Developing a Project
From Concept to Completion




        www.ecb.co.uk
                        Sources of Grant Aid and Funding for Cricket Clubs   1
Contents                                                Developing a Project – From Concept to Completion



    Section                                              Page


              Introduction                                1

      1       Geting Started                              2     When embarking on the development of a facility
      2       Project Development Team                    2
                                                                project, careful consideration and planning is required
                                                                to ensure the final product meets the original concept.
      3       Successful Clients                          3

      4       Getting Support                             4
                                                                The purpose of this document is to set a clear project
      5       Local Communities                           4     development methodology in taking any new facility
      6       Consultant Services                         5     from concept to completion.

      7       Technical Compliance                        9
                                                                This document will assist any type of facility project
      8       RIBA Design Work Stages                     9
                                                                meeting the requirements of potential partners/funders
      9       Planning Consent                            10    and the aspirations of people engaged as deliverers
     10 Competitive Tendering                             11    of sport.
     11 Tender Analysis                                   12
                                                                “Developing a Project” provides advice and guidance
     12 FFU Contact Details                               13
                                                                with a series of useful links and contacts to support
     13 Design Work Stages                                14
                                                                you throughout the process. The document has been
                                                                written in conjunction with the England and Wales
                                                                Cricket Board’s Funding Programmes Guidance Notes
                                                                which are available to download from
                                                                www.ecb.co.uk/funding




2   Sources of Grant Aid and Funding for Cricket Clubs                                            Developing a Project – From Concept to Completion   1
1        Getting Started                                                                        3     Successful Clients

    Think about the aims of your project and                                                         The Commission for Architecture               4. Develop and communicate a
    ways to accommodate the current and                                                              and the Built Environment (CABE)                 clear brief
    future needs of the club/organisation,                                                           publication “Creating Excellent
                                                                                                                                                   5. Make a realistic financial
    including how often the facility will be                                                         Buildings” describes how to be a
                                                                                                                                                      commitment from
    used on a weekly and seasonal basis.                                                             successful client.
                                                                                                                                                      the outset
    It is important that you consult within
                                                                                                     Each development project is unique,
    your membership as widely as possible                                                                                                          6. Adopt integrated processes
                                                                                                     with special local conditions for site, use
    about the aims and objectives of your
                                                                                                     patterns and social context. However,         7. Find the right people for the job
    club/organisation.
                                                                                                     all projects need well structured project
                                                                                                                                                   8. Respond and contribute to the
                                                                                                     management and can benefit from the
                                                                                                                                                      context
                                                                                                     ten key ways the client can help achieve
                                                                                                     design quality.                               9. Commit to sustainability
       2        Project Development Team                                                             1. Provide strong client leadership           10. Sign off all key stages
                                                                                                     2. Give enough time at the right time         All work stages require sign-off so allow
    It is strongly recommended that you                  remove themselves from the committee                                                      time to review the drawings and reports
    form a project development team and                  until the completion of the project.        3. Learn from your own and other
                                                                                                                                                   prepared by the design team, carefully
    appoint a team leader who should                                                                    successful projects
                                                         The project team should be established                                                    checking your requirements against the
    remain consistent throughout the                                                                                                               design.
                                                         prior to starting any design work and
    duration of the project. The project team
                                                         remain operational until final completion
    should consist of individuals with skill
                                                         of the works. NB: the size and skill sets
    sets that are relevant and appropriate
                                                         required to drive the project may change
    for the project.
                                                         throughout the lifespan of the works.
    When forming the project team, do
    not limit its composition to the club/
    organisation members unless the
    members can clearly evidence that
    they have the relevant experience and
    qualifications to compliment the planned
    project work.
    It should be noted if a member of the
    club/organisation is engaged to carry
    out any works on the project and they
    are current members of the committee,
    this would be seen as a conflict of
    interests. Therefore, any members who
    find themselves in this position should


2   Developing a Project and Funding for to Completion
    Sources of Grant Aid – From Concept Cricket Clubs                                                                                                     Developing a Project –and Funding forto Completion
                                                                                                                                                           Sources of Grant Aid From Concept Cricket Clubs     3
4        Getting Support                                                                             6       Consultant Services

    The ECB Funding and Facilities                      Funding and planning permission are             If the appropriate skills are not available     2   Structural Engineer
    Unit (FFU) should be your first point               two important hurdles in the preparation        within the project team, you may need
                                                                                                                                                            Structural engineers design and
    of call for advice. You should make                 and design stages of a project. The ECB         to engage the services of specialists,
                                                                                                                                                            calculate the building structure and
    contact with the FFU during work stage              Regional Funding and Facilities Manager         as follows:
                                                                                                                                                            foundations. They sometimes also
    A, as outlined in section 8, and show               will assess the proposals for technical
                                                                                                        Building Projects (including renovation             design below ground drainage.
    them your project (refer to contacts                compliance, sports development and
                                                                                                        and refurbishments)                                 Refer to www.istructe.org
    page 13). Consulting the ECB at the                 financial affordability.
    earliest opportunity allows their input to                                                          1       Architect                               3   Mechanical and Electrical (M&E)
    be more valuable.                                                                                                                                       Services Engineer
                                                                                                                Architects design new buildings,
                                                                                                                the spaces around them and                  M&E services engineers design and
                                                                                                                alterations to existing buildings.          coordinate the services of buildings
       5       Local Communities                                                                                They also advise on the restoration         including gas, electricity, heating,
                                                                                                                and conservation of old buildings,          lighting, ventilation, water and
                                                                                                                layouts for groups of buildings             renewable energy. They sometimes
    Good communication with the local                   club arranged temporary contractor’s
                                                                                                                and most of what is referred to as          also design the drainage. They
    community is important. Potentially it              access through adjacent land which
                                                                                                                the built environment. They liaise          calculate the proposed energy use
    could lessen objections to your planning            made larger deliveries possible and
                                                                                                                with current users, clients, and            of the buildings.
    application and help towards a smooth               shortened the construction period.
                                                                                                                construction specialists and their          Refer to www.cibse.org
    relationship with neighbours before,                Good links with the local community
                                                                                                                designs take account of information
    during and after construction. People               also provides the opportunity to make                                                           4   Quantity Surveyor
                                                                                                                about cost, safety and social
    can be sensitive to change so it’s                  contact with new members. One way of
                                                                                                                factors from other specialists in           Quantity surveyors measure,
    worth finding ways to keep neighbours               communicating is to develop a master
                                                                                                                the team. They advise clients on            estimate and advise on the cost of
    informed. This could have surprising                plan of the site inclusive of all your future
                                                                                                                the practicality of building projects       the designs produced by architects,
    and beneficial results, for example one             plans (see example below).
                                                                                                                and seek permission and approval            structural engineers and services
                                                                                                                to see if the proposals can be put          engineers. www.RICS.org
                                                                                                                into practice. Once building starts
                                                                                                                                                        5   Construction Design
                                                                                                                they can coordinate and administer
                                                                                                                                                            Management
                                                                                                                the building contract through
                                                                                                                                                            (CDM) Coordinator
                                                                                                                to completion. Refer to RIBA
                                                                                                                Commissioning Architecture leaflet          CDM coordinators advise clients on
                                                                                                                and website                                 health and safety issues, risks and
                                                                                                                www.architecture.com/                       the competency of the design team.
                                                                                                                UseAnArchitect.                             This is applicable across all project
                                                                                                                                                            themes. They must be appointed by
                                                                                                                                                            work stage C/ concept design, as
                                                                                                                                                            outlined in section 8.




4   Developing a Project – From Concept to Completion                                                                                                          Developing a Project – From Concept to Completion   5
6       Consultant Services (continued)                                                           6      Consultant Services (continued)

    6     Other Specialists                              	   •		 eritage	and	conservation	
                                                               H                                      	       •		 roject	managers	take	
                                                                                                                P                                      Fine Turf Projects
                                                               specialists advise on preserving                 responsibility for planning and
          Some projects might also                                                                                                                     As this type of work carries high levels
                                                               historic buildings and restoration.              facilitating a project. They can act
          require further specialist input                                                                                                             of risk regarding climate and tight
                                                                                                                on the client’s behalf providing
          during the design stage which                  	   •		 ighways	engineers	design	and	
                                                               H                                                                                       timescales, ECB advises that extremely
                                                                                                                advice and be given responsibility
          will become apparent during the                      advise on new roads or alterations                                                      tight control of all phases of work is
                                                                                                                for making key decisions.
          preparation stage:                                   to the public highways.                                                                 maintained by a qualified professional.
    	     •		 ccess	consultants	advise	on	
            A                                            	   •		 andscape	architects	design	the	
                                                               L                                                                                       To minimise risk within the supply
            designing inclusive buildings for                  spaces and landscape around the        Fine Turf Projects (including new                chain contracts scheduled for late
            people of all abilities.                           buildings including details for hard   construction and renovations) and                summer / early autumn should be
                                                               and soft areas, trees and pitches.     Non Turf Projects                                contracted by the end of February
    	     •		 nvironmental	consultants	
            E
                                                                                                                                                       of the year the work is planned.
            and ecologists advise on                     	   •		 lanning	consultants	provide	
                                                               P                                      The design, construction and project
            environmental issues which might                   specialist advice when preparing       management of new facilities requires            Larger scale schemes will require a
            be required if the site is a natural               planning submissions or appeals        specialist consultants who in turn               development period of up to two years.
            habitat for protected species.                     in areas with sensitive                have access to high quality survey and
                                                                                                                                                       www.ecb.co.uk/techspecs
                                                               planning issues.                       analysis technology.
                                                                                                      Fine turf consultants will offer a range
                                                                                                      of services at different costs. Please           Non Turf Projects
                                                                                                      ensure you confirm what service you are
                                                                                                                                                       Larger scale schemes will require a
                                                                                                      receiving and that the price is fixed.
                                                                                                                                                       development period of up to 12 months.
                                                                                                      While projects may be less complex               www.ecb.co.uk/techspecs
                                                                                                      than most building projects the club/
                                                                                                      organisation should follow the same
                                                                                                      methodology as the RIBA work stages
                                                                                                      as outlined in this document.
                                                                                                      It should be noted that the ECB can
                                                                                                      advise of the type of services and
                                                                                                      support you may require.




6   Developing a Project and Funding for to Completion
    Sources of Grant Aid – From Concept Cricket Clubs                                                                                                         Developing a Project –and Funding forto Completion
                                                                                                                                                               Sources of Grant Aid From Concept Cricket Clubs     7
6        Consultant Services (continued)                                                         7    Technical Compliance

                                                                                                      Technical Guidance Notes – Each             whichever is the higher quality
       Useful Contacts                                                                                project’s design and specification          design specification.
                                                                                                      should comply with, as a minimum,
                                                                                                                                                  Designers of projects should consult
                                                                                                      Sport England Technical Guidance
       Sports & Play Construction                         Sports & Fitness Equipment                                                              with the relevant organisations and
                                                                                                      Notes (www.sportengland.org) or
       Association (SAPCA)                                Association (SAFEA)                                                                     technical specifications throughout the
                                                                                                      ECB Technical Guidance Notes
                                                                                                                                                  design stage.
       Federation House                                   Federation House                            (www.ecb.co.uk/techspecs) -
       Stoneleigh Park                                    Stoneleigh Park
       Warwickshire                                       Warwickshire
       CV8 2RF                                            CV8 2RF
       Tel: 024 7641 6316                                 Tel: 024 7641 4999                            8    RIBA Design Work Stages
       Website: www.sapca.org.uk                          Website: www.safea.org.uk


       The Royal Institute of British                     The Royal Institute of Chartered            The Royal Institute of British Architects   Preparation for work stage A:
       Architects (RIBA)                                  Surveyors (RICS)                            (RIBA) uses a plan of work to set out
                                                                                                                                                  1. Business plan
       66 Portland Place                                  RICS Contact Centre                         five main stages for building projects:
       London                                             Surveyor Court                              preparation, design, pre-construction,      2. The site including address, details of
       W1B 1AD                                            Westwood Way                                construction and use. The main stages          the boundary and any rights of way
                                                          Coventry                                    are sub-divided into smaller work stages
       Tel: 020 7580 5533                                                                                                                         3. Details of the freehold or leasehold,
                                                          CV4 8JE                                     A to L as summarised in table one
       Website: www.architecture.com                                                                                                                 length of lease and security of
                                                                                                      (refer to page 14). These are usually
                                                          Tel: 0870 3331600                                                                          tenure – in some cases this can take
                                                                                                      carried out in sequence. This is
                                                          Website: www.rics.org                                                                      a while to obtain
                                                                                                      applicable across all project themes.
       Institute of Groundsmanship (IoG)                                                                                                          4. Information about the existing
                                                                                                      In preparation for work stage A, as
       28 Stratford Office Village                                                                                                                   buildings or facilities, mains services
                                                                                                      outlined in table one you should,
       Walker Avenue                                                                                                                                 and utilities, pitches and ground
                                                                                                      assemble some useful information
       Wolverton Mill East                                                                                                                           conditions, asbestos survey plan
                                                                                                      about your club/organisation, the
       Milton Keynes                                                                                  existing facilities and the                 5. Contact details for key club/
       MK12 5TW                                                                                       proposed project.                              organisation members
       Tel: 01908 312 511                                                                                                                         6. Existing and future match fixtures
       Website: www.iog.org                                                                                                                          and programme of use
                                                                                                                                                  7. Sports development
       It should be noted that legal and professional fees will not be supported by the England and
       Wales Cricket Board’s Funding Programmes.




8   Developing a Project and Funding for to Completion
    Sources of Grant Aid – From Concept Cricket Clubs                                                                                                    Developing a Project –and Funding forto Completion
                                                                                                                                                          Sources of Grant Aid From Concept Cricket Clubs     9
8       RIBA Design Work Stages                                                              10    Competitive Tendering

     8. Other events or sports use (if the               11. Records of early consultation          Careful project planning requires that      and for projects over £25k three
        facilities are shared with other                     with the local authority planning      your proposals have been properly           competitive quotes must be provided.
        sports then refer to the appropriate                 department, previous planning          costed at an early stage in order to        A Tender Analysis should be conducted
        guidance notes from the other                        applications, review of planning       set a budget for the project. These         (see section 11).
        sports governing bodies)                             guidance documents                     costs should be revisited and updated
                                                                                                                                                Each quote should be independently
                                                                                                    throughout the project life cycle to
     9. Outline schedule of accommodation                                                                                                       obtained and should relate to a specific
                                                                                                    ensure that the project remains
                                                                                                                                                project brief outlining your requirements.
     10. Facilities for car parking and public                                                      on budget.
                                                                                                                                                You must be able to compare each
         transport links                                                                            Many of the funding streams                 quote like for like.
                                                                                                    administered by the ECB draw from
                                                                                                                                                To ensure that there is no conflict of
                                                                                                    public funding, as such they are subject
                                                                                                                                                interests, you must indicate whether
                                                                                                    to the EU procurement requirements as
                                                                                                                                                a potential contractor or consultant is
                                                                                                    a commitment to best value. It should
         9        Planning Consent                                                                  be noted that this does not solely relate
                                                                                                                                                associated with the club/organisation,
                                                                                                                                                its directors or employees.
                                                                                                    to price. For projects up to £25k two
                                                                                                    competitive quotes must be provided
     Written confirmation on the status of               The importance of planning permission
     Planning Consent of the Project must                is easy to overlook and should be one of
     be evidenced. Failure to do so will delay           the first things you consider when you
     the Project.                                        begin to plan the project.
     Planning permission (or ‘consent’ or                Further information can be found at:
     ‘approval’) is the legal authority you
                                                         http://www.sportengland.org/
     require to carry out development, so it is
                                                         making_a_planning_application_-_
     important at the outset of any project to
                                                         a_guide_for_sports_clubs.pdf
     clarify what constitutes ‘development’
     and whether or not you need to make a
     formal planning application.




10   Developing a Project – From Concept to Completion                                                                                                 Developing a Project – From Concept to Completion   11
11        Tender Analysis                                                                  12   ECB FFU Contact Details

     A tender analysis is defined as a                   to interview a short list of tendering
     comparative exercise assessing                      companies and invite them to explain
     the quality and cost of each tender                 their submission and any areas           Dan Musson                              John Huband
     submission. To do this effectively there            of ambiguity.
                                                                                                  Regional Funding & Facilities Manager   Regional Funding & Facilities Manager
     must be consistent assessment criteria
                                                         ECB require a tender analysis to be      (North)                                 (Midlands)
     and clear sections for comparative
                                                         submitted with each application. The     England and Wales Cricket Board         England and Wales Cricket Board
     analysis. A quality assessment is
                                                         purpose of the analysis exercise is to   c/o County Cricket Ground               c/o County Cricket Ground
     conducted on the company, its past
                                                         evidence best value (a combination of    Old Trafford                            Edgbaston
     performance and its adherence to
                                                         quality and cost) and to explain why     Manchester                              Birmingham
     the design criteria whilst a cost sum
                                                         the club/organisation has preferred a    M16 0PX                                 B5 7QU
     analysis or bill of quantities will clarify
                                                         particular contractor or supplier.
     cost. Where there is little difference in                                                    Tel: 0161 877 6834                      Tel: 07500 992 659
     tender submissions you may choose                                                            Email: daniel.musson@ecb.co.uk          Email: john.huband@ecb.co.uk


                                                                                                  Tim Nicholls                            Chris Whitaker
                                                                                                  Regional Funding & Facilities Manager   Regional Funding & Facilities Manager
                                                                                                  (London & East)                         (South)
                                                                                                  England and Wales Cricket Board         England and Wales Cricket Board
                                                                                                  Lord’s Cricket Ground                   Lord’s Cricket Ground
                                                                                                  London                                  London
                                                                                                  NW8 8QZ                                 NW8 8QZ
                                                                                                  Tel: 020 7432 1176                      Tel: 020 7432 1206
                                                                                                  Email: tim.nicholls@ecb.co.uk           Email: chris.whitaker@ecb.co.uk


                                                                                                  Fiona Prescott                          ECB Website Links
                                                                                                  Research and Development Manager        www.ecb.co.uk/facilities
                                                                                                  (Applications across Wales only)
                                                                                                                                          www.ecb.co.uk/funding
                                                                                                  England and Wales Cricket Board
                                                                                                  c/o County Cricket Ground               www.ecb.co.uk/techspecs
                                                                                                  Old Trafford
                                                                                                  Manchester
                                                                                                  M16 0PX
                                                                                                                                          General Enquiries
                                                                                                  Tel: 07785 527 105
                                                                                                  Email: fiona.prescott@ecb.co.uk         facilities@ecb.co.uk


12   Developing a Project – From Concept to Completion                                                                                          Developing a Project – From Concept to Completion   13
13        Table 1 – Design Work Stages


        Main Stage                                        Work Stage                                 Brief Description
                                                                                                     The applicants needs and objectives are identified along with the business case and any possible
                                                                                                     constraints on the development Feasibility studies should be prepared and the options assessed
                                                          A   Appraisal                              by the applicant to enable them to decide whether to proceed. Documenting some ideas and
                                                                                                     options with approximate costs can be done relatively inexpensively.
        Preparation
                                                                                                     At this stage key requirement, constraints, procurement methods and consultants are identified.
                                                          B   Design Brief                           The range of professional consultants and skills required will depend on the project size and its
                                                                                                     complexity, as outlined in Section 6 of this document.


                                                                                                     The design stage is divided into three: stage C, Concept Design is where outline proposals,
                                                          C   Concept
                                                                                                     specifications and cost plans are prepared and the procurement route is reviewed. The design is
                                                                                                     developed further in stage D and this is when planning applications are typically (but not always)
                                                                                                     submitted. Stage E is when the technical designs and specifications are developed sufficiently to
        Design                                            D   Design Development                     coordinate all the different elements of the project. Once a project is underway the lead consultant
                                                                                                     will guide you through the subsequent work stages which all require client sign-off. Allow time to
                                                                                                     review the drawings and reports prepared by the design team, checking your requirements against
                                                                                                     the design. Early changes and requests are much easier to accommodate whereas late
                                                          E   Technical Design                       changes can have cost implications out of scale with the amendments.


                                                                                                     The pre-construction stage is also divided into three: F/ Production Information is when detailed
                                                          F   Product Information
                                                                                                     information for construction is prepared and submitted to building control for approval.
                                                                                                     G/ Tender Documentation is the preparation and collation of sufficient information to enable
                                                                                                     tenders to be obtained. In this instance, a tender is an offer by a contractor to execute the work at
        Pre-Construction                                  G   Tender Documentation                   a fixed price. H/ Tender Action are when potential contractors and specialists are identified and
                                                                                                     evaluated, then invited to prepare tenders. Once tenders are obtained and appraised, the design
                                                                                                     team will submit their recommendations to the client. Compiling the list of potential contractors will
                                                          H   Tender Action                          often start well in advance of the tender period.


                                                                                                     The construction stage is divided into two: J/ Mobilisation are when the contract is let, the
                                                          I   Construction Mobilisation              contractor appointed, construction information is issued to the contractor and the site is handed
                                                                                                     over by the client. The contractor will need time to prepare before starting on site, for example,
        Construction                                                                                 they will organise their construction team, place orders for materials and arrange sub-contracts.
                                                                                                     K/ Construction are when the contract is administered and the project is built (or refurbished).
                                                          J   Construction to Practical Completion   The design team will issue further information to the contractor if required and also review
                                                                                                     information prepared by the contractor or any specialists.


                                                                                                     The final stage is using the new facilities. The completed project is handed over to the client and
                                                                                                     the contractor leaves site. Some contract administration takes place after practical completion
        Use                                               K   Post Practical Completion              including making final inspections after the defects liability period. The clients might require
                                                                                                     some assistance during initial occupation period, for example, maintenance.


14   Developing a Project and Funding for to Completion
     Sources of Grant Aid – From Concept Cricket Clubs                                                                                                             Developing a Project –and Funding forto Completion
                                                                                                                                                                    Sources of Grant Aid From Concept Cricket Clubs     15
Sources of Grant Aid and Funding for Cricket Clubs   17
England and Wales Cricket Board
                          Lords Cricket Ground London NW8 8QZ
                          T: 020 7432 1200 F: 020 7289 5619 E: facilities@ecb.co.uk
                          www.ecb.co.uk

                          From playground to Test arena
                          August 2009




18   Sources of Grant Aid and Funding for Cricket Clubs

Contenu connexe

Similaire à Developing a Project from Concept to Completion

Top10 Key Attributes For A Successful Project
Top10 Key Attributes For A Successful ProjectTop10 Key Attributes For A Successful Project
Top10 Key Attributes For A Successful Projectarjencornelisse
 
Opportunity Analysis
Opportunity AnalysisOpportunity Analysis
Opportunity AnalysisBob Prieto
 
Cognizant Presentation for Task 1.pptx
Cognizant Presentation for Task 1.pptxCognizant Presentation for Task 1.pptx
Cognizant Presentation for Task 1.pptxqqsw1
 
Cognizant Presentation for Task 1.pptx
Cognizant Presentation for Task 1.pptxCognizant Presentation for Task 1.pptx
Cognizant Presentation for Task 1.pptxMannuMatamAkash
 
Major Projects Booklet
Major Projects BookletMajor Projects Booklet
Major Projects BookletRichard Cole
 
Implementation of the pmo proposal
Implementation of the pmo proposalImplementation of the pmo proposal
Implementation of the pmo proposalHugh Shults
 
Conceptcsi Capabilities 2012.1 B
Conceptcsi Capabilities 2012.1 BConceptcsi Capabilities 2012.1 B
Conceptcsi Capabilities 2012.1 Bmsilla
 
Project management playbook innovate vancouver (2019)
Project management playbook   innovate vancouver (2019)Project management playbook   innovate vancouver (2019)
Project management playbook innovate vancouver (2019)Innovate Vancouver
 
Open source engagement – best practices_v0.5
Open source engagement – best practices_v0.5Open source engagement – best practices_v0.5
Open source engagement – best practices_v0.5CloudExpoEurope
 
Requirements Gathering for Project Management Success
Requirements Gathering for Project Management SuccessRequirements Gathering for Project Management Success
Requirements Gathering for Project Management SuccessWG Consulting
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management OverviewTechNoleGirl
 
Project Management 101
Project Management 101Project Management 101
Project Management 101Ryan Campbell
 
Top Project Management Best Practices.pdf
Top Project Management Best Practices.pdfTop Project Management Best Practices.pdf
Top Project Management Best Practices.pdfOrangescrum
 
Practices of an agile developer
Practices of an agile developerPractices of an agile developer
Practices of an agile developerDUONG Trong Tan
 

Similaire à Developing a Project from Concept to Completion (20)

Top10 Key Attributes For A Successful Project
Top10 Key Attributes For A Successful ProjectTop10 Key Attributes For A Successful Project
Top10 Key Attributes For A Successful Project
 
Opportunity Analysis
Opportunity AnalysisOpportunity Analysis
Opportunity Analysis
 
7 keys
7 keys7 keys
7 keys
 
Cognizant Presentation for Task 1.pptx
Cognizant Presentation for Task 1.pptxCognizant Presentation for Task 1.pptx
Cognizant Presentation for Task 1.pptx
 
Cognizant Presentation for Task 1.pptx
Cognizant Presentation for Task 1.pptxCognizant Presentation for Task 1.pptx
Cognizant Presentation for Task 1.pptx
 
UNIT-1.pptx
UNIT-1.pptxUNIT-1.pptx
UNIT-1.pptx
 
Stanford apm ashish v0.1
Stanford apm   ashish v0.1Stanford apm   ashish v0.1
Stanford apm ashish v0.1
 
Major Projects Booklet
Major Projects BookletMajor Projects Booklet
Major Projects Booklet
 
TODAY 2016_03_31
TODAY 2016_03_31TODAY 2016_03_31
TODAY 2016_03_31
 
Implementation of the pmo proposal
Implementation of the pmo proposalImplementation of the pmo proposal
Implementation of the pmo proposal
 
Conceptcsi Capabilities 2012.1 B
Conceptcsi Capabilities 2012.1 BConceptcsi Capabilities 2012.1 B
Conceptcsi Capabilities 2012.1 B
 
Project management playbook innovate vancouver (2019)
Project management playbook   innovate vancouver (2019)Project management playbook   innovate vancouver (2019)
Project management playbook innovate vancouver (2019)
 
Open source engagement – best practices_v0.5
Open source engagement – best practices_v0.5Open source engagement – best practices_v0.5
Open source engagement – best practices_v0.5
 
Managing revolving project resources
Managing revolving project resourcesManaging revolving project resources
Managing revolving project resources
 
Requirements Gathering for Project Management Success
Requirements Gathering for Project Management SuccessRequirements Gathering for Project Management Success
Requirements Gathering for Project Management Success
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Project Management 101
Project Management 101Project Management 101
Project Management 101
 
Top Project Management Best Practices.pdf
Top Project Management Best Practices.pdfTop Project Management Best Practices.pdf
Top Project Management Best Practices.pdf
 
Practices of an agile developer
Practices of an agile developerPractices of an agile developer
Practices of an agile developer
 

Plus de Yorkshire Cricket Board

Funding 4 sport ycb club seminar west yorkshire presentation v2
Funding 4 sport ycb club seminar west yorkshire presentation v2Funding 4 sport ycb club seminar west yorkshire presentation v2
Funding 4 sport ycb club seminar west yorkshire presentation v2Yorkshire Cricket Board
 
Selecting grass seed for your cricket square
Selecting grass seed for your cricket squareSelecting grass seed for your cricket square
Selecting grass seed for your cricket squareYorkshire Cricket Board
 
Nat west cricketforce 2011 newsletter february
Nat west cricketforce 2011 newsletter   februaryNat west cricketforce 2011 newsletter   february
Nat west cricketforce 2011 newsletter februaryYorkshire Cricket Board
 
Yorkshire cricket foundation leaflet nov 10
Yorkshire cricket foundation leaflet nov 10Yorkshire cricket foundation leaflet nov 10
Yorkshire cricket foundation leaflet nov 10Yorkshire Cricket Board
 
ECB TS5- Guidance Notes on Pavilions & Clubhouses
ECB TS5- Guidance Notes on Pavilions & ClubhousesECB TS5- Guidance Notes on Pavilions & Clubhouses
ECB TS5- Guidance Notes on Pavilions & ClubhousesYorkshire Cricket Board
 

Plus de Yorkshire Cricket Board (19)

Adult participation presentation
Adult participation presentationAdult participation presentation
Adult participation presentation
 
2013 YCB Cricket seminars sport england
2013 YCB Cricket seminars   sport england2013 YCB Cricket seminars   sport england
2013 YCB Cricket seminars sport england
 
Ecb seminar 2013 cdm pp pres
Ecb seminar 2013 cdm pp presEcb seminar 2013 cdm pp pres
Ecb seminar 2013 cdm pp pres
 
Club leaders
Club leadersClub leaders
Club leaders
 
Funding 4 sport ycb club seminar west yorkshire presentation v2
Funding 4 sport ycb club seminar west yorkshire presentation v2Funding 4 sport ycb club seminar west yorkshire presentation v2
Funding 4 sport ycb club seminar west yorkshire presentation v2
 
ECB Cricket Factory Flyer 2011
ECB Cricket Factory Flyer 2011ECB Cricket Factory Flyer 2011
ECB Cricket Factory Flyer 2011
 
ECB Planning for Long Term Success
ECB Planning for Long Term SuccessECB Planning for Long Term Success
ECB Planning for Long Term Success
 
YCB GA Introduction
YCB GA IntroductionYCB GA Introduction
YCB GA Introduction
 
Selecting grass seed for your cricket square
Selecting grass seed for your cricket squareSelecting grass seed for your cricket square
Selecting grass seed for your cricket square
 
South Yorkshire Disability Case study
South Yorkshire Disability Case study South Yorkshire Disability Case study
South Yorkshire Disability Case study
 
Nat west cricketforce 2011 newsletter february
Nat west cricketforce 2011 newsletter   februaryNat west cricketforce 2011 newsletter   february
Nat west cricketforce 2011 newsletter february
 
Yorkshire cricket foundation leaflet nov 10
Yorkshire cricket foundation leaflet nov 10Yorkshire cricket foundation leaflet nov 10
Yorkshire cricket foundation leaflet nov 10
 
CASC YCB Club Development Seminar
CASC YCB Club Development SeminarCASC YCB Club Development Seminar
CASC YCB Club Development Seminar
 
Fundrazor Presentation
Fundrazor Presentation Fundrazor Presentation
Fundrazor Presentation
 
Stuart Canvas
Stuart CanvasStuart Canvas
Stuart Canvas
 
Club Seminar November 2010
Club Seminar November 2010Club Seminar November 2010
Club Seminar November 2010
 
Ts4 2007
Ts4 2007Ts4 2007
Ts4 2007
 
Guidelines for rolling in cricket
Guidelines for rolling in cricketGuidelines for rolling in cricket
Guidelines for rolling in cricket
 
ECB TS5- Guidance Notes on Pavilions & Clubhouses
ECB TS5- Guidance Notes on Pavilions & ClubhousesECB TS5- Guidance Notes on Pavilions & Clubhouses
ECB TS5- Guidance Notes on Pavilions & Clubhouses
 

Dernier

ppt on Myself, Occupation and my Interest
ppt on Myself, Occupation and my Interestppt on Myself, Occupation and my Interest
ppt on Myself, Occupation and my InterestNagaissenValaydum
 
Croatia vs Albania Clash of Euro Cup 2024 Squad Preparations and Euro Cup Dre...
Croatia vs Albania Clash of Euro Cup 2024 Squad Preparations and Euro Cup Dre...Croatia vs Albania Clash of Euro Cup 2024 Squad Preparations and Euro Cup Dre...
Croatia vs Albania Clash of Euro Cup 2024 Squad Preparations and Euro Cup Dre...Eticketing.co
 
Jankipuram / Call Girls Lucknow | Whatsapp No 🫗 8923113531 🎳 VIP Escorts Serv...
Jankipuram / Call Girls Lucknow | Whatsapp No 🫗 8923113531 🎳 VIP Escorts Serv...Jankipuram / Call Girls Lucknow | Whatsapp No 🫗 8923113531 🎳 VIP Escorts Serv...
Jankipuram / Call Girls Lucknow | Whatsapp No 🫗 8923113531 🎳 VIP Escorts Serv...gurkirankumar98700
 
Plan d'orientations stratégiques rugby féminin
Plan d'orientations stratégiques rugby fémininPlan d'orientations stratégiques rugby féminin
Plan d'orientations stratégiques rugby fémininThibaut TATRY
 
Who Is Emmanuel Katto Uganda? His Career, personal life etc.
Who Is Emmanuel Katto Uganda? His Career, personal life etc.Who Is Emmanuel Katto Uganda? His Career, personal life etc.
Who Is Emmanuel Katto Uganda? His Career, personal life etc.Marina Costa
 
Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...
Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...
Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...World Wide Tickets And Hospitality
 
( Sports training) All topic (MCQs).pptx
( Sports training) All topic (MCQs).pptx( Sports training) All topic (MCQs).pptx
( Sports training) All topic (MCQs).pptxParshotamGupta1
 
Italy vs Albania Tickets: Italy's Quest for Euro Cup Germany History, Defendi...
Italy vs Albania Tickets: Italy's Quest for Euro Cup Germany History, Defendi...Italy vs Albania Tickets: Italy's Quest for Euro Cup Germany History, Defendi...
Italy vs Albania Tickets: Italy's Quest for Euro Cup Germany History, Defendi...Eticketing.co
 
Tableaux 9ème étape circuit fédéral 2024
Tableaux 9ème étape circuit fédéral 2024Tableaux 9ème étape circuit fédéral 2024
Tableaux 9ème étape circuit fédéral 2024HechemLaameri
 
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...Neil Horowitz
 
CALL ON ➥8923113531 🔝Call Girls Telibagh Lucknow best Night Fun service 🧣
CALL ON ➥8923113531 🔝Call Girls Telibagh Lucknow best Night Fun service  🧣CALL ON ➥8923113531 🔝Call Girls Telibagh Lucknow best Night Fun service  🧣
CALL ON ➥8923113531 🔝Call Girls Telibagh Lucknow best Night Fun service 🧣anilsa9823
 
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts serviceChennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts servicevipmodelshub1
 
JORNADA 4 LIGA MURO 2024TUXTEPEC1234.pdf
JORNADA 4 LIGA MURO 2024TUXTEPEC1234.pdfJORNADA 4 LIGA MURO 2024TUXTEPEC1234.pdf
JORNADA 4 LIGA MURO 2024TUXTEPEC1234.pdfArturo Pacheco Alvarez
 
CALL ON ➥8923113531 🔝Call Girls Chinhat Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Chinhat Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Chinhat Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Chinhat Lucknow best sexual serviceanilsa9823
 
🔝|97111༒99012🔝 Call Girls In {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
🔝|97111༒99012🔝 Call Girls In  {Delhi} Cr Park ₹5.5k Cash Payment With Room De...🔝|97111༒99012🔝 Call Girls In  {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
🔝|97111༒99012🔝 Call Girls In {Delhi} Cr Park ₹5.5k Cash Payment With Room De...Diya Sharma
 
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改atducpo
 

Dernier (20)

Call Girls Service Noida Extension @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Noida Extension @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Noida Extension @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Noida Extension @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
ppt on Myself, Occupation and my Interest
ppt on Myself, Occupation and my Interestppt on Myself, Occupation and my Interest
ppt on Myself, Occupation and my Interest
 
Croatia vs Albania Clash of Euro Cup 2024 Squad Preparations and Euro Cup Dre...
Croatia vs Albania Clash of Euro Cup 2024 Squad Preparations and Euro Cup Dre...Croatia vs Albania Clash of Euro Cup 2024 Squad Preparations and Euro Cup Dre...
Croatia vs Albania Clash of Euro Cup 2024 Squad Preparations and Euro Cup Dre...
 
Jankipuram / Call Girls Lucknow | Whatsapp No 🫗 8923113531 🎳 VIP Escorts Serv...
Jankipuram / Call Girls Lucknow | Whatsapp No 🫗 8923113531 🎳 VIP Escorts Serv...Jankipuram / Call Girls Lucknow | Whatsapp No 🫗 8923113531 🎳 VIP Escorts Serv...
Jankipuram / Call Girls Lucknow | Whatsapp No 🫗 8923113531 🎳 VIP Escorts Serv...
 
Plan d'orientations stratégiques rugby féminin
Plan d'orientations stratégiques rugby fémininPlan d'orientations stratégiques rugby féminin
Plan d'orientations stratégiques rugby féminin
 
Who Is Emmanuel Katto Uganda? His Career, personal life etc.
Who Is Emmanuel Katto Uganda? His Career, personal life etc.Who Is Emmanuel Katto Uganda? His Career, personal life etc.
Who Is Emmanuel Katto Uganda? His Career, personal life etc.
 
Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...
Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...
Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...
 
( Sports training) All topic (MCQs).pptx
( Sports training) All topic (MCQs).pptx( Sports training) All topic (MCQs).pptx
( Sports training) All topic (MCQs).pptx
 
Italy vs Albania Tickets: Italy's Quest for Euro Cup Germany History, Defendi...
Italy vs Albania Tickets: Italy's Quest for Euro Cup Germany History, Defendi...Italy vs Albania Tickets: Italy's Quest for Euro Cup Germany History, Defendi...
Italy vs Albania Tickets: Italy's Quest for Euro Cup Germany History, Defendi...
 
Tableaux 9ème étape circuit fédéral 2024
Tableaux 9ème étape circuit fédéral 2024Tableaux 9ème étape circuit fédéral 2024
Tableaux 9ème étape circuit fédéral 2024
 
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...
 
CALL ON ➥8923113531 🔝Call Girls Telibagh Lucknow best Night Fun service 🧣
CALL ON ➥8923113531 🔝Call Girls Telibagh Lucknow best Night Fun service  🧣CALL ON ➥8923113531 🔝Call Girls Telibagh Lucknow best Night Fun service  🧣
CALL ON ➥8923113531 🔝Call Girls Telibagh Lucknow best Night Fun service 🧣
 
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts serviceChennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts service
 
JORNADA 4 LIGA MURO 2024TUXTEPEC1234.pdf
JORNADA 4 LIGA MURO 2024TUXTEPEC1234.pdfJORNADA 4 LIGA MURO 2024TUXTEPEC1234.pdf
JORNADA 4 LIGA MURO 2024TUXTEPEC1234.pdf
 
Call Girls In Vasundhara 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In Vasundhara 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICECall Girls In Vasundhara 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In Vasundhara 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
 
CALL ON ➥8923113531 🔝Call Girls Chinhat Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Chinhat Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Chinhat Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Chinhat Lucknow best sexual service
 
Call Girls In RK Puram 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In RK Puram 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICECall Girls In RK Puram 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In RK Puram 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
 
🔝|97111༒99012🔝 Call Girls In {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
🔝|97111༒99012🔝 Call Girls In  {Delhi} Cr Park ₹5.5k Cash Payment With Room De...🔝|97111༒99012🔝 Call Girls In  {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
🔝|97111༒99012🔝 Call Girls In {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
 
Call Girls 🫤 Malviya Nagar ➡️ 9999965857 ➡️ Delhi 🫦 Russian Escorts FULL ENJOY
Call Girls 🫤 Malviya Nagar ➡️ 9999965857  ➡️ Delhi 🫦  Russian Escorts FULL ENJOYCall Girls 🫤 Malviya Nagar ➡️ 9999965857  ➡️ Delhi 🫦  Russian Escorts FULL ENJOY
Call Girls 🫤 Malviya Nagar ➡️ 9999965857 ➡️ Delhi 🫦 Russian Escorts FULL ENJOY
 
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改
 

Developing a Project from Concept to Completion

  • 1. Developing a Project From Concept to Completion www.ecb.co.uk Sources of Grant Aid and Funding for Cricket Clubs 1
  • 2. Contents Developing a Project – From Concept to Completion Section Page Introduction 1 1 Geting Started 2 When embarking on the development of a facility 2 Project Development Team 2 project, careful consideration and planning is required to ensure the final product meets the original concept. 3 Successful Clients 3 4 Getting Support 4 The purpose of this document is to set a clear project 5 Local Communities 4 development methodology in taking any new facility 6 Consultant Services 5 from concept to completion. 7 Technical Compliance 9 This document will assist any type of facility project 8 RIBA Design Work Stages 9 meeting the requirements of potential partners/funders 9 Planning Consent 10 and the aspirations of people engaged as deliverers 10 Competitive Tendering 11 of sport. 11 Tender Analysis 12 “Developing a Project” provides advice and guidance 12 FFU Contact Details 13 with a series of useful links and contacts to support 13 Design Work Stages 14 you throughout the process. The document has been written in conjunction with the England and Wales Cricket Board’s Funding Programmes Guidance Notes which are available to download from www.ecb.co.uk/funding 2 Sources of Grant Aid and Funding for Cricket Clubs Developing a Project – From Concept to Completion 1
  • 3. 1 Getting Started 3 Successful Clients Think about the aims of your project and The Commission for Architecture 4. Develop and communicate a ways to accommodate the current and and the Built Environment (CABE) clear brief future needs of the club/organisation, publication “Creating Excellent 5. Make a realistic financial including how often the facility will be Buildings” describes how to be a commitment from used on a weekly and seasonal basis. successful client. the outset It is important that you consult within Each development project is unique, your membership as widely as possible 6. Adopt integrated processes with special local conditions for site, use about the aims and objectives of your patterns and social context. However, 7. Find the right people for the job club/organisation. all projects need well structured project 8. Respond and contribute to the management and can benefit from the context ten key ways the client can help achieve design quality. 9. Commit to sustainability 2 Project Development Team 1. Provide strong client leadership 10. Sign off all key stages 2. Give enough time at the right time All work stages require sign-off so allow It is strongly recommended that you remove themselves from the committee time to review the drawings and reports form a project development team and until the completion of the project. 3. Learn from your own and other prepared by the design team, carefully appoint a team leader who should successful projects The project team should be established checking your requirements against the remain consistent throughout the design. prior to starting any design work and duration of the project. The project team remain operational until final completion should consist of individuals with skill of the works. NB: the size and skill sets sets that are relevant and appropriate required to drive the project may change for the project. throughout the lifespan of the works. When forming the project team, do not limit its composition to the club/ organisation members unless the members can clearly evidence that they have the relevant experience and qualifications to compliment the planned project work. It should be noted if a member of the club/organisation is engaged to carry out any works on the project and they are current members of the committee, this would be seen as a conflict of interests. Therefore, any members who find themselves in this position should 2 Developing a Project and Funding for to Completion Sources of Grant Aid – From Concept Cricket Clubs Developing a Project –and Funding forto Completion Sources of Grant Aid From Concept Cricket Clubs 3
  • 4. 4 Getting Support 6 Consultant Services The ECB Funding and Facilities Funding and planning permission are If the appropriate skills are not available 2 Structural Engineer Unit (FFU) should be your first point two important hurdles in the preparation within the project team, you may need Structural engineers design and of call for advice. You should make and design stages of a project. The ECB to engage the services of specialists, calculate the building structure and contact with the FFU during work stage Regional Funding and Facilities Manager as follows: foundations. They sometimes also A, as outlined in section 8, and show will assess the proposals for technical Building Projects (including renovation design below ground drainage. them your project (refer to contacts compliance, sports development and and refurbishments) Refer to www.istructe.org page 13). Consulting the ECB at the financial affordability. earliest opportunity allows their input to 1 Architect 3 Mechanical and Electrical (M&E) be more valuable. Services Engineer Architects design new buildings, the spaces around them and M&E services engineers design and alterations to existing buildings. coordinate the services of buildings 5 Local Communities They also advise on the restoration including gas, electricity, heating, and conservation of old buildings, lighting, ventilation, water and layouts for groups of buildings renewable energy. They sometimes Good communication with the local club arranged temporary contractor’s and most of what is referred to as also design the drainage. They community is important. Potentially it access through adjacent land which the built environment. They liaise calculate the proposed energy use could lessen objections to your planning made larger deliveries possible and with current users, clients, and of the buildings. application and help towards a smooth shortened the construction period. construction specialists and their Refer to www.cibse.org relationship with neighbours before, Good links with the local community designs take account of information during and after construction. People also provides the opportunity to make 4 Quantity Surveyor about cost, safety and social can be sensitive to change so it’s contact with new members. One way of factors from other specialists in Quantity surveyors measure, worth finding ways to keep neighbours communicating is to develop a master the team. They advise clients on estimate and advise on the cost of informed. This could have surprising plan of the site inclusive of all your future the practicality of building projects the designs produced by architects, and beneficial results, for example one plans (see example below). and seek permission and approval structural engineers and services to see if the proposals can be put engineers. www.RICS.org into practice. Once building starts 5 Construction Design they can coordinate and administer Management the building contract through (CDM) Coordinator to completion. Refer to RIBA Commissioning Architecture leaflet CDM coordinators advise clients on and website health and safety issues, risks and www.architecture.com/ the competency of the design team. UseAnArchitect. This is applicable across all project themes. They must be appointed by work stage C/ concept design, as outlined in section 8. 4 Developing a Project – From Concept to Completion Developing a Project – From Concept to Completion 5
  • 5. 6 Consultant Services (continued) 6 Consultant Services (continued) 6 Other Specialists • eritage and conservation H • roject managers take P Fine Turf Projects specialists advise on preserving responsibility for planning and Some projects might also As this type of work carries high levels historic buildings and restoration. facilitating a project. They can act require further specialist input of risk regarding climate and tight on the client’s behalf providing during the design stage which • ighways engineers design and H timescales, ECB advises that extremely advice and be given responsibility will become apparent during the advise on new roads or alterations tight control of all phases of work is for making key decisions. preparation stage: to the public highways. maintained by a qualified professional. • ccess consultants advise on A • andscape architects design the L To minimise risk within the supply designing inclusive buildings for spaces and landscape around the Fine Turf Projects (including new chain contracts scheduled for late people of all abilities. buildings including details for hard construction and renovations) and summer / early autumn should be and soft areas, trees and pitches. Non Turf Projects contracted by the end of February • nvironmental consultants E of the year the work is planned. and ecologists advise on • lanning consultants provide P The design, construction and project environmental issues which might specialist advice when preparing management of new facilities requires Larger scale schemes will require a be required if the site is a natural planning submissions or appeals specialist consultants who in turn development period of up to two years. habitat for protected species. in areas with sensitive have access to high quality survey and www.ecb.co.uk/techspecs planning issues. analysis technology. Fine turf consultants will offer a range of services at different costs. Please Non Turf Projects ensure you confirm what service you are Larger scale schemes will require a receiving and that the price is fixed. development period of up to 12 months. While projects may be less complex www.ecb.co.uk/techspecs than most building projects the club/ organisation should follow the same methodology as the RIBA work stages as outlined in this document. It should be noted that the ECB can advise of the type of services and support you may require. 6 Developing a Project and Funding for to Completion Sources of Grant Aid – From Concept Cricket Clubs Developing a Project –and Funding forto Completion Sources of Grant Aid From Concept Cricket Clubs 7
  • 6. 6 Consultant Services (continued) 7 Technical Compliance Technical Guidance Notes – Each whichever is the higher quality Useful Contacts project’s design and specification design specification. should comply with, as a minimum, Designers of projects should consult Sport England Technical Guidance Sports & Play Construction Sports & Fitness Equipment with the relevant organisations and Notes (www.sportengland.org) or Association (SAPCA) Association (SAFEA) technical specifications throughout the ECB Technical Guidance Notes design stage. Federation House Federation House (www.ecb.co.uk/techspecs) - Stoneleigh Park Stoneleigh Park Warwickshire Warwickshire CV8 2RF CV8 2RF Tel: 024 7641 6316 Tel: 024 7641 4999 8 RIBA Design Work Stages Website: www.sapca.org.uk Website: www.safea.org.uk The Royal Institute of British The Royal Institute of Chartered The Royal Institute of British Architects Preparation for work stage A: Architects (RIBA) Surveyors (RICS) (RIBA) uses a plan of work to set out 1. Business plan 66 Portland Place RICS Contact Centre five main stages for building projects: London Surveyor Court preparation, design, pre-construction, 2. The site including address, details of W1B 1AD Westwood Way construction and use. The main stages the boundary and any rights of way Coventry are sub-divided into smaller work stages Tel: 020 7580 5533 3. Details of the freehold or leasehold, CV4 8JE A to L as summarised in table one Website: www.architecture.com length of lease and security of (refer to page 14). These are usually Tel: 0870 3331600 tenure – in some cases this can take carried out in sequence. This is Website: www.rics.org a while to obtain applicable across all project themes. Institute of Groundsmanship (IoG) 4. Information about the existing In preparation for work stage A, as 28 Stratford Office Village buildings or facilities, mains services outlined in table one you should, Walker Avenue and utilities, pitches and ground assemble some useful information Wolverton Mill East conditions, asbestos survey plan about your club/organisation, the Milton Keynes existing facilities and the 5. Contact details for key club/ MK12 5TW proposed project. organisation members Tel: 01908 312 511 6. Existing and future match fixtures Website: www.iog.org and programme of use 7. Sports development It should be noted that legal and professional fees will not be supported by the England and Wales Cricket Board’s Funding Programmes. 8 Developing a Project and Funding for to Completion Sources of Grant Aid – From Concept Cricket Clubs Developing a Project –and Funding forto Completion Sources of Grant Aid From Concept Cricket Clubs 9
  • 7. 8 RIBA Design Work Stages 10 Competitive Tendering 8. Other events or sports use (if the 11. Records of early consultation Careful project planning requires that and for projects over £25k three facilities are shared with other with the local authority planning your proposals have been properly competitive quotes must be provided. sports then refer to the appropriate department, previous planning costed at an early stage in order to A Tender Analysis should be conducted guidance notes from the other applications, review of planning set a budget for the project. These (see section 11). sports governing bodies) guidance documents costs should be revisited and updated Each quote should be independently throughout the project life cycle to 9. Outline schedule of accommodation obtained and should relate to a specific ensure that the project remains project brief outlining your requirements. 10. Facilities for car parking and public on budget. You must be able to compare each transport links Many of the funding streams quote like for like. administered by the ECB draw from To ensure that there is no conflict of public funding, as such they are subject interests, you must indicate whether to the EU procurement requirements as a potential contractor or consultant is a commitment to best value. It should 9 Planning Consent be noted that this does not solely relate associated with the club/organisation, its directors or employees. to price. For projects up to £25k two competitive quotes must be provided Written confirmation on the status of The importance of planning permission Planning Consent of the Project must is easy to overlook and should be one of be evidenced. Failure to do so will delay the first things you consider when you the Project. begin to plan the project. Planning permission (or ‘consent’ or Further information can be found at: ‘approval’) is the legal authority you http://www.sportengland.org/ require to carry out development, so it is making_a_planning_application_-_ important at the outset of any project to a_guide_for_sports_clubs.pdf clarify what constitutes ‘development’ and whether or not you need to make a formal planning application. 10 Developing a Project – From Concept to Completion Developing a Project – From Concept to Completion 11
  • 8. 11 Tender Analysis 12 ECB FFU Contact Details A tender analysis is defined as a to interview a short list of tendering comparative exercise assessing companies and invite them to explain the quality and cost of each tender their submission and any areas Dan Musson John Huband submission. To do this effectively there of ambiguity. Regional Funding & Facilities Manager Regional Funding & Facilities Manager must be consistent assessment criteria ECB require a tender analysis to be (North) (Midlands) and clear sections for comparative submitted with each application. The England and Wales Cricket Board England and Wales Cricket Board analysis. A quality assessment is purpose of the analysis exercise is to c/o County Cricket Ground c/o County Cricket Ground conducted on the company, its past evidence best value (a combination of Old Trafford Edgbaston performance and its adherence to quality and cost) and to explain why Manchester Birmingham the design criteria whilst a cost sum the club/organisation has preferred a M16 0PX B5 7QU analysis or bill of quantities will clarify particular contractor or supplier. cost. Where there is little difference in Tel: 0161 877 6834 Tel: 07500 992 659 tender submissions you may choose Email: daniel.musson@ecb.co.uk Email: john.huband@ecb.co.uk Tim Nicholls Chris Whitaker Regional Funding & Facilities Manager Regional Funding & Facilities Manager (London & East) (South) England and Wales Cricket Board England and Wales Cricket Board Lord’s Cricket Ground Lord’s Cricket Ground London London NW8 8QZ NW8 8QZ Tel: 020 7432 1176 Tel: 020 7432 1206 Email: tim.nicholls@ecb.co.uk Email: chris.whitaker@ecb.co.uk Fiona Prescott ECB Website Links Research and Development Manager www.ecb.co.uk/facilities (Applications across Wales only) www.ecb.co.uk/funding England and Wales Cricket Board c/o County Cricket Ground www.ecb.co.uk/techspecs Old Trafford Manchester M16 0PX General Enquiries Tel: 07785 527 105 Email: fiona.prescott@ecb.co.uk facilities@ecb.co.uk 12 Developing a Project – From Concept to Completion Developing a Project – From Concept to Completion 13
  • 9. 13 Table 1 – Design Work Stages Main Stage Work Stage Brief Description The applicants needs and objectives are identified along with the business case and any possible constraints on the development Feasibility studies should be prepared and the options assessed A Appraisal by the applicant to enable them to decide whether to proceed. Documenting some ideas and options with approximate costs can be done relatively inexpensively. Preparation At this stage key requirement, constraints, procurement methods and consultants are identified. B Design Brief The range of professional consultants and skills required will depend on the project size and its complexity, as outlined in Section 6 of this document. The design stage is divided into three: stage C, Concept Design is where outline proposals, C Concept specifications and cost plans are prepared and the procurement route is reviewed. The design is developed further in stage D and this is when planning applications are typically (but not always) submitted. Stage E is when the technical designs and specifications are developed sufficiently to Design D Design Development coordinate all the different elements of the project. Once a project is underway the lead consultant will guide you through the subsequent work stages which all require client sign-off. Allow time to review the drawings and reports prepared by the design team, checking your requirements against the design. Early changes and requests are much easier to accommodate whereas late E Technical Design changes can have cost implications out of scale with the amendments. The pre-construction stage is also divided into three: F/ Production Information is when detailed F Product Information information for construction is prepared and submitted to building control for approval. G/ Tender Documentation is the preparation and collation of sufficient information to enable tenders to be obtained. In this instance, a tender is an offer by a contractor to execute the work at Pre-Construction G Tender Documentation a fixed price. H/ Tender Action are when potential contractors and specialists are identified and evaluated, then invited to prepare tenders. Once tenders are obtained and appraised, the design team will submit their recommendations to the client. Compiling the list of potential contractors will H Tender Action often start well in advance of the tender period. The construction stage is divided into two: J/ Mobilisation are when the contract is let, the I Construction Mobilisation contractor appointed, construction information is issued to the contractor and the site is handed over by the client. The contractor will need time to prepare before starting on site, for example, Construction they will organise their construction team, place orders for materials and arrange sub-contracts. K/ Construction are when the contract is administered and the project is built (or refurbished). J Construction to Practical Completion The design team will issue further information to the contractor if required and also review information prepared by the contractor or any specialists. The final stage is using the new facilities. The completed project is handed over to the client and the contractor leaves site. Some contract administration takes place after practical completion Use K Post Practical Completion including making final inspections after the defects liability period. The clients might require some assistance during initial occupation period, for example, maintenance. 14 Developing a Project and Funding for to Completion Sources of Grant Aid – From Concept Cricket Clubs Developing a Project –and Funding forto Completion Sources of Grant Aid From Concept Cricket Clubs 15
  • 10. Sources of Grant Aid and Funding for Cricket Clubs 17
  • 11. England and Wales Cricket Board Lords Cricket Ground London NW8 8QZ T: 020 7432 1200 F: 020 7289 5619 E: facilities@ecb.co.uk www.ecb.co.uk From playground to Test arena August 2009 18 Sources of Grant Aid and Funding for Cricket Clubs