SlideShare une entreprise Scribd logo
1  sur  21
SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONOURS)

QSB1524 – Construction Technology II
Scaffolding
August Semester 2013
Construction Technology II Report
Submission Date: 6thDecember 2013

Name

StudentID

Yam Yih Hwan

0305861

Low Rong Tzuoo

0304924

Janice Kong Yin Ying

0308798

Harvey Yap Zhu Guang

0309325

Wong Ha Shiong

0309640

Construction Technology II - Report

1
Table of Content

Page

Cover Page

1

Table of Content

2

Introduction

3

Objective

4

Methodology of Scaffolding

5-7

Safety Precautions

8 - 11

Material Used in Scaffolding

12 - 14

Suitability of Usage

15 - 18

Conclusion

19

References

20 - 21

Construction Technology II - Report

2
Introduction
On 26thSeptember 2013, along with my group mates, we went for a site visit in a
construction site located at SS16, Subang Jaya. It is somewhere nearby the Subang Jaya
Komuter Station. In this project, the main contractor is KP Synergies Berhad – Transgrid
Ventures Sdn. Bhd. (Consortium), and the sub-contractor is Bintang Puspa. Once the
construction work is done, it will be passed over to TNB, even the contractors/employees are
restricted to enter the land, unless with permission.
The size of the land is roughly around 5 acres, 20234.3m2, and a combination of two lots.
It was then merged together for the construction of the TNB building. The purpose of the land is
to build the Subang Jaya Tower Center (Live Station), also known as ―Pencawang Masuk
Utama‖. It is a 2 years contract, estimated to complete on 20th October 2014 including the
engineering, construction & commissioning works. For your information, the total amount spend
is RM 130 million, and RM 17 million only on the construction and civil structure. Once the
building is completed, it will be around 5m high all the way to the roof of the tower.
Firstly, they clear off the site in order to make platforms for the piling machine to enter the
site. Piling must be done in flat ground. Then, they excavate vary from the size of the loading,
particular pile group thickness. Excavation level is depending on the size of the pile cap, the
depth/width/length of the pile cap = volume (m3). The higher the loadings, it requires bigger size
pile caps & deep excavation. As for smaller loadings, it only requires smaller size pile caps
&swallow excavation. Pile is around 300mm2 deep into the ground, using reinforced pre-cast
concrete piles 45mm thick.
Moreover, total numbers of 5 transformers is placed under the building with the depth of
1.5m. On the left side, it contains three 240 MVA (megavolt) transformers. And on the right side,
it contains two 90 MVA (megavolt) transformers. Each one of the transformer contains of 87
thousand liters of transformer oil. Furthermore, returning walls are built at the sides of the lower
ground; it is required to raise up the platform for the construction of walls, and then backfill it.
This project is a conventional construction; it does not use any system formwork or any
special plan off construction metrology. The only precast unit used is precast piles, because it is
cheaper as compared to in-situ casting.

Construction Technology II - Report

3
Objective

 To help us get a more understanding on the basics of construction process while
paying a visit to the site.
 Let us experience the actual working environment as a Quantity Surveyor on site
dealing with uncertain circumstances such as the weather condition and the risks
that may take place on the site.
 Let us aware of the importance of personal safety on site, and the safety
precautions that we need to take in order to avoid accidents from happening. For
instance, we are required to wear safety helmet on site.
 Increase our knowledge on the basic construction process by observing the
building team and gathering information on the actual practice that carried on the
site.
 Explore and identify various types of building materials and type of technology
used in construction while constructing a building.

Construction Technology II - Report

4
Methodology of Scaffolding

Scaffolding is a structure or framework that is temporarily used to support loads of
humans and materials during a construction process. It is also used to ease the accessibility of a
person going from one floor to another and provides a safe working space at an elevated height.
Scaffolding system normally uses metal tubes or metal pipes to connect with each other and it
can also be from other materials besides metal. For example, bamboo, that is widely used in
Asia. Scaffolding is normally used when the working level is 1.5 m above the ground.

Structural elements of scaffolding
The basic elements of a scaffold are the three components such as: standards, ledgers
and transoms. The standards, also known as uprights, are the vertical long pipe or tube that
transfers the loading mass of the structure to the ground where they rest on a square base plate
for the spreading of the load. There is a shank in the centre of the base plate to hold the tube
and sometimes it is pinned to a sole board. In between each standard, the component that runs
horizontally is called ledger. It adds further support and weight distribution to the whole structure.
There is also a component called transom, which are placed upon the ledgers at right angles.
Main transoms are placed next to the standards and they hold the standards in place to provide
support for boards. Whereas intermediate transoms are placed in between the main transoms to
lend additional board support.
Besides standards, ledgers and transoms, there are a few other supportive elements that
are also used to reinforce the fundamental scaffolding. One of it is the braces. There are many
different types of braces such as the cross braces, façade braces, and additional couplers. It can
be used in different combinations to support the structure in several ways. Cross braces are
braces that run diagonally between ledgers and it is attach securely to standards to increase a
structure’s overall rigidity. However, they can also secure themselves to ledgers, in which case
they are simply called ledger braces. In order to prevent the structure from swaying, façade
braces are attached on the face of the scaffold. It runs the length of the face of the structure and
securely attaching at every level.

Construction Technology II - Report

5
Methodology of Scaffolding
Furthermore, couplers help in connecting structural elements, and come in several
variants. A right-angle coupler is used to connect a ledger or transom to a standard. A putlog or
single-coupler should be used if a transom supports a board and must be connected to a ledger.
A swivel coupler is recommended for any other angle of connection between scaffold piping.
The width, length, and height of each scaffold element depend on the need of the
building, but there are several required measurements for each basic component. Generally, the
width of a scaffold is determined by the width of the scaffolding boards. The height between
ledgers, which is also known as the lift height, is usually between 2 to 2.7 m. The placement of
transom depends on the board thickness. If the board is 38 mm thick, the transoms should be
1.2 meters apart, at the most. A 50 mm thick board requires that transoms be not more than 2.6
meters apart.
In addition to the basic structural elements of a scaffold, there are a few different kinds of
ties to secure a scaffold to the adjoining building. As a general rule, ties are attached at every 4
meters on alternating lift levels. However, depending on the kind of scaffold, the patterns and
types of ties used can also varies. For example, ties can be used to secure a scaffold to a
building by entering a building’s open window. A box ties are used to help in securing a scaffold
by attaching to a building’s external features, such as strong pillars.
Firstly, a level surface that is stable should be used to erect the, and if it is not, the
contractor will have to stabilize it and make sure that it is adequate to support the scaffolds.
Appropriate measures need to be taken if the scaffolding is to be erected in a public place as the
safety of bystanders is incredibly important. For example, the work can be scheduled to proceed
during quiet periods (usually at night), which less people are likely to be in proximity to the
structure or roads can be closed through council permission. An important reminder is that
scaffolding should never be erected near power lines as this can be extremely dangerous and
result in fatalities.

Construction Technology II - Report

6
Methodology of Scaffolding

Construction Technology II - Report

7
Safety Precautions

Scaffolding can also be a dangerous place to work if it is not properly installed or used.
Your live might be at risk and also the people beneath might face fatal injuries if knocked by
falling objects from high level. A scaffold must always be erected plumb. This is because it will
be more stable for the workers while working on it. An OSHA-defined qualified person should
have knowledge about the bracing, load and safety code requirements for each and every job
site. A ―competent person‖ described by the COSHA should inspect all the elements of the
scaffolding to make sure in is in good condition before it is being used.
1. Ensure each and every worker is well trained.
As stated in the safety regulations code, workers are required to be trained in the design
structure and operation of scaffolding. The training should cover important safety work practices
such as how to safely get on and off the scaffold (using an access ladder, not the scaffold frame;
unless it is specially designed to be climbed and both hands are free to grab the rungs). Besides
that, it should also cover comprehensive fall protection training specific to the type of scaffolding,
dismantling and erecting procedures for those who will be involved.

2. Take time for the preparation work.
Before using scaffolding, we must make sure that the base is level, adjusted and sound no
matter how long it takes. The legs of the scaffolding must be plumb and all braces in place. Next,
make sure that the locking devices and ties are secured, cross members are levelled and the
planks, decks and guardrails are installed and secure. Last but not least, check the location for
ground conditions, such as slopes, and stay clear away from hazards such as overhead wires.

Construction Technology II - Report

8
Safety Precautions

3. Understand the load capacity.
Failure to consider the loads to which the scaffold may be subjected is one of the top things that
go wrong at the design stage. The scaffold must be strong enough and capable of holding the
desired weight, otherwise it could collapse. Do not try to fit as many workers as you can on the
platform just to speed up the construction process. Do not overload it with equipment and
materials that it is not supposed to and we are not supposed to rest anything near the guardrails
as they might just fall off.

4. Ensure the scaffold is properly secured.
The scaffold must be properly braced or tied to the building. It could be blown over if it isn’t well
secured. According to the Construction Safety Association of Manitoba, ―Bracing must be
properly secured in place; otherwise scaffold movement may dislodge an end, reducing the
stability of the scaffold. There is several braces retention or locking systems found on scaffolds.
These devices must operate freely for ease of assembling and dismantling, and also lock
securely to prevent a brace from dislodging. Nails and other miscellaneous odds and ends
should not be used in place of proper retention parts supplied by the manufacturer.‖

5. Use guardrails.
The design of the scaffold must incorporate guardrails on at least the three sides facing away
from the building if the scaffold is more than 10 feet above ground. There should be a top rail,
mid rail and bottom rail (toe board). If you must remove any guardrails while hoisting materials,
replace them promptly. Wear fall protection at all times, ex: Safety harness. People tend to
neglect the importance of guardrails as it might be an additional cost implied to the project.

Construction Technology II - Report

9
Safety Precautions
6. Inspect and maintain.
Scaffolding must be routinely inspected by the supervisor or by a competent person — ideally a
professional engineer or a person designated in writing by a professional engineer. In the case
of a suspended platform, inspect and test all components including welds, stirrups, connecting
pins, connecting plates, trusses, beams and working surface. Check whether the lumber is of
good quality and if any pieces get broken or damaged, replace them right away. Frames, braces
and other components must be inspected for damage, bends and excessive rust or wear. Also
check motors, platforms or wire ropes for damage from chemicals or corrosive material.
7. Use appropriate PPE (Personal Protective Equipment).
This includes non-slip protective footwear, head protection and fall protection as required, in the
form of a safety harness tied off to a solid structure, such as the building or on the scaffolding.
Ontario’s construction safety regulations indicate that the harness can be tied off to the
suspended platform or scaffold only ―if all or part of the platform or scaffold has more than one
independent means of support and the platform or scaffold is so designed, constructed and
maintained that the failure of one means of support will not cause the collapse of all or part of
the platform or scaffold.’
8. Good housekeeping.
There isn’t much room on a scaffold, so it’s important to store tools and materials in an orderly
fashion. Keep the platform free of obstructions. Place debris and waste material in a container or
remove it from the platform immediately.

Construction Technology II - Report

10
Safety Precautions

9. Keep your balance.
A scaffold and its platform must be perfectly level (CSA standard says it mustn’t deviate from the
vertical by more than 12 millimeters per three meters of height) to minimize the risk of workers
losing balance and falling off. Particularly on swing stages, there must be an adequately
weighted counterweight. Pay attention when working on a scaffold. Any sudden movements, or
reaching too far from the platform, can cause a loss of balance.

Construction Technology II - Report

11
Materials Used in Scaffolding

A scaffold, properly designed, erected and maintained will provide both a means of
access and working place which is as safe as those found in existing structures and on
permanent structures.
Basically the materials used in scaffolding are tubes,
couplers and boards. Tubes can be steel or aluminium,
although composite scaffolding uses filament wound tubes of
glass fibre in a nylon or polyester matrix. They are either in
'black' or galvanized. The tubes come in a variety of lengths
and a standard diameter of 48.3 mm. One basic 24 pounds
per unit a scaffold of many sizes and heights could be
assembled easily by a couple of labourers without the nuts or
bolts. The main difference between the two types of tubes is
the lighter weight of aluminium tubes, a greater flexibility and
lower strength. Tubes are generally bought in 6.3 m lengths and can be cut down to certain
typical sizes.
On the other hand, boards offer a safety working surface for scaffold users. They are
qualified wood and come in three thicknesses which are 38mm (usual), 50mm and 63mm. The
standard width is 225mm and the maximum length is 3.9m. The board ends are protected either
by metal plates called hoop irons or sometimes nail plates. (Google Book, n.d.)

The requirement of timber scaffold board is BS
2482. Steel, laminated boards or aluminium decking can
also be used. In addition to the boards for the working
platform, there are sole boards which are placed beneath
the scaffolding if the surface is soft.

Construction Technology II - Report

12
Materials Used in Scaffolding

Besides that, couplers are the fittings
which hold the tubes together. The most common
are called scaffold couplers. There are many
types of couplers of scaffolding and the three
basic types are right-angle couplers, putlog
couplers and swivel couplers. The coupler used
at construction in Malaysia is Swivel coupler
because Swivel coupler are highly flexible, have
exceptional performance, rotates in all directions
and it has international standard. The function of
the coupler is to connect horizontal and vertical
tubes together. Only right angle couplers and
swivel couplers can be used to fix tube in a 'load-bearing connection'. Single couplers are not
load-bearing couplers and have no load-bearing capacity.

Other types of common scaffolding
components include base plates, ladders, ropes,
anchor ties, and reveal ties, gin wheels, sheeting,
and many more. All elements in the scaffolding that
are made from metal can be painted. However,
elements that are made of wood should not be
painted as this could hide defects. Many scaffolds
measure tubes and boards in imperial units, with
tubes from 21 ft. down and boards from 13 ft. down,
despite the metric measurements given.

Construction Technology II - Report

13
Materials Used in Scaffolding

The construction site that we have visited is the Tenaga Nasional Berhad (TNB), located
atSelangor. The construction site uses steel scaffolding, swivel couplers and a piece of wood
placed on the scaffolding. We think the platform used in the construction is very dangerous
compared to the other countries. Basically in Malaysia, they are using the same type of platform,
a piece of wood, the reason why they used that type of platform is to lower the cost but it
increases the safety risks of the users on
the scaffolding.
In an international scope, like
Hong Kong, bamboo scaffolding is
commonly used, with nylon straps tied
into knots as couplers. In India, bamboo
or other wooden scaffolding is also
commonly used, with poles being
pounded together using ropes made from
coconut hair known as coir. (Unknown,

Construction Technology II - Report

14
n.d.)

Suitability of Usage
There are many different types of scaffoldings that are used in the construction industry
today. Each of them can also serve different purposes such as bricklaying, plastering, or
demolition. When deciding which types of scaffoldings should be used, the design, shape and
location of the building or structure should be considered. The most suitable or adaptable
scaffolding should be selected. Generally, there are 3 basic types of scaffoldings that are
supported, suspended, and aerial lifts.

The supported scaffolding is the most widely used scaffolding. It is set on the ground and
can be stacked up to very high altitudes. As the taller and wider the scaffolding gets, its stability
also increases. Workers can reach the upper platform by using the ladders at the side, or in
modern scaffoldings, through the stairs. There is also a similar type of supported scaffolding, but
with wheels installed at the bottom to allow movement and flexibility. However this type of
scaffolding is less safe than the common supported scaffolding as the stability is lower and it has
a limited height.

Construction Technology II - Report

15
Suitability of Usage

The suspended scaffolding however, is very different from the supported scaffolding. It is
suspended above the ground with special ropes which can support its required weight. It allows
workers to be able to do their job more conveniently due to its flexibility to move around the
building to the sides. It is much easier to install compared to the supported scaffolding but it has
higher risks. It cannot be placed too high on a building or structure as it can be dangerous.
There is also a cantilever type where there are no ropes to hold the scaffolding but instead is
supported with beams connected to the building or structure.

Construction Technology II - Report

16
Suitability of Usage

Aerial lifts are rarely used. They are considered to be vehicle-mounted aerial devices.
They are used only when some levels or location are harder to reach. Workers can ride on it and
be lifted up to the desired level or location.
Since scaffoldings are so widely used, the wide variety of scaffoldings can be brought
down to specific types. This means that they have different characteristics and serve different
purposes.
Birdcage scaffold is mainly used for carrying out ceiling works. It is normally constructed
inside the building from corners to corners to internal ceiling works.
Tower scaffold is very similar to mobile scaffolds. Mobile scaffolds have rollers attached
to them for movement. Tower scaffold has the same qualities but with additions of bracers that
are attached to the ground at the corners for better stability.

Construction Technology II - Report

17
Suitability of Usage

Tube and coupler scaffold is a system
that can have a connection of two tubes to be
placed at any position and is usually used on
structures with unusual design, shape or
function. The diameter and strength of the
components when using this type of scaffolding
should be considered. Tube and coupler
scaffold can be of metal, however, it is
important not to mix aluminium and steel tubes
in one scaffold.

Frame scaffolds are often minor scaffolds and
similar to the supported scaffoldings but with the use of
prefabricated frames, braces, and accessories. It does
not require a licensed scaffolder to construct or

dismantle. It is commonly used for bricklaying,
plastering, and painting.
Hung scaffold is similar to the suspended
scaffoldings. However, it does not have special ropes
to hold it, instead, it is an independent scaffold that
hangs from another structure which prevents its ability
to move around the building vertically or to the sides.

Construction Technology II - Report

18
Conclusion

After the site visit, we had gained experiences from the actual work environment on site.
We found that working on site is definitely not an easy job as the weather is usually hot. Even
after a few hours of site visit, we are so tired and exhausted. As a professional Quantity
Surveyor, sometime we haveto go on site to check out stuffs on our own. So, we have no choice
but to adapt such circumstances.

Construction Technology II - Report

19
References

1. WorkCover NSW (2011). Erecting, altering and dismantling scaffolding. Retrieved on
December 2nd, 2013 from
http://www.workcover.nsw.gov.au/formspublications/publications/Documents/erecting_alt
ering_dismantling_scaffold_part2_2826.pdf
2. Morra,M. (2011). 10 scaffold safety essentials. Retrieved on December 2nd, 2013 from
http://www.facebook.com/l.php?u=http%3A%2F%2Fwww.cosmag.com%2FPPE%2FPPE-Stories%2F10-scaffold-safety-essentials.html&h=AQH4UhCi
3. Google Book. (n.d.).Popular Mechanics (1954 February).Retrieved on November 30th,
2013,
fromhttp://books.google.com.my/books?id=Nt8DAAAAMBAJ&pg=PA103&dq=1954+Pop
ular+Mechanics&hl=en&sa=X&ei=sJAKTnTDMqRgQenq_mzAg&redir_esc=y#v=onepage&q&f=true

4. Unknown. (n.d.). Guidelines on the Design and Construction of Bamboo Scaffolds.
Retrieved on November 30th, 2013,
fromhttp://www.bd.gov.hk/english/documents/code/GDCBS.pdf
5. Safe Work Australia. (n.d.). Scaffolds and Scaffolding Work. Retrieved on December 4th,
2013 from http://www.safeworkaustralia.gov.au/sites/SWA/model-whs-laws/modelCOP/Documents/Draft-COP-December-2012/DRAFT-scaffolds-scaffolding-workCOP.pdf

6. Home Improvement Ideas, Tips and Guide. (2012). Different Types of Scaffolding and
Their Uses.Retrieved on December 4th, 2013 fromhttp://refresh-detroit.org/42/differenttypes-of-scaffolding-and-their-uses.html

Construction Technology II - Report

20
References

7. The University of Tennessee Office of Environmental Health & Safety. (n.d.). Scaffolding.
Retrieved on December 4th, 2013 fromhttp://web.utk.edu/~ehss/pdf/Scaffolding.pdf

8. Princeton University. (n.d.). Scaffolds and Aerial Lifts Requirements. Retrieved on
December 4th, 2013 from http://web.princeton.edu/sites/ehs/healthsafetyguide/B17.htm

Construction Technology II - Report

21

Contenu connexe

Tendances

Building Construction Project 01 Final Report
Building Construction Project 01 Final ReportBuilding Construction Project 01 Final Report
Building Construction Project 01 Final ReportjolynnTJL
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Construction technology assignment 1
Construction technology assignment 1Construction technology assignment 1
Construction technology assignment 1Doreen Yeo
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achahAisyah Asyikin
 
Temporary Work in Building Construction
Temporary Work in Building ConstructionTemporary Work in Building Construction
Temporary Work in Building ConstructionEr.Karan Chauhan
 
Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]JerotichMaswan
 
Building Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structuresBuilding Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structuresRithika Ravishankar
 
Site visit report
Site visit reportSite visit report
Site visit reportJordon Wong
 
PREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEMPREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEMFarah Sham
 
Blockwork system
Blockwork systemBlockwork system
Blockwork systemWen Crystal
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequenceRanjith Kumar
 
Construction of Brick Wall
Construction of Brick WallConstruction of Brick Wall
Construction of Brick WallI'mMiss Lily
 
Building construction 1 group report
Building construction 1 group reportBuilding construction 1 group report
Building construction 1 group reportXingYue0907
 

Tendances (20)

Building Construction Project 01 Final Report
Building Construction Project 01 Final ReportBuilding Construction Project 01 Final Report
Building Construction Project 01 Final Report
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Construction technology assignment 1
Construction technology assignment 1Construction technology assignment 1
Construction technology assignment 1
 
Probe machintosh
Probe machintoshProbe machintosh
Probe machintosh
 
Stairs
StairsStairs
Stairs
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achah
 
Temporary Work in Building Construction
Temporary Work in Building ConstructionTemporary Work in Building Construction
Temporary Work in Building Construction
 
Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]
 
Building Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structuresBuilding Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structures
 
Site visit report
Site visit reportSite visit report
Site visit report
 
PREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEMPREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEM
 
Scaffoldings
ScaffoldingsScaffoldings
Scaffoldings
 
Blockwork system
Blockwork systemBlockwork system
Blockwork system
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Scaffolding and formwork ppt
Scaffolding and  formwork pptScaffolding and  formwork ppt
Scaffolding and formwork ppt
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Construction of Brick Wall
Construction of Brick WallConstruction of Brick Wall
Construction of Brick Wall
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
Building construction 1 group report
Building construction 1 group reportBuilding construction 1 group report
Building construction 1 group report
 
Window topic 8
Window topic 8Window topic 8
Window topic 8
 

En vedette

Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)마 이환
 
Sustainable Housing Development
Sustainable Housing DevelopmentSustainable Housing Development
Sustainable Housing Development마 이환
 
Idj compilation
Idj compilationIdj compilation
Idj compilation마 이환
 
Building services i report
Building services i   reportBuilding services i   report
Building services i report마 이환
 
Site surveying report i
Site surveying   report iSite surveying   report i
Site surveying report i마 이환
 
79338922 survey-report
79338922 survey-report79338922 survey-report
79338922 survey-reportirwandavid
 
Surveying by using Digital Theodolite
Surveying by using Digital TheodoliteSurveying by using Digital Theodolite
Surveying by using Digital TheodoliteEhab AL-Timimi
 
Site surveying report ii
Site surveying   report iiSite surveying   report ii
Site surveying report ii마 이환
 
Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)마 이환
 
Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)마 이환
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 

En vedette (14)

Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)
 
Sustainable Housing Development
Sustainable Housing DevelopmentSustainable Housing Development
Sustainable Housing Development
 
Idj compilation
Idj compilationIdj compilation
Idj compilation
 
Building services i report
Building services i   reportBuilding services i   report
Building services i report
 
Theodolite report
Theodolite reportTheodolite report
Theodolite report
 
Site surveying report i
Site surveying   report iSite surveying   report i
Site surveying report i
 
79338922 survey-report
79338922 survey-report79338922 survey-report
79338922 survey-report
 
Surveying by using Digital Theodolite
Surveying by using Digital TheodoliteSurveying by using Digital Theodolite
Surveying by using Digital Theodolite
 
Site surveying report ii
Site surveying   report iiSite surveying   report ii
Site surveying report ii
 
Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)
 
Measurement V
Measurement VMeasurement V
Measurement V
 
Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 

Similaire à Construction technology ii report

Site report
Site reportSite report
Site reportvaylu
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Chin Tze Wei
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Developmentijsrd.com
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement reportKailyn Lee
 
How to Build Bricklaying Scaffolding_ Reach New Heights in Construction!.pdf
How to Build Bricklaying Scaffolding_ Reach New Heights in Construction!.pdfHow to Build Bricklaying Scaffolding_ Reach New Heights in Construction!.pdf
How to Build Bricklaying Scaffolding_ Reach New Heights in Construction!.pdfssusereee489
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxNaveenVerma126
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report I'mMiss Lily
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)I'mMiss Lily
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit reportMomo Poyi
 
Sem 2 Building Construction Project 1
Sem 2 Building Construction Project 1 Sem 2 Building Construction Project 1
Sem 2 Building Construction Project 1 Jervain Ng
 
NMRC Civil Construction
NMRC Civil Construction NMRC Civil Construction
NMRC Civil Construction ajinkyaraj
 

Similaire à Construction technology ii report (20)

Construction Site Report
Construction Site ReportConstruction Site Report
Construction Site Report
 
Site report
Site reportSite report
Site report
 
Site report
Site reportSite report
Site report
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)
 
Site report
Site reportSite report
Site report
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Development
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
 
How to Build Bricklaying Scaffolding_ Reach New Heights in Construction!.pdf
How to Build Bricklaying Scaffolding_ Reach New Heights in Construction!.pdfHow to Build Bricklaying Scaffolding_ Reach New Heights in Construction!.pdf
How to Build Bricklaying Scaffolding_ Reach New Heights in Construction!.pdf
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
 
Industrial buildings
Industrial buildingsIndustrial buildings
Industrial buildings
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
Pragati towers
Pragati towersPragati towers
Pragati towers
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
 
Sem 2 Building Construction Project 1
Sem 2 Building Construction Project 1 Sem 2 Building Construction Project 1
Sem 2 Building Construction Project 1
 
Table formwork
Table formwork Table formwork
Table formwork
 
NMRC Civil Construction
NMRC Civil Construction NMRC Civil Construction
NMRC Civil Construction
 
Demolition of buildings
Demolition of buildingsDemolition of buildings
Demolition of buildings
 
Mod. 1.pptx
Mod. 1.pptxMod. 1.pptx
Mod. 1.pptx
 

Plus de 마 이환

Chapter 10a Insurance:Contractor's Indemnity to Employer
Chapter 10a   Insurance:Contractor's Indemnity to EmployerChapter 10a   Insurance:Contractor's Indemnity to Employer
Chapter 10a Insurance:Contractor's Indemnity to Employer마 이환
 
Financial Management:Presentation Slides
Financial Management:Presentation SlidesFinancial Management:Presentation Slides
Financial Management:Presentation Slides마 이환
 
Financial Report:Comments & Evaluations
Financial Report:Comments & EvaluationsFinancial Report:Comments & Evaluations
Financial Report:Comments & Evaluations마 이환
 
Financial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance SheetFinancial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance Sheet마 이환
 
Building Economics:Tender Report
Building Economics:Tender ReportBuilding Economics:Tender Report
Building Economics:Tender Report마 이환
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment마 이환
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides마 이환
 
Schedule of agreed datelines
Schedule of agreed datelinesSchedule of agreed datelines
Schedule of agreed datelines마 이환
 
Reply for queries (architect)
Reply for queries (architect)Reply for queries (architect)
Reply for queries (architect)마 이환
 
Request for queries (architect)
Request for queries (architect)Request for queries (architect)
Request for queries (architect)마 이환
 
Lembayung impian sdn bhd
Lembayung impian sdn bhdLembayung impian sdn bhd
Lembayung impian sdn bhd마 이환
 
Software application:appendices
Software application:appendicesSoftware application:appendices
Software application:appendices마 이환
 
Software application:assignment
Software application:assignmentSoftware application:assignment
Software application:assignment마 이환
 
Organization Chart
Organization ChartOrganization Chart
Organization Chart마 이환
 
Bank guarantee
Bank guaranteeBank guarantee
Bank guarantee마 이환
 
Letter of invitation
Letter of invitationLetter of invitation
Letter of invitation마 이환
 
Virtigo holding berhad
Virtigo holding berhadVirtigo holding berhad
Virtigo holding berhad마 이환
 
Measurement III:Doors & Windows
Measurement III:Doors & WindowsMeasurement III:Doors & Windows
Measurement III:Doors & Windows마 이환
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System마 이환
 

Plus de 마 이환 (20)

Chapter 10a Insurance:Contractor's Indemnity to Employer
Chapter 10a   Insurance:Contractor's Indemnity to EmployerChapter 10a   Insurance:Contractor's Indemnity to Employer
Chapter 10a Insurance:Contractor's Indemnity to Employer
 
Financial Management:Presentation Slides
Financial Management:Presentation SlidesFinancial Management:Presentation Slides
Financial Management:Presentation Slides
 
Financial Report:Comments & Evaluations
Financial Report:Comments & EvaluationsFinancial Report:Comments & Evaluations
Financial Report:Comments & Evaluations
 
Financial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance SheetFinancial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance Sheet
 
Building Economics:Tender Report
Building Economics:Tender ReportBuilding Economics:Tender Report
Building Economics:Tender Report
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides
 
Schedule of agreed datelines
Schedule of agreed datelinesSchedule of agreed datelines
Schedule of agreed datelines
 
Reply for queries (architect)
Reply for queries (architect)Reply for queries (architect)
Reply for queries (architect)
 
Request for queries (architect)
Request for queries (architect)Request for queries (architect)
Request for queries (architect)
 
Internal memo
Internal memoInternal memo
Internal memo
 
Lembayung impian sdn bhd
Lembayung impian sdn bhdLembayung impian sdn bhd
Lembayung impian sdn bhd
 
Software application:appendices
Software application:appendicesSoftware application:appendices
Software application:appendices
 
Software application:assignment
Software application:assignmentSoftware application:assignment
Software application:assignment
 
Organization Chart
Organization ChartOrganization Chart
Organization Chart
 
Bank guarantee
Bank guaranteeBank guarantee
Bank guarantee
 
Letter of invitation
Letter of invitationLetter of invitation
Letter of invitation
 
Virtigo holding berhad
Virtigo holding berhadVirtigo holding berhad
Virtigo holding berhad
 
Measurement III:Doors & Windows
Measurement III:Doors & WindowsMeasurement III:Doors & Windows
Measurement III:Doors & Windows
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 

Dernier

Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 

Dernier (20)

Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 

Construction technology ii report

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) QSB1524 – Construction Technology II Scaffolding August Semester 2013 Construction Technology II Report Submission Date: 6thDecember 2013 Name StudentID Yam Yih Hwan 0305861 Low Rong Tzuoo 0304924 Janice Kong Yin Ying 0308798 Harvey Yap Zhu Guang 0309325 Wong Ha Shiong 0309640 Construction Technology II - Report 1
  • 2. Table of Content Page Cover Page 1 Table of Content 2 Introduction 3 Objective 4 Methodology of Scaffolding 5-7 Safety Precautions 8 - 11 Material Used in Scaffolding 12 - 14 Suitability of Usage 15 - 18 Conclusion 19 References 20 - 21 Construction Technology II - Report 2
  • 3. Introduction On 26thSeptember 2013, along with my group mates, we went for a site visit in a construction site located at SS16, Subang Jaya. It is somewhere nearby the Subang Jaya Komuter Station. In this project, the main contractor is KP Synergies Berhad – Transgrid Ventures Sdn. Bhd. (Consortium), and the sub-contractor is Bintang Puspa. Once the construction work is done, it will be passed over to TNB, even the contractors/employees are restricted to enter the land, unless with permission. The size of the land is roughly around 5 acres, 20234.3m2, and a combination of two lots. It was then merged together for the construction of the TNB building. The purpose of the land is to build the Subang Jaya Tower Center (Live Station), also known as ―Pencawang Masuk Utama‖. It is a 2 years contract, estimated to complete on 20th October 2014 including the engineering, construction & commissioning works. For your information, the total amount spend is RM 130 million, and RM 17 million only on the construction and civil structure. Once the building is completed, it will be around 5m high all the way to the roof of the tower. Firstly, they clear off the site in order to make platforms for the piling machine to enter the site. Piling must be done in flat ground. Then, they excavate vary from the size of the loading, particular pile group thickness. Excavation level is depending on the size of the pile cap, the depth/width/length of the pile cap = volume (m3). The higher the loadings, it requires bigger size pile caps & deep excavation. As for smaller loadings, it only requires smaller size pile caps &swallow excavation. Pile is around 300mm2 deep into the ground, using reinforced pre-cast concrete piles 45mm thick. Moreover, total numbers of 5 transformers is placed under the building with the depth of 1.5m. On the left side, it contains three 240 MVA (megavolt) transformers. And on the right side, it contains two 90 MVA (megavolt) transformers. Each one of the transformer contains of 87 thousand liters of transformer oil. Furthermore, returning walls are built at the sides of the lower ground; it is required to raise up the platform for the construction of walls, and then backfill it. This project is a conventional construction; it does not use any system formwork or any special plan off construction metrology. The only precast unit used is precast piles, because it is cheaper as compared to in-situ casting. Construction Technology II - Report 3
  • 4. Objective  To help us get a more understanding on the basics of construction process while paying a visit to the site.  Let us experience the actual working environment as a Quantity Surveyor on site dealing with uncertain circumstances such as the weather condition and the risks that may take place on the site.  Let us aware of the importance of personal safety on site, and the safety precautions that we need to take in order to avoid accidents from happening. For instance, we are required to wear safety helmet on site.  Increase our knowledge on the basic construction process by observing the building team and gathering information on the actual practice that carried on the site.  Explore and identify various types of building materials and type of technology used in construction while constructing a building. Construction Technology II - Report 4
  • 5. Methodology of Scaffolding Scaffolding is a structure or framework that is temporarily used to support loads of humans and materials during a construction process. It is also used to ease the accessibility of a person going from one floor to another and provides a safe working space at an elevated height. Scaffolding system normally uses metal tubes or metal pipes to connect with each other and it can also be from other materials besides metal. For example, bamboo, that is widely used in Asia. Scaffolding is normally used when the working level is 1.5 m above the ground. Structural elements of scaffolding The basic elements of a scaffold are the three components such as: standards, ledgers and transoms. The standards, also known as uprights, are the vertical long pipe or tube that transfers the loading mass of the structure to the ground where they rest on a square base plate for the spreading of the load. There is a shank in the centre of the base plate to hold the tube and sometimes it is pinned to a sole board. In between each standard, the component that runs horizontally is called ledger. It adds further support and weight distribution to the whole structure. There is also a component called transom, which are placed upon the ledgers at right angles. Main transoms are placed next to the standards and they hold the standards in place to provide support for boards. Whereas intermediate transoms are placed in between the main transoms to lend additional board support. Besides standards, ledgers and transoms, there are a few other supportive elements that are also used to reinforce the fundamental scaffolding. One of it is the braces. There are many different types of braces such as the cross braces, façade braces, and additional couplers. It can be used in different combinations to support the structure in several ways. Cross braces are braces that run diagonally between ledgers and it is attach securely to standards to increase a structure’s overall rigidity. However, they can also secure themselves to ledgers, in which case they are simply called ledger braces. In order to prevent the structure from swaying, façade braces are attached on the face of the scaffold. It runs the length of the face of the structure and securely attaching at every level. Construction Technology II - Report 5
  • 6. Methodology of Scaffolding Furthermore, couplers help in connecting structural elements, and come in several variants. A right-angle coupler is used to connect a ledger or transom to a standard. A putlog or single-coupler should be used if a transom supports a board and must be connected to a ledger. A swivel coupler is recommended for any other angle of connection between scaffold piping. The width, length, and height of each scaffold element depend on the need of the building, but there are several required measurements for each basic component. Generally, the width of a scaffold is determined by the width of the scaffolding boards. The height between ledgers, which is also known as the lift height, is usually between 2 to 2.7 m. The placement of transom depends on the board thickness. If the board is 38 mm thick, the transoms should be 1.2 meters apart, at the most. A 50 mm thick board requires that transoms be not more than 2.6 meters apart. In addition to the basic structural elements of a scaffold, there are a few different kinds of ties to secure a scaffold to the adjoining building. As a general rule, ties are attached at every 4 meters on alternating lift levels. However, depending on the kind of scaffold, the patterns and types of ties used can also varies. For example, ties can be used to secure a scaffold to a building by entering a building’s open window. A box ties are used to help in securing a scaffold by attaching to a building’s external features, such as strong pillars. Firstly, a level surface that is stable should be used to erect the, and if it is not, the contractor will have to stabilize it and make sure that it is adequate to support the scaffolds. Appropriate measures need to be taken if the scaffolding is to be erected in a public place as the safety of bystanders is incredibly important. For example, the work can be scheduled to proceed during quiet periods (usually at night), which less people are likely to be in proximity to the structure or roads can be closed through council permission. An important reminder is that scaffolding should never be erected near power lines as this can be extremely dangerous and result in fatalities. Construction Technology II - Report 6
  • 7. Methodology of Scaffolding Construction Technology II - Report 7
  • 8. Safety Precautions Scaffolding can also be a dangerous place to work if it is not properly installed or used. Your live might be at risk and also the people beneath might face fatal injuries if knocked by falling objects from high level. A scaffold must always be erected plumb. This is because it will be more stable for the workers while working on it. An OSHA-defined qualified person should have knowledge about the bracing, load and safety code requirements for each and every job site. A ―competent person‖ described by the COSHA should inspect all the elements of the scaffolding to make sure in is in good condition before it is being used. 1. Ensure each and every worker is well trained. As stated in the safety regulations code, workers are required to be trained in the design structure and operation of scaffolding. The training should cover important safety work practices such as how to safely get on and off the scaffold (using an access ladder, not the scaffold frame; unless it is specially designed to be climbed and both hands are free to grab the rungs). Besides that, it should also cover comprehensive fall protection training specific to the type of scaffolding, dismantling and erecting procedures for those who will be involved. 2. Take time for the preparation work. Before using scaffolding, we must make sure that the base is level, adjusted and sound no matter how long it takes. The legs of the scaffolding must be plumb and all braces in place. Next, make sure that the locking devices and ties are secured, cross members are levelled and the planks, decks and guardrails are installed and secure. Last but not least, check the location for ground conditions, such as slopes, and stay clear away from hazards such as overhead wires. Construction Technology II - Report 8
  • 9. Safety Precautions 3. Understand the load capacity. Failure to consider the loads to which the scaffold may be subjected is one of the top things that go wrong at the design stage. The scaffold must be strong enough and capable of holding the desired weight, otherwise it could collapse. Do not try to fit as many workers as you can on the platform just to speed up the construction process. Do not overload it with equipment and materials that it is not supposed to and we are not supposed to rest anything near the guardrails as they might just fall off. 4. Ensure the scaffold is properly secured. The scaffold must be properly braced or tied to the building. It could be blown over if it isn’t well secured. According to the Construction Safety Association of Manitoba, ―Bracing must be properly secured in place; otherwise scaffold movement may dislodge an end, reducing the stability of the scaffold. There is several braces retention or locking systems found on scaffolds. These devices must operate freely for ease of assembling and dismantling, and also lock securely to prevent a brace from dislodging. Nails and other miscellaneous odds and ends should not be used in place of proper retention parts supplied by the manufacturer.‖ 5. Use guardrails. The design of the scaffold must incorporate guardrails on at least the three sides facing away from the building if the scaffold is more than 10 feet above ground. There should be a top rail, mid rail and bottom rail (toe board). If you must remove any guardrails while hoisting materials, replace them promptly. Wear fall protection at all times, ex: Safety harness. People tend to neglect the importance of guardrails as it might be an additional cost implied to the project. Construction Technology II - Report 9
  • 10. Safety Precautions 6. Inspect and maintain. Scaffolding must be routinely inspected by the supervisor or by a competent person — ideally a professional engineer or a person designated in writing by a professional engineer. In the case of a suspended platform, inspect and test all components including welds, stirrups, connecting pins, connecting plates, trusses, beams and working surface. Check whether the lumber is of good quality and if any pieces get broken or damaged, replace them right away. Frames, braces and other components must be inspected for damage, bends and excessive rust or wear. Also check motors, platforms or wire ropes for damage from chemicals or corrosive material. 7. Use appropriate PPE (Personal Protective Equipment). This includes non-slip protective footwear, head protection and fall protection as required, in the form of a safety harness tied off to a solid structure, such as the building or on the scaffolding. Ontario’s construction safety regulations indicate that the harness can be tied off to the suspended platform or scaffold only ―if all or part of the platform or scaffold has more than one independent means of support and the platform or scaffold is so designed, constructed and maintained that the failure of one means of support will not cause the collapse of all or part of the platform or scaffold.’ 8. Good housekeeping. There isn’t much room on a scaffold, so it’s important to store tools and materials in an orderly fashion. Keep the platform free of obstructions. Place debris and waste material in a container or remove it from the platform immediately. Construction Technology II - Report 10
  • 11. Safety Precautions 9. Keep your balance. A scaffold and its platform must be perfectly level (CSA standard says it mustn’t deviate from the vertical by more than 12 millimeters per three meters of height) to minimize the risk of workers losing balance and falling off. Particularly on swing stages, there must be an adequately weighted counterweight. Pay attention when working on a scaffold. Any sudden movements, or reaching too far from the platform, can cause a loss of balance. Construction Technology II - Report 11
  • 12. Materials Used in Scaffolding A scaffold, properly designed, erected and maintained will provide both a means of access and working place which is as safe as those found in existing structures and on permanent structures. Basically the materials used in scaffolding are tubes, couplers and boards. Tubes can be steel or aluminium, although composite scaffolding uses filament wound tubes of glass fibre in a nylon or polyester matrix. They are either in 'black' or galvanized. The tubes come in a variety of lengths and a standard diameter of 48.3 mm. One basic 24 pounds per unit a scaffold of many sizes and heights could be assembled easily by a couple of labourers without the nuts or bolts. The main difference between the two types of tubes is the lighter weight of aluminium tubes, a greater flexibility and lower strength. Tubes are generally bought in 6.3 m lengths and can be cut down to certain typical sizes. On the other hand, boards offer a safety working surface for scaffold users. They are qualified wood and come in three thicknesses which are 38mm (usual), 50mm and 63mm. The standard width is 225mm and the maximum length is 3.9m. The board ends are protected either by metal plates called hoop irons or sometimes nail plates. (Google Book, n.d.) The requirement of timber scaffold board is BS 2482. Steel, laminated boards or aluminium decking can also be used. In addition to the boards for the working platform, there are sole boards which are placed beneath the scaffolding if the surface is soft. Construction Technology II - Report 12
  • 13. Materials Used in Scaffolding Besides that, couplers are the fittings which hold the tubes together. The most common are called scaffold couplers. There are many types of couplers of scaffolding and the three basic types are right-angle couplers, putlog couplers and swivel couplers. The coupler used at construction in Malaysia is Swivel coupler because Swivel coupler are highly flexible, have exceptional performance, rotates in all directions and it has international standard. The function of the coupler is to connect horizontal and vertical tubes together. Only right angle couplers and swivel couplers can be used to fix tube in a 'load-bearing connection'. Single couplers are not load-bearing couplers and have no load-bearing capacity. Other types of common scaffolding components include base plates, ladders, ropes, anchor ties, and reveal ties, gin wheels, sheeting, and many more. All elements in the scaffolding that are made from metal can be painted. However, elements that are made of wood should not be painted as this could hide defects. Many scaffolds measure tubes and boards in imperial units, with tubes from 21 ft. down and boards from 13 ft. down, despite the metric measurements given. Construction Technology II - Report 13
  • 14. Materials Used in Scaffolding The construction site that we have visited is the Tenaga Nasional Berhad (TNB), located atSelangor. The construction site uses steel scaffolding, swivel couplers and a piece of wood placed on the scaffolding. We think the platform used in the construction is very dangerous compared to the other countries. Basically in Malaysia, they are using the same type of platform, a piece of wood, the reason why they used that type of platform is to lower the cost but it increases the safety risks of the users on the scaffolding. In an international scope, like Hong Kong, bamboo scaffolding is commonly used, with nylon straps tied into knots as couplers. In India, bamboo or other wooden scaffolding is also commonly used, with poles being pounded together using ropes made from coconut hair known as coir. (Unknown, Construction Technology II - Report 14
  • 15. n.d.) Suitability of Usage There are many different types of scaffoldings that are used in the construction industry today. Each of them can also serve different purposes such as bricklaying, plastering, or demolition. When deciding which types of scaffoldings should be used, the design, shape and location of the building or structure should be considered. The most suitable or adaptable scaffolding should be selected. Generally, there are 3 basic types of scaffoldings that are supported, suspended, and aerial lifts. The supported scaffolding is the most widely used scaffolding. It is set on the ground and can be stacked up to very high altitudes. As the taller and wider the scaffolding gets, its stability also increases. Workers can reach the upper platform by using the ladders at the side, or in modern scaffoldings, through the stairs. There is also a similar type of supported scaffolding, but with wheels installed at the bottom to allow movement and flexibility. However this type of scaffolding is less safe than the common supported scaffolding as the stability is lower and it has a limited height. Construction Technology II - Report 15
  • 16. Suitability of Usage The suspended scaffolding however, is very different from the supported scaffolding. It is suspended above the ground with special ropes which can support its required weight. It allows workers to be able to do their job more conveniently due to its flexibility to move around the building to the sides. It is much easier to install compared to the supported scaffolding but it has higher risks. It cannot be placed too high on a building or structure as it can be dangerous. There is also a cantilever type where there are no ropes to hold the scaffolding but instead is supported with beams connected to the building or structure. Construction Technology II - Report 16
  • 17. Suitability of Usage Aerial lifts are rarely used. They are considered to be vehicle-mounted aerial devices. They are used only when some levels or location are harder to reach. Workers can ride on it and be lifted up to the desired level or location. Since scaffoldings are so widely used, the wide variety of scaffoldings can be brought down to specific types. This means that they have different characteristics and serve different purposes. Birdcage scaffold is mainly used for carrying out ceiling works. It is normally constructed inside the building from corners to corners to internal ceiling works. Tower scaffold is very similar to mobile scaffolds. Mobile scaffolds have rollers attached to them for movement. Tower scaffold has the same qualities but with additions of bracers that are attached to the ground at the corners for better stability. Construction Technology II - Report 17
  • 18. Suitability of Usage Tube and coupler scaffold is a system that can have a connection of two tubes to be placed at any position and is usually used on structures with unusual design, shape or function. The diameter and strength of the components when using this type of scaffolding should be considered. Tube and coupler scaffold can be of metal, however, it is important not to mix aluminium and steel tubes in one scaffold. Frame scaffolds are often minor scaffolds and similar to the supported scaffoldings but with the use of prefabricated frames, braces, and accessories. It does not require a licensed scaffolder to construct or dismantle. It is commonly used for bricklaying, plastering, and painting. Hung scaffold is similar to the suspended scaffoldings. However, it does not have special ropes to hold it, instead, it is an independent scaffold that hangs from another structure which prevents its ability to move around the building vertically or to the sides. Construction Technology II - Report 18
  • 19. Conclusion After the site visit, we had gained experiences from the actual work environment on site. We found that working on site is definitely not an easy job as the weather is usually hot. Even after a few hours of site visit, we are so tired and exhausted. As a professional Quantity Surveyor, sometime we haveto go on site to check out stuffs on our own. So, we have no choice but to adapt such circumstances. Construction Technology II - Report 19
  • 20. References 1. WorkCover NSW (2011). Erecting, altering and dismantling scaffolding. Retrieved on December 2nd, 2013 from http://www.workcover.nsw.gov.au/formspublications/publications/Documents/erecting_alt ering_dismantling_scaffold_part2_2826.pdf 2. Morra,M. (2011). 10 scaffold safety essentials. Retrieved on December 2nd, 2013 from http://www.facebook.com/l.php?u=http%3A%2F%2Fwww.cosmag.com%2FPPE%2FPPE-Stories%2F10-scaffold-safety-essentials.html&h=AQH4UhCi 3. Google Book. (n.d.).Popular Mechanics (1954 February).Retrieved on November 30th, 2013, fromhttp://books.google.com.my/books?id=Nt8DAAAAMBAJ&pg=PA103&dq=1954+Pop ular+Mechanics&hl=en&sa=X&ei=sJAKTnTDMqRgQenq_mzAg&redir_esc=y#v=onepage&q&f=true 4. Unknown. (n.d.). Guidelines on the Design and Construction of Bamboo Scaffolds. Retrieved on November 30th, 2013, fromhttp://www.bd.gov.hk/english/documents/code/GDCBS.pdf 5. Safe Work Australia. (n.d.). Scaffolds and Scaffolding Work. Retrieved on December 4th, 2013 from http://www.safeworkaustralia.gov.au/sites/SWA/model-whs-laws/modelCOP/Documents/Draft-COP-December-2012/DRAFT-scaffolds-scaffolding-workCOP.pdf 6. Home Improvement Ideas, Tips and Guide. (2012). Different Types of Scaffolding and Their Uses.Retrieved on December 4th, 2013 fromhttp://refresh-detroit.org/42/differenttypes-of-scaffolding-and-their-uses.html Construction Technology II - Report 20
  • 21. References 7. The University of Tennessee Office of Environmental Health & Safety. (n.d.). Scaffolding. Retrieved on December 4th, 2013 fromhttp://web.utk.edu/~ehss/pdf/Scaffolding.pdf 8. Princeton University. (n.d.). Scaffolds and Aerial Lifts Requirements. Retrieved on December 4th, 2013 from http://web.princeton.edu/sites/ehs/healthsafetyguide/B17.htm Construction Technology II - Report 21