueenslandSafe Work at Heights by Queensland
Safe Work at Heights by Queensland
 
Expert Operator White Paper
Expert Operator White PaperExpert Operator White Paper
Expert Operator White Paper
 
Heavy equipments in construction
Heavy equipments in constructionHeavy equipments in construction
Heavy equipments in construction
 
Safety topics
Safety topicsSafety topics
Safety topics
 
Equipment Operation, Skid Loader
Equipment Operation, Skid LoaderEquipment Operation, Skid Loader
Equipment Operation, Skid Loader
 
Forklift Safety Methods
Forklift Safety MethodsForklift Safety Methods
Forklift Safety Methods
 

En vedette

Indg163five steps to risk assessment
Indg163five steps to risk assessmentIndg163five steps to risk assessment
Indg163five steps to risk assessmentwirethehouse
 
Presentazione realkasa
Presentazione realkasaPresentazione realkasa
Presentazione realkasaREALKASA
 
QUE HAGO- DA VINCI J.M.LOBERA ART COACHING
QUE HAGO- DA VINCI J.M.LOBERA ART COACHINGQUE HAGO- DA VINCI J.M.LOBERA ART COACHING
QUE HAGO- DA VINCI J.M.LOBERA ART COACHINGWhite Crow
 
Content Marketing in the Digital Age
Content Marketing in the Digital AgeContent Marketing in the Digital Age
Content Marketing in the Digital AgeZizzo Group
 
Prototipare in Axure - Milan UX Book Club workshop
Prototipare in Axure - Milan UX Book Club workshopPrototipare in Axure - Milan UX Book Club workshop
Prototipare in Axure - Milan UX Book Club workshopStefano Pedrioli
 
Modulo1 relaciones contexto y escuela
Modulo1 relaciones contexto y escuelaModulo1 relaciones contexto y escuela
Modulo1 relaciones contexto y escuelaSofiaEduInfantil2013
 
Como solucionar problemas informaticos
Como solucionar problemas informaticosComo solucionar problemas informaticos
Como solucionar problemas informaticosJhosf24
 
Llibret 25aniversari-ajmacorlleida
Llibret 25aniversari-ajmacorlleidaLlibret 25aniversari-ajmacorlleida
Llibret 25aniversari-ajmacorlleidaamandixfc
 
Ti cs nativos_e_inmigrantes_digitales_1
Ti cs nativos_e_inmigrantes_digitales_1Ti cs nativos_e_inmigrantes_digitales_1
Ti cs nativos_e_inmigrantes_digitales_1Juliana
 

En vedette (20)

Indg163five steps to risk assessment
Indg163five steps to risk assessmentIndg163five steps to risk assessment
Indg163five steps to risk assessment
 
Presentazione realkasa
Presentazione realkasaPresentazione realkasa
Presentazione realkasa
 
Poly vision board
Poly vision boardPoly vision board
Poly vision board
 
QUE HAGO- DA VINCI J.M.LOBERA ART COACHING
QUE HAGO- DA VINCI J.M.LOBERA ART COACHINGQUE HAGO- DA VINCI J.M.LOBERA ART COACHING
QUE HAGO- DA VINCI J.M.LOBERA ART COACHING
 
hjkl
hjklhjkl
hjkl
 
Content Marketing in the Digital Age
Content Marketing in the Digital AgeContent Marketing in the Digital Age
Content Marketing in the Digital Age
 
Prototipare in Axure - Milan UX Book Club workshop
Prototipare in Axure - Milan UX Book Club workshopPrototipare in Axure - Milan UX Book Club workshop
Prototipare in Axure - Milan UX Book Club workshop
 
The Mobile Retail Landscape
The Mobile Retail LandscapeThe Mobile Retail Landscape
The Mobile Retail Landscape
 
Snowman
SnowmanSnowman
Snowman
 
Anuario escolar
Anuario escolarAnuario escolar
Anuario escolar
 
Modulo1 relaciones contexto y escuela
Modulo1 relaciones contexto y escuelaModulo1 relaciones contexto y escuela
Modulo1 relaciones contexto y escuela
 
Comunicación corta
Comunicación cortaComunicación corta
Comunicación corta
 
100visita
100visita100visita
100visita
 
Artista favito
Artista favitoArtista favito
Artista favito
 
Como solucionar problemas informaticos
Como solucionar problemas informaticosComo solucionar problemas informaticos
Como solucionar problemas informaticos
 
Baeh m2 u3_a1
Baeh m2 u3_a1Baeh m2 u3_a1
Baeh m2 u3_a1
 
18 de julio
18 de julio18 de julio
18 de julio
 
Microprocesadores
MicroprocesadoresMicroprocesadores
Microprocesadores
 
Llibret 25aniversari-ajmacorlleida
Llibret 25aniversari-ajmacorlleidaLlibret 25aniversari-ajmacorlleida
Llibret 25aniversari-ajmacorlleida
 
Ti cs nativos_e_inmigrantes_digitales_1
Ti cs nativos_e_inmigrantes_digitales_1Ti cs nativos_e_inmigrantes_digitales_1
Ti cs nativos_e_inmigrantes_digitales_1
 

Similaire à Cis58

MEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptxMEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptxSyed Neyaz Ahmad
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationComplianceSigns, LLC
 
Crane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfCrane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfManoj Kumar
 
Get the right MEWP for the job
Get the right MEWP for the jobGet the right MEWP for the job
Get the right MEWP for the jobMECandPMV
 
Ruben urquidez
Ruben urquidezRuben urquidez
Ruben urquidezrujsd1
 
Reducing The Risk Of Falls From Tail Lifts
Reducing The Risk Of Falls From Tail LiftsReducing The Risk Of Falls From Tail Lifts
Reducing The Risk Of Falls From Tail LiftsAlan Bassett
 
How to Operate a Scissor Lift? - BVM Transport
How to Operate a Scissor Lift? - BVM TransportHow to Operate a Scissor Lift? - BVM Transport
How to Operate a Scissor Lift? - BVM TransportBVM Transport LLC
 
TS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.pptTS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.pptajith30276
 
Powered_Industrial_Trucks Training Module 30JAN2018.pptx
Powered_Industrial_Trucks Training Module 30JAN2018.pptxPowered_Industrial_Trucks Training Module 30JAN2018.pptx
Powered_Industrial_Trucks Training Module 30JAN2018.pptxFarizSafarulla1
 
Ruben urquidez
Ruben urquidezRuben urquidez
Ruben urquidezrujsd1
 
5 Forklift Hazardsto Eliminate from the Workplace - By Randstad
5 Forklift Hazardsto Eliminate from the Workplace - By Randstad5 Forklift Hazardsto Eliminate from the Workplace - By Randstad
5 Forklift Hazardsto Eliminate from the Workplace - By RandstadForklift Trucks in Minnesota
 
Mechanical Handling updated.ppt
Mechanical Handling updated.pptMechanical Handling updated.ppt
Mechanical Handling updated.pptCheDillon1
 
HSE Procedures Awareness Oil & Gas 27.09.2022.pptx
HSE Procedures Awareness Oil & Gas 27.09.2022.pptxHSE Procedures Awareness Oil & Gas 27.09.2022.pptx
HSE Procedures Awareness Oil & Gas 27.09.2022.pptxSyed Neyaz Ahmad
 
Sfpsg best-practice-guide-for-mew ps-100715-4a
Sfpsg best-practice-guide-for-mew ps-100715-4aSfpsg best-practice-guide-for-mew ps-100715-4a
Sfpsg best-practice-guide-for-mew ps-100715-4aAlan Bassett
 

Similaire à Cis58 (20)

MEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptxMEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptx
 
MEWP TRAINING.pptx
MEWP TRAINING.pptxMEWP TRAINING.pptx
MEWP TRAINING.pptx
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane Operation
 
Crane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfCrane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdf
 
Get the right MEWP for the job
Get the right MEWP for the jobGet the right MEWP for the job
Get the right MEWP for the job
 
Ruben urquidez
Ruben urquidezRuben urquidez
Ruben urquidez
 
Reducing The Risk Of Falls From Tail Lifts
Reducing The Risk Of Falls From Tail LiftsReducing The Risk Of Falls From Tail Lifts
Reducing The Risk Of Falls From Tail Lifts
 
arman1
arman1arman1
arman1
 
How to Operate a Scissor Lift? - BVM Transport
How to Operate a Scissor Lift? - BVM TransportHow to Operate a Scissor Lift? - BVM Transport
How to Operate a Scissor Lift? - BVM Transport
 
Overhead crane
Overhead crane Overhead crane
Overhead crane
 
E20815
E20815E20815
E20815
 
TS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.pptTS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.ppt
 
Powered_Industrial_Trucks Training Module 30JAN2018.pptx
Powered_Industrial_Trucks Training Module 30JAN2018.pptxPowered_Industrial_Trucks Training Module 30JAN2018.pptx
Powered_Industrial_Trucks Training Module 30JAN2018.pptx
 
Ruben urquidez
Ruben urquidezRuben urquidez
Ruben urquidez
 
Fork Lift Truck Association Safety 4MOST
Fork Lift Truck Association  Safety 4MOSTFork Lift Truck Association  Safety 4MOST
Fork Lift Truck Association Safety 4MOST
 
26.pdf
26.pdf26.pdf
26.pdf
 
5 Forklift Hazardsto Eliminate from the Workplace - By Randstad
5 Forklift Hazardsto Eliminate from the Workplace - By Randstad5 Forklift Hazardsto Eliminate from the Workplace - By Randstad
5 Forklift Hazardsto Eliminate from the Workplace - By Randstad
 
Mechanical Handling updated.ppt
Mechanical Handling updated.pptMechanical Handling updated.ppt
Mechanical Handling updated.ppt
 
HSE Procedures Awareness Oil & Gas 27.09.2022.pptx
HSE Procedures Awareness Oil & Gas 27.09.2022.pptxHSE Procedures Awareness Oil & Gas 27.09.2022.pptx
HSE Procedures Awareness Oil & Gas 27.09.2022.pptx
 
Sfpsg best-practice-guide-for-mew ps-100715-4a
Sfpsg best-practice-guide-for-mew ps-100715-4aSfpsg best-practice-guide-for-mew ps-100715-4a
Sfpsg best-practice-guide-for-mew ps-100715-4a
 

Plus de wirethehouse

Environmental ppt gshp ashp
Environmental ppt gshp ashpEnvironmental ppt gshp ashp
Environmental ppt gshp ashpwirethehouse
 
Br pdf ad_j_2010_v2
Br pdf ad_j_2010_v2Br pdf ad_j_2010_v2
Br pdf ad_j_2010_v2wirethehouse
 
Br pdf ad_g_2010_v2
Br pdf ad_g_2010_v2Br pdf ad_g_2010_v2
Br pdf ad_g_2010_v2wirethehouse
 
Br pdf ad_f_2010_v2
Br pdf ad_f_2010_v2Br pdf ad_f_2010_v2
Br pdf ad_f_2010_v2wirethehouse
 
Br pdf ad_l1_a_2010_v2
Br pdf ad_l1_a_2010_v2Br pdf ad_l1_a_2010_v2
Br pdf ad_l1_a_2010_v2wirethehouse
 
_rain_and_greywater
_rain_and_greywater_rain_and_greywater
_rain_and_greywaterwirethehouse
 
Environmental legislation powerpoint
Environmental legislation powerpointEnvironmental legislation powerpoint
Environmental legislation powerpointwirethehouse
 
Rain and Greywater
Rain and GreywaterRain and Greywater
Rain and Greywaterwirethehouse
 
Combine Heating and Power (chp)
Combine Heating and Power (chp)Combine Heating and Power (chp)
Combine Heating and Power (chp)wirethehouse
 
Streching questions pv
Streching questions pvStreching questions pv
Streching questions pvwirethehouse
 
Photovoltaic systems
Photovoltaic systemsPhotovoltaic systems
Photovoltaic systemswirethehouse
 
Air Source Heat Pumps
Air Source Heat PumpsAir Source Heat Pumps
Air Source Heat Pumpswirethehouse
 
Ground_Source Heat Pumps
Ground_Source Heat PumpsGround_Source Heat Pumps
Ground_Source Heat Pumpswirethehouse
 

Plus de wirethehouse (20)

Environmental ppt gshp ashp
Environmental ppt gshp ashpEnvironmental ppt gshp ashp
Environmental ppt gshp ashp
 
Br pdf ad_p_2013
Br pdf ad_p_2013Br pdf ad_p_2013
Br pdf ad_p_2013
 
Br pdf ad_j_2010_v2
Br pdf ad_j_2010_v2Br pdf ad_j_2010_v2
Br pdf ad_j_2010_v2
 
Br pdf ad_h_2010
Br pdf ad_h_2010Br pdf ad_h_2010
Br pdf ad_h_2010
 
Br pdf ad_g_2010_v2
Br pdf ad_g_2010_v2Br pdf ad_g_2010_v2
Br pdf ad_g_2010_v2
 
Br pdf ad_f_2010_v2
Br pdf ad_f_2010_v2Br pdf ad_f_2010_v2
Br pdf ad_f_2010_v2
 
Br pdf ad_l1_a_2010_v2
Br pdf ad_l1_a_2010_v2Br pdf ad_l1_a_2010_v2
Br pdf ad_l1_a_2010_v2
 
_rain_and_greywater
_rain_and_greywater_rain_and_greywater
_rain_and_greywater
 
Environmental legislation powerpoint
Environmental legislation powerpointEnvironmental legislation powerpoint
Environmental legislation powerpoint
 
Rain and Greywater
Rain and GreywaterRain and Greywater
Rain and Greywater
 
Hydro
HydroHydro
Hydro
 
Combine Heating and Power (chp)
Combine Heating and Power (chp)Combine Heating and Power (chp)
Combine Heating and Power (chp)
 
Wind Turbines
Wind Turbines Wind Turbines
Wind Turbines
 
Biomass
BiomassBiomass
Biomass
 
Streching questions pv
Streching questions pvStreching questions pv
Streching questions pv
 
PV worksheet 1
PV worksheet 1 PV worksheet 1
PV worksheet 1
 
Photovoltaic systems
Photovoltaic systemsPhotovoltaic systems
Photovoltaic systems
 
Air Source Heat Pumps
Air Source Heat PumpsAir Source Heat Pumps
Air Source Heat Pumps
 
Ground_Source Heat Pumps
Ground_Source Heat PumpsGround_Source Heat Pumps
Ground_Source Heat Pumps
 
Solar_Thermal
Solar_ThermalSolar_Thermal
Solar_Thermal
 

Dernier

How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...SOFTTECHHUB
 
How to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your BusinessHow to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your BusinessHelp Desk Migration
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
71368-80-4.pdf Fast delivery good quality
71368-80-4.pdf Fast delivery  good quality71368-80-4.pdf Fast delivery  good quality
71368-80-4.pdf Fast delivery good qualitycathy664059
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...PRnews2
 
Customizable Contents Restoration Training
Customizable Contents Restoration TrainingCustomizable Contents Restoration Training
Customizable Contents Restoration TrainingCalvinarnold843
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...ssuserf63bd7
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfDanny Diep To
 
Entrepreneurial ecosystem- Wider context
Entrepreneurial ecosystem- Wider contextEntrepreneurial ecosystem- Wider context
Entrepreneurial ecosystem- Wider contextP&CO
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
Data Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesData Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesAurelien Domont, MBA
 
Rakhi sets symbolizing the bond of love.pptx
Rakhi sets symbolizing the bond of love.pptxRakhi sets symbolizing the bond of love.pptx
Rakhi sets symbolizing the bond of love.pptxRakhi Bazaar
 
Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverseSiemens
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfJamesConcepcion7
 

Dernier (20)

How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
 
How to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your BusinessHow to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your Business
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
71368-80-4.pdf Fast delivery good quality
71368-80-4.pdf Fast delivery  good quality71368-80-4.pdf Fast delivery  good quality
71368-80-4.pdf Fast delivery good quality
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors Data
 
Authentically Social - presented by Corey Perlman
Authentically Social - presented by Corey PerlmanAuthentically Social - presented by Corey Perlman
Authentically Social - presented by Corey Perlman
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
 
Customizable Contents Restoration Training
Customizable Contents Restoration TrainingCustomizable Contents Restoration Training
Customizable Contents Restoration Training
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
 
Entrepreneurial ecosystem- Wider context
Entrepreneurial ecosystem- Wider contextEntrepreneurial ecosystem- Wider context
Entrepreneurial ecosystem- Wider context
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
Data Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesData Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and Templates
 
Rakhi sets symbolizing the bond of love.pptx
Rakhi sets symbolizing the bond of love.pptxRakhi sets symbolizing the bond of love.pptx
Rakhi sets symbolizing the bond of love.pptx
 
Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverse
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdf
 

Cis58

  • 1. Health and Safety Executive The selection and management of mobile elevating work platforms HSE information sheet Introduction This information sheet is aimed at those responsible for selecting, specifying and managing mobile elevating work platforms (MEWPs) on site and should be read alongside Preventing falls from boom­type mobile elevating work platforms.1 It tells you what you should consider before selecting a MEWP to gain access to work at height and the risks that need to be managed while the MEWP is in use. All types of MEWPs are covered by this guidance, including ones that are: ■ ■ ■ ■ vertical ‘scissor’ lift; self­propelled boom; vehicle­mounted boom; and trailer­mounted boom. This information sheet has been produced in consultation with the International Powered Access Federation Ltd (IPAF), the Construction Plant­hire Association and the British Constructional Steelwork Association. What the law requires The Work at Height Regulations 2005 require an assessment to be carried out before starting any work at height. If the assessment says that the work can be carried out in a way that avoids having someone working at height then this must be done. Construction Information Sheet No 58 The Provision and Use of Work Equipment Regulations 1998 (PUWER) require the risks from using equipment at work to be prevented or controlled and Part III of PUWER specifically focuses on minimising the overturning risks associated with mobile work equipment such as MEWPs. This is particularly relevant when considering the ground conditions that the MEWP will cross and be used on, and how it will be used, eg to install long or heavy materials. The Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) require that any equipment used for lifting or lowering loads or people should have been designed to a recognised standard and thoroughly examined at regular intervals thereafter. Assessing the risk MEWPs are increasingly being used as temporary working platforms that provide a safe place of work at height. In relation to the fall protection hierarchy, they are considered to be work equipment that prevents a fall. It is important for employers and others responsible for selecting, specifying and managing MEWPs on site to understand the risks associated with the use of a MEWP and take adequate precautions to eliminate or control those risks. Planning is crucial to their safe operation and the stages below are designed to help you with your planning. Selection criteria However, if the assessment confirms that there is no alternative to working at height then the work must be properly planned and organised in advance by a competent person to make sure that the most suitable work equipment is chosen, taking into account the nature of the work. When choosing the most suitable work equipment, you must follow the fall protection hierarchy. This states the order in which protective measures should be taken to prevent and mitigate the risks where you cannot avoid working at height.2 There are several different types of MEWP with various rated capacities, working heights and outreaches. Before you decide which type of MEWP is the most suitable for the job, think about the following (this list is not exhaustive): ■ What work needs to be done? ■ Who is going to operate the MEWP? ■ At what stage in the job will the MEWP be needed and what will the ground conditions be like at that 1 of 6 pages
  • 2. Health and Safety Executive ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ stage (ie rough, prepared, poured slab, finished surface etc)? What access is there to the site? How much base area is available at the work position? What terrain and gradient will the MEWP have to cross to get to the work position and is visibility and segregation adequate for the manoeuvre? What is the maximum ground bearing capacity at the work area and along the route to and from the work positions? How many people need to be lifted? What height/outreach is required? Will the MEWP be expected to move in the elevated position? Are there any overhead power lines on site? Are there likely to be any overhead structures which the operator could be crushed against? Are there any materials to be lifted and if so how heavy/long are they? Are there any manual handling issues? What interface is there with other vehicles and pedestrians and are there any unusual issues, eg aircraft or rail traffic? What fuel type is allowed on site and where will refuelling take place? What wind loads can be expected? parking position and the brakes applied. If it has to be parked on a gradient, the wheels should be chocked. When not in use, all keys should be removed from the MEWP to make sure it cannot be used by unauthorised persons. Alternatively, the MEWP can be isolated using a security keypad with a designated PIN number. Positioning before and during work ■ What type of ground will the MEWP have to travel ■ ■ ■ Thinking about the points above should help you to select the most suitable MEWP for the job. ■ Managing the risk Once you have chosen the most suitable type and size of MEWP for the job you need to look at the hazards associated with using it, assess the risks and identify control measures to develop a safe working method. The following areas should be considered: Transport and delivery to site Think about what size of delivery vehicle or vehicle­ mounted MEWP will need access to site or whether a self­propelled MEWP will have to be offloaded on the public highway: ■ What time of day will be most appropriate and what additional measures will be required? across before reaching its work position, eg hard, firm, soft, sloping, uneven terrain, soft spots, subterranean hazards (such as tanks, cellars and culverts, inspection covers, sewers and service trenches), paved areas, footpaths, waterlogged areas, frozen ground etc? What is the ground bearing capacity at the work position and along the route to and from it? Is there enough space for the outriggers to be deployed and what is the maximum point load (under a wheel, outrigger or jack pad)? Are spreader plates required? Will the MEWP have to pass beneath any overhead power lines? If so is there enough clearance and has the area been demarcated? Will the MEWP have to be lifted into position by crane? Are the MEWP lifting points well indicated and is the weight known? Will the MEWP have to operate on elevated floor slabs? Has the risk of the MEWP running off the edge of an elevated floor slab been considered? How will the risk be controlled? Handling materials If MEWPs are to be used directly to install materials, it is essential to know the weight and dimensions of those materials and to properly consider any manual handling and load distribution issues. Boom­type MEWPs generally have smaller baskets and lower lift capacities than scissor­type MEWPs and their platforms can ‘bounce’ at height due to the boom structure flexing. This usually makes them unsuitable to use for installing long or heavy materials, or bulky materials that may obstruct the function controls. ■ Will the MEWP need to be reversed off the carrier or, if vehicle­mounted, reversed onto site? What size turning circle will be needed? Storage/charging area Wherever possible, keep MEWPs in a secure compound or in a designated area with the engine or motor switched off, the working platform lowered to its In these cases, consider using a scissor lift, crane or a telehandler of appropriate capacity in conjunction with an appropriate material handling attachment where necessary. This combination reduces the risk of overturning, removes the need to balance materials on the MEWP’s handrails and minimises the risk of injury due to manual handling. 2 of 6 pages
  • 3. Health and Safety Executive Figure 1 If you plan the work properly the need for outreach may be avoided by, for example, preparing or reinstating the ground conditions in the area directly beneath planned overhead work or by adjusting the work schedule to delay the construction of low­level structures until work overhead has been completed. Hazards during use Look out for localised ground features, such as trenches, manholes and uncompacted backfill, which could lead to overturning? If operating on a pre­cast concrete slab, check the slab loading limits and how this compares with the maximum weight of the MEWP. Has enough time been allowed for the concrete to cure? What measures are in place to stop the MEWP running off the edge of the slab onto soft ground? Think about wet, cold and windy weather: ■ What is the manufacturer’s maximum wind speed in which the MEWP can operate safely? ■ How will the wind speed be checked (usually with an anemometer) and by whom? ■ Is the MEWP being operated between buildings can be a particular problem? ■ What about the potential for wind chill, which can affect the operator’s dexterity and concentration? On some MEWPs fitted with proportional controls there can be an element of ‘run­on’ when the controls are released. This is designed to create a smoother operation but can mean that the MEWP continues to move after the controls have been released. Therefore particular care must be taken when working close to overhead structures to avoid the risk crushing. If there are overhead structures against which an operator could be trapped and then pushed onto the MEWP controls causing sustained involuntary operation of the platform, consider selecting a MEWP which has been designed to prevent such accidental contact with the controls. MEWPs with shrouded or otherwise protected controls are available. Extra care must be taken if MEWPs are used to manoeuvre up through several levels of steelwork as there is a risk of the operator being trapped should the boom or basket strike the steelwork. This risk increases with the number of levels the MEWP operates through and if materials are loaded out onto the lower levels which can reduce clearance. where increased wind speed and/or turbulence 3 of 6 pages
  • 4. Health and Safety Executive Manoeuvring the basket with the operator crouched over the control panel to try to avoid overhead obstructions is dangerous and should not be done. Is there a risk of trapping other workers between the counterweight and an adjacent structure during slewing? Look for any overhead hazards such as power lines, pipe bridges, arches or trees. Think about how the MEWP interacts with other site traffic and personnel: ■ Does the operator have limited visibility, particularly during reversing? ■ What is required in terms of vehicle route signage, pedestrian segregation barriers, cones, crossings etc? ■ Does any part of the MEWP protrude out of the confines of the site? ■ Are people below protected from the risk of falling objects? ■ When working in an area used by other workers or vehicles, the entire MEWP work area (based on reach distances and not just base structure footprint) should be barricaded using cones and warning signs etc. Maintenance The trained operator is responsible for carrying out a basic daily/pre­use inspection and function check and records of these checks should be kept. The operator should also be fully aware of the procedure you expect to be followed should they identify a fault with the MEWP, ie isolate the controls, tag the machine and report the defect to the person in control. You should request a copy of the maintenance records as evidence that the MEWP and any related materials handling attachments that are going to be used on your site have been properly maintained. Thorough examination MEWPs, and any material handling attachments, must be thoroughly examined at least every six months by a competent person or in accordance with an examination scheme drawn up by such a competent person. You should ask to see and retain the report of the thorough examination for the equipment you are going to allow to be used on your site. If the report shows any defects seek confirmation from the supplier that they have been remedied. Figure 2 Operator training and certification All MEWP operators should have attended a recognised operator training course. On successful completion of the course they will receive a certificate, card or ‘licence’, eg IPAF’s Powered Access Licence (PAL) or Construction Skills’ CPCS card, which clearly identifies the bearer and lists the categories of MEWP they are trained to operate. This document can be updated as the operator undergoes further training. You should check the expiry date of the training licence or card. Operators using material handling attachments should have received additional training in accordance with the attachment manufacturer’s recommendations. Familiarisation Before being authorised to operate a particular make or model of MEWP, the operator should be familiarised with it by a competent person. Familiarisation should follow on from basic training and should cover: ■ manufacturer’s warnings and safety instructions; ■ the control functions specific to the particular MEWP; ■ the function of each safety device specific to the particular MEWP; ■ operating limitations such as limiting wind speed, wheel and outrigger loadings, set up requirements, maximum operating slope etc; ■ emergency lowering procedures; 4 of 6 pages
  • 5. Health and Safety Executive ■ safe working loads or load charts; ■ the maximum number of people who can be changes in site access, ground conditions, the task to be carried out, the weather conditions etc. carried; and ■ the maximum safe operating speed. All of the above can be found in the information supplied with the machine. On completion of their familiarisation, the operator should know whether or not that particular MEWP is designed for the operator to travel on with the work platform in the elevated position and whether or not the controls are protected to prevent accidental contact with the operator’s torso. It is important that you allow enough time for your operator to check, inspect, function test and familiarise themself with every new MEWP. All familiarisations should be recorded. Personal protective equipment One of the biggest risks in using boom­type platforms is being thrown out of the basket if the boom swings, jolts or tilts away from the machine’s centre of gravity, or if the operator overreaches (usually by standing on the guard rails). Precautions are described elsewhere in this guidance to minimise the chances of this happening but any risk assessment must still consider the use of personal fall protection equipment. This is covered in more detail in Preventing falls from boom­ type mobile elevating work platforms.1 A hard hat with chinstrap and cold/wet weather high­ visibility clothing should also be worn. Make a record of who has been briefed and issued with the plan. Tell those involved in the work to report any problems with the plan immediately. Should they need to deviate from the plan, this should be agreed with the competent person before any changes are made. Further reading and references 1 Preventing falls from boom­type mobile elevating work platforms Information Sheet MISC614 HSE Books 2003 www.hse.gov.uk/pubns/misc614.pdf 2 The Work at Height Regulations 2005 (as amended): A brief guide Leaflet INDG401(rev1) HSE Books 2007 (single copy free or priced packs of 10 ISBN 978 0 7176 6231 9) www.hse.gov.uk/pubns/indg401.pdf Inspecting fall arrest equipment made from webbing or rope Leaflet INDG367 HSE Books 2002 (single copy free or priced packs of 10 ISBN 978 0 7176 2552 9) www.hse.gov.uk/pubns/indg367.pdf BS 8460:2005 Safe use of MEWPs. Code of Practice British Standards Institution Crane stability on site C703 (Second edition) CIRIA 2003 ISBN 978 0 86017 703 6 ISO 18878:2004 Mobile elevating work platforms. Operator (driver) training British Standards Institution Emergency and rescue procedure The emergency and rescue plan should identify trained, site­based personnel who would be available to lower the work platform using the control panel or emergency descent system situated at ground level. These people should be included in the familiarisation training for the specific machines being used on site. The plan should also include the call­out details for the service engineer or other person who is competent and authorised to lower the work platform in the event of an emergency. Avoidance of danger from overhead electric powerlines General Guidance Note GS6 (Third edition) HSE Books 1997 ISBN 978 0 7176 1348 9 Managing health and safety in construction. Construction (Design and Management) Regulations 2007. Approved Code of Practice L144 HSE Books 2007 ISBN 978 0 7176 6223 4 Management of health and safety at work. Management of Health and Safety at Work Regulations 1999. Approved Code of Practice and guidance L21 (Second edition) HSE Books 2000 ISBN 978 0 7176 2488 1 Documenting what you have done The next stage is to record the planning and communicate it to all those involved with the work. Safe use of work equipment. Provision and Use of Work Equipment Regulations 1998. Approved Code of Practice and guidance L22 (Third edition) HSE Books 2008 ISBN 978 0 7176 6295 1 Before work starts the plan should be reviewed to allow for any changes in circumstances, such as 5 of 6 pages
  • 6. Health and Safety Executive Safe use of lifting equipment. Lifting Operations and Lifting Equipment Regulations 1998. Approved Code of Practice and guidance L113 HSE Books 1998 ISBN 978 0 7176 1628 2 Manual handling. Manual Handling Operations Regulations 1992 (as amended). Guidance on Regulations L23 (Third edition) HSE Books 2004 ISBN 978 0 7176 2823 0 Safety harnesses in mobile elevating work platforms Technical Guidance Note H1 IPAF 2005 Familiarisation of MEWPs Technical Guidance Note F1 IPAF 2007 Further information HSE priced and free publications are available by mail order from HSE Books, PO Box 1999, Sudbury, Suffolk CO10 2WA Tel: 01787 881165 Fax: 01787 313995 Website: www.hsebooks.co.uk (HSE priced publications are also available from bookshops and free leaflets can be downloaded from HSE’s website: www.hse.gov.uk.) For information about health and safety ring HSE’s Infoline Tel: 0845 345 0055 Fax: 0845 408 9566 Textphone: 0845 408 9577 e­mail: hse.infoline@natbrit.com or write to HSE Information Services, Caerphilly Business Park, Caerphilly CF83 3GG. British Standards are available from BSI Customer Services, 389 Chiswick High Road, London W4 4AL Tel: 020 8996 9001 Fax: 020 8996 7001 e­mail: cservices@bsi­global.com Website: www.bsi­global.com This leaflet contains notes on good practice which are not compulsory but which you may find helpful in considering what you need to do. © Crown copyright This publication may be freely reproduced, except for advertising, endorsement or commercial purposes. First published 08/08. Please acknowledge the source as HSE. Printed and published by the Health and Safety Executive CIS58 08/08 C250 6 of 6 pages